Letter Sequence RAI |
---|
|
|
MONTHYEARML0522102682005-08-12012 August 2005 RAI - Request for Relief from the Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI Project stage: RAI NRC 2005-0108, Response to Request for Additional Information: Relief Request from the Provisions of ASME Section Xl, IWA-5244, Buried Components, Relief Request 152005-08-26026 August 2005 Response to Request for Additional Information: Relief Request from the Provisions of ASME Section Xl, IWA-5244, Buried Components, Relief Request 15 Project stage: Response to RAI NRC 2005-0133, Request for Withdrawal: Relief Request from the Provisions of ASME Section XI IWA-5244, Buried Components, Relief Request 152005-10-14014 October 2005 Request for Withdrawal: Relief Request from the Provisions of ASME Section XI IWA-5244, Buried Components, Relief Request 15 Project stage: Request ML0531300822005-12-14014 December 2005 Withdrawal of Relief Request from the Provisions of ASME Code XI, Relief Request 15 (TACs MC7770 and MC7771) Project stage: Withdrawal 2005-12-14
[Table View] |
|
---|
Category:Letter
MONTHYEARML24352A1272024-12-18018 December 2024 Notification of NRC Baseline Inspection and Request for Information IR 05000266/20240122024-12-10010 December 2024 NRC Inspection Report 05000266/2024012 & 05000301/2024012 and Notice of Violation ML24323A2442024-12-0505 December 2024 Regulatory Audit in Support of Review of Application to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components ML24338A1452024-12-0303 December 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Point Beach SLR L-2024-182, Subsequent License Renewal Application Environmental Review Supplemental Environmental Audit December 2, 2024 L-2024-182 10 CFR 54 Response to Requests for Confirmation of Information and Requests for Additional Information2024-12-0202 December 2024 Subsequent License Renewal Application Environmental Review Supplemental Environmental Audit December 2, 2024 L-2024-182 10 CFR 54 Response to Requests for Confirmation of Information and Requests for Additional Information L-2024-196, Subsequent License Renewal Application - Fourth Annual Update2024-11-25025 November 2024 Subsequent License Renewal Application - Fourth Annual Update L-2024-189, Notification of Deviation from NEI 03-08, OG-21-160, Regarding Clevis Insert Bolting UT Exam2024-11-20020 November 2024 Notification of Deviation from NEI 03-08, OG-21-160, Regarding Clevis Insert Bolting UT Exam IR 05000266/20244022024-11-14014 November 2024 Security Baseline Inspection Report 05000266/2024402 and 05000301/2024402 IR 05000266/20240032024-11-0505 November 2024 Integrated Inspection Report 05000266/2024003 and 05000301/2024003 ML24295A1142024-10-31031 October 2024 Suppl Env Audit Summary Letter W/Enclosure 1 L-2024-176, Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2024-10-30030 October 2024 Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums L-2024-160, Core Operating Limits Report (COLR) Unit 2 Reload Cycle 41 (U2C41)2024-10-21021 October 2024 Core Operating Limits Report (COLR) Unit 2 Reload Cycle 41 (U2C41) ML24295A0862024-10-21021 October 2024 Notification of NRC Baseline Inspection and Request for Information Inspection Report 0500026/2025002 L-2024-169, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes2024-10-15015 October 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes L-2024-118, Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1)2024-10-0808 October 2024 Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1) L-2024-120, LAR 301 - Revise Renewed Facility Operating Licenses to Adopt an Alternative Approach for Addressing Seismic Risk in 10 CFR 50.69 Risk-Informed Categorization2024-10-0808 October 2024 LAR 301 - Revise Renewed Facility Operating Licenses to Adopt an Alternative Approach for Addressing Seismic Risk in 10 CFR 50.69 Risk-Informed Categorization L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000266/20240112024-09-18018 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000266/2024011 and 05000301/2024011 L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-145, Notification of Deviation from EPRI MRP-227, Revision 1-A Baffle Bolt Inspection Frequency2024-09-0909 September 2024 Notification of Deviation from EPRI MRP-227, Revision 1-A Baffle Bolt Inspection Frequency ML24207A0202024-08-28028 August 2024 Response to Request for Re-Engagement Regarding the Subsequent License Renewal Environmental Review for Point Beach Nuclear Plant, Units 