ML23118A106

From kanterella
Revision as of 09:06, 8 May 2023 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Email Dated April 25, 2023 from N. Garcia Santos (NRC) to R. Boyle (DOT) - Subject: Staggered RAIs for the Model No. FCC-3 (Material Properties, Structural Evaluation
ML23118A106
Person / Time
Site: Orano USA
Issue date: 04/25/2023
From: Garcia-Santos N
Division of Fuel Management
To: Boyle R
US Dept of Transportation (DOT), Office of Hazardous Materials Safety
Shared Package
ML23118A023 List:
References
A33010, EPID L-2022-DOT-0007
Download: ML23118A106 (1)


Text

From: Norma Garcia Santos To: Boyle, Rick (PHMSA)

Cc: Yong Kim; Juan Lopez; Jason Huang; Yoira Diaz Sanabria

Subject:

Staggered RAIs for the Model No. FCC-3 Date: Tuesday, April 25, 2023 2:19:00 PM Attachments: RAI for FCC-3 .pdf

Dear Rick Boyle:

The schedule for conducting the U.S. Nuclear Regulatory Commission (NRC) staff review of your submittal indicates an estimated date to issue requests for additional information (RAIs) by April 2023. However, the RAI letter may be issued approximately, the first week of May 2023.

Nevertheless, the NRC staff has completed the development of the attached RAIs.

Therefore, we have decided to stagger the RAIs and transmit them to you as they are completed. At this time, I am transmitting the RAIs completed up to this point for your information and to allow you to start working on your responses. Please note that these RAIs may change as we develop RAIs in other areas of the review.

A comprehensive RAI package with the final RAIs will be issued by the date referenced above. You may provide your responses to the staggered RAIs in phases or you may submit all of the responses in a single submittal (i.e., the responses should be submitted altogether in your response letter to the NRC around the end of May-beginning of June 2023).

In accordance with Title 10 of the Code of Federal Regulations, Section 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this communication, without the enclosure, will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of the NRCs ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

If you have any questions regarding this communication, please contact me via e-mail to Norma.GarciaSantos@nrc.gov.

Sincerely, Norma Garcia Santos Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 07103083