Letter Sequence Other |
---|
|
|
MONTHYEARCP-201500671, Relief Request T-1 for Inservice Testing Program for Application of an Alternative to the ASME OM Code Frequency Specifications, (2007 Edition of ASME Code, Section XI, 2008 Addenda Third Interval Start Date: August 3.2015-06-30030 June 2015 Relief Request T-1 for Inservice Testing Program for Application of an Alternative to the ASME OM Code Frequency Specifications, (2007 Edition of ASME Code, Section XI, 2008 Addenda Third Interval Start Date: August 3. Project stage: Request CP-201501050, Revision to Relief Request T-1, Inservice Testing Program for Application of an Alternative to the ASME OM Code Frequency Specifications (2004 Edition of Asmeom Code, 2006 Addenda2015-11-0505 November 2015 Revision to Relief Request T-1, Inservice Testing Program for Application of an Alternative to the ASME OM Code Frequency Specifications (2004 Edition of Asmeom Code, 2006 Addenda Project stage: Request ML16011A0732016-01-19019 January 2016 Relief Request T-1; Alternative to the ASME OM Code Frequency Specifications for Inservice Testing for the Third 10-Year IST Interval Project stage: Other 2015-06-30
[Table View] |
|
---|
Category:Code Relief or Alternative
MONTHYEARML23198A3212023-07-27027 July 2023 Authorization and Safety Evaluation for Proposed Alternative RV-1 ML23121A2202023-05-0404 May 2023 Proposed Alternative P-1 Regarding Safeguard Building Sump Pumps ML22077A8412022-03-24024 March 2022 Proposed Alternative SNB-3 for the Snubber Inservice Program Third Interval Extension ML21021A1002021-02-0101 February 2021 Proposed Alternative to the Requirements of the ASME OM Code to Extend the Inservice Testing Program Interval for Certain Snubbers (EPID L-2020-LLR-0095 (Covid 19)) ML21013A1282021-01-28028 January 2021 Approval of Proposed Alternative to the Requirements of the ASME Code to Extend the Third Inservice Inspection Interval (EPID L-2020-LLR-0092 (COVID-19)) ML21021A0022021-01-28028 January 2021 Approval of Proposed Alternatives 1A4-1 and 1A4-2 from Certain Requirements of 10 CFR 50.55a for Inservice Inspection of Nuclear Power Plants ML20253A1172020-10-0505 October 2020 Approval of Request for Alternative from Certain Requirements of 10 CFR 50.55a for Operation and Maintenance of Nuclear Power Plants (EPIDs L-2020-LLR-0063, L-2020-LLR-0064, and L-2020-LLR-0065 (COVID-19)) CP-202000431, Relief Request 1A4-1 Supplement - Reactor Vessel (Rv) Upper Head Examinations2020-08-0505 August 2020 Relief Request 1A4-1 Supplement - Reactor Vessel (Rv) Upper Head Examinations ML20196L8232020-07-14014 July 2020 Relief Request SNB-1, Snubber Testing ML20196L8242020-07-14014 July 2020 Relief Request 1A3-2, Inservice Inspection (Isi), Table 1 ML20196L8252020-07-14014 July 2020 Relief Request SNB-1, Snubber Testing, Table 1 ML20196L8262020-07-14014 July 2020 Relief Request V-3, Inservice Testing (IST) ML20196L8292020-07-14014 July 2020 Relief Request 1A3-2, Inservice Inspection (ISI) ML20196L8272020-07-14014 July 2020 Relief Request 1A4-2, Reactor Vessel (Rv) Bottom Mounted Instrumentation (Bmi) Nozzle Penetration Examination ML20196L8302020-07-14014 July 2020 Relief Request V-3, Inservice Testing (Ist), Table 1 CP-202000262, Snubber Testing and Snubber Visual Examinations Relief Request2020-04-10010 April 2020 Snubber Testing and Snubber Visual Examinations Relief Request CP-202000261, Inservice Inspection (ISI) and Inservice Testing (IST) Program Relief Requests2020-04-0707 April 2020 Inservice Inspection (ISI) and Inservice Testing (IST) Program Relief Requests ML17095A2512017-04-0707 April 2017 Request for Alternative 2B3-1 Re Examination of Reactor Vessel Closure Head Penetration Nozzles ML16179A4052016-07-11011 July 2016 Relief Request Nos. B-9, B-3, B-10, and B-11 for Piping Welds, Second 10-year Inservice Inspection Interval ML16074A0012016-03-14014 March 2016 Relief Request 1B3-3, Alternative for Reactor Pressure Vessel Cold Leg Weld Inspection Frequency from Not to Exceed 7 Years to 9 Years for the Third 10-Year Inservice Inspection Interval ML16063A0012016-03-11011 March 2016 Relief Request No. B-15, C-2, and C-4 for Welds in the RPV and Containment Spray and Residual Heat Removal Heat Exchanger Shells, Second 10-year Inservice Inspection Interval ML16011A0732016-01-19019 January 2016 Relief Request T-1; Alternative to the ASME OM Code Frequency Specifications for Inservice Testing for the Third 10-Year IST Interval ML15259A0042015-10-30030 October 2015 Relief Request 1B3-4, Alternative for Reactor Pressure Vessel Head Penetration Weld Inspection Frequency (from 10 to 15 Years), Third 10-Year Inservice Inspection Interval ML15257A2422015-09-18018 September 2015 Relief Request 2A3-1, from ASME Code Section XI Requirements, Risk-Informed Process for Selection of Class 1 and Class 2 Piping Weld Examinations, Third 10-Year Inservice Inspection Interval ML15257A2402015-09-15015 September 2015 Relief Request 2C3-1, from ASME Code, Section XI Requirements Reactor Pressure Vessel Leak-Off Flange for the Third 10-Year Inservice Inspection Interval CP-201500671, Relief Request T-1 for Inservice Testing Program for Application of an Alternative to the ASME OM Code Frequency Specifications, (2007 Edition of ASME Code, Section XI, 2008 Addenda Third Interval Start Date: August 3.2015-06-30030 June 2015 Relief Request T-1 for Inservice Testing Program for Application of an Alternative to the ASME OM Code Frequency Specifications, (2007 Edition of ASME Code, Section XI, 2008 Addenda Third Interval Start Date: August 3. ML15090A1042015-04-0303 April 2015 Relief Requests B-7, B-12, and B-13 - Steam Generator Head-to-Tube Sheet Welds for the Second 10-Year Inservice Inspection Interval ML14087A0662014-04-10010 April 2014 Relief Request No. 1/2E-1 for Containment Electrical Penetrations for the Third 10-Year Inservice Inspection Interval