ES-401 PWR Examination Outline Form ES-401-2 Facility: DAVIS-BESSE NUCLEAR POWER STATION Date of Exam: February 2021 Tier Group RO K/A Category Points SRO-Only Points K1 K2 K3 K4 K5 K6 A1 A2 A3 A4 G*
Total A2 G*
Total
- 1.
Emergency and Abnormal Plant Evolutions 1
N/A N/A 3
3 6
2 2
2 4
Tier Totals 5
5 10
- 2.
Plant Systems 1
3 2
5 2
0 1
2 3
Tier Totals 4
4 8
- 3. Generic Knowledge and Abilities Categories 1
2 3
4 1
2 3
4 7
2 2
1 2
Note: 1.
Ensure that at least two topics from every applicable K/A category are sampled within each tier of the RO and SRO-only outline sections (i.e., except for one category in Tier 3 of the SRO-only section, the Tier Totals in each K/A category shall not be less than two). (One Tier 3 radiation control K/A is allowed if it is replaced by a K/A from another Tier 3 category.)
- 2.
The point total for each group and tier in the proposed outline must match that specified in the table. The final point total for each group and tier may deviate by +/-1 from that specified in the table based on NRC revisions. The final RO exam must total 75 points, and the SRO-only exam must total 25 points.
- 3.
Systems/evolutions within each group are identified on the outline. Systems or evolutions that do not apply at the facility should be deleted with justification. Operationally important, site-specific systems/evolutions that are not included on the outline should be added. Refer to Section D.1.b of ES-401 for guidance regarding the elimination of inappropriate K/A statements.
- 4.
Select topics from as many systems and evolutions as possible. Sample every system or evolution in the group before selecting a second topic for any system or evolution.
- 5.
Absent a plant-specific priority, only those K/As having an importance rating (IR) of 2.5 or higher shall be selected. Use the RO and SRO ratings for the RO and SRO-only portions, respectively.
- 6.
Select SRO topics for Tiers 1 and 2 from the shaded systems and K/A categories.
- 7.
The generic (G) K/As in Tiers 1 and 2 shall be selected from Section 2 of the K/A catalog, but the topics must be relevant to the applicable evolution or system. Refer to Section D.1.b of ES-401 for the applicable K/As.
- 8.
On the following pages, enter the K/A numbers, a brief description of each topic, the topics IRs for the applicable license level, and the point totals (#) for each system and category. Enter the group and tier totals for each category in the table above. If fuel-handling equipment is sampled in a category other than Category A2 or G* on the SRO-only exam, enter it on the left side of Column A2 for Tier 2, Group 2. (Note 1 does not apply). Use duplicate pages for RO and SRO-only exams.
- 9.
For Tier 3, select topics from Section 2 of the K/A catalog and enter the K/A numbers, descriptions, IRs, and point totals (#) on Form ES-401-3. Limit SRO selections to K/As that are linked to 10 CFR 55.43.
G* Generic K/As These systems/evolutions must be included as part of the sample (as applicable to the facility) when Revision 3 of the K/A catalog is used to develop the sample plan. They are not required to be included when using earlier revisions of the K/A catalog.
These systems/evolutions may be eliminated from the sample (as applicable to the facility) when Revision 3 of the K/A catalog is used to develop the sample plan.
ES-401 2
Form ES-401-2 ES-401 PWR Examination Outline Form ES-401-2 Emergency and Abnormal Plant EvolutionsTier 1/Group 1 (SRO)
E/APE # / Name / Safety Function K
1 K
2 K3 A1 A2 G*
K/A Topic(s)
IR 000007 (EPE 7; BW E02&E10; CE E02) Reactor Trip, Stabilization, Recovery / 1 01 EA2.1 - Ability to determine and interpret the following as they apply to the (Vital System Status Verification):
Facility conditions and selection of appropriate procedures during abnormal and emergency operations.
(CFR: 43.5 / 45.13) 4.0 1
000008 (APE 8) Pressurizer Vapor Space Accident / 3 000009 (EPE 9) Small Break LOCA / 3 000011 (EPE 11) Large Break LOCA / 3 000015 (APE 15) Reactor Coolant Pump Malfunctions
/ 4 000022 (APE 22) Loss of Reactor Coolant Makeup / 2 04-45 G2.4.45: Ability to prioritize and interpret the significance of each annunciator or alarm.
