Forwards Status Rept for Aug 1988 Re Std Plant Design Technical Reviews
ML20154E405
Person / Time
Site: 05000000, 05000605, 05000601
Issue date: 09/14/1988
From: Chris Miller
Office of Nuclear Reactor Regulation
To: Congel F, Grimes B, Houston R, Rowe J, Shao L
Office of Nuclear Reactor Regulation, NRC OFFICE OF NUCLEAR REGULATORY RESEARCH (RES)
References
PROJECT-669R, PROJECT-675R, PROJECT-676R NUDOCS 8809160315
Download: ML20154E405 (16)


Text

-

8# og UNITED STATES

!" o - -

N!! CLEAR REGULATORY COMMISSION

, [4

- ,I W ASHING TON. D. C. 20555

%... ,* September 14, 1988 Docket No. 50-601 and 50-605 Project Nos. 669, 675, and 676 MEMORANDUM FOR: L. Shao, Director Division of Engineering and System Technology, NRR B. Grimes, Director Division of Reactor Inspection and Safeguards, NRR F. Congel, Director Division of Radiation Protection -

and Emergency Preparedness, NRR J. Roe, Director Division of Licensee Performance and Quality Evaluation, NRR R. W. Houston, Director Division of Safety Issue Resolution, RES B. Sheron, Director Division of Systems Research, RFS FROM: Charles L. Miller, Acting Director Standardization and Non-Power Reactor Project Directorate Division of Reactor Projects III, IV, Y and Special Projects, NRR

SUBJECT:

STATUS REPORT ON STANDARD PLANT DESIGN TECHNICAL REVIEWS Attached is the August status report concerning the current review milestones for each of the standard plant projects (EPRI, ABWit, RESAR SP/90, and CE System 80+).

Note the "Due Date" column reflects dates established in the January 25, 1988 "Revised Program Plan For Standard Plant Reviews" or dates for which modifica-tion was agreed to by PDSNP and the review branch.

/

8809160315 DR 680914 ADOCK 05000601 PDC s CONTACT: F Ig T. Kenyon, NRR/PDSNP tk g 492-1120 \ /(

September 14, 1988 The column "Expected Input Date" reflects input from appropriate technical branch managenent. Category 1 items have been discussed with the appropriate Assistant Directors. I request any problems in meeting these input dates be identified te re by the appropriate Assistant Director within a week of receipt of this meno.

Yo. c, lN L. b Charles L. Miller, Acting Director Standardization and Non-Power Reactor Project Directorate Division of Reactor Projects III, IV, Y and Special Projects, NRR

Enclosure:

As stated cc: T. Murley J. Sniezek F. Miraglia D. Crutchfield L. Rubenstein J. Richardson C. Y. Cheng L. B. Marsh C. McCracken l A. Tnada'11 J. Joyce J. Mauk ,

F. Rosa J. Craig M. W. Hodges B. Grimes R. Erickson I D. Matthews R. Barrett L. Cunningham J. Zwolinski S. Weiss W. Regan, Jr.

J. Murphy G. Bagchi S. Newberry o l 1

l

Sept mber 14, 1988 t

The column "Expected Input Date" reflects input from appropriate technical branch management. Category 1 items have been discussed with the appropriate Assistant Directors. I request any problems in meeting these input dates be identified to me by the appropriate Assistant Director within a week of receipt of this memo.

l Charles L. Miller, Acting Director i Standardization and Non-Power Reactor Project Directorate Division of Reactor Projects III, IV, Y and Special Projects, NRR t

Enclosure:

l As stated cc: T. Murley '

J. Sniezek l F. Miraglia  !

D. Crutchfield '

L. Rubenstein ,

J. Richardson l C. Y. Cheng L. B. Marsh C. McCracken A. Thadani J. Joyce J. Mauk F. Rosa .

J. Craig H. W. Hodges

! B. Grimes  !

R. Erickson l

.i D. Matthews  !

R. Barrett l L. Cunningham .

J. Zowlinski '

, S. Weiss W. Regan, Jr.

J. Murphy G. Easchi ,

S. Newberry D.STRIBUTION:

pocaat Fue. j EHylton l NRC POR DScaletti l PDSNP Reading TKenyon i GVissing RLong  ;

Chiller l P AD:PDSNP on:cw Cililler g/88 Of////88 -

D:t2: August 26, 1988

~~.

REVIEW STATUS REPORT ON .

WESTINGHOUSE RESAR SP/90 - -

PDA REVIEW Expected Division / Due Input Brecch Reviewer Modules Subject

  • Milestone Date Date Cat.** Comments DEST /EMTB Johnson 1, 4, 5, 688, 7, Materials Engineering Draft SER 3/31/88 4/29/88 4 Complete 10 to P.M. 5/5/83

, DEST /EMEB Rajan/Braaner*** 1, 4, 5, 7, Mechanical Engineering Draft SER 9/30/88 9/30/88 2 W Input

  • l to P.M. rec'd 7/6/88 l

j DEST /ESGB Staley 3 Hydrology Draft SER 3/31/88 3/30/88 4 Complete to P.M.

l l Giese-Koch 3 Geology & Seismology Draft SER 3/31/88 3/30/88 4 Complete l

to P.M.

t l Chan 7 Civil Engineering Draft SER 4/29/88 4/28/88 4 Complete l to P.M.

1

  • See September 29, 1987 memo for complete listing of review assignments
    • Category definitions:

1 1. AD or above attention requested

2. Branch Chief attention requested
3. On schedule
4. Complete
      • Brasser providing assistance l- _ _ _ _ _ - - - - - _ _ - - - _ _ - - - - _ - _ _ _ _ _ _ _ _ _ -_- ..

. _ - _ - _ - _ _ . - =

. - - . _ _ . =_ -. . . _ - . _ . . _ . _ _ _ _ _ - .. .. -

Datt: August 26, 1988 REVIEW STATUS REPORT ON

~

WESTINGHOUSE RESAR SP/90 . .

PDA REVIEW (Cont.)

Expected Division / Due Input Brtnch Reviewer Modules Subject

  • Milestone Date Date Cat.** Comments DEST /ECEB Wing 1, 688, 10, 13 Chemical Engineering Draft SEP. 3/31/88 3/17/88 4 Complete Notley 13 Fire Protection Draft SER 7/15/88 9/01/88 4 Complete to P.M.

DEST /SICB Burrows 9, 13, 15 Instrumentation & Draft SER 3/31/88 4/07/88 4 Complete Controls to P.M.

DEST /SELB Trehan 9, 13 Electrical Engineering Draft SER 3/31/88 4/13/88 4- Complete to P.M.

DEST /SPLB Shum (lead) 1, 10, 13 Containment Systems Draft SER 6/21/88# 6/21/88 4 Complete to P.M.

  • See September 29, 1987 memo for complete listing of review assignments

" Category def4nitions:

1. AD or above attention requested 1 2. Branch Chief attention requested l 3. On schedule 1 4. Orplete

Date: Argust 26, 1988 REVIEW STATUS REPORT ON WESTINGHOUSE RESAR SP/90 , .

PDA REVIEW - -

(Cont.)

l Expected l Division / Due Input i Brcnch Reviewer Modules Subject

  • Milestone Date Date Cat.**

t Conunents l

DEST /SPLB Wagner 688, 7 Plant Systems Draft SER 6/21/88 6/21/88 4 Complete

! (cont.) to P.M.

Walker 7 Equipment Qualification Draft SER 6/21/88 6/21/88 4 Complete to P.if.

l Gill 4 Plant Systems Draft SER 6/21/88 6/21//88 4 Complete to P.M.

Lee 6&8, 10, HVAC Systems, Waste Draft SER 6/21/88 6/21/88 4 Complete 12, 13 Management, Steam & to P.M.

Power Conversion See Septes6er 29,1987 memo for complete listing of review assignments

    • Category definitions:
1. AD or above attention requested
2. Branch Chief attention requested
3. On schedule
4. Complete l

- - . . -.-=_.- - -._- __- - - - _ _ _ - - - = _ . - . - _ - ... - - _-. .

e Date: Aug:st 26, 1988 REVIEW STATUS REPORT ON WESTINGHOUSE RESAR SP/90 , ,

PDA REVIEW (Cont.)