ML14073A5442014-04-0101 April 2014 Relief Request No. B-14 for Reactor Pressure Vessel Hot Leg Nozzle Weld Examinations for the Second 10-Year Inservice Inspection Interval ML13158A0932013-06-26026 June 2013 Relief Request No. E-1 Containment Electrical Penetrations, for the Second 10-Year Inservice Inspection Interval ML13148A4372013-06-26026 June 2013 Relief Request No. P-1 for Pumps and Valves, Third 10-Year Inservice Testing Plan Interval ML13113A3792013-05-0808 May 2013 Relief Request No. V-1, from ASME Code for Operation and Maintenance of Nuclear Power Plants Requirements for Pumps and Valves, for the Third 10-Year Inservice Testing Interval ML13046A3852013-03-19019 March 2013 Relief Request C-2 for the Reactor Pressure Vessel Flange Leak-Off Piping, Third 10-Year Inservice Inspection Interval ML13056A5032013-03-15015 March 2013 Relief Request B-2, Alternative to ASME Code Requirements for Examination of Reactor Vessel Hot-Leg Nozzle Welds, for the Third 10-Year Inservice Inspection Interval CP-201300003, Submittal of Relief Request No. B-2, Third 10 Year ISI Interval from 10CFR50.55a Requirements for Reactor Vessel Hot Leg Nozzle Weld Examinations (Third ISI Interval Start Date August 13, 2010)2013-01-16016 January 2013 Submittal of Relief Request No. B-2, Third 10 Year ISI Interval from 10CFR50.55a Requirements for Reactor Vessel Hot Leg Nozzle Weld Examinations (Third ISI Interval Start Date August 13, 2010) CP-201201384, Response to Request for Additional Information for Relief Request No. E-12012-11-14014 November 2012 Response to Request for Additional Information for Relief Request No. E-1 ML12194A2502012-08-14014 August 2012 Relief Request A-1 for Approval of Risk-Informed Alternative to ASME Code, Section XI for Class 1 and 2 Piping Welds, Third 10-Year Inservice Inspection Interval ML1131100922011-12-19019 December 2011 Relief Request No. C-9, Reactor Pressure Vessel Flange Leak-off Piping Configuration, Second 10-Year Inservice Inspection Interval ML1126500832011-11-10010 November 2011 Approval of Relief Request Nos. B-10 and B-11 for the Second 10-Year Inservice Inspection Interval CP-201001546, Relief Request No. B-11 for the Second 10 Years ISI Interval from 10 CFR 50.55a Inspection Requirements Due to Physical Interferences (Second Interval Start Date: August 13, 2000)2010-12-15015 December 2010 Relief Request No. B-11 for the Second 10 Years ISI Interval from 10 CFR 50.55a Inspection Requirements Due to Physical Interferences (Second Interval Start Date: August 13, 2000) CP-201001544, Relief Request No. C-9 for the Second 10 Year Interval from 10 CFR 50.55a Inspection Requirements Due to Hardship (Second Interval Start Date: August 13, 2000)2010-12-15015 December 2010 Relief Request No. C-9 for the Second 10 Year Interval from 10 CFR 50.55a Inspection Requirements Due to Hardship (Second Interval Start Date: August 13, 2000) CP-201000890, Relief Request No. C-7 for the Second 10 Year ISI Interval from 10 CFR 50.55a Inspection Requirements Due to Physical Interferences (Second Interval Start Date: August 13, 2000)2010-12-15015 December 2010 Relief Request No. C-7 for the Second 10 Year ISI Interval from 10 CFR 50.55a Inspection Requirements Due to Physical Interferences (Second Interval Start Date: August 13, 2000) ML0928706372009-12-22022 December 2009 Relief Request B-9 for Unit 1 and B-8 for Unit 2 to Extend the Inservice Inspection Interval for the Reactor Vessel Weld Examination CP-200901227, Revision to Request for Relief to Extend the Unit 1 and 2 in Service Inspection Interval for the Reactor Vessel Weld Examination and Withdrawal of License Amendment Request 09-004 to Add License Condition for Submittal of ISI Informatio2009-09-14014 September 2009 Revision to Request for Relief to Extend the Unit 1 and 2 in Service Inspection Interval for the Reactor Vessel Weld Examination and Withdrawal of License Amendment Request 09-004 to Add License Condition for Submittal of ISI Information an ML0916205482009-07-23023 July 2009 Relief Request P-2, Inservice Testing Plan for Pumps and Valves for Second Interval CP-200801132, Relief Request No. P-2 for the Unit 1 and Unit 2 Inservice Testing Plan for Pumps and Valves (ASME OM Code 1998 Edition, Through 2000 Addenda; Interval Start Date: August 3, 2004, Second Interval)2008-09-24024 September 2008 Relief Request No. P-2 for the Unit 1 and Unit 2 Inservice Testing Plan for Pumps and Valves (ASME OM Code 1998 Edition, Through 2000 Addenda; Interval Start Date: August 3, 2004, Second Interval) ML0821301472008-08-22022 August 2008 Request for Relief B-2 for Second 10-Year Inservice Inspection Interval from 10 CFR 50.55a Inspections Requirements Due to Physical Interferences CP-200800927, (Cpnpp), Relief Request B-8 for Unit 1 Second 10 Year ISI Interval & B-6 for Unit 2 Second 10 Year ISI Interval from 10 CFR 50.55a Requirements for Reactor Vessel Hot & Cold Leg Nozzle Weld Examinations (Unit 1 Second Interval Start..2008-07-10010 July 2008 (Cpnpp), Relief Request B-8 for Unit 1 Second 10 Year ISI Interval & B-6 for Unit 2 Second 10 Year ISI Interval from 10 CFR 50.55a Requirements for Reactor Vessel Hot & Cold Leg Nozzle Weld Examinations (Unit 1 Second Interval Start.. ML0805201952008-03-10010 March 2008 Relief Request B-5 for Second 10-Year ISI Interval from 10 CFR 50.55a Requirements for Class 1 Repair/Replacement of Control Rod Drive Mechanism Canopy Seal Welds ML0804306622008-02-29029 February 2008 Request for Relief No. B-4 from Certain Requirements of ASME Code, Section XI for Implementation of the EPRI-PDI Supplement 11 Program and Application of Weld Overlays 2023-07-27
[Table view] Category:Letter
