05000254/LER-1997-003-05, :on 970429,visual Exam (VT-2) Was Not Performed Due to Procedural Deficiencies Following HPCI Sys Valve Replacement Required by Asme,Section XI & TS Section 4.0.E. Examined VT-2 of 1-2301-45 Valve

From kanterella
Revision as of 17:25, 11 December 2024 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
:on 970429,visual Exam (VT-2) Was Not Performed Due to Procedural Deficiencies Following HPCI Sys Valve Replacement Required by Asme,Section XI & TS Section 4.0.E. Examined VT-2 of 1-2301-45 Valve
ML20140B150
Person / Time
Site: Quad Cities 
Issue date: 05/29/1997
From: Peterson C
COMMONWEALTH EDISON CO.
To:
Shared Package
ML20140B147 List:
References
LER-97-003-05, LER-97-3-5, NUDOCS 9706060056
Download: ML20140B150 (4)


LER-1997-003, on 970429,visual Exam (VT-2) Was Not Performed Due to Procedural Deficiencies Following HPCI Sys Valve Replacement Required by Asme,Section XI & TS Section 4.0.E. Examined VT-2 of 1-2301-45 Valve
Event date:
Report date:
2541997003R05 - NRC Website

text