ML22343A124
Letter Sequence Other | |
---|---|
Administration Results Other: A33010, Transmittal Letter Dated 5/31/23 from Richard Boyle (DOT) to Ngarcia (NRC) - Responses to the RAIs Related to the FCC-4 Revalidation Request, ML22271A186, ML22271A189, ML22271A190, ML22271A450, ML22271A452, ML22271A454, ML22271A455, ML22271A458, ML22271A460, ML22271A461, ML22271A463, ML22271A465, ML22271A466, ML22271A468, ML22271A470, ML22271A471, ML22271A472, ML22271A474, ML22271A476, ML22271A477, ML22271A479, ML22271A481, ML22271A482, ML22271A484, ML22271A486, ML22271A487, ML22271A636, ML22271A637, ML22271A638, ML22271A639, ML22271A640, ML22271A641, ML22271A642, ML22271A643, ML22271A644, ML22271A645, ML22271A646, ML22271A647, ML22271A648... further results | |
MONTHYEARML22271A6411998-08-19019 August 1998
[Table View]E-61283 Enclosure 4, 009h1 Ap 2.1-8 TFXDC2108EN Npv, Revision B, Modified RCC Container - Proto 2 - Regulatory Test Programme (Public) Project stage: Other ML22277A7611998-08-19019 August 1998 E-61285, Enclosure 4, 009h1 Appendix 2.1-8, Document No. TFXDC2108, Modified RCC Container - Proto 2 - Regulatory Test Programme (Public) Project stage: Other ML22271A6392004-05-0404 May 2004 E-61283 Enclosure 4, 009G1 AP 2.1-7 TFXEDC2104-NPV, Rev. E, Modification of FCC Containers Choice of Prototype 2 Drop Configurations for Regulatory Tests (Public) Project stage: Other ML22277A7592004-05-0505 May 2004 E-61285, Enclosure 4, 009g1 Appendix 2.1-7, Document No. TFXEDC2104, Revision E, Modification of RCC Containers Choice of Prototype 2 Drop Configurations for Regulatory Tests (Public) Project stage: Other ML22277A7832004-10-29029 October 2004 E-61285, Enclosure 4, 013c1 Appendix 2.5-3, Document No. FF/DC/01106 E0, Revision a, Safety/Criticality Study of FCC3v2 Containers 14 X 14 8 Foot and 14 X 14 10 Footassemblies (FCC-3/FCC-4) (Public) Project stage: Other ML22271A8002004-10-29029 October 2004 E61283, Enclosure 4, 013c1 Appendix 2.5-3, Document No. FF/DC/01106 Revision a, E0, Safety/Criticality Study of FCC3v2 Containers 14 X 14 8 Foot and 14 X 14 10 Foot Assemblies (Public) Project stage: Other ML22277A7852007-12-19019 December 2007 E-61285, Enclosure 4, 013d1 Appendix 2.5-4, Document No. FF/DC/04191, Revision B, Safety/Criticality Study for FCC4 Packages & 17x17XL Assemblies Justification for an Increased Cavity Cross Section (Public) Project stage: Other ML22271A8022007-12-19019 December 2007 E61283, Enclosure 4, 013d1 Appendix 2.5-4, FF DC 04191, Revision B, Safety/Criticality Study for FCC4 Packages & 17x17XL Assemblies Justification for an Increased Cavity Cross Section (Public) Project stage: Other ML22271A6462009-01-0101 January 2009 E-61283 Enclosure 4, 009c1 Ap 2.1-3 Document No. NTC-08-00135891E-NPV, Revision No. 01E, Analysis of the Fatigue Strength of the FCC3/FCC4 Containers (Public) Project stage: Other ML22277A7512009-01-0101 January 2009 E-61285, Enclosure 4, 009c1 Ap 2.1-3 Document No. NTC-08-00135891E-NPV, Revision 01E, Analysis of the Fatigue Strength of the FCC3/FCC4 Containers (Public) Project stage: Other ML22271A4702009-05-0101 May 2009 E-61283 Enclosure 4, 009a1 Appendix 2.1-1, FFDC05090-A EN Npv, FCC3 Containers - Lashing Diagrams (Public) Project stage: Other