MONTHYEARIR 05000445/20244042024-10-23023 October 2024 Security Baseline Inspection Report 05000445/2024404 and 05000446/2024404 (Public) IR 05000445/20243012024-10-15015 October 2024 NRC Initial Operator Licensing Examination Approval 05000445/2024301 and 05000446/2024301 IR 07200074/20244012024-10-10010 October 2024 Independent Spent Fuel Storage Installation Security Inspection Report 07200074/2024401 Public 05000445/LER-2024-002-01, Condition Prohibited by Technical Specifications Due to Inoperable Remote Shutdown System Functions2024-10-0303 October 2024 Condition Prohibited by Technical Specifications Due to Inoperable Remote Shutdown System Functions 05000446/LER-2024-001-01, Unit Two, Recurring Reactor Scrams Associated with Main Feedwater System Modifications2024-09-30030 September 2024 Unit Two, Recurring Reactor Scrams Associated with Main Feedwater System Modifications CP-202400335, License Amendment Request to Adopt TSTF-51, TSTF-471, and TSTF-571-T to Eliminate Use of the Term Core Alterations and Revise Requirements During Handling of Irradiated Fuel2024-09-12012 September 2024 License Amendment Request to Adopt TSTF-51, TSTF-471, and TSTF-571-T to Eliminate Use of the Term Core Alterations and Revise Requirements During Handling of Irradiated Fuel ML24031A6322024-09-11011 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4), Final Safety Analysis Report Update Schedule (EPID L-2023-LLE-0023) - Letter ML24243A0152024-09-0303 September 2024 – Notification of Comprehensive Engineering Team Inspection (05000445/2025012 and 05000446/2025012) and Request for Information ML24194A1332024-08-28028 August 2024 Issuance of Amendment Nos. 190 and 190, Respectively, Revision to Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown ML24228A2252024-08-22022 August 2024 Relief to Use Later Code Edition for Inservice Inspection Program ML24179A0772024-08-20020 August 2024 Issuance of Amendment Nos. 189 and 189, Respectively, Extension of Allowed Outage Time for an Inoperable Emergency Diesel Generator ML24232A2262024-08-19019 August 2024 Information Request, Security IR 2024404 ML24232A2412024-08-19019 August 2024 Information Request, ISFSI Security IR 2024401 IR 05000445/20240052024-08-15015 August 2024 Updated Inspection Plan for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2024005 and 05000446/2024005) CP-202400294, (CPNPP) - Response to RAI for Exemption Request from 10 CPR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 (CPNPP) - Response to RAI for Exemption Request from 10 CPR 50.71(e)(4) Final Safety Analysis Update Schedule CP-202400319, (CPNPP) - Revision to CPNPP Letter to the NRC, Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality2024-08-13013 August 2024 (CPNPP) - Revision to CPNPP Letter to the NRC, Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality ML24177A2692024-08-0707 August 2024 Issuance of Amendment Nos. 188 and 188, Respectively, Revision to Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program CP-202400315, (Cpnpp), Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality2024-08-0505 August 2024 (Cpnpp), Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality IR 05000445/20240022024-07-31031 July 2024 Units 1 and 2 - Integrated Inspection Report 05000445/2024002 and 05000446/2024002,and Independent Spent Fuel Storage Installation Inspection Report 07200074/2024001 IR 05000445/20244032024-07-16016 July 2024 Security Baseline Inspection Report 05000445/2024403 and 05000446/2024403 (Full Report) ML24187A0372024-07-15015 July 2024 Withdrawal of Requested Licensing Action Exemption from Select Requirements of 10 CFR Part 55, Operators Licenses ML24192A1862024-07-10010 July 2024 Notification of Inspection (NRC Inspection Report 05000445/2024003 and 05000446/2024003) and Request for Information ML24185A1382024-07-0202 July 2024 Inservice Inspection Request for Information CP-202400253, (Cpnpp), Units 1 & 2 Inservice Testing Plan for Pumps & Valves Third Interval, Revision 52024-06-26026 June 2024 (Cpnpp), Units 1 & 2 Inservice Testing Plan for Pumps & Valves Third Interval, Revision 5 IR 05000445/20244012024-06-26026 June 2024 MC&A Program Inspection Report 05000445-2024401 and 05000446-2024401 Public-Final CP-202400235, (Cpnpp), Units 1 & 2, Inservice Testing Plan for Pumps & Valves Fourth Interval, Revision 02024-06-18018 June 2024 (Cpnpp), Units 1 & 2, Inservice Testing Plan for Pumps & Valves Fourth Interval, Revision 0 IR 05000445/20240122024-06-17017 June 2024 Design Basis Assurance Inspection (Programs) Inspection Report 05000445/2024012 and 05000446/2024012 ML24120A3632024-06-10010 June 2024 Issuance of Amendment Nos. 187 and 187, Respectively Adoption of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Plants CP-202400120, (Cpnpp), Unit 1, Condition Prohibited by Technical Specifications Due to Inoperable Remote Shutdown System Functions2024-06-0303 June 2024 (Cpnpp), Unit 1, Condition Prohibited by Technical Specifications Due to Inoperable Remote Shutdown System Functions CP-202400205, (Cpnpp), Units 1and 2, Submittal of the Snubber Inservice Program Plan for the Fourth Ten Year Interval2024-05-30030 May 2024 (Cpnpp), Units 1and 2, Submittal of the Snubber Inservice Program Plan for the Fourth Ten Year Interval CP-202400175, (CPNPP) - Supplement to License Amendment Request to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator2024-05-16016 May 2024 (CPNPP) - Supplement to License Amendment Request to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator CP-202400100, (Cpnpp), Unit 2, Two Recurring Reactor Scrams Associated with Main Feedwater System Modifications2024-05-13013 May 2024 (Cpnpp), Unit 2, Two Recurring Reactor Scrams Associated with Main Feedwater System Modifications CP-202400097, Re Potential Loss of Safety Function Due to Inoperability of Both Trains of Uninterruptible Power Supply Heating, Ventilation & Air Conditioning2024-05-0606 May 2024 Re Potential Loss of Safety Function Due to Inoperability of Both Trains of Uninterruptible Power Supply Heating, Ventilation & Air Conditioning