(CFR: 41.10 / 43.5 / 45.3 / 45.12) 4.3 2
000025 (APE 25) Loss of Residual Heat Removal System / 4 000026 (APE 26) Loss of Component Cooling Water /
8 77000027 (APE 27) Pressurizer Pressure Control System Malfunction / 3 000029 (EPE 29) Anticipated Transient Without Scram
/ 1 08 EA2.08 - Ability to determine or interpret the following as they apply to an ATWS: Rod bank step counters and RPI (CFR 43.5 / 45.13) 3.5 3
000038 (EPE 38) Steam Generator Tube Rupture / 3 000040 (APE 40; BW E05; CE E05; W E12) Steam Line RuptureExcessive Heat Transfer / 4 02-37 G2.2.37: Ability to determine operability and/or availability of safety related equipment.
(CFR: 41.7 / 43.5 / 45.12) 4.6 4
000054 (APE 54; CE E06) Loss of Main Feedwater /4 01-31 G2.1.31: Ability to locate control room switches, controls, and indications, and to determine that they correctly reflect the desired plant lineup.
(CFR: 41.10 / 45.12) 4.3 5
000055 (EPE 55) Station Blackout / 6 04 EA2.04 - Ability to determine or interpret the following as they apply to a Station Blackout: Instruments and controls operable with only dc battery power available (CFR 43.5 / 45.13) 4.1 6
000056 (APE 56) Loss of Offsite Power / 6 000057 (APE 57) Loss of Vital AC Instrument Bus / 6 000058 (APE 58) Loss of DC Power / 6 000062 (APE 62) Loss of Nuclear Service Water / 4 000065 (APE 65) Loss of Instrument Air / 8 000077 (APE 77) Generator Voltage and Electric Grid Disturbances / 6 (W E04) LOCA Outside Containment / 3 NOT APPLICABLE (W E11) Loss of Emergency Coolant Recirculation / 4 NOT APPLICABLE (BW E04; W E05) Inadequate Heat TransferLoss of Secondary Heat Sink / 4 K/A Category Totals:
0 0 0
0 3
3 Group Point Total:
6
ES-401 3
Form ES-401-2 ES-401 PWR Examination Outline Form ES-401-2 Emergency and Abnormal Plant EvolutionsTier 1/Group 2 (SRO)
E/APE # / Name / Safety Function K1 K2 K3 A1 A2 G*
K/A Topic(s)
IR 000001 (APE 1) Continuous Rod Withdrawal / 1 000003 (APE 3) Dropped Control Rod / 1 03 AA2.03 - Ability to determine and interpret the following as they apply to the Dropped Control Rod: Dropped rod, using in-core/ex-core instrumentation, in-core or loop temperature measurements (CFR: 43.5 / 45.13) 3.8 7 000005 (APE 5) Inoperable/Stuck Control Rod / 1 000024 (APE 24) Emergency Boration / 1 000028 (APE 28) Pressurizer (PZR) Level Control Malfunction / 2 000032 (APE 32) Loss of Source Range Nuclear Instrumentation
/ 7 000033 (APE 33) Loss of Intermediate Range Nuclear Instrumentation / 7 02-22 G2.2.22: Knowledge of limiting conditions for operations and safety limits.