ML22277A7732009-06-27027 June 2009 E-61285, Enclosure 4, 010d1 Appendix 2.2-4, Document No. NTC-08-00118662E-NPV, Revision 1E, Note on the Characterization of Resin Fs 69 (Public) Project stage: Other ML22271A8162009-06-27027 June 2009 E-61283 Enclosure 4, 010d1 Appendix 2.2-4, NTC-08-00118662E-NPV, Rev. 1E, Note on the Characterization of Resin Fs 69 Project stage: Other ML22271A6442010-07-0101 July 2010 E-61283 Enclosure 4, 009b1 Ap 2.1-2 F2, Document No. NEEL-F 2008 DC 117EN, Revision B, FCC3 Containers for Fresh Fuel Assemblies Data for the Fatigue Strength Analysis of the Lifting Boxes and Upper Shell (Public) Project stage: Other ML22277A7492012-01-18018 January 2012 E-61285, Enclosure 4, 009b1 Appendix 2.1-2, Document No. NEEL-F 2008 DC 118, Revision B E1 (Npv), FCC4 Containers for Fresh Fuel Assemblies Data for the Fatigue Strength Analysis of the Lifting Boxes and Upper Shell (Public) Project stage: Other ML22277A7722012-04-0202 April 2012 E-61285, Enclosure 4, 010d Appendix 2.2-4, Document No. DOS-13-00081778-204-NPV, Revision 00, Reference to 10373-B-1, Revision 3, Summary Note on the Characterisation of Fs 69 Resin (FCC-3 - FCC-4) (Public) Project stage: Other ML22277A7582012-04-0202 April 2012 E-61285, Enclosure 4, 009g Appendix 2.1-7, Document No. DOS-13-00081778-107-NPV, Revision 00, Reference to Tfxedc 2104, Revision E, Modification of RCC Containers - Selection of Drop Configurations for Prototype 2 in the Context of Regulato Project stage: Other ML22277A7602012-04-0202 April 2012 E-61285, Enclosure 4, 009h Appendix 2.1-8, Document No. DOS-13-00081778-108-NPV, Revision 00, Reference to Tfx DC 2108, Revision B, Modified RCC Container - Prototype 2 - Regulatory Test Programme (FCC-3 - FCC-4) (Public) Project stage: Other ML22277A7482012-04-0202 April 2012 E-61285, Enclosure 4, 009b Appendix 2.1-2, Document No. DOS-13-00081778-102-NPV, Rev 00, Reference to NEEL-F 2008 DC 118, Rev. B, FCC4 Containers for Fresh Fuel Assemblies Data for Fatigue Resistance Analysis of Lifting Boxes and Upper Shel Project stage: Other ML22277A7622012-04-0202 April 2012 E-61285, Enclosure 4, 009i Appendix 2.1-9, Document No. DOS-13-00081778-109-NPV, Revision 00, Reference to Tfx DC 2087, Revision a, Container Prototype n1 Drop Test Report (FCC-3 - FCC-4) (Public) Project stage: Other ML22277A7632012-04-0202 April 2012 E-61285, Enclosure 4, 009j Appendix 2.1-10, Document No. DOS-13-00081778-110-NPV, Revision 00, Reference to Tfxe DC 2132, Revision B, Container Prototype No. 2 Drop Test Report (FCC-3 - FCC4) (Public) Project stage: Other ML22277A7972012-04-0202 April 2012 E-61285 Enclosure 4, 002d Appendix 1.3-4, Document No. DOS-13-00081778-034-NPV, Rev. 00, Reference to SQ/95/602PBO/CC, Revision 0,, Leaching Tests on Enriched Reprocessed Uranium (Eru) Pellets (Public) Project stage: Other ML22277A7822012-04-0202 April 2012 E-61285, Enclosure 4, 013c Appendix 2.5-3, Document No. DOS-13-00081778-503-NPV, Revision 00, Reference to Ffdc 01106, Revision a, Criticality-safety Analysis of FCC3 Containers Version 2-Assembly Types 14x14 8-foot and 14x14 10-ft (FCC-3/F Project stage: Other ML22277A7382012-04-0202 April 2012 E-61285 Enclosure 4, 003d Appendix 1.4-4, Document No. DOS-13-00081778-044-NPV, Rev. 