ML24120A2942024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Gonzalez, B, Caddo Nation ML24120A3032024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-SpottedBird, L, Kiowa Indian Tribe ML24120A2972024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Martin, R, Tonkawa Tribe of Oklahoma ML24120A3072024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Yargee, W, Alabama-Quassarte Tribal Town ML24120A3062024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Yahola, s, Kialegee Tribal Town ML24107B1012024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Cernek, J, Coushatta Tribe of Louisiana ML24120A3012024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Parton, T, Wichita and Affiliated Tribes ML24120A3042024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Sylestine, R, Alabama-Coushatta Tribe of Texas ML24120A2932024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Garza, Jr, Juan, Kickapoo Traditional Tribe of Texas ML24120A2902024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Bunch, J, United Keetoowah Band of Cherokee Indians ML24120A2912024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Cooper, D, Apache Tribe of Oklahoma ML24120A2962024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Kaskaske, D, Kickapoo Tribe of Oklahoma ML24120A3002024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Morrow, R K, Thlopthlocco Tribal Town ML24120A2922024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Dotson, Delaware Nation ML24120A2952024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Johnson, L.J., Seminole Nation of Oklahoma CP-202400153, (Cpnpp), Registration of Dry Spent Fuel Storage Canisters2024-04-29029 April 2024 (Cpnpp), Registration of Dry Spent Fuel Storage Canisters ML24120A2982024-04-29029 April 2024 Lr Feis Section 106 Consultation Letters, Tribes-Martinez, E, Mescalero Apache Tribe 2024-09-30
[Table view] Category:Safety Evaluation
MONTHYEARML24179A0772024-08-20020 August 2024 Issuance of Amendment Nos. 189 and 189, Respectively, Extension of Allowed Outage Time for an Inoperable Emergency Diesel Generator ML24177A2692024-08-0707 August 2024 Issuance of Amendment Nos. 188 and 188, Respectively, Revision to Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program ML24120A3632024-06-10010 June 2024 Issuance of Amendment Nos. 187 and 187, Respectively Adoption of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Plants ML24023A2962024-02-0909 February 2024 Issuance of Amendment Nos. 186 and 186 Regarding General Design Criterion 5 of Appendix a to 10 CFR Part 50 and Regulatory Guide 1.81 ML23319A3872023-12-20020 December 2023 Issuance of Amendment Nos. 185 and 185 Regarding Implementation of Full Spectrum Loss-of-Coolant Accident (Fsloca) Methodology ML23313A0732023-12-0606 December 2023 Issuance of Amendment Nos. 184 and 184 Regarding Revision to Technical Specifications to Implement WCAP-17661-P-A, Rev. 1, Improved Roac and CAOC Fq Surveillance Technical Specifications ML23237B4282023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 2, Draft Conforming License Amendments ML23237B4302023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 4, Safety Evaluation for Transfer of Licenses and Draft Conforming License Amendments (EPID L-2023-LLM-0000) (Public) ML23198A3212023-07-27027 July 2023 Authorization and Safety Evaluation for Proposed Alternative RV-1 ML22192A0072022-08-22022 August 2022 Issuance of Amendment Nos. 183 and 183 Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-505, Revision 2 ML22194A0592022-07-14014 July 2022 Correction to Amendment Nos. 182 and 182 to Revise Technical Specifications to Adopt TSTF-577, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ML22129A0722022-05-16016 May 2022 Review of Quality Assurance Program Changes ML22077A8412022-03-24024 March 2022 Proposed Alternative SNB-3 for the Snubber Inservice Program Third Interval Extension ML21321A3492022-02-24024 February 2022 Issuance of Amendment Nos. 182 and 182 to Revise Technical Specifications to Adopt TSTF-577, Rev. 1, Revised Frequencies for Steam Generator Tube Inspections ML21322A1032021-12-0707 December 2021 Proposed Alternative for the Continued Use of a Risk-Informed Process for the Selection of Class 1 and 2 Piping Welds for Inservice Inspection ML21132A0892021-06-0909 June 2021 Issuance of Amendment Nos. 181 and 181 Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-567, Rev. 1, Add Containment Sump TS to Address GSI - 191 Issues ML21061A2172021-05-19019 May 2021 Issuance of Amendment Nos. 180 and 180 to Authorize Revision of Certain Emergency Action Levels of the Emergency Plan ML21103A0392021-04-23023 April 2021 Issuance of Amendment Nos. 179 and 179 the Adoption of Technical Specifications Task Force Traveler, TSTF-569, Revision 2, Revise Response Time Testing Definition (EPID L-2020-0147) ML21015A2122021-02-12012 February 2021 Issuance of Amendment Nos. 178 and 178 Regarding One-Time Revision to Technical Specifications 3.7.8 Station Service Water System (Ssws) and 3.8.1 AC Sources - Operating ML21022A1622021-02-0808 February 2021 Proposed Alternative to the Requirements of the ASME OM Code to Extend the Inservice Testing Program Interval for Certain Check and Relief Valves (EPID L-2020-LLR-0096 (COVID-19)) ML21021A1002021-02-0101 February 2021 Proposed Alternative to the Requirements of the ASME OM Code to Extend the Inservice Testing Program Interval for Certain Snubbers (EPID L-2020-LLR-0095 (Covid 19)) ML20346A0192021-02-0101 February 2021 Issuance of Amendment Nos. 177 and 177 Regarding Revision to Technical Specifications 3.8.1, AC Sources - Operating ML21013A1282021-01-28028 January 2021 Approval of Proposed Alternative to the Requirements of the ASME Code to Extend the Third Inservice Inspection Interval (EPID L-2020-LLR-0092 (COVID-19)) ML21021A0022021-01-28028 January 2021 Approval of Proposed