(CFR: 41.5 / 43.2 / 45.2) 4.7 8 000036 (APE 36; BW/A08) Fuel-Handling Incidents / 8 000037 (APE 37) Steam Generator Tube Leak / 3 000051 (APE 51) Loss of Condenser Vacuum / 4 02 AA2.02 - Ability to determine and interpret the following as they apply to the Loss of Condenser Vacuum: Conditions requiring reactor and/or turbine trip (CFR: 43.5 / 45.13) 4.1 9 000059 (APE 59) Accidental Liquid Radwaste Release / 9 000060 (APE 60) Accidental Gaseous Radwaste Release / 9 000061 (APE 61) Area Radiation Monitoring System Alarms / 7 000067 (APE 67) Plant Fire On Site / 8 000068 (APE 68; BW A06) Control Room Evacuation / 8 000069 (APE 69; W E14) Loss of Containment Integrity / 5 000074 (EPE 74; W E06 & E07) Inadequate Core Cooling / 4 000076 (APE 76) High Reactor Coolant Activity / 9 000078 (APE 78*) RCS Leak / 3 (W E01 & E02) Rediagnosis & SI Termination / 3 NOT APPLICABLE (W E13) Steam Generator Overpressure / 4 NOT APPLICABLE (W E15) Containment Flooding / 5 NOT APPLICABLE (W E16) High Containment Radiation /9 NOT APPLICABLE (BW A01) Plant Runback / 1 (BW A02 & A03) Loss of NNI-X/Y/7 (BW A04) Turbine Trip / 4 (BW A05) Emergency Diesel Actuation / 6 (BW A07) Flooding / 8 (BW E03) Inadequate Subcooling Margin / 4 02-40 G2.2.40: Ability to apply Technical Specifications for a system.
(CFR: 41.10 / 43.2 / 43.5 / 45.3) 4.7 10 (BW E08; W E03) LOCA CooldownDepressurization / 4 (BW E09; CE A13**; W E09 & E10) Natural Circulation/4 (BW E13 & E14) EOP Rules and Enclosures (CE A11**; W E08) RCS OvercoolingPTS/ 4 NOT APPLICABLE (CE A16) Excess RCS Leakage / 2 NOT APPLICABLE (CE E09) Functional Recovery NOT APPLICABLE K/A Category Point Totals:
0 0
0 0
2 2
Group Point Total:
4
ES-401 4
Form ES-401-2 ES-401 PWR Examination Outline Form ES-401-2 Plant SystemsTier 2/Group 1 (SRO)
System # / Name K1 K2 K3 K4 K5 K6 A1 A2 A3 A4 G*
K/A Topic(s)
IR 003 (SF4P RCP) Reactor Coolant Pump 004 (SF1; SF2 CVCS) Chemical and Volume Control 005 (SF4P RHR) Residual Heat Removal 006 (SF2; SF3 ECCS) Emergency Core Cooling 04 A2.04 Ability to (a) predict the impacts of the following malfunctions or operations on the ECCS; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Improper discharge pressure. (CFR: 41.5 / 45.5) 3.8 11 007 (SF5 PRTS) Pressurizer Relief/Quench Tank 008 (SF8 CCW) Component Cooling Water 010 (SF3 PZR PCS) Pressurizer Pressure Control 012 (SF7 RPS) Reactor Protection 02-25 G2.2.25: Knowledge of the bases in Technical Specifications for limiting conditions for operations and safety limits. (CFR: 41.5 / 41.7 / 43.2) 4.2 12 013 (SF2 ESFAS) Engineered Safety Features Actuation 022 (SF5 CCS) Containment Cooling 025 (SF5 ICE) Ice Condenser NOT APPLICABLE 026 (SF5 CSS) Containment Spray 039 (SF4S MSS) Main and Reheat Steam 059 (SF4S MFW) Main Feedwater 12 A2.12 - Ability to (a) predict the impacts of the following malfunctions or operations on the MFW; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Failure of feedwater regulating valves (CFR: 41.5 / 43.5 / 45.3 / 45.13) 3.4 13 061 (SF4S AFW) Auxiliary/Emergency Feedwater 062 (SF6 ED AC) AC Electrical Distribution 04-41 G2.4.41: Knowledge of the emergency action level thresholds and classifications. (CFR: 41.10 / 43.5 /
45.11) 4.6 14 063 (SF6 ED DC) DC Electrical Distribution 064 (SF6 EDG) Emergency Diesel Generator 06 A2.06 - Ability to (a) predict the impacts of the following malfunctions or operations on the ED/G system; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Operating unloaded, lightly loaded, and highly loaded time limit (CFR: 41.5 / 43.5 / 45.3 / 45.13) 3.3 15 073 (SF7 PRM) Process Radiation Monitoring 076 (SF4S SW) Service Water 078 (SF8 IAS) Instrument Air 103 (SF5 CNT) Containment 053 (SF1; SF4P ICS*) Integrated Control NOT APPLICABLE K/A Category Point Totals:
0 0
0 0
0 0
0 3
0 0
2 Group Point Total:
5
ES-401 5
Form ES-401-2 ES-401 PWR Examination Outline Form ES-401-2 Plant SystemsTier 2/Group 2 (SRO)
System # / Name K1 K2 K3 K4 K5 K6 A1 A2 A3 A4 G*
K/A Topic(s)
IR 001 (SF1 CRDS) Control Rod Drive 002 (SF2; SF4P RCS) Reactor Coolant 011 (SF2 PZR LCS) Pressurizer Level Control 014 (SF1 RPI) Rod Position Indication 015 (SF7 NI) Nuclear Instrumentation 02-36 G2.2.36: Ability to analyze the effect of maintenance activities, such as degraded power sources, on the status of limiting conditions for operations.