00, Reference to Photographs_FCC4, Rev. 0, Photographs of the FCC4 Package (Public) Project stage: Other ML22271A8152012-04-0202 April 2012 E-61283 Enclosure 4, 010d Appendix 2.2-4 DOS-13-00081778-204-NPV, Rev. 00, Reference to 10373-B-1, Revision 3, Summary Note on the Characterization of Fs 69 Resin Project stage: Other ML22271A4842012-04-30030 April 2012 E-61283 Enclosure 4, 002d Appendix 1.3-4, Document No. DOS-13-00081778-034-NPV, Revision 00, Appendix 1.3-4 - Test Report Leaching of Enriched Reprocessed Uranium (Eru) Pellets (Public) Project stage: Other ML22271A4772012-04-30030 April 2012 E-61283 Enclosure 4, 002a Appendix 1.3-1,Document No. DOS-13-00081779-031-NPV, Revision 00, Appendix 1.3-1 - Description of Fuel Rod Boxes for FCC3 Containers (Public) Project stage: Other ML22271A6422012-04-30030 April 2012 E-61283 Enclosure 4, 009i Ap 2.1-9 DOS-13-00081778-109-NPV, Revision 00, Container Prototype No. 1, Drop Test Report (Public) Project stage: Other ML22271A6402012-04-30030 April 2012 E-61283 Enclosure 4, 009h Ap 2.1-8 DOS-13-00081778-108-NPV, Revision 00, Modified RCC Container - Prototype 2 - Regulatory Test Programme (Public) Project stage: Other ML22271A4712012-04-30030 April 2012 E-61283 Enclosure 4, 009b Appendix 2.1-2, Document No. DOS-13-00081779-102-NPV, Revision 00, FCC3 Containers for Fresh Fuel Assemblies Data for Fatigue Resistance Analysis of Lifting Boxes and Upper Shell (Public) Project stage: Other ML22271A4682012-04-30030 April 2012 E-61283 Enclosure 4, 009a Appendix 2.1-1, Document No. DOS-13-00081779-101-NPV, Revision 00, Table of Contents, FCC3 Containers - Tie-down Diagrams, Areva (Public) Project stage: Other ML22271A4792012-04-30030 April 2012 E-61283 Enclosure 4, 002b Ap 1.3-2 DOS-13-00081779-032-NPV, Revision 00, Appendix 1.3-2 - Drawing of Fuel Rod Boxes for FCC3 Containers (Public) Project stage: Other ML22271A6432012-04-30030 April 2012 E-61283 Enclosure 4, 009j Ap 2.1-10 DOS-13-00081778-110-NPV, Revision 00, Container Prototype No. 2, Drop Test Report (Public) Project stage: Other ML22271A6382012-04-30030 April 2012 E-61283 Enclosure 4, 009g Ap 2.1-7 DOS-13-00081778-107-NPV, Modification of RCC Containers - Selection of Drop Configurations for Prototype 2 in the Context of Regulatory Tests (Public) Project stage: Other ML22271A4542012-04-30030 April 2012 E-61283 Enclosure 4, 003d Appendix 1.4-4, Document No. DOS-13-00081779-044-NPV, Revision 00, Table of Contents, Photographs of the FCC3 Package (Public) Project stage: Other ML22271A4522012-04-30030 April 2012 E-61283 Enclosure 4, 003c Appendix 1.4-3, Document No. DOS-13-00081778-043-NPV, Revision 00, Table of Contents, Summary of Toughness Tests Project stage: Other ML22271A8012012-09-0303 September 2012 E61283, Enclosure 4, 013d Appendix 2.5-4 (FCC3-FCC4), DOS-13-00081778-504-00-NPV, Rev. 00, Reference to Ffdc 04191, Rev. B, Safety/Criticality Study for FCC4 Packages and 17x17 Xl Assemblies Justification for an Increased Cavity Cross Secti Project stage: Other ML22277A7842012-09-0303 September 2012 E-61285, Enclosure 4, 013d Appendix 2.5-4, Document No. DOS-13-00081778-504-NPV, Rev. 00, Reference to Ffdc 04191, Rev. B, Safety/Criticality Study for FCC4 Packages, 17x17 Xl Assemblies Justification for an Increased Cavity Cross (FCC-3/FC Project stage: Other 2009-05-01 |