Alternatives 1A4-1 and 1A4-2 from Certain Requirements of 10 CFR 50.55a for Inservice Inspection of Nuclear Power Plants ML20282A7092020-11-17017 November 2020 Proposed Alternative to the Requirements of the ASME Omcode to Extend the Inservice Testing Program Interval for Certain Snubbers (EPID L-2020-LLR-0060 (COVID-19)) ML20281A4722020-11-0404 November 2020 Use of Later Code Edition to the Requirements of the ASME OM Code ML20255A1002020-10-0707 October 2020 Proposed Alternative to the Requirements of the ASME OM Code to Extend the Inservice Test Program Interval for Certain Check and Relief Valves (EPID L-2020-LLR-0061 and EPID L-2020-LLR-0062 (COVID-19)) ML20223A3492020-08-31031 August 2020 Issuance of Amendment Nos. 175 and 175 Regarding One-Time Revision to Technical Specification 3.7.19, Safety Chilled Water ML20226A0132020-08-17017 August 2020 Use of Later Code Edition to the Requirements of the ASME Code ML20167A3182020-07-0606 July 2020 Issuance of Amendment Nos. 174 and 174 Regarding Revision to Technical Specifications to Adopt TSTF-563, Revision 0 ML20108E8782020-04-17017 April 2020 Issuance of Amendment Nos. 173 and 173 Revision to TS 5.5.9, Unit 1 Model D76 and Unit 2 Model D5 Steam Generator (SG) Program (Exigent Circumstances) ML20054A2762020-02-27027 February 2020 Approval of Change to the Quality Assurance Program as Described in the Comanche Peak Nuclear Power Plant Final Safety Analysis Report ML19267A0182019-11-0404 November 2019 Issuance of Amendment Nos. 172 and 172 to Revise Augmentation Times and Emergency Response Organization Staffing for the Emergency Plan ML18304A4872018-11-30030 November 2018 Issuance of Amendments 171 and 171 Regarding Revision to Technical Specifications for Engineered Safety Feature Actuation System Instrumentation ML18267A3842018-10-25025 October 2018 Issuance of Amendment Nos. 170 and 170 Revision to Technical Specification 3.8.4, DC Sources - Operating, Condition B (Exigent Circumstances) ML18221A6322018-08-15015 August 2018 Eicb Safety Evaluation - Comanche Peak Nuclear Power Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.3.2 Engineered Safety Feature Actuation System Instrumentation Docket/Epid 000976/05000446/L-2018-LLA-0 ML17129A0242017-06-29029 June 2017 Comanche Peak Nuclear Power Plant, Units 1 and 2 - Issuance of Amendment Nos. 169 and 169 Re: Administrative Change to Licensee Name (CAC Nos. MF8933 and MF8934) ML17074A4942017-04-13013 April 2017 Issuance of Amendment Nos. 168 and 168 Adoption of TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing ML17095A2512017-04-0707 April 2017 Request for Alternative 2B3-1 Re Examination of Reactor Vessel Closure Head Penetration Nozzles ML16334A1732016-12-14014 December 2016 Comanche Peak Nuclear Power Plant, Units 1 And 2; Safety Evaluation Regarding Implementation Of Mitigating Strategies And Reliable Spent Fuel Pool Instrumentation Related To Orders EA-12-049 And EA-12-051 ML16179A4052016-07-11011 July 2016 Relief Request Nos. B-9, B-3, B-10, and B-11 for Piping Welds, Second 10-year Inservice Inspection Interval ML16137A0562016-06-14014 June 2016 Issuance of Amendment Nos. 166 and 166, Request to Revise Emergency Action Levels Based on Nuclear Energy Institute (NEI) 99-01, Revision 6 ML16096A2642016-05-0606 May 2016 Draft Conforming Amendments, Application for Order Approving Direct and Indirect Transfer of Licenses and Conforming License Amendments ML16096A2662016-05-0606 May 2016 Redacted Letter, Order, Safety Evaluation, and Draft Conforming Amendments, Application for Order Approving Direct and Indirect Transfer of Licenses and Conforming License Amendments ML16074A0012016-03-14014 March 2016 Relief Request 1B3-3, Alternative for Reactor Pressure Vessel Cold Leg Weld Inspection Frequency from Not to Exceed 7 Years to 9 Years for the Third 10-Year Inservice Inspection Interval ML16063A0012016-03-11011 March 2016 Relief Request No. B-15, C-2, and C-4 for Welds in the RPV and Containment Spray and Residual Heat Removal Heat Exchanger Shells, Second 10-year Inservice Inspection Interval ML16011A0732016-01-19019 January 2016 Relief Request T-1; Alternative to the ASME OM Code Frequency Specifications for Inservice Testing for the Third 10-Year IST Interval ML15309A0732015-12-30030 December 2015 Issuance of Amendment Nos. 165 and 165, Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, to Increase ILRT Test Interval from 10 to 15 Years and Type C Tests from 60 to 75 Mos ML15259A0042015-10-30030 October 2015 Relief Request 1B3-4, Alternative for Reactor Pressure Vessel Head Penetration Weld Inspection Frequency (from 10 to 15 Years), Third 10-Year Inservice Inspection Interval ML15257A2422015-09-18018 September 2015 Relief Request 2A3-1, from ASME Code Section XI Requirements, Risk-Informed Process for Selection of Class 1 and Class 2 Piping Weld Examinations, Third 10-Year Inservice Inspection Interval 2024-08-07
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 19, 2016 Mr. Rafael Flores Senior Vice President and Chief Nuclear Officer Attention: Regulatory Affairs Luminant Generation Company LLC P.O. Box 1002 Glen Rose, TX 76043
SUBJECT:
COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2 - RELIEF REQUEST NO. T-1 FOR APPROVAL OF AN ALTERNATIVE TO THE INSERVICE TESTING FREQUENCY REQUIREMENTS OF AMERICAN SOCIETY OF MECHANICAL ENGINEERS CODE FOR OPERATION AND MAINTENANCE OF NUCLEAR POWER PLANTS (CAC NOS. MF6405 AND MF6406)
Dear Mr. Flores:
By letter dated June 30, 2015 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML15198A150), as supplemented by letter dated November 5, 2015 (ADAMS Accession No. ML15322A158), Luminant Generation Company LLC (the licensee) submitted Relief Request (RR) T-1 to the U.S. Nuclear Regulatory Commission (NRC) for Comanche Peak Nuclear Power Plant (CPNPP), Units 1 and 2, for the third 10-year inservice testing (IST) interval.