(CFR: 41.10 / 43.2 / 45.13) 4.2 16 016 (SF7 NNI) Nonnuclear Instrumentation 017 (SF7 ITM) In-Core Temperature Monitor 02 A2.02 - Ability to (a) predict the impacts of the following malfunctions or operations on the ITM system; and (b) based on those predictions, use procedures to correct, control or mitigate the consequences of those malfunctions or operations: Core damage (CFR: 41.5 / 43.5 / 45.3 / 45.5) 4.1 17 027 (SF5 CIRS) Containment Iodine Removal NOT APPLICABLE 0
028 (SF5 HRPS) Hydrogen Recombiner and Purge Control NOT APPLICABLE 0
029 (SF8 CPS) Containment Purge 033 (SF8 SFPCS) Spent Fuel Pool Cooling 034 (SF8 FHS) Fuel-Handling Equipment 035 (SF 4P SG) Steam Generator 041 (SF4S SDS) Steam Dump/Turbine Bypass Control 045 (SF 4S MTG) Main Turbine Generator 02-12 G2.2.12: Knowledge of surveillance procedures. (CFR: 41.10 / 45.13) 4.1 18 055 (SF4S CARS) Condenser Air Removal 056 (SF4S CDS) Condensate 068 (SF9 LRS) Liquid Radwaste 071 (SF9 WGS) Waste Gas Disposal 072 (SF7 ARM) Area Radiation Monitoring 075 (SF8 CW) Circulating Water 079 (SF8 SAS**) Station Air 086 Fire Protection 050 (SF 9 CRV*) Control Room Ventilation NOT APPLICABLE 0
K/A Category Point Totals:
0 0
0 0
0 0
0 1
0 0
2 Group Point Total:
3
ES-401 Generic Knowledge and Abilities Outline (Tier 3)
Form ES-401-3 Facility: DAVIS-BESSE NUCLEAR POWER STATION Date of Exam: February 2021 Category K/A #
Topic RO SRO-only IR Q#
IR Q#
2.1.4 Knowledge of individual licensed operator responsibilities related to shift staffing, such as medical requirements, no-solo operation, maintenance of active license status, 10CFR55, etc.
(CFR: 41.10 / 43.2) 3.8 19 2.1.6 Ability to manage the control room crew during plant transients.
(CFR: 41.10 / 43.5 / 45.12 / 45.13) 4.8 20 Subtotal 2
2.2.21 Knowledge of pre-and post-maintenance operability requirements. (CFR: 41.10 / 43.2) 4.1 21 2.2.36 Ability to analyze the effect of maintenance activities, such as degraded power sources, on the status of limiting conditions for operations. (CFR: 41.10 / 43.2 / 45.13)
K/A Change to 2.2.11 4.2 22 Subtotal 2
2.3.6 Ability to approve release permits. (CFR: 41.13 / 43.4 / 45.10) 3.8 23 Subtotal 1
2.4.40 Knowledge of SRO responsibilities in emergency plan implementation. (CFR: 41.10 / 43.5 / 45.11) 4.5 24 2.4.44 Knowledge of emergency plan protective action recommendations. (CFR: 41.10 / 41.12 / 43.5 / 45.11) 4.4 25 Subtotal 2
Tier 3 Point Total 7