ML22343A124 | |
Person / Time | |
---|---|
Site: | Orano USA, 07103097 |
Issue date: | 12/09/2022 |
From: | Vescovi P TN Americas LLC |
To: | Boyle R, Garcia-Santos N Storage and Transportation Licensing Branch, US Dept of Transportation (DOT) |
Garcia-Santos N | |
References | |
EPID L-2022-DOT-0007, EPID L-2022-DOT-0008, CAC A33010 | |
Download: ML22343A124 (1) | |
Category:E-Mail
MONTHYEARML23174A0222023-06-22022 June 2023
[Table view]Email Dated June 22, 2023 from P. Vescovi (Orano) to N. Garcia Santos (Cc: R. Boyle, Dot), Confirmation of the Need Date for the Revalidation Recommendation Requests of the French Packages FCC-3 and FCC-4 (Docket Nos. 71-3083 and 71-3097, R ML23118A1062023-04-25025 April 2023 Email Dated April 25, 2023 from N. Garcia Santos (NRC) to R. Boyle (DOT) - Subject: Staggered RAIs for the Model No. FCC-3 (Material Properties, Structural Evaluation ML23118A1512023-04-25025 April 2023 Email Dated 4-25-23 from N. Garcia Santos (NRC) to R. Boyle (DOT) Staggered RAIs for the Model No. FCC-4 ML22343A1242022-12-0909 December 2022 Email from P. Vescovi (Tn Americas LLC) to N.Garcia Santos (Nrc), Subject: FCC-3 and FCC-4 - Rsi Letter, Tn Americas LLC Request of Additional Time to Address Rsis ML22285A0822022-10-12012 October 2022 Email from N. Garcia Santos (NRC) to R. Boyle (DOT) FCC-3 and FCC-4 Applications Deficiencies ML22271A3542022-08-18018 August 2022 Email from R. Boyle (DOT) to N. Garcia Santos (Nrc), - FCC3 Request for Review and Recommendation (Public) ML22277A7262022-08-18018 August 2022 Email Dated 8/18/22 from Rboyle (DOT) to Ngarcia Santos (Nrc), Subject: FCC4 - Request for Review and Recommendation ML20189A6072020-06-29029 June 2020 Email Dated 6/29/20 from M.Conroy (DOT) to N.Garcia Santos (NRC) Rsi Response, FCC-4 Revalidation ML20118C1452020-04-14014 April 2020 Email Dated 4/14/20 from Pvescovi (Orano Tn) to Ngarcia Santos (NRC) Estimated FCC-3 and FCC-4 Shipping Schedule (Docket Nos. 71-3083 and 71-3097) 2023-06-22 |
Text
From: VESCOVI Peter (ORANO)
To: Norma Garcia Santos; Boyle, Rick (PHMSA)
Cc: SHAW Donis (ORANO)
Subject:
[External_Sender] RE: FCC-3 and FCC RSI Letter Date: Friday, December 9, 2022 10:34:56 AM
- Norma, Thank you. The 4 week request for response would be the first week after return from holiday weeks. A reasonable expectation is to provide responses by 2nd or3rd week in January since there are up to 2 weeks when persons in France are out of office for holidays between now and the start of the new year.
Peter Vescovi
+1 336 420-8325 From: Norma Garcia Santos <Norma.GarciaSantos@nrc.gov>
Sent: Friday, December 9, 2022 10:25 AM To: Boyle, Rick (PHMSA) <rick.boyle@dot.gov>
Cc: SHAW Donis (ORN-NPS) <donis.shaw@orano.group>; VESCOVI Peter (ORN-NPS)
<peter.vescovi@orano.group>
Subject:
FCC-3 and FCC RSI Letter Security Notice: Please be aware that this email was sent by an external sender.
Good afternoon, Attached is the RSI letter for the FCC-3 and FCC-4 transportation packages.
Feel free to contact me if you have questions about this request.
Thanks in advance, Norma Garcia Santos Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards