3F0197-10, Revises Date Established for Implementation of post-fire Safe SD Analysis Changes as Resolution of Thermo-Lag Fire Barrier Issues

From kanterella
Revision as of 19:58, 14 December 2021 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Revises Date Established for Implementation of post-fire Safe SD Analysis Changes as Resolution of Thermo-Lag Fire Barrier Issues
ML20134C377
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 01/29/1997
From: Boldt G
FLORIDA POWER CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
3F0197-10, 3F197-10, NUDOCS 9702030049
Download: ML20134C377 (9)


Text

. .

4

@ l l

Florida l Power CORPORATION oysw Fe w una a i Dodd Nu. p302 l l

January 29, 1997 1 3F0197-10 l

U.S. Nuclear Regulatory Commission Attention: Document Control Desk I Washington, D.C. 20555-0001

Subject:

Resolution of Thermo-Lag Issues

References:

A. FPC to NRC letter, 3F1295-05, dated December 21, 1995 B. FPC to NRC letter, 3F0996-19, dated September 27, 1996 l C. FPC to NRC letter, 3F1296-05, dated December 16, 1996 1

Dear Sir:

In Reference A, Florida Power Corporation (FPC) described our proposed plan for resolution of Thermo-Lag fire barrier issues at Crystal River Unit 3 (CR-3). A key element of our Thermo-Lag resolution strategy is reducing the plant's reliance on fire barriers through revision of the post-fire safe shutdown analysis based, in part, on using offsite power sources for post-fire safe shutdown.

Our evaluation of fire-induced failure of circuits that could adversely impact the use of offsite power sources, identified a concern with current transformers (cts) associated with the 4kV switchgear. Resolution of this issue will delay implementation of the analysis changes intended to reduce reliance on Thermo-Lag.

As a result, this letter revises the date established in Reference B for implementation of the post-fire safe shutdown analysis changes.

\

' \'

pe CRYSTAL RNER ENERGY COMPLEX: 15760 W Power une St . Crystal River. Florida 344284708 + (352) 7954486 A Florida Progress Company 9702030049 970129 PDR ADOCK 05000302 P ,

PDR

U. S. Nuclear Regulatory Commission 3F0197-10 Page 2 of 2 In Reference C, Attachment B, FPC committed to resolve the CT issues prior to restart from our current outage. The analysis changes described in Reference A will be completed within 90 days after restart. This additional delay will not impact our completion date for full resolution of Thermo-Lag issues scheduled for December 29, 2000. The attached Thermo-Lag Resolution Implementation Plan flow chart, milestone chart, and project schedule are provided for information, and are being utilized to track CR-3 Thermo-Lag resolution activities and scheduled commitments.

Please contact W. L. Rossfeld at (352) 563-4374 'if you have any questions concerning this submittal.

Sincerely, G. L. B ldt Vice President Nuclear Production Attachments xc: Regional Administrator, Region II Senior Resident Inspector NRR Project Manager I

l l

l I

4

U. S. Nuclear Regulatory Commission 3F0197-10 1/23/97

. Page 1 of 1 1

Attachment 1 FLORIDA POWER CORPORATION 1

THERMO-LAG RESOLUTION IMPLEMENTATION PLAN RESOLUTION EVALUATION & SELECTION (SAFETY BENElslT/ COST EVALUATION)

Analysis Changes Circuit Reroutes Repair Procedure Mecatiss Exemptions Ampacity j 'R format MARS MAR to Support Nub '/ NSubmit/ lNestin(]

-8BOs Prepare Repair Activities TesfRe s Exetn on

, ,__ Package ____ f[equestA l ' Associated Perform Work V V l l Calculations l V Ci its Draft Procedure NRC y l Document Chiculati Changes

& Review NRC T Work Order l Review l 'Re:xxtIl l

Fire V 'Mecatiss' Y Y y Protection issue Procedure ,1nstalla MAR l NRC Review l N

Issue Deviations & Prpp re' If needed Update Work Order g MA _ Prepare AP-880 install _ Package _

4 Perform Work l

V V V V V V V V THERMO-LAG FIRE DARRIERS RESOLVED I l l l l V V V V V V Revise Update Fire Update Assess Fire Close Barrier Terminate 3

Fire Study Topical DBC l

FHA J Protection Program Breaches Fire Tours

~

V Update Barrier

. Surveillance Proc.

Florida Power Corporation W. L Rossfeld M

U. S. Nuclear Regulatory Commission 3F0197-10 Page 1 of 4 accacnment 4 TIIERMO-LAG RESOLUTION IMPLEMENTATION MII ESTONES AS OF JANUARY 17,1997 Responsible Due Task Task Description Team Date Status

1. Reformat AP-880 to reflect availabJe equipment per current Fire Study (39 fire Complete areas / zones)
2. Prepare packages for analysis changes (6 document and drawing packages) B. Spear Restart In progress D. Rhoads + 60 days 75% complete N. Fioravante 07/31/97

! 3. Issue AP-880 with analysis changes incorporated (38 fire areas / zones) G. Becker Restart In progress l N. Fioravante + 60 days 50% complete t

D. Rhoads 08/29/97 4a. Complete Multiple liigh Impedance Fault Calculations Complete 4b. Review Fire-Induced Spurious Operation Evaluation Complete

5. Prepare Fire Protection Engineering Evaluations for openings in fire area L. Dymek Resian In progress boundaries (7 evaluations) + 60 days 80% complete 06/30/97 6a. Part 1 - Prepare conceptual designs for circuit reroutes (13 designs) Complete 6a. Part 2 - Prepare MARS for cable reroutes (13 MARS) C. Kish 12/29/00 In progress B. Spear 6b. Prepare work packages for cable reroutes (13 MARS) C. Kish 12/29/00 B. Spear 6c. Perform work for cable reroutes (13 MARS) C. Kish 12/29/00 B. Spear B

.e4 -- ,-=s- 1 -, w 9 r -m ,- %-y y .. ,- -. -- y , , c. y,. ,,, ,, , ,-.w,- ,, __ ---i- m M * - - w

U. S. Nuclear Regulatory Comission 3F0197-10 Page 2 of 6 s e e new e ,

TilERND-LAG RESOLUTION IMPLEMENTATION MILESTONES AS OF JANUARY 17,1997 Responsible Due Task Task Description Team Date Status 6d. Breaker and fuse changes to support high impedance fault calculation C.Kish 12/29/00 In progress B. Spear

7. Prepare, schedule and perform MAR to support cold shutdown repair (1 MAR) C. Kish 12/29/00 B. Spear
8. Draft cold shutdown repair procedures and maintenance work orders (4 C. Kish 9/28/00 procedures) B. Spear G. Becker
9. Issue cold shutdown repair procedures and maintenance work orders (4 C. Kish 12/29/00

[ procedures) B. Spear G. Becker 10a. Complete testing program for Mecatiss and submit test packages to the NRC Complete 10b. Complete additional fire tests for Mecatiss and submit test packages to the '*RC Complete

11. Suppon NRC review of test packages W. Rossfeld In progress L. Dymek S. Powell 12a. Prepare MAR for installation of Mecatiss (1 MAR) Complete 12b. Prepare work packages for installation of Mecatiss (1 MAR) Complete 12c. Install Mecatiss

' W. Rossfeld ,

Complete E. Bosworth M AR close-out in progress G

e

( - _ _ _ _ _

l U. S. Nuclear Regulatory Commission i 3F0197-10 l Page 3 of 6 i s..,

j t___. 3 TIIERMO-LAG RESOLUTION IMPLEMENTATION MILESTONES

AS OF JANUARY 17,1997 l

Responsible Due l Task Task Description Team Date Status

13. Submit exemption request to the NRC (4 new exemptions, revise 2 existing W. Rossfeld 09/30/97 In progress
exemptions and delete 2 existing exemptions) L. Dymek 65% complete j [The new exemptions have been submitted. He remaining effort is related to S. Powell

! revising and deleting existing exemptions.] N. Fioravante i

! 14. Support NRC review of exemption request W. Rossfeld 03/31/97 in progress l L. Dymek 4

S. Powell .

15. Prepare MARS if needed to resolve NRC concerns with exemption request W. Rossfeld 12/29/00 Waiting NRC Review L. Dymek 15a. Resolve Thermo-Lag in the Reactor Building Complete 16a. Complete ampacity testing program Complete 16b. Finalize ampacity calculations for Thermo-Lag and Mecatiss configurations D. Kelly 06/30/97 In progress B. Spear 5% complete 16c. Submit preliminary report for ampacity Complete 16d. Support NRC review of ampacity report B. Spear 03/31/97 In progress S. Powell
17. Revise Fire Study Report to reflect resolution ofDermo-12g C. Kish 09/30/97 B. Spear N. Fioravante I 8. Revise Appendix R DBD to reflect resolution ofThermo-Lag C. Kish 09/30/97 B. Spear N. Fioravante 4

t

U. S. Nuclear Regulatory Commission 3F0197-10 Page 4 of 4 A t t a c hme ri e 2 TIIERMO-LAG RESOLUTION IMPLEMENTATION MILESTONES AS OF JANUARY 17,1997 Responsible Due Task Task Description Team Date Status

19. Revise Fire Hazards Analysis to reflect resolution ofThermo-Lag L. Dymek 12/31/97
20. Assess Fire Protection Program with respect to commitment made during the L. Dymek 12/31/97 exemption process and to reflect the resolution ofThemio-Lag
21. Update Fire Barrier surveillance procedure H. Howard 12/29/00
22. Close Thermo-Lag breaches J. Russell 12/29/00
23. Terminate Thermo-Lag Fire Tours W. Rossfeld 1329/00 9

0

.t O

_._..___._ _ __ _ v _____. _ _ . _ ___

U. S. Nuclear Regulatory Commission Attachment 3 3F0197-10 Page 1 of 2. THERMO-LAG RESOLUTION IMPLEMENTATION PLAN 1997 1998 ID Task Name Start Finish Jan l Feb l Mar l Apr l May l Jun l Jul l Aug l Sep l Oct l Nov l Dec Jan l Feb l Mar l rpr ] May l Jun l Jul 1 Analysis Changes 1111/95 8/29197 2 Task 1- Re-format AP-880 11/185 4906 .

3 Task 2- Document Changes 11/105 7/3107 m ;q 4 Task 3-Issue AP-880 41S6 8/2987 g q 5 Task 4a - Multiple Fauft Caic. 11/1/96 8/15S6 ,

8 Task 4b - Spurious Signal Calc. 6066 100Q96  :

7 Task 5 - F.P. Deviations 11/185 60097 q 8 Circuit Retoutes 811/9 6 12/29/00 , .

9 Task 6a - Conceptual Designs 8/1B6 12/31/96 ,

10 Task 6a - Prepare MARS 1/1 B 7 12/2900  ;;

11 Task 6b-Work Packages 6/30S7 12/2900 g Task 6c - Perform Work 90007 12/2900 12 p' 13 Task 6d - Breaker / fuse Change 1/1B7 12/3KD .. p 14 Repair Procedure 1/1/98 12/29/00 15 Task 7- MAR for Repairs 1/1/98 12/2900 j h 16 Task 8 - Draft Procedure 60006 9/2800 ,

l'-'

17 Task 9 - Issue Procedure 10f200 12/2900 -

18 Mecatiss 12/11/95 3/31197 19 Task 10a - Submd Test Packag 12/1106 NIS6 -

20 Task 10 b - Additonal Tests 1/2S6 10rmS6 21 Task 11 - NRC Review 4/2S6 3/31G 7 :  ;, q Task ljc -l Summary Rolled Up Progress -

Fbrida Power Corporaton Progress - Rolied Up Task l! il Date: 1/23G7 MJestone k Roned Up Milestone <

- Page1

U. S. Nuclear Regulatory Commission Attachment 3 3F0197-10 Page 2 of 2 THERMO-LAG RESOLUTION IMPLEMENTATION PLAN 1997 1998 ID Task Name Start Finish Jan l Feb l Mar l Apr l May l Jun l JJ l Aug l Sep l Oct l Nov l Dec Jan l Feb l Mar l Apr l May ] Jun l Jul 22 Task 12a - Prepare MAR 1/2S6 5/27S6  :

23 Task 12b -Work Packages 5/2106 6/496  :

24 Task 12c - Install Mecatrss 6/2006 12/31S 6 f

~ "'

25 Exemptions 11/1/95 26 Task 13 - Submd Exemptions 11/105 90097 gg -

g 27 Task 14- NRC Review 6/2496 3/31 S 7 g q 28 Task 15- Prepare MAR. if need 4/187 12/2900 j p;';

29 Task 15a - Remove TSIin RB 2/IS6 45S6  :

30 Ampacity 11/1/95 6/30197 31 Task 16a - Complete Testing 11/1S 5 5/15M  :

32 Task 16b - Finaltre Calculatons 2/1G6 60007  :

.; p g 33 Task 16c - Submit Prelim. Repc 6G96 6/28 S 6  :

34 Task 16d - NRC Revkw 7/1S6 30187 g q 35 Close-out Activities 711/97 12/29/00 '

36 Task 17 - Revise Fire Study 7/187 90057 g g 37 Task 18 - Revise App. R D8D 7/1S7 90097 .

g; q 38 Task 19- Revise FHA G0097 12/31 S 7 g.g 3;j 39 Task 20- Assess F.P. Program 1G187 12/3187 { g ;; .;j.

40 Task 21 - Update Barrier Survel  ;

101S7 12/2900 p g_

41 Task 22 - Close TSI Breaches 1GIS7 12/2900 g3 42 Task 23 - Terminate TSI Fire Tt 1GIS7 12/2900 l5 W. L Rossfeld Task l: il F Summary Rolled Up Progress -

Florida Power Corporation Progress - Rolled Up Task l ii JJ

  • Date:1/2397

, Milestone $ Rolled Up Milestone Q Page 2