Expected Division / Due Input Branch Reviewer Modules Subject

  • Milestone Date Date Cat.** Cowenents DEST /SPLB Raval 13 Plant Systems Draft SER 6/21/88 6/21/88 4 Complete (cont.) to P.M.

DEST /SPL8 Tinkler 16 PRA Review DSER 11/14/88 11/14/88 3 re: PRA l

DEST /SRX8 Liang 1, 4, 5, 6&8, Reactor Systems Draft SER 6/28/88 6/28/88 4 Complete 9, 10, 11, 12 to P.M.

DEST /SRIB Liang 16 PRA Review DSER 11/14/88 11/14/88 3 Reviewer.

l re: PRA providing i Assistance to l

SPLB DRIS/RSG8 Mendelsohn 2 Physical Security Draft SER 3/31/88 3/22/88 4 Complete to P.M.

DLPQ/LQAB Spraul 13 Quality Assurance Draft SER 4/29/88 4/06/88 4 Complete I

to P.M.

l

  • See September 29, 1987 memo for couplete listing of review assignments
    • Category definitions:

1 1. AD er above attention requested

2. Branch Chief attention requested i 3. On schedule 1 4. Complete

=

--- -- - - ---- -----_,---,-r---,-- , - - - . + - ,.-,- ----w w

,-m--- ,- , .,,m- --- , ,-

_ _ - _ . ~_ -. _ _-_.__. _ . - - - - -_ - _ _ _ . . _ . . __ __ = _ - - _ . __ _ _ _ _ _ _ _ . . . .. .

Date: A gust 26, 1988 REVIEW STATUS REPORT DN .

WESTINGHOUSE RESAR SP/90 - -

PDA REVIEW (Cont.)

Expected Division / Due Input Branch Reviewer Modules Subject

  • Milestone Date Date Cat.** Comments DLPQ/LHF8 Lapinski 15 Control Room / Human Draft SER 3/31/88 5/05/88 4 Complete Factors Engineering to P.M.

DREP/PRF8 Spickler 1, 3, 4, 5, Radiologi al Accident 6A8, 9, 10 Analysis Draft SER 8/01/88 8/12/88 4 Complete to P.M.

Skopec 12 Process & Effluent Radiological Draft SER 7/15/88 7/13/88 4 Complete to P.'M.

Monitoring & Sampling Systems DREP/PRAB Margulies 16 PRA Review DSER 11/14/88 11/14/88 3 re: PRA RES/PRA Chellfah/BNL 16 Probabilistic Safety Draft 7/15/88 7/15/88 4 Complete Study - back end SER to P.M.

s See Septe & r 29, 1987 meno for complete listing of review assignments

! ** Category definitions:

1. AD or above attention requested
2. Branch Chief attention requested
3. On schedule
4. Complete

Dato: August 26, 1988 REVIEW STATUS REPORT ON ,

CE SYSTEM 80+

CESSAR-DC REVIEW i . .

Expected Division / Due Input Branch Reviewer Chapter Subject Milestone Date Date ' Cat.* Comments DEST /0MTB M. Hun 4 Rev 8 Reactor RAI 07/10/88 09/12/88 2

{ DEST /EMEB J. Rajan 5 Rev B Reactor Coolant System RAI 07/10/88 08/22/88 4 DEST /EMTB M. Hun 5 Rev 8 Reactor Coolant System RAI 07/10/88 09/12/88 2

! DEST /SPLB J. Raval 5 Rev B Reactor Coolant System RAI 07/10/88 07/29/88 4 DEST /SPLB J. Raval 9 Rev B Auxiliary System RAI 07/10/88 07/29/88 4 DEST /0MEB J. Rajan 5 Rev C Reactor Cooling System RAI 09/30/88 09/30/88 3 DEST /SRIB L.Kopp 5 Rev C Reactor Cooling System RAI 09/30/88 09/30/88 3

DEST /ENTB M. Hum 5 Rev C Reactor Coolant System RAI 09/30/88 09/30/88 3 DEST /SPLB J. Raval 5 Rev C Reactor Coolant System RAI 09/30/88 09/30/88 3