1 and 2 (Docket Numbers: 50-0266 and 50-0301) IR 05000266/20240052024-08-21021 August 2024 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2024005 and 05000301/2024005) IR 05000266/20240022024-08-13013 August 2024 Integrated Inspection Report 05000266/2024002 and 05000301/2024002 L-2024-131, Response to Request for Additional Information Regarding License Amendment Request 300, Modify Containment Average Air Temperature Requirements2024-08-0909 August 2024 Response to Request for Additional Information Regarding License Amendment Request 300, Modify Containment Average Air Temperature Requirements ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review ML24214A3092024-08-0202 August 2024 Confirmation of Initial License Examination ML24194A1802024-07-24024 July 2024 – Revision to the Reactor Vessel Material Surveillance Capsule Withdrawal Schedule L-2024-113, License Amendment Request 294, Application to Revise Technical Specifications to Adopt TSTF- 577, Revised Frequencies for Steam Generator Tube Inspections2024-07-24024 July 2024 License Amendment Request 294, Application to Revise Technical Specifications to Adopt TSTF- 577, Revised Frequencies for Steam Generator Tube Inspections L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000266/20244012024-07-23023 July 2024 Public - Point Beach Nuclear Plant Cyber Security Inspection Report 05000266/2024401 and 05000301/2024401 ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan L-2024-116, Preparation and Scheduling of Operator Licensing Examinations2024-07-11011 July 2024 Preparation and Scheduling of Operator Licensing Examinations L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal IR 05000266/20240102024-07-10010 July 2024 Age-Related Degradation Inspection Report 05000266/2024010 and 05000301/2024010 L-2024-105, License Amendment Request 300, Modify Containment Average Air Temperature Requirements2024-06-26026 June 2024 License Amendment Request 300, Modify Containment Average Air Temperature Requirements L-2024-107, Schedule for Subsequent License Renewal Environmental Review2024-06-25025 June 2024 Schedule for Subsequent License Renewal Environmental Review ML24176A2242024-06-24024 June 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter L-2024-093, Steam Generator Divider Plate Assemblies Bounding Analysis Evaluation for Aging Management Commitment 14 Revision2024-06-10010 June 2024 Steam Generator Divider Plate Assemblies Bounding Analysis Evaluation for Aging Management Commitment 14 Revision IR 05000266/20244202024-06-0505 June 2024 Security Baseline Inspection Report 05000266/2024420 and 05000301/2024420 ML24149A1922024-05-28028 May 2024 Notification of NRC Baseline Inspection and Request for Information ML24141A1382024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection.Docx ML24127A0632024-05-0606 May 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000266/20243012024-04-29029 April 2024 NRC Initial License Examination Report 05000266/2024301; 05000301/2024301 L-2024-067, Annual Monitoring Report2024-04-26026 April 2024 Annual Monitoring Report ML24116A0402024-04-23023 April 2024 Periodic Update of the Updated Final Safety Analysis Report ML24071A0912024-04-22022 April 2024 Issuance of Relief Request I6-RR-03 - Extension of the Unit 2 Steam Generator Primary Nozzle Dissimilar Metal Welds Sixth 10-Year Inservice Inspection Program Interval IR 05000266/20240012024-04-11011 April 2024 Integrated Inspection Report 05000266/2024001 and 05000301/2024001 L-2024-030, Supplement to Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements2024-03-27027 March 2024 Supplement to Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements 2024-09-09
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24215A2092024-08-0101 August 2024 NRR E-mail Capture - Final RAI - Point Beach 1 & 2 - License Amendment Request to Modify Containment Average Air Temperature Requirements ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan ML24176A2242024-06-24024 June 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24149A1922024-05-28028 May 2024 Notification of NRC Baseline Inspection and Request for Information ML24141A1382024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection.Docx ML24030A0352024-01-30030 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection ML23173A1522023-06-22022 June 2023 Request for Additional Information NextEra Fleet Emergency Plan Amendment Request ML23163A2422023-06-13013 June 