Pursuant to Title 10 of the Code of Federal Regulations (10 CFR) paragraph 50.55a(z)(2), the licensee requested to use the proposed alternative in determining acceptable tolerances for pump and valve test frequencies, as specified in American Society of Mechanical Engineers Code for Operation and Maintenance of Nuclear Power Plants (ASME OM Code), Code Case OMN-20, "lnservice Test Frequencies," on the basis that ASME OM Code requirements present an undue hardship without a compensating increase in the level of quality and safety.
The NRC staff has reviewed the subject request and concludes, as set forth in the enclosed safety evaluation, that the proposed alternative in RR T-1 provides reasonable assurance of operational readiness of the affected components, and complying with the ASME OM Code requirements would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety. Accordingly, the NRC staff concludes that the licensee has adequately addressed all of the regulatory requirements set forth in 10 CFR 50.55a(z)(2).
Therefore, the NRC staff authorizes RR T-1 for the remainder of the CPNPP, Units 1 and 2, third 10-year IST program interval, which began on August 3, 2013, and is scheduled to end on August 2, 2023. All other ASME OM Code requirements for which relief was not specifically requested and approved in the subject request remains applicable.
R. Flores If you have any questions, please contact Balwant K. Singal at 301-415-3016 or via e-mail at Balwant.Singal@nrc.gov.
Sincerely, Robert J. Pascarelli, Chief Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-445 and 50-446
Enclosure:
Safety Evaluation cc w/encl: Distribution via Listserv
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELIEF REQUEST T-1 THIRD 10-YEAR INSERVICE TESTING INTERVAL LUMINANT GENERATION COMPANY LLC COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2 DOCKET NOS. 50-445 AND 50-446
1.0 INTRODUCTION
By letter dated June 30, 2015 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML15198A150), as supplemented by letter dated November 5, 2015 (ADAMS Accession No. ML15322A158), Luminant Generation Company LLC (the licensee) submitted Relief Request (RR) T-1 to the U.S. Nuclear Regulatory Commission (NRC) for Comanche Peak Nuclear Power Plant (CPNPP), Units 1 and 2, for the third 10-year inservice testing (IST) interval. Pursuant to Title 10 of the Code of Federal Regulations (10 CFR) paragraph 50.55a(z)(2), the licensee requested to use the proposed alternative in determining acceptable tolerances for pump and valve test frequencies, as specified in American Society of Mechanical Engineers Code for Operation and Maintenance of Nuclear Power Plants (ASME OM Code), Code Case OMN-20, "lnservice Test Frequencies," on the basis that ASME OM Code requirements present an undue hardship without a compensating increase in the level of quality and safety.
2.0 REGULATORY EVALUATION
Paragraph 10 CFR 50.55a(f), "lnservice testing requirements," requires, in part, that IST of certain ASME Code Class 1, 2, and 3 components must meet the requirements of the ASME OM Code and applicable addenda, except where alternatives have been authorized by the NRC pursuant to paragraphs (z)(1) or (z)(2) of 10 CFR 50.55a.
Paragraph 10 CFR 50.55a(z), states, in part, that alternatives to the requirements of 10 CFR 50.55a(f) may be authorized by the NRC if the licensee demonstrates that: (1) the proposed alternative provides an acceptable level of quality and safety, or (2) compliance with the specified requirements would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety.
Based on the above, and subject to the following technical evaluation, the NRC staff finds that regulatory authority exists for the licensee to request and the Commission to grant the relief requested by the licensee.
Enclosure
3.0 TECHNICAL EVALUATION
The Code of record for CPNPP, Units 1 and 2, third 10-year IST program is the 2004 Edition through 2006 Addenda of ASME OM Code. The third 10-year IST program interval at CPNPP, Units 1 and 2, began on August 3, 2013, and is scheduled to end on August 2, 2023.
- 3. 1 Licensee's Alternative Request T-1 3.1.1 Applicable Code Requirements This request applies to the frequency specifications of the ASME OM Code. The frequencies for tests given in the ASME OM Code include the following, but do not include a tolerance band:
- ISTA-3120, "lnservice Test Interval," (a) states, "The frequency for inservice testing shall be in accordance with the requirements of Section IST."
- ISTB-3400, "Frequency of lnservice Tests," states, "An inservice test shall be run on each pump as specified in Table ISTB-3400-1."
- ISTC-3510, "Exercising Test Frequency," states, "Active Category A, Category B, and Category C check valves shall be exercised nominally every 3 months, except as provided by ISTC-3520, ISTC-3540, ISTC-3550, ISTC-3570, ISTC-5221, and ISTC-5222. Power-operated valves shall be exercise tested once per fuel cycle."
- ISTC-3540, "Manual Valves," states, "Manual valves shall be full-stroke exercised at least once every 2 years, except where adverse conditions may require the valve to be tested more frequently to ensure operational readiness.
Any increased testing frequency shall be specified by the Owner. The valve shall exhibit the required change of obturator position."
