Forwards W Repts Conceptual Remediation Plan & Conceptual Decommissioning Plan, Which Provides Time Schedule for Radiological Remediation of Wtr Facility & Objectives, Priorities,Schedule & Remediation Approaches
ML20147H893
Person / Time
Site: Waltz Mill
Issue date: 04/07/1997
From: Nardi A
WESTINGHOUSE ELECTRIC COMPANY, DIV OF CBS CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20147H897 List:
References
NUDOCS 9704090295
Download: ML20147H893 (2)


Text

i.

m)  !

~

N_/ '

Westinghouse Energy Systems sa 355 Pinsbu@ Ptennsylvania 15230-0355 Electric Corporation April 7,1997 RA-97-039 U. S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attention: Document Control Center

Subject:

Submittal of Remediation Plan for the Westinghouse Test Reactor USNRC License Number TR-2, Docket 50-22

References:

1) Westinghouse Letter dated June 17,1996 from AJ. Nardi to USNRC
2) Westinghouse Letter dated November 27,1996 from A. J. Nardi to USNRC The Westinghouse Electric Corporation hereby submits the attached report entitled " Westinghouse f Test Reactor, TR2, Conceptual DecomWssioning Plan". This report provides a general plan and time 1 schedule for the radiological remediathn of the WTR facility on the Westinghouse Waltz Mill Site which is covered by License Number TR-2. Westinghouse had presented an overall schedule and priorities for the Waltz Mill Sit: G<eference 1) and has submitted the Remediation Plan (Reference 2) for those facilities covered by USNRC License Number SNM-770.

The overall priorities and objectives of this program remain as stated in the referenced letters. 'Ite first priority is to address the soil and groundwater issues so that the site can be removed from the SDMP list, followed by remediation of the SNM-770 retired facilities, and finally to decommission the Westinghouse Test Reactor facility so that the TR-2 license can be terminated.

Since Westinghouse plans to transfer the WTR facility to the SNM-770 license, the decommissioning plan is based on objectives which recognize the ALARA concept along with the intent to continue the use of the facility as licensed operations. The plan provides the objectives, priorities, schedule, and remediation approaches. Note that this plan is not a detailed engineering plan. Additional engineering detail will be defined as specific plans are developed.

' 9704090295 970407  ?

PDR ADOCK 05000022 _

p PDR J

t -

The basic concept of the WTR Decommissioning Plan is to:

1. Remove the remaining reactor vessel internal contents, the reactor vessel, and the biological shield.
2. Transfer the remaining residual radioactivity and remaining WTR facilities to the SNM-770 License.
3. Perform an independent verification that the remaining reactor vessel and the biological shield have been removed.
4. Terminate the 3 R-2 License.

If y a trave any questions concerning the information provided in this letter, please contact me at the above address or call me at (412) 374-4652.

Sincerely, j'

+

/ r l /-

A. . Nardi, Superv sory Engineer ESBU Regulatory Affairs cc: Dr. Ronald R. Bellamy U. S. Nuclear Regulatory Commission, Region i James G. Yusko, PA Department of Environmental Protection ts Attachment Copies transmitted: 3 notarized and 5 conformed COMMONWEALTH OF PENNSYLVANIA)

COUNTY OF ALLEGHENY) ss Sworn and subscribed before me this day of ,1997.

Yw>w O M Notary Public f}

t Notarial Sea!

Wonne N. Thompson. Notaty Public Monroevitle Boro.Mogheny County My Comnnssion Empires Aug. 2,1999 MuntJer, hrinsykdu Aasonasonof Noerles