Email Dated 4/14/20 from Pvescovi (Orano Tn) to Ngarcia Santos (NRC) Estimated FCC-3 and FCC-4 Shipping Schedule (Docket Nos. 71-3083 and 71-3097)
ML20118C145
Person / Time
Site: Orano USA, 07103097
Issue date: 04/14/2020
From: Vescovi O
Orano TN Americas
To: Conroy M, Garcia-Santos N
Office of Nuclear Material Safety and Safeguards, US Dept of Transportation (DOT)
Garcia-Santos N
References
Download: ML20118C145 (2)


Text

From: VESCOVI Peter (ORANO)

To: Garcia Santos, Norma; Conroy, Michael (PHMSA)

Subject:

[External_Sender] RE: FCC-3 adn FCC-4 Shipping Schedule Date: Tuesday, April 14, 2020 12:49:33 PM Attachments: image001.png image002.png image003.png image004.png image005.png image006.png

Mike, The information provided is not proprietary.

Peter Vescovi

+1 336-420-8325 From: Garcia Santos, Norma [1]

Sent: Tuesday, April 14, 2020 11:58 AM To: VESCOVI Peter (ORN-NPS); Conroy, Michael (PHMSA)

Subject:

RE: FCC-3 adn FCC-4 Shipping Schedule Security Notice: Please be aware that this email was sent by an external sender.

Good morning, This information is very helpful. Please confirm if this information is proprietary or not. If it is proprietary, please provide an affidavit stating the rationale why the information in the email below is considered proprietary. Then, the information in this string of emails can be placed and profiled in ADAMS.

Thanks in advance, Norma Garcia Santos Project Manager Division of Fuel Management Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Telephone No.: 301-415-6999 Email: Norma.Garcia-Santos@nrc.gov From: VESCOVI Peter (ORANO) <peter.vescovi@orano.group>

Sent: Tuesday, April 14, 2020 11:53 AM To: Conroy, Michael (PHMSA) <Michael.Conroy@dot.gov>

Cc: Garcia Santos, Norma <Norma.GarciaSantos@nrc.gov>

Subject:

[External_Sender] FCC-3 adn FCC-4 Shipping Schedule

Mike,

The first need for Framatome is to transport gadolinium rods (PWR AFA3G 17x17 design) between the US and France The objective is to qualify the production of these gadolinium rods in their Richland, WA facility for their French customer EDF in 2022 first semester.

240 rods (12 and 14) are forecasted to be fabricated and shipped to Romans, France end of 2022 first semester in 1 FCC3 and 2 FCC4.

The second need is to qualify the Richland, WA facility to fabricate 28 fuel assemblies PWR AFA3G 17x17 UNE 12 for their French customer EDF and ship them to Romans, France The shipping schedule is not finalized yet but if possible they would like to ship as early as Q3-2022 in 14 FCC3.

The third need is to transport gadolinium rods (PWR AFA3G 17x17 design and AFA3G 15x15 design) between the US and France.

The objective is to qualify the production of these gadolinium rods in their Richland, WA facility for their customers abroad (outside of France) in 2023 first semester.

260 rods (12) are forecasted to be fabricated and shipped to Romans, France end of 2023 first semester in 1 or 2 FCC3.

Peter Vescovi, P.E.

Technical Advisor, Orano TN Phone:+1 410.910.6533 Cell: +1 336.420.8325 www.orano.group follow us!

CONFIDENTIALITY The information contained in this e-mail and any accompanying documents may contain information that is confidential or otherwise protected from disclosure. If you are not the intended recipient, please immediately alert the sender by reply e-mail and then delete this message, including any attachments. Any dissemination, distribution or other use of the contents of this message by anyone other than the intended recipient is strictly prohibited.

CONFIDENTIALITÉ L'information contenue dans ce message et ses pices jointes est confidentielle et établie l'intention exclusive de ses destinataires. Au cas o ce message ne vous serait pas destiné, nous vous remercions de bien vouloir en aviser immédiatement l'émetteur et de le supprimer. Toute copie, diffusion ou autre utilisation du contenu de ce message par toute personne autre que le destinataire est interdite.