- ISTC-3630, "Leakage Rate for Other Than Containment Isolation Valves," (a)
"Frequency," states, "Tests shall be conducted at least once every 2 years."
- ISTC-3700, "Position Verification Testing," states, in part, "Valves with remote position indicators shall be observed locally at least once every 2 years to verify that valve operation is accurately indicated."
- ISTC-5221, "Valve Obturator Movement," (c)(3), states, "At least one valve from each group shall be disassembled and examined at each refueling outage; all valves in each group shall be disassembled and examined at least once every 8 years."
- Mandatory Appendix I, "lnservice Testing of Pressure Relief Devices in Light-Water Reactor Nuclear Power Plants," 1-1320, "Test Frequencies, Class 1 Pressure Relief Valves," (a), "5-Year Test Interval," states, in part, "Class 1 pressure relief valves shall be tested at least once every 5 years, starting with initial electric power generation."
- Mandatory Appendix I, 1-1330, "Test Frequency, Class 1 Nonreclosing Pressure Relief Devices," states, "Class 1 nonreclosing pressure relief devices shall be replaced every 5 years unless historical data indicates a requirement for more frequent replacement."
- Mandatory Appendix I, 1-1340, "Test Frequency, Class 1 Pressure Relief Valves That Are Used for Thermal Relief Application, states, "Tests shall be performed in accordance with 1-1320, Test Frequencies, Class 1 Pressure Relief Valves."
- Mandatory Appendix I, 1-1350, "Test Frequency, Classes 2 and 3 Pressure Relief Valves, (a), "10-Year Test Interval, states, in part, "Class 2 and 3 pressure relief valves, with the exception of PWR [pressurized-water reactor] main steam safety valves, shall be tested every 10 years, starting with initial electric power generation."
- Mandatory Appendix I, 1-1360, "Test Frequency, Classes 2 and 3 Nonreclosing Pressure Relief Devices, states, "Classes 2 and 3 nonreclosing pressure relief devices shall be replaced every 5 years, unless historical data indicates a requirement for more frequent replacement."
- Mandatory Appendix I, 1-1370, "Test Frequency, Classes 2 and 3 Primary Containment Vacuum Relief Valves, (a) states, "Tests shall be performed on all Classes 2 and 3 containment vacuum relief valves at each refueling outage or every 2 years, whichever is sooner, unless historical data requires more frequent testing." 1-1370 (b) states "Leak tests shall be performed on all Classes 2 and 3 containment vacuum relief valves at a frequency designated by the Owner in accordance with Table ISTC-3500-1."
- Mandatory Appendix I, 1-1380, "Test Frequency, Classes 2 and 3 Vacuum Relief Valves, Except for Primary Containment Vacuum Relief Valves, states, "All Classes 2 and 3 vacuum relief valves shall be tested every 2 years, unless performance data suggest the need for a more appropriate test interval."
- Mandatory Appendix I, 1-1390, "Test Frequency, Classes 2 and 3 Pressure Relief Devices That Are Used for Thermal Relief Application, states, "Tests shall be performed on all Classes 2 and 3 relief devices used in thermal relief application every 1O years, unless performance data indicate more frequent testing is necessary. In lieu of tests the Owner may replace the relief devices at a frequency of every 10 years, unless performance data indicate more frequent replacements are necessary."
3.1.2 Components for which Relief is Requested All pumps and valves contained within the CPNPP, Units 1 and 2, IST Program scope.
3.1.3 Licensee's Reason for Requesting Relief In its letter dated November 5, 2015, the licensee stated, in part, that:
ASME OM Code Section IST establishes the inservice test frequency for all components within the scope of the Code. The frequencies (e.g., quarterly) have always been interpreted as "nominal" frequencies (generally as defined in the Table 3.2 of NUREG-1482, Guidelines for lnservice Testing at Nuclear Power Plants, Revision 2 [,dated October 2013 (ADAMS Accession No. ML13295A020)]) and owners routinely applied the surveillance extension time period (i.e., grace period) contained in the plant Technical Specifications (TSs) Surveillance Requirements (SRs). The TSs typically allow for a less than or equal to 25% extension of the surveillance test interval to accommodate plant conditions that may not be suitable for conducting the surveillance (TS SR 3.0.2).
However, Regulatory Issue Summary 2012-10, NRC Staff Position on Applying Surveillance Requirements (SRs) 3.0.2 and 3.0.3 to Administrative Controls Program Tests, [dated August 23, 2012 (ADAMS Accession No. ML12079A393),]
states that SR 3.0.2 and 3.0.3 cannot be applied to TS 5.5, Programs and Manuals, for tests that are not associated with a TS SR TS SR 3.0.2 is equivalent to SR 3.0.2 contained in NUREG-1431, Standard Technical Specifications, Westinghouse Plants, [Revision 4 (ADAMS Accession No. ML12100A222)]
The lack of a tolerance band on the ASME OM Code inservice test frequency restricts operational flexibility. There may be a conflict where a surveillance test could be required (i.e., its frequency could expire), but where it is not possible or not desired that it be performed until sometime after a plant condition or associated Limiting Condition for Operation (LCO) is within its applicability.
The NRC recognized this potential issue in the TSs by allowing a frequency tolerance as described in TS SR 3.0.2. The lack of a similar tolerance applied to the [ASME] OM Code testing places an unusual hardship on the plant to adequately schedule work tasks without operational flexibility.
Thus, just as with TS-required surveillance testing, some tolerance is needed to allow adjusting [ASME] OM Code testing intervals to suit the plant conditions and other maintenance and testing activities. This assures operational flexibility when scheduling surveillance tests that minimize the conflicts between the need to complete the surveillance and plant conditions.
3.1.4 Licensee's Proposed Alternative The licensee proposed to use ASME OM Code Case OMN-20, repeated below, for determining acceptable tolerances for pump and valve test frequencies. The proposed alternative will be
utilized for the remainder of the third 10-year interval and will apply to the various frequency specifications of the ASME OM Code for all pumps and valves contained within the IST Program scope.
