Documents Closure of ABWR FSER Confirmatory Items
ML20081K936
Person / Time
Site: 05200001
Issue date: 12/22/1994
From: Quirk J
GENERAL ELECTRIC CO.
To: Borchardt R
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM), Office of Nuclear Reactor Regulation
References
MFN-164-94, NUDOCS 9503290346
Download: ML20081K936 (3)


Text

- 4" .,.

l  : '

O ,

GENudearEnergy Josefh F. Owt GeneralElectric Company PtgioctManager 175 Curtner Annue, l' 782; San Jose, CA 951251014 ABWR CertMication 4009256219(phone) 400 925-4257(facsimne)

December 22,1994 MFN No.164-94 r

Docket No.52-001

" Document Control Desk U.S. Nuclear Regulatory Commission

_. Washington, D.C. 20555-0001 b

Attention: R.W. Borchardt, Director Standardization Project Directorate 7 Subject; Closure of ABWR FSER Confirmatory Items h

References:

(1) J.F. Quirk to Mr. Dennis Crutchfield, Submittal of Final ABWR Design Control Document, MFN No.134-94, dated October 28,1994.

(2) R.W. Borchardt to Mr. Joseph Quirk, dated December 8,1994.

(3) J.F. Quirk to R.W. Borchardt to Mr. Joseph Quirk, e

' Submittal of Revision 1 to the ABWR Design Control g Document, MFN No.163-94, dated December 22,1994.

(4) J.N. Fox to T.H. Boyce, Final SSAR and CDM Modifications, datedJuly 12,1994.

(5) J.N. Fox to Distnbution, Final ABWR SSAR Amendment 35 and CDM Revision 4, July 20,1994.

The purpose of this letter is to document closure of all ABWR FSER Confirmatory Items. Each one of these items are individually addressed below.

Fl.2.2-1 Certification that DCD not affected by changes to CEDs GE certifies that the final Tier I and Tier 2 information submittal on December 22, 1994 (Reference 3) has not been affected by any changes made in the common engineering design documents (CEDs).

F1.2.2-2 Submittal oflist of CEDs and DALs The FDA and final submittals of DCD Tier 1 and Tier 2 are not affected by changes in CEDs or design action list (DAL) items. All of the drawings and design descri tions are 9503290346 941222 PDR- ADOCK 05200001 M A PDR ((,,h g

  • 1In

m - - - -

. g :. .-

O 9

findi in Tier 1 and Tier 2 as approved by the FDA. In point of fact, all of the pertinent CED information and DALs have been or will be incorporated in the ABWR design.

Future work in these areas will directed to folding the appropriate CED material and DALs into documents supporting Tier 1 and Tier 2. All such resulting documents must be consistent with the design as approved.

F1.5-1 Submittal of DCD GE submitted the ABWR DCD for the staff's review in October 1994 (Reference 1).

Following the staff's review (Reference 2), GE submitted Revision 1 to the DCD (Reference 3).

F1.7-1 IdentifyTier 2* Information Tier 2* information as delineated by Section 1.7 of the FSER is identified in Table 1 of the introduction to the DCD (Reference 3). This information is designated in Tier 2 with brackets, italicized text, and an asterisk (or similar symbol). A plant-specific change to any of this designated information requires NRC Staff approval prior to implementing the change. -

^

F14.3.7.5-1 Reliability Assurance Protrram GE incorporated the D-RAP commitment in itsjuly 12,1994 letter (Reference 4) in the CDhi onJuly 20,1994 (Reference 5)

Sincerely

  • i

/

[ sep F. Quirk 2

a e

gew

\

-bcci J.A. Beard (GE) S.M. Franks (DOE) F.J. Miraglia(NRC)

_ N.D. Fletcher (DOE) - T.H. Boyce(NRC) W.H. Rasin(NEI)

S.P. Frantz(Morgan, S.A. Hucik(GE) R.L. Simard(NEI) .

Lewis & Bockius) F.A. Ross(DOE) R.J. Bell (NEI)

M. A. Rowden(Fried, N.T. Patel(GE) J.N. Fox (GE)

Frank...)

i 1

'l I

i e

6 l

3

.