MONTHYEARML24036A2652024-02-0505 February 2024 Notice of Inspection and Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000266/2024010 and 05000301/2024010 IR 05000266/20230042024-02-0101 February 2024 Integrated Inspection Report 05000266/2023004 and 05000301/2023004 ML24030A0352024-01-30030 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection L-2024-001, Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements2024-01-26026 January 2024 Relief Request CISl-03-01 for Relief Concerning Containment Unbonded Post-Tensioning System Inservice Inspection Requirements L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML24005A3242024-01-24024 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0040 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23352A2752024-01-23023 January 2024 Issuance of Amendment Nos. 274 and 276 Regarding Revision to Technical Specification 5.5.17, Pre-Stressed Concrete Containment Tendon Surveillance Program L-2023-173, Quality Assurance Topical Report (FPL-1) Revision 30 Update2023-12-15015 December 2023 Quality Assurance Topical Report (FPL-1) Revision 30 Update L-2023-174, Subsequent License Renewal Application - Third Annual Update2023-12-13013 December 2023 Subsequent License Renewal Application - Third Annual Update L-2023-176, Supplement to Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-11-29029 November 2023 Supplement to Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule L-2023-155, Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-06542023-11-28028 November 2023 Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, L-2023-159, Part 3 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks and Security Event Notifications Final Rule2023-11-16016 November 2023 Part 3 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks and Security Event Notifications Final Rule IR 05000266/20234022023-11-14014 November 2023 Security Baseline Inspection Report 05000266/2023402 and 05000301/2023402 ML23279A0672023-11-0909 November 2023 Issuance of Relief Request I6 RR 02 - Examination of the Unit 2 Steam Generator Feedwater Nozzle Extension to Nozzle Weld Sixth 10 Year Inservice Inspection Program Interval IR 05000266/20230032023-10-16016 October 2023 Integrated Inspection Report 05000266/2023003 and 05000301/2023003 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published L-2023-128, License Amendment Request to Revise TS 5.5.17, Pre-Stressed Concrete Containment Tendon Surveillance Program2023-09-19019 September 2023 License Amendment Request to Revise TS 5.5.17, Pre-Stressed Concrete Containment Tendon Surveillance Program ML23243A9102023-09-0606 September 2023 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors IR 05000266/20235012023-08-29029 August 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000266/2023501 and 05000301/2023501 ML23208A2262023-08-28028 August 2023 Exemption from the Requirements of 10 CFR 50,46, Acceptance Criteria for Emergency Core Cooling Systems for Light Water Nuclear Power Reactors (EPID L-2022-LLE-0026) - Letter ML23208A0952023-08-28028 August 2023 Issuance of Amendment Nos. 273 and 275 Regarding Revising Licensing Basis to Address Generic Safety Issue-191 and Respond to Generic Letter 2004-02 Using a Risk Informed Approach IR 05000266/20230052023-08-24024 August 2023 Updated Inspection Plan for Point Beach Nuclear Plant (Report 05000266/2023005 and 05000301/2023005) ML23160A0642023-08-21021 August 2023 Issuance of Amendment Nos. 272 and 274 Regarding Revision to Use Beacon Power Distribution Monitoring System L-2023-114, Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update2023-08-17017 August 2023 Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update ML23221A0522023-08-0909 August 2023 Confirmation of Initial License Examination, March 2024 L-2023-098, and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 22023-08-0707 August 2023 and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 ML23201A0872023-08-0303 August 2023 Audit Plan in Support of Review of License Amendment L-2023-089, Refueling Outage Owner'S Activity Report (OAR-1) Unit 2 for Inservice Inspections2023-07-24024 July 2023 Refueling Outage Owner'S Activity Report (OAR-1) Unit 2 for Inservice Inspections IR 05000266/20230022023-07-18018 July 2023 Integrated Inspection Report 05000266/2023002 and 05000301/2023002 IR 05000266/20234012023-07-13013 July 2023 Public-Point Beach Nuclear Plant-Security Baseline Inspection Report 05000266/2023401; 05000301/2023401; Independent Spent Fuel Storage Security Inspection Report 07200005/2023401 L-2023-087, Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452)2023-06-29029 June 2023 Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452) ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III L-2023-088, 10 CFR 50.55a Requests, Relief Requests I6-RR-1, I6-RR-2, and I6-RR-3 Sixth Ten-Year Inservice Inspection Program Interval2023-06-27027 June 2023 10 CFR 50.55a Requests, Relief Requests I6-RR-1, I6-RR-2, and I6-RR-3 Sixth Ten-Year Inservice Inspection Program Interval