, DEST /ECEB F. Witt 5 Rev C Reactor Coolant System RAI 09/30/88 09/30/88 3 DEST /SPLB J. Raval 6 Rev C Engineered Safety Features RAI 09/30/88 09/30/88 3 DEST /ECEB F. Witt 6 Rev C Engineered Safety Features RAI 09/30/88 09/30/88 3 DEST /EMTB M. Hun 6 Rev C Engineered Safety Features RAI 09/30/88 09/30/88 3 DEST /SPLB J. Raval 10 Rev C Steam 8 Power Conversion RAI 09/30/88 09/30/88 3

- System DEST /ECEB F. Witt 10 Rev C Steam & Power Conversion RAI 09/30/88 09/30/88 3 System

l .' .

l Date: August 26, 1988 REVIEW STATUS REPORT ON ,

CE SYSTEM 80+

CESSAR-DC REVIEW Expected Division / Due Input Branch Reviewer Chapter Subject Milestone Date Date Cat.* Comments DEST /ENT8 M. Hun 10 Rev C Steam & Power Conversion RAI 09/30/88 09/30/88 3 Systen RES/DRAA/ E. Che111ah Base Line Base Line PRA Cossents 10/30/88 10/30/88 3 PRAB PRA o CCtegory definition:

1. AD or above attention requested
2. Branch Chief attention requested
3. On schedule
4. Complete 9 Input delayed due to availability of reviewer.

l-__..-- _ - _ . -.- .-- . -. - - -

e Data: August 26, 1988 REVIEW STATUS REPORT ON '

SYSTEM 80 CESSAR-F REVIEW i

Expected

  • Division / Due Input Branch Reviewer Chapter Subject Milestone Date Date Cat.* Comoents DEST /SRIB C. Liang TAC 66400, AEPSS ISSUE Final SER open open 3 Wating res-to P.M. ponse from CE on RAI DEST /EM B J. Rajan TAC 66401, Steam Cen. Tube Vibration RAIs to open open 3 Waiting res-P.M. ponse from Cf. on RAI DEST /EMTB W. Wickman TAC 66401, Steam Gen. Tube Vibration RAls to open open 3 Waiting res-P.M. ponse from CE on RAI DREP/PRP8 I. Spickler TAC 66400 ASPSS ISSUE (SGT Rupture) Final SER open open- 3 to SRXB/PM s
  • Cat = gory deffaition:
1. AD or a*:sre attention requested
2. Branch Citief attention requested
3. On schedsle
4. Cosplete
    • Close out issue

I l

  • Dat2: August 26, 1988

~

REVIEW STATUS REPORT ON CE SY5itM 80+ '

CESSAR-DC REVIEW -

ARSAP TOPIC PAPERS Expected Division / Due Input Branch Reviewer Chapter Subject ._

Milestone Date Date Cat.* Comments l RES/SAIB C. Ferrell Topic Paper Set 10 ARSAP Issues RAI 06/15/88 08/01/88 1 Comunents -

l No. I provided l

CE at meeting 6/21/88 RES/SAIB C. Ferrell, et al Topic Paper Set 6 ARSAP Issues RAI 08/30/88 08/30/88 3 No. 2 RES/SAIB C, Ferrell, et al Topic T ' r Set 3 ARSAP Issues RAI 09/30/88 09/30/88 3 No. 3 o Category definition:

1. A0 or above attention requested
2. Branch Chief attention requeste<t
3. On schedule
4. Complete

I I

e Date: August 26, 1988 REVIEW STATUS REPORT tNE GE ABWR FDA/DC REVIEW .

Expected Division / SRP Due Input -

Branch , ,

1 Chapter Subject Milestone Date. , Date Cat.* Comments j DEST / Sri ' re v6 - ra" 4, 5, 6, 15 Plant Systems RAIs to 6/30/88 6/30/88 4 P.M.

