ML21137A342
ML21137A342 | |
Person / Time | |
---|---|
Site: | Davis Besse |
Issue date: | 02/18/2021 |
From: | Gregory Roach NRC/RGN-III/DRS/OLB |
To: | |
Roach G | |
Shared Package | |
ML20136A266 | List: |
References | |
Download: ML21137A342 (16) | |
Text
Davis-Besse DB1LOT21 NRC Exam Plant JPM P1
Appendix C, Rev. 11 Job Performance Measure Form ES-C-1 Worksheet Plant JPM P1 Facility: Davis-Besse Task No: 064-026-05-0401 Task
Title:
Energize Station Blackout Diesel Generator Auxiliaries K/A
Reference:
064 A2.12 (2.8/3.1) Job Performance Measure No: P1 (OPSJPM258)
Examinee:
NRC Examiner: Date:
Method of testing:
Simulated Performance __ X _ Actual Performance ___
Classroom ___ Simulator _ _ Plant _ X __
Read to the examinee:
I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
Initial Conditions:
The plant conditions are specified in the Initial Conditions and Initiating Cues.
Task Standard:
- Energize Station Blackout Diesel Generator Auxiliaries
- Emergency Shutdown Station Blackout Diesel Generator (Loss of Air-Cooling Fans)
Required Materials:
- DB-OP-06334 L&P 2.2.21
- Section 4.10 of DB-OP-06334, Station Blackout Diesel Generator Operating Procedure with steps 10.1-10.3 signed off and indicating barring not required
- Section 5.2 of DB-OP-06334, Emergency Shutdown of Station Blackout Diesel Generator General
References:
None Initiating Cue:
The plant conditions are specified in the Initial Conditions and Initiating Cues.
Time Critical Task: No Alternate Path: Yes Validation Time: 20 minutes NUREG-1021, Revision 11 Page 1 of 7
Appendix C, Rev. 11 Job Performance Measure Form ES-C-1 Worksheet Plant JPM P1 EXAMINER COPY INITIAL CONDITIONS:
The plant is operating at 100% power Ambient temperature is 45°F Breaker AD213, SBODG to D2, has been opened in preparation for breaker maintenance AD213 was opened 15 minutes ago INITIATING CUES:
The Unit Supervisor directs you to perform Section 4.10, Energizing the Station Blackout Diesel Generator Auxiliaries from the Station Blackout Diesel Generator, of DB-OP-06334.
The Station Blackout Diesel Generator is being placed in a state of increased readiness and Barring of the Station Blackout Diesel Generator is not required.
(Provide the examinee a copy of Section 4.10 (with steps 10.1-10.3 signed off indicating barring not required) of DB-OP-06334, Station Blackout Diesel Generator Operating Procedure)
(A copy of Section 5.2 of DB-OP-06334 will be required for the examinee later during this Job Performance Measure)
NUREG-1021, Revision 11 Page 2 of 7
Appendix C, Rev. 11 Job Performance Measure Form ES-C-1 Worksheet Plant JPM P1 CANDIDATE COPY INITIAL CONDITIONS:
The plant is operating at 100% power Ambient temperature is 45°F Breaker AD213, SBODG to D2, has been opened in preparation for breaker maintenance AD213 was opened 15 minutes ago INITIATING CUES:
The Unit Supervisor directs you to perform Section 4.10, Energizing the Station Blackout Diesel Generator Auxiliaries from the Station Blackout Diesel Generator, of DB-OP-06334.
The Station Blackout Diesel Generator is being placed in a state of increased readiness and Barring of the Station Blackout Diesel Generator is not required.
NUREG-1021, Revision 11 Page 3 of 7
Appendix C, Rev. 11 Job Performance Measure Form ES-C-1 Worksheet Plant JPM P1 PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT assumed unless denoted in the "Comments".
START TIME: __________
- 1. PERFORMANCE STEP: Depress and hold the FUEL PRIME pushbutton.
STANDARD: Depresses the FUEL PRIME pushbutton and looks at fuel oil pressure stabilizes greater than 15 PSIG on the black indicator of PI 11160.
CUE: PI 11160 FUEL FILTER Pressure is 17 PSIG SAT UNSAT
- 2. PERFORMANCE STEP: Place the ELECT PROTECT-MODE SELECT Switch in the TEST position
........C........
STANDARD: Rotate the ELECT PROTECT-MODE SELECT Switch counter clockwise to the TEST position on C30202.
CUE: The ELECT PROTECT - MODE SELECT Switch has been rotated counter clockwise and points towards TEST SAT UNSAT
- 3. PERFORMANCE STEP: Verify Station Blackout Diesel Generator OUTPUT BREAKER AD301 is open STANDARD: On panel C30202, Verify AD301 GREEN light is lit CUE: AD301 is GREEN LIGHT is lit SAT UNSAT NUREG-1021, Revision 11 Page 4 of 7
Appendix C, Rev. 11 Job Performance Measure Form ES-C-1 Worksheet Plant JPM P1
- 4. PERFORMANCE STEP: Start the SBODG
........C........
STANDARD: Depress the START pushbutton.
CUE: The START pushbutton has been depressed SAT UNSAT
- 5. PERFORMANCE STEP: CHECK that the Station Blackout Diesel Generator starts.
STANDARD: Station Blackout Diesel Generator starts and accelerates to approximately 450 rpm as indicated on ENGINE TACHOMETER on C30203 CUE: Tachometer reads 450 rpm SAT UNSAT
- 6. PERFORMANCE STEP: After approximately 30 seconds, the Station Blackout Diesel Generator accelerates to 900 rpm.
STANDARD: Station Blackout Diesel Generator starts and accelerates to approximately 900 rpm in 30 seconds as indicated on ENGINE TACHOMETER on C30203 NOTE: Green MDT: Tach reads 780 RPM when the SBODG is at 900 RPM.
If not repaired prior to exam, cue should be per MDT.
CUE: Tachometer reads 900 rpm SAT UNSAT
- 7. PERFORMANCE STEP: Place the SYNCHRONIZE switch in the ON position
........C........
STANDARD: Rotate the SYNCHONIZE switch to the ON position CUE: The SYNCHRONIZE switch is in the ON position, synchroscope pointer indicates 1200 SAT UNSAT NUREG-1021, Revision 11 Page 5 of 7
Appendix C, Rev. 11 Job Performance Measure Form ES-C-1 Worksheet Plant JPM P1
- 8. PERFORMANCE STEP: Close Breaker AD 301, SBODG OUTPUT BREAKER on Panel C30202.
........C........
STANDARD: Rotate AD301 to the close position CUE: AD 301 RED LIGHT is ON SAT UNSAT
- 9. PERFORMANCE STEP: Place the SYNCHRONIZE switch to OFF STANDARD: Rotate the SYNCHRONIZE switch to OFF position CUE: The SYNCHRONIZE switch is in the OFF position SAT UNSAT
- 10. PERFORMANCE STEP: Verify both Station Blackout Diesel Generator Jacket Water Radiator fans are operating STANDARD: Check the status of the fans by observing the breaker lights and/or observing the fans locally.
CUE: Both fan breaker lights indicate GREEN (or the fans are not turning if checked locally)
SAT UNSAT
- 11. PERFORMANCE STEP: Go to Section 5.2, Emergency Shutdown of the Station Blackout Diesel Generator STANDARD: Routes to Section 5.2 of DB-OP-06334 CUE: (Provide the examinee a copy of Section 5.2 of DB-OP-06334)
SAT UNSAT NUREG-1021, Revision 11 Page 6 of 7
Appendix C, Rev. 11 Job Performance Measure Form ES-C-1 Worksheet Plant JPM P1
- 12. PERFORMANCE STEP: Stop the Station Blackout Diesel Generator
........C........
STANDARD: Depress the Emergency Stop pushbutton on panel C30202 or panel C30203.
CUE: The Emergency Stop has been depressed. The Station Blackout Diesel Generator slows down and then stops (If asked) AD301 GREEN light is ON, RED light is OFF SAT UNSAT
- 13. PERFORMANCE STEP: Station Blackout Diesel Generator stops STANDARD: Verify Engine Tachometer reads zero on C30203 CUE: The Station Blackout Diesel Generator tachometer reads zero SAT UNSAT
- 14. PERFORMANCE STEP: Notify the Shift Manager the Station Blackout Diesel Generator is NOT functional AND verify the Station Blackout Diesel Generator is NOT required.
STANDARD: Notify the Shift Manager CUE: Shift Manager has been notified and the Shift Manager is referring to Technical Requirement 8.8.2.
SAT UNSAT TERMINATING CUES This JPM is complete. (Terminated by the evaluator)
END TIME NUREG-1021, Revision 11 Page 7 of 7
Davis-Besse DB1LOT21 NRC Exam Plant JPM P2
Appendix C, Rev. 11 Job Performance Measure Form ES-C-1 Worksheet Plant JPM P2 Facility: Davis-Besse Task No: 000-078-05-0100 / 086-016-04-0100 Task
Title:
Actions outside the Control Room of the Primary Side Reactor Operator for a Serious Control Room Fire K/A
Reference:
068 AA1.21 (3.9,4.1) Job Performance Measure No: P2 (OPSJPM003)
Examinee:
NRC Examiner: Date:
Method of testing:
Simulated Performance _X_ Actual Performance ___
Classroom___ Simulator ___ Plant _X_
Read to the examinee:
I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
Initial Conditions:
This JPM is not dependent on any specific simulator initial conditions since the task is administrative in nature.
The plant conditions are specified in the Initial Conditions and Initiating Cues.
Requires entry into #1 ECCS Room, EPR 1, MPR 3 Task Standard:
Perform steps 4.0, 5.0, and 6.0 of Attachment 3 of DB-OP-02519, Actions outside the Control Room of the Primary Side Reactor Operator for a Serious Control Room Fire Required Materials:
Attachment 3 of DB-OP-02519, Actions outside the Control Room of the Primary Side Reactor Operator for a Serious Control Room Fire General
References:
None Initiating Cue:
The plant conditions are specified in the Initial Conditions and Initiating Cues.
Time Critical Task: No Alternate Path: No Validation Time: 23 minutes NUREG-1021, Revision 11 Page 1 of 7
Appendix C, Rev. 11 Job Performance Measure Form ES-C-1 Worksheet Plant JPM P2 EXAMINER COPY This JPM starts from the Radiologically Restricted Area (RRA) side of the emergency entrance to the Aux Building INITIAL CONDITIONS:
The Control Room has been evacuated due to a serious Control Room fire.
INITIATION CUE:
The Shift Manager has directed you to perform Attachment 3 of DB-OP-02519, Actions outside the Control Room of the Primary Side Reactor Operator for a Serious Control Room Fire.
Steps 1.0 and 2.0 have already been completed.
(Hand Candidate a copy of Attachment 3 of DB-OP-02519, completed up through step 2.0)
NUREG-1021, Revision 11 Page 2 of 7
Appendix C, Rev. 11 Job Performance Measure Form ES-C-1 Worksheet Plant JPM P2 CANDIDATE COPY INITIAL CONDITIONS:
The Control Room has been evacuated due to a serious Control Room fire.
INITIATION CUE:
The Shift Manager has directed you to perform Attachment 3 of DB-OP-02519, Actions outside the Control Room of the Primary Side Reactor Operator for a Serious Control Room Fire.
Steps 1.0 and 2.0 have already been completed.
NUREG-1021, Revision 11 Page 3 of 7
Appendix C, Rev. 11 Job Performance Measure Form ES-C-1 Worksheet Plant JPM P2 PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT required unless denoted in the "Comments".
START TIME: _______
- 1. PERFORMANCE STEP: Verify BE111 Open STANDARD: Verify CTMT Spray Pump 1 stopped using NP0561 (#1 ECCS Rm)
CUE:
- NP0561 Green light is ON Red light is OFF
- #1 CTMT Spray Pump is not rotating
- OFF pushbutton has been depressed SAT UNSAT
- 2. PERFORMANCE STEP: Open BE 1160, AUXILIARY FEEDWATER TO STEAM
........C........ GENERATOR 1 LINE STOP AF608, on E11E STANDARD: Press down on handle to open BE 1160 on E11E (EPR 1)
CUE: Breaker handle pulled down and indicates OFF SAT UNSAT
- 3. PERFORMANCE STEP: Place disconnect switch RC 110 in LOCAL at CDE16B
........C........
STANDARD: Rotate RC 110 LOCAL/REMOTE knob to the LOCAL position CUE: Switch (for RC 110) has been rotated clockwise to the LOCAL position SAT UNSAT
- 4. PERFORMANCE STEP: Close RC 11, PORV Block Valve
........C........
STANDARD: At BKR BE1602 on E16B Press the CLOSE button. Check Green light ON Red light OFF CUE: The CLOSED button (on BE 1602) has been depressed Green light ON Red light OFF SAT UNSAT NUREG-1021, Revision 11 Page 4 of 7
Appendix C, Rev. 11 Job Performance Measure Form ES-C-1 Worksheet Plant JPM P2
- 5. PERFORMANCE STEP: Place disconnect switches to LOCAL on CD E11E
........C........
STANDARD: Place AF 3869 and DH 64 disconnect switches in the LOCAL position CUE: Disconnect switch (for AF 3869) has been placed in the LOCAL position Disconnect switch (for DH 64) has been placed in the LOCAL position SAT UNSAT
- 6. PERFORMANCE STEP: Verify CRD Trip BKR D is open STANDARD: Check CRD Trip BKR D OPEN/CLOSE position. Verify OPEN CUE: The position indicating window indicates GREEN OPEN SAT UNSAT
- 7. PERFORMANCE STEP: Check power is dropping in the source range at C4808, GAMMA METRICS CABINET STANDARD: Observe Neutron level is in the source range using NY-5874C CUE: (NY-5874C) Power range is 10-7 Source range indicated 102 and lowering Source range Startup rate is -0.33 dpm SAT UNSAT
- 8. PERFORMANCE STEP: Inform the Shift Manager of source range level STANDARD: Using Gaitronics or radio call the Shift Manager and report source range level COMMENT: Sign on door to room prohibits radio usage CUE: Shift Manager acknowledges source range level SAT UNSAT
........C........
STANDARD: Rotate MU215 in the clockwise direction until valve stem is down CUE: (MU215) Valve has been rotated in the Clockwise direction until valve stem is down and handwheel will NOT turn SAT UNSAT NUREG-1021, Revision 11 Page 5 of 7
Appendix C, Rev. 11 Job Performance Measure Form ES-C-1 Worksheet Plant JPM P2
- 10. PERFORMANCE STEP: Open BE 1180 on E11B
........C........
STANDARD: OPEN breaker BE 1180 for YE2 240 VAC MCC on E11B CUE: (BE 1180) breaker handle has been pulled down and indicates OFF (OPEN)
SAT UNSAT
- 11. PERFORMANCE STEP: Place disconnect switches to LOCAL on CDE11B-2
........C........
STANDARD: Place the following disconnect switches in LOCAL at CDE11B-2 MU 59C MU 59D RC 240A CC1407A DH 12 CUE: (MU 59C) disconnect switch is placed in LOCAL (MU 59D) disconnect switch is placed in LOCAL (RC 240A) disconnect switch is placed in LOCAL (CC 1407A) disconnect switch is placed in LOCAL (DH 12) disconnect switch is placed in LOCAL SAT UNSAT
- 12. PERFORMANCE STEP: Place disconnect switches to LOCAL on CDE11B-1
........C........
STANDARD: Place all CDE11B-1 disconnect switches in LOCAL position CUE: Disconnect switches have been placed in the LOCAL position on CDE11B-1 SAT UNSAT
- 13. PERFORMANCE STEP: Place disconnect switches to LOCAL on CDE11C
........C........
STANDARD: Place all CDE11C disconnect switches in LOCAL position NOTE: Placing SPARE switches in LOCAL is not considered critical CUE: Disconnect switches have been placed in the LOCAL position on CDE11C SAT UNSAT NUREG-1021, Revision 11 Page 6 of 7
Appendix C, Rev. 11 Job Performance Measure Form ES-C-1 Worksheet Plant JPM P2
- 14. PERFORMANCE STEP: Place disconnect switches to LOCAL on CDE11A
........C........
STANDARD: Place all CDE11A disconnect switches in LOCAL position CUE: Disconnect switches have been placed in the LOCAL position on CDE11A SAT UNSAT
- 15. PERFORMANCE STEP: Place disconnect switches to LOCAL on CDYE2
........C........
STANDARD: Place all CDYE2 disconnect switches in LOCAL NOTE: Placing SPARE switch in LOCAL is not considered critical CUE: Disconnect switches have been placed in the LOCAL position (on CDYE2)
SAT UNSAT TERMINATING CUES: This JPM is complete (Terminated by the examiner)
END TIME NUREG-1021, Revision 11 Page 7 of 7