ML23171B1062023-06-21021 June 2023 Info Meeting with a Question and Answer Session to Discuss NRC 2022 EOC Plant Performance Assessment of Ptbh, Units 1 and 2 ML23163A2422023-06-13013 June 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2023004 L-2023-075, Response to Request for Additional Information (RAI) Regarding Exemption Request, License Amendment Request and Revised Response in Support of a Risk-Informed Resolution of Generic Letter 2004-022023-06-0909 June 2023 Response to Request for Additional Information (RAI) Regarding Exemption Request, License Amendment Request and Revised Response in Support of a Risk-Informed Resolution of Generic Letter 2004-02 L-2023-073, Subsequent License Renewal Application, Second Annual Update Request for Additional Information Set 1 Response2023-06-0101 June 2023 Subsequent License Renewal Application, Second Annual Update Request for Additional Information Set 1 Response ML23103A1332023-06-0101 June 2023 Issuance of Amendment Nos. 271 and 273 Regarding Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b L-2023-071, NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal2023-05-22022 May 2023 NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal ML23118A1762023-05-0404 May 2023 Audit Summary for License Amendment Request Regarding Risk-Informed Approach for Closure of Generic Safety Issue 191 IR 05000266/20230012023-05-0101 May 2023 Integrated Inspection Report 05000266/2023001 and 05000301/2023001 ML23114A1222023-04-25025 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-2023-058, 2022 Annual Monitoring Report2023-04-10010 April 2023 2022 Annual Monitoring Report L-2023-021, Units, 1 and 2, Turkey Point, Units 3 and 4, Seabrook Station and Point Beach, Units 1 and 2 - Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update2023-03-28028 March 2023 Units, 1 and 2, Turkey Point, Units 3 and 4, Seabrook Station and Point Beach, Units 1 and 2 - Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update L-2023-028, and Point Beach Units 1 and 2, 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2023-03-27027 March 2023 and Point Beach Units 1 and 2, 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications 2024-02-05
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24030A0352024-01-30030 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection ML23173A1522023-06-22022 June 2023 Request for Additional Information NextEra Fleet Emergency Plan Amendment Request ML23163A2422023-06-13013 June 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2023004 ML23136A2802023-05-0505 May 2023 SLRA Second Annual Update RAI Set 1 ML23122A0132023-05-0101 May 2023 NRR E-mail Capture - Point Beach 1 & 2 - Final RAI - License Amendment Request Regarding Risk-Informed Approach to Address GSI-191 ML23033A0292023-01-31031 January 2023 NRR E-mail Capture - Point Beach 1 & 2 - Final RAI (Volume 2) - License Amendment Request Regarding TSTS-505 ML23003A8022023-01-0303 January 2023 Notification of NRC Baseline Inspection and Request for Information ML22354A1612022-12-20020 December 2022 NRR E-mail Capture - Point Beach 1 & 2 - Final RAI - License Amendment Request Regarding TSTS-505 ML22311A5582022-11-22022 November 2022 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request for Cep ML22266A0872022-09-23023 September 2022 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML22172A1192022-06-27027 June 2022 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request to Adopt TSTF-505 Provide Risk Informed Extended Complete Times - RITSTF Initiative 4B ML22130A5712022-05-12012 May 2022 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML22041B0752022-02-10010 February 2022 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000266/2022002 ML21362A6812021-12-17017 December 2021 SLRA Safety RAIs Set 14 Final ML21362A6822021-12-17017 December 2021 SLRA Safety RAIs Set 14 Final Email ML21362A6712021-12-15015 December 2021 SLRA Safety RAIs Set 13 Final Email ML21362A6702021-12-15015 December 2021 SLRA Safety RAIs Set 13 Final ML21287A0852021-10-14014 October 2021 SLRA Safety RAI Set 11 Final Email ML21286A6032021-10-0505 October 2021 SLRA Safety RAIs Set 10 Final Email ML21286A6042021-10-0505 October 2021 SLRA Safety RAIs Set 10 Final ML21287A0862021-09-29029 September 2021 SLRA Safety RAI Set 11 Final ML21273A0222021-09-29029 September 2021 SLRA Safety RAI Set 9 Final ML21253A1672021-09-10010 September 2021 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information Inspection Report 05000266/2022010 05000301/2022010 ML21242A2282021-08-27027 August 2021 SLRA Draft Safety RAI Set 9 ML21242A2292021-08-27027 August 2021 SLRA Draft Safety RAI Set 9 Email ML21242A2472021-08-26026 August 2021 SLRA Safety RAIs Set 8 Final ML21242A2232021-08-23023 August 2021 SLRA Draft Safety RAI Set 8 Email ML21242A2222021-08-23023 August 2021 SLRA Draft Safety RAI Set 8 ML21242A2192021-08-20020 August 2021 SLRA Safety RAI Set 7 Final Email ML21242A2202021-08-20020 August 2021 SLRA Safety RAI Set 7 Final ML21242A2132021-08-13013 August 2021 SLRA Safety RAIs Set 7 Draft