DEST /SPLC Ches 1 y; an 3 i sant Systems RAls to 6/30/88 8/18/88 4 New Input P.M. established (memo 7/1/88)

RAIs are being i

j DEST /SRXB Thomas 5, 6, 15 Reactor Systems RAls to 6/30/88 10/01/88 3 discussions on

' P.M. SER input date are being carried out. We have 1

proposed a final scheduie so as not to slip the SER issue date (3/30/89), DEST r

has agreed to the proposed schedule DEST!i.cEB Witt 7,8,9,11,12,13, Chemical Engineering RAIs To 9/30/88 S/14/88 4

! 14, 8 17 P.M.

~

  • Cctegory definitions:
1. AD or above attention requested
2. Branch Chief attention requested
3. On schedule

? 4. Complete

_ - , _ - - - - - - y -- -- _

Date: August 26, 1988 i

~

REVIEW STATUS REPORT ON GE ABWR FDA7DC' REVIEW (Cont.)

Expected

  • Division / SRP Due Input Srrnch Reviewer Chapter Subject Milestone Date Date Ca t.
  • Comunents DREP/PRPB Brown 15 Radiation Protection Draft 7/31/S8 9/30/88 3 8/19/88 meno
SER cosimitting to to 9/30/88 SER input DREP/PRPB browa 2 I;eteorology RAI to 6/30/88 6/2S/88 4 P.M.

DEST /EMEB Rajan 4, 5, 6, 15 Mechanical Engineering Draft 7/31/88 8/31/88 3 (Code Cases) SER DEST /FME8 Rajan , 2, 3 Mechanical Engineering RAIs to 6/30/88 8/31/88 2 RAIs 80%

P.M. complete, Expected shortly DEST /EMTS Tsao 4, 5, 6, 15 Materials Engineering Draft 7/31/88 7/18/88 4 s 5:R DEST /EMTB Tsao I, 2, 3 Materials Engfreering RAIs to 6/30/88 5/23/88 a P.M.

! DEST /ESGB Tei./Pichumani 1, 2, 3, Structural & Geosciences RAls to 6/30/88 7/6/88 4 P.M.

s

  • Cctegory definitions:
1. AD or above attention recuested
2. Branch Chief attention requested
3. On schedule
4. Casplete

Dat2: August 26, 1988 REVIEW STATUS REPORT ON EPRI'5 ALWR REQUIRDIENTS DOCUMENT Expected Division / Due Input Branch Reviewer Chapter Subject

  • Milestone Date Date Ca t.* Comments DEST /EME8 Rajan 5 Eng. Safety Systems DSER to 10/28/88** 2 P.M.

DEST /EMTB Tsao 5 Eng. Safety Systems DSER to N/A 4 Reviewer will P.H. have no input DEST / SIC 8 Stewart 5 Eng. Safety Systems DSER to 10/28/88** 2 P.M.

DEST /SELB Lazevnick 5 209. Safety Systems DSER to 10/28/88** 3 P.M.

DEST /SPL8 Shum 5 Eng. Safety Systems DSER to 10/28/88** 2 P.M.

DEST /SRX8 Schwenk 5 Eng. ! lety Systems DSER to 10/28/88** 4 7/8/88 DSER P.M. Input needs revisian

  • Category Definition:
1. AG or abcVe attention requested
2. 8C atter. tion requested
3. On schedule
4. Complete s 00 Due date revised to reflect receipt cf additional information dated 08/16/88 cnd ACRS schedele

Date: August 26, 1988 l

l REVIEW STATUS REPORT Det l

EPRI5~RLWR REQUIREMENTS DOCUPENT .

(Cont.) -

1 l ,

Expected l Division / Due Input i

Brcnch Reviewer Chapter _ Subject

  • Milestone Date Date Cat.* Comments l

DREP/RPB Martin 5 Eng. Safety Systems DSER to 10/28/83** 2 e.M.

l DEST /ECEB Parczewski 5 Eng. Safety Systems DSER to 10/28/88** 2 l P.M.

l I DREP/RAB Kelly 5 Eng. Safety Systems DSER to 10/28/88** 2 P.M.

i l

l t

l l

l l

o Category Defigition:

i 1. AD or above attention requested l 2. BC attention requested l 3. On schedule

4. Complete
    • Due date revised to reflect receipt l

of additional informattor dated 08/16/88 and ACRS schedule