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2023004 ML23136A2802023-05-0505 May 2023 SLRA Second Annual Update RAI Set 1 ML23122A0132023-05-0101 May 2023 NRR E-mail Capture - Point Beach 1 & 2 - Final RAI - License Amendment Request Regarding Risk-Informed Approach to Address GSI-191 ML23033A0292023-01-31031 January 2023 NRR E-mail Capture - Point Beach 1 & 2 - Final RAI (Volume 2) - License Amendment Request Regarding TSTS-505 ML23003A8022023-01-0303 January 2023 Notification of NRC Baseline Inspection and Request for Information ML22354A1612022-12-20020 December 2022 NRR E-mail Capture - Point Beach 1 & 2 - Final RAI - License Amendment Request Regarding TSTS-505 ML22311A5582022-11-22022 November 2022 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request for Cep ML22266A0872022-09-23023 September 2022 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML22172A1192022-06-27027 June 2022 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request to Adopt TSTF-505 Provide Risk Informed Extended Complete Times - RITSTF Initiative 4B ML22130A5712022-05-12012 May 2022 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML22041B0752022-02-10010 February 2022 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000266/2022002 ML21362A6812021-12-17017 December 2021 SLRA Safety RAIs Set 14 Final ML21362A6822021-12-17017 December 2021 SLRA Safety RAIs Set 14 Final Email ML21362A6702021-12-15015 December 2021 SLRA Safety RAIs Set 13 Final ML21362A6712021-12-15015 December 2021 SLRA Safety RAIs Set 13 Final Email ML21287A0852021-10-14014 October 2021 SLRA Safety RAI Set 11 Final Email ML21286A6042021-10-0505 October 2021 SLRA Safety RAIs Set 10 Final ML21286A6032021-10-0505 October 2021 SLRA Safety RAIs Set 10 Final Email ML21273A0222021-09-29029 September 2021 SLRA Safety RAI Set 9 Final ML21287A0862021-09-29029 September 2021 SLRA Safety RAI Set 11 Final ML21253A1672021-09-10010 September 2021 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information Inspection Report 05000266/2022010 05000301/2022010 ML21242A2292021-08-27027 August 2021 SLRA Draft Safety RAI Set 9 Email ML21242A2282021-08-27027 August 2021 SLRA Draft Safety RAI Set 9 ML21242A2472021-08-26026 August 2021 SLRA Safety RAIs Set 8 Final ML21242A2222021-08-23023 August 2021 SLRA Draft Safety RAI Set 8 ML21242A2232021-08-23023 August 2021 SLRA Draft Safety RAI Set 8 Email ML21242A2192021-08-20020 August 2021 SLRA Safety RAI Set 7 Final Email ML21242A2202021-08-20020 August 2021 SLRA Safety RAI Set 7 Final ML21242A2142021-08-13013 August 2021 SLRA Safety RAIs Set 7 Draft ML21242A2132021-08-13013 August 2021 SLRA Safety RAIs Set 7 Draft Email ML21242A0152021-08-12012 August 2021 SLRA Safety RAIs Set 6 Final ML21242A2392021-08-12012 August 2021 SLRA Safety RAIs Set 6 Final ML21242A2032021-08-12012 August 2021 Srla Safety RAIs Set 5 Final ML21242A2382021-08-12012 August 2021 SLRA Safety RAIs Set 6 Final Email ML21242A2042021-08-12012 August 2021 SLRA Safety RAIs Set 5 Final Email ML21242A0122021-08-0909 August 2021 SLRA Draft Safety RAIs Set 6 ML21285A1212021-08-0505 August 2021 SLRA Public Meeting Discussion Questions August 5 2021 ML21242A2002021-08-0505 August 2021 SLRA Draft Safety RAIs Set 5 Email ML21242A1992021-08-0505 August 2021 Srla Draft Safety RAIs Set 5 ML21238A2322021-08-0404 August 2021 SLRA Safety RAI Set 4 Final Email ML21238A2332021-08-0404 August 2021 SLRA Safety RAI Set 4 Final ML21237A0062021-08-0202 August 2021 SLRA Draft Safety RAIs Set 4 ML21208A1892021-07-27027 July 2021 SLRA Safety RAIs Set 2 Final 2024-08-01
[Table view] |
Text
August 12, 2005 Mr. Dennis L. Koehl Site Vice President Point Beach Nuclear Plant Nuclear Management Company, LLC 6590 Nuclear Road Two Rivers, WI 54241
SUBJECT:
POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION RE: RELIEF REQUEST FROM THE PROVISIONS OF THE AMERICAN SOCIETY OF MECHANICAL ENGINEERS BOILER AND PRESSURE VESSEL CODE, SECTION XI (TAC NOS. MC7770 AND MC7771)
Dear Mr. Koehl:
By letter to the Nuclear Regulatory Commission (NRC) dated January 21, 2005, Nuclear Management Company, LLC, submitted a request for relief for Point Beach Nuclear Plant, Units 1 and 2. Your submittal proposes relief from certain requirements of the 1998 Edition through the 2000 Addenda of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code,Section XI, IWA-5244, "Buried Components," for the fourth inservice interval in accordance with the provisions of Section 50.55a(a)(3)(ii) of Title 10 of the Code of Federal Regulations.