Email ML21242A2142021-08-13013 August 2021 SLRA Safety RAIs Set 7 Draft ML21242A2032021-08-12012 August 2021 Srla Safety RAIs Set 5 Final ML21242A2382021-08-12012 August 2021 SLRA Safety RAIs Set 6 Final Email ML21242A2392021-08-12012 August 2021 SLRA Safety RAIs Set 6 Final ML21242A2042021-08-12012 August 2021 SLRA Safety RAIs Set 5 Final Email ML21242A0152021-08-12012 August 2021 SLRA Safety RAIs Set 6 Final ML21242A0122021-08-0909 August 2021 SLRA Draft Safety RAIs Set 6 ML21242A1992021-08-0505 August 2021 Srla Draft Safety RAIs Set 5 ML21242A2002021-08-0505 August 2021 SLRA Draft Safety RAIs Set 5 Email ML21285A1212021-08-0505 August 2021 SLRA Public Meeting Discussion Questions August 5 2021 ML21238A2332021-08-0404 August 2021 SLRA Safety RAI Set 4 Final ML21238A2322021-08-0404 August 2021 SLRA Safety RAI Set 4 Final Email ML21237A0062021-08-0202 August 2021 SLRA Draft Safety RAIs Set 4 ML21214A0842021-07-27027 July 2021 SLRA Safety RAIs Set 3 Final ML21208A1892021-07-27027 July 2021 SLRA Safety RAIs Set 2 Final ML21172A2382021-07-21021 July 2021 (Pbn) Subsequent License Renewal Application (SLRA) Draft Requests for Additional Information (Rais) Safety - Set 2 ML21214A0722021-07-20020 July 2021 Subsequent License Renewal Application Draft Safety RAIs Set 3 ML21161A1192021-06-10010 June 2021 RAIs Set 1 Final Aging Management of Irradiated Concrete and Steel Reactor Vessel Supports Final ML21134A0582021-05-14014 May 2021 Final Request for Additional Information and Requests for Confirmation of Information - Point Beach SLRA Environmental Review (EPID No. L-2020-SLE-0002) - Email 2024-01-30
[Table view] |
Text
May 11, 2022 Mr. Michael Strope Site Vice President NextEra Energy Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241-9516
SUBJECT:
POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2INFORMATION REQUEST TO SUPPORT THE NRC ANNUAL BASELINE EMERGENCY ACTION LEVEL AND EMERGENCY PLAN CHANGES INSPECTION
Dear Mr. Strope:
This letter is to request information to support the Emergency Action Level and Emergency Plan Change Inspection that will be conducted during the third and fourth quarters of 2022. This inspection will be performed as an in-office review and in accordance with the U.S. Nuclear Regulatory Commission (NRC) Baseline Inspection Procedure 71114.04. The list of requested documents needed from your staff for this inspection is enclosed. We are requesting that these documents are for the time period specified in the list, as applicable.
The point of contact for this request is Michelle Garza, Region III Emergency Preparedness Inspector, and can be reached at 630-829-9719. We will keep in close communications with the Emergency Preparedness staff at your site regarding this request and the inspection when performed.
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget Control Number.
M. Strope This letter and its enclosure will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations, Part 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Signed by Pelke, Patricia on 05/11/22 Patricia Pelke, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-266, 50-301 and 72-005 License Nos. DPR-24 and DPR-27
Enclosure:
Emergency Action Level and Emergency Plan Changes Inspection Document Request cc: Distribution via LISTSERV
M. Strope Letter to Michael Strope from Patricia Pelke dated May 11, 2022.
SUBJECT:
POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2INFORMATION REQUEST TO SUPPORT THE NRC ANNUAL BASELINE EMERGENCY ACTION LEVEL AND EMERGENCY PLAN CHANGES INSPECTION DISTRIBUTION:
Jessie Quichocho Robert Orlikowski RidsNrrDorlLpl3 RidsNrrPMPointBeach RidsNrrDroIrib Resource John Giessner Mohammed Shuaibi Shelbie Lewman Allan Barker DRPIII DRSIII ADAMS Accession Number: ML22130A571 OFFICE RIII RIII NAME MGarza:mb PPelke DATE 05/10/2022 05/11/2022 OFFICIAL RECORD COPY
EAL AND EMERGENCY PLAN CHANGES INSPECTION DOCUMENT REQUEST Please have the documents uploaded to a share file or web-based platform for our inspectors to access no later than July 15, 2022. Contact Michelle Garza with any questions about the electronic submittal.
Documents:
- 1. Current revision of the Emergency Plan
- 2. Current Emergency Action Level (EAL) scheme
- 3. Most recent Safety Evaluation Report for the Emergency Plan and EALs
- 4. On Shift Staffing Analysis baseline
- 5. Most recent Evacuation Time Estimate
- 6. Governing site document for Title 10 of the Code of Federal Regulations (CFR),
Part 50.54(q) evaluation process
- 7. Title 10 CFR 50.54(q) evaluator training program and qualification records
- 8. Title 10 CFR 50.54(q) screenings and evaluations for Emergency Plan and EAL changes that were completed between July 1, 2021, and June 30, 2022
- 9. For each change of the Emergency Plan and EALs, submit the previous revision, proposed revision, and the associated 50.54(q) screening and evaluation (if performed)
- 10. Corrective Action Program entries related to 50.54(q) screenings, 50.54(q) evaluations, EAL changes and Emergency Plan changes dated between July 1, 2021, and June 30, 2022 Enclosure