ASME OM Code Case OMN-20, "lnservice Test Frequency" ASME OM, Division 1, Section IST and earlier editions and addenda of ASME OM Code specify component test frequencies based either on elapsed time periods (e.g., quarterly, 2 years, etc.)
or on the occurrence of plant conditions or events (e.g., cold shutdown, refueling outage, upon detection of a sample failure, following maintenance, etc.). ASME OM Code, Code Case OMN-20, describes test frequency grace periods associated with the IST program for pumps and valves as follows:
(a) Components whose test frequencies are based on elapsed time periods shall be tested at the frequencies specified in Section IST with a specified time period between tests as shown in [the table below].
Frequency Specified Time Period Between Tests Quarterly 92 days (or everv 3 months)
Semiannually 184 days (or everv 6 months)
Annually (or every vear) 366 days x calendar years x Years where 'x' is a whole number of vears ~ 2 The specified time period between tests may be reduced or extended as follows:
- 1) For periods specified as less than 2 yr, the period may be extended by up to 25 percent for any given test.
- 2) For periods specified as greater than or equal to 2 yr, the period may be extended by up to 6 months for any given test.
- 3) All periods specified may be reduced at the discretion of the owner (i.e., there is no minimum period requirement).
Period extension is to facilitate test scheduling and considers plant operating conditions that may not be suitable for performance of the required testing (e.g.,
performance of the test would cause an unacceptable increase in the plant risk profile due to transient conditions or other ongoing surveillance, test or maintenance activities). Period extensions are not intended to be used repeatedly merely as an operational convenience to extend test intervals beyond those specified.
Period extensions may also be applied to accelerated test frequencies (e.g.,
pumps in alert range) and other less than 2-yr test frequencies not specified in
[the table above].
Period extensions may not be applied to the test frequency requirements specified in [ASME OM Code] Subsection ISTD, Preservice and lnservice Examination and Testing of Dynamic Restraints (Snubbers) in Light-Water Reactor Nuclear Power Plants, as Subsection ISTD contains its own rules for period extensions.
(b) Components whose test frequencies are based on the occurrence of plant conditions or events may not have their period between tests extended except as allowed [the ASME OM Code].
3.1.5 NRC Staff Evaluation Historically, licensees have applied and the NRC staff has accepted the standard TS definitions for IST interval (including allowable interval) extensions) to ASME OM Code required testing (Reference NUTEG-1482, Revision 2, Section 3.1.3). Recently, the NRC staff reconsidered the allowance of the TS testing intervals and interval extensions, for IST not associated with TS SRs. As noted in Regulatory Issue Summary (RIS) 2012-10, the NRC determined that programmatic test frequencies cannot be extended in accordance with the TS SR 3.0.2. This includes all IST described in the ASME OM Code not specifically required by the TS SRs. The lack of a tolerance band on the ASME OM Code IST frequency restricts operational flexibility. There may be a conflict where IST could be required (i.e., the frequency could expire), but where it is not possible or not desired that it be performed until after a plant condition or associated Limiting Condition for Operation is within its applicability. Therefore, to avoid this conflict, the IST should be performed when plant conditions allow.
The NRC staff recognized that, just as with TS-required surveillance testing, some tolerance is needed to allow adjusting ASME OM Code testing intervals to suit the plant conditions and other maintenance and testing activities. To provide operational flexibility when scheduling IST that minimize the conflicts between the need to complete the testing and plant conditions, the NRC staff sponsored and co-authored an ASME OM Code inquiry and Code Case to modify the ASME OM Code to include TS-like test interval definitions and interval extension criteria. The resultant ASME-Approved Code Case OMN-20, as described above, was approved by the ASME Operation and Maintenance Standards Committee on February 15, 2012, with the NRC representative voting in the affirmative. Code Case OMN-20 was subsequently published in conjunction with the 2012 Edition of ASME OM Code.
Requiring the licensee to meet the ASME OM Code requirements, without an allowance for defined frequency and frequency extensions for IST of pumps and valves, results in a hardship without a compensating increase in the level of quality and safety. Based on that the licensee proposed to adopt the ASME OM Code Case OMN-20 in its entirety, the NRC staff concludes that implementation of this ASME OM Code Case provides reasonable assurance of operational readiness of pumps and valves subject to the IST requirements of ASME OM Code.
4.0 CONCLUSION
As set forth above, the NRC staff determines that the proposed alternative in RR T-1 provides reasonable assurance of operational readiness of the affected components, and complying with the ASME OM Code requirements would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety. Accordingly, the NRC staff concludes that the licensee has adequately addressed all of the regulatory requirements set forth in 10 CFR 50.55a(z)(2).
Therefore, the NRC staff authorizes RR T-1 for the remainder of the CPNPP, Units 1 and 2, third 10-year IST program interval, which began on August 3, 2013, and is scheduled to end on August 2, 2023. All other ASME OM Code requirements for which relief was not specifically requested and approved in the subject request remains applicable.
Principal Contributor: John Huang, NRR/DE/EPNB Date: January 19, 2016
R. Flores If you have any questions, please contact Balwant K. Singal at 301-415-3016 or via e-mail at Balwant.Singal@nrc.gov.
Sincerely, IRA/
Robert J. Pascarelli, Chief Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-445 and 50-446
Enclosure:
Safety Evaluation cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsNrrDorllpl4-1 Resource LPL4-1 Reading RidsNrrLAJBurkhardt Resource RidsACRS_MailCTR Resource RidsNrrPMComanchePeak Resource RidsNrrDeEpnb Resource RidsRgn4MailCenter Resource RidsNrrDorlDpr Resource JHuang, NRR/DE/EPNB ADAMS Access1on No. ML16011A073 *M emo dae t d J anuary 6 2016 OFFICE NRR/DORL/LPL4-1 /PM NRR/DORL/LPL4-1 /LA NRR/DE/EPNB/BC NRR/DORL/LPL4-1 /BC NAME BSingal JBurkhardt DAiiey* RPascarelli DATE 1/14/16 1/12/16 01/06/16 1/19/16 OFFICIAL AGENCY RECORD