The NRC staff is reviewing your request and has determined that additional information is required to complete the review. The specific information requested is addressed in the enclosure to this letter.
This request was discussed with Mr. Aldo Capristo, of your staff, on August 4, 2005.
Mr. Capristo agreed to respond to this request by August 31, 2005. If you have any questions concerning this matter, please contact me at (301) 415-4018.
Sincerely,
/RA by Adrian Muniz for/
Harold K. Chernoff, Sr. Project Manager, Section 1 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301
Enclosure:
As stated cc w/encl: See next page
.: ML052210268 OFFICE PDIII-1/PE PDIII-1/PM DE/EMCB/SC PDIII-1/LA PDIII-1/SC NAME AMuniz HChernoff JTsao for TChan PCoats for DClarke LRaghavan DATE 8/11/05 8/11/05 8/12/05 8/11/05 8/12/05 Point Beach Nuclear Plant, Units 1 and 2 cc:
Jonathan Rogoff, Esquire Mr. Jeffery Kitsembel Vice President, Counsel & Secretary Electric Division Nuclear Management Company, LLC Public Service Commission of Wisconsin 700 First Street P.O. Box 7854 Hudson, WI 54016 Madison, WI 53707-7854 Mr. F. D. Kuester Nuclear Asset Manager President & Chief Executive Officer Wisconsin Electric Power Company WE Generation 231 West Michigan Street 231 West Michigan Street Milwaukee, WI 53201 Milwaukee, WI 53201 John Paul Cowan Regulatory Affairs Manager Executive Vice President & Chief Nuclear Point Beach Nuclear Plant Officer Nuclear Management Company, LLC Nuclear Management Company, LLC 6610 Nuclear Road 700 First Street Two Rivers, WI 54241 Hudson, WI 54016 Mr. Ken Duveneck Douglas E. Cooper Town Chairman Senior Vice President - Group Operations Town of Two Creeks Palisades Nuclear Plant 13017 State Highway 42 Nuclear Management Company, LLC Mishicot, WI 54228 27780 Blue Star Memorial Highway Covert, MI 49043 Chairman Public Service Commission Site Director of Operations of Wisconsin Nuclear Management Company, LLC P.O. Box 7854 6610 Nuclear Road Madison, WI 53707-7854 Two Rivers, WI 54241 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4351 Resident Inspector's Office U.S. Nuclear Regulatory Commission 6612 Nuclear Road Two Rivers, WI 54241
REQUEST FOR ADDITIONAL INFORMATION RELATED TO NUCLEAR MANAGEMENT COMPANY, LLC POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 DOCKET NOS. 50-266 AND 50-301 By letter to the Nuclear Regulatory Commission (NRC) dated January 21, 2005, Nuclear Management Company, LLC, submitted a request for relief for Point Beach Nuclear Plant (PBNP), Units 1 and 2. Your submittal proposes relief from certain requirements of the 1998 Edition through the 2000 Addenda of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code),Section XI, IWA-5244, Buried Components, during the fourth interval in accordance with the provisions of Section 50.55a(a)(3)(ii) of Title 10 of the Code of Federal Regulations.
In order for the NRC staff to complete its review, responses to the following questions are requested.
- 1. The licensee stated that: A review of previous PBNP pressures tests indicated that prior Inservice Inspection (ISI) intervals had not met Code requirements for performing pressure testing on buried portions of the main SW headers as required by IWA-5244 of the 1986 Edition of ASME Section XI. Please explain in detail the tests that were performed in place of the required pressure tests and the actions taken as a result of not meeting the ASME Code,Section XI, requirements for the previous intervals.
- 2. The licensee stated that the piping is not susceptible to Microbiologically Influenced Corrosion (MIC) because of continuous high flow rate of water through the piping.
Please identify the construction materials of the underground piping. State if either lining on the internal diameter or pipe wrapping on the outside diameter has been employed and the material used.
Enclosure