|
---|
Category:GENERAL EXTERNAL TECHNICAL REPORTS
MONTHYEARML17286B2761991-07-31031 July 1991 Rev 0 to Washington Nuclear Plant 3 Seismic Design Basis Model Validation,Soil Variation Studies. ML17286B2681991-05-0707 May 1991 Justification for Revised Tornado Design Criteria. ML20147D3921988-02-29029 February 1988 Seismic Hazards Assessment for Washington Nuclear Plant-3, Satsop,Wa Contract C-20453, Final Rept ML20211A8421986-09-0808 September 1986 Final Rept of Earthwork Module C3-01 of Facility Const Assurance Program of Facility Readiness Review Program ML20203E6321986-06-30030 June 1986 Validation of Ebasco Foundation Spring Modeling for Elastic Half-Space Seismic Model ML20132H0331985-07-31031 July 1985 Rev 1 to Evaluation of Itt/Grinnel Figure 215 Stiff Clamp Application on Safety-Related Piping Sys ML20129A0631985-02-20020 February 1985 Rev 2 to Preservation of Assets Preventative Program ML20090C1221984-06-30030 June 1984 Seismic Dynamic Analysis Comparison of Finite Boundaries Approach & Half-Space Approach ML20105C7121984-01-20020 January 1984 Northwest Us Subduction Zone Seismic Risk Assessment, Proposal to Research Program ML17277B2961983-11-30030 November 1983 Rept to Governor J Spellman of State of Wa & Governor V Atiyeh of State of Or. ML20076C2801983-08-0404 August 1983 Mgt Plan for Extended Const Delay of WNP-3,Executive Summary (Level I & Level II) ML20098C8831983-05-27027 May 1983 Implications of WPPSS Problems on Investor Owned Utils in Pacific Northwest ML20063C0431982-08-20020 August 1982 Info for Antitrust Review of OL Application for WPPSS Nuclear Project 3 ML20053D4291982-05-25025 May 1982 Info for Antitrust Review of OL Application for Wppss 3. ML20052E1911982-02-28028 February 1982 Termination Program Directors Monthly Repts for Feb & Mar 1982 ML20040A3441981-10-14014 October 1981 Mgt Plan for Extended Const Delay. ML20040D5731981-03-26026 March 1981 Alternative Evaluations WNP-4/5. ML19312D7991980-01-31031 January 1980 Groundwater Drainage Sys:Analysis of Sys Performance. Oversize Drawings Encl ML20079E0851980-01-30030 January 1980 Level 1 Mgt Info Rept. Related Info Encl ML19296A0911978-12-0101 December 1978 Wppss Nuc Proj Nos 3 & 5 Groundwater Drainage Sys.Analysis of Sys Performance & Data to Date.Suppl#3. Incl Observation of Piezometer Recordings Rainfall Data,Wall Seepage & Gwds Discharges.Incl Oversize Drawings ML20079E0921978-04-30030 April 1978 Project Status Rept for WNP-1,2,3,4 & 5 ML20100M4121977-09-30030 September 1977 Bidding Documents & Plans & Specs:Spec 3240-18,HVAC Packaged Air Cleaning Units. Records of 820601,0803, & 17,0902 & 27 Telcons Encl 1991-07-31
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20202C8081999-01-22022 January 1999 Safety Evaluation Supporting Order Terminating Construction Permit CPPR-154 ML17292B4791998-12-31031 December 1998 Washington Public Power Supply Sys 1998 Annual Rept. with 981215 Ltr ML17292B2121997-12-31031 December 1997 Washington Public Power Supply Sys Annual Rept for 1997. W/980108 Ltr ML17292A6361996-12-31031 December 1996 Washington Public Power Supply Sys Annual Rept for 1996. W/961212 Ltr ML17291B1501995-12-31031 December 1995 Washington Public Power Supply Sys Annual Rept 1995. W/ 951201 Ltr ML17291A6761994-12-31031 December 1994 Washington Public Power Supply Sys 1994 Annual Rept. W/ 950302 Ltr ML17290A9581993-12-31031 December 1993 Washington Public Power Supply Sys Annual Rept,1993. W/940209 Ltr ML17289B1231992-12-31031 December 1992 Washington Public Power Supply Sys 1992 Annual Rept. W/930119 Ltr ML17289A2761991-12-31031 December 1991 Washington Public Power Supply Sys 1991 Annual Rept. W/ 920128 Ltr ML17286B2761991-07-31031 July 1991 Rev 0 to Washington Nuclear Plant 3 Seismic Design Basis Model Validation,Soil Variation Studies. ML20079B8591991-06-10010 June 1991 Interim Deviation/Noncompliance Rept 067 Re dry-type Insulator Cracking in Transformer Supplied by Westinghouse.Initially Reported on 910513.Util Notified Vendor on 910430 That Problem Affects Class 1E Transformer ML17286B2681991-05-0707 May 1991 Justification for Revised Tornado Design Criteria. ML17286A5541990-12-31031 December 1990 WPPSS,1990 Annual Financial Rept. W/910115 Ltr ML17285A9891989-12-31031 December 1989 WPPSS,1989 Annual Rept. W/900129 Ltr ML20245B8701989-04-21021 April 1989 Deficiency & Part 21 Rept Re Degradation of Nonmetallic Components & Sludge Formation in Lubricating Oil.Initially Reported on 890327.Degradation of Nonmetallic Parts & Fouled Bearings Evaluated ML20154D3231988-05-16016 May 1988 Safety Evaluation Supporting Util 841102 & 860310 Requests for Extension of Plant Const Completion Date from 850101 to 990701 ML20147D3921988-02-29029 February 1988 Seismic Hazards Assessment for Washington Nuclear Plant-3, Satsop,Wa Contract C-20453, Final Rept ML17279A7641987-12-31031 December 1987 WPPSS,1987 Annual Rept. W/880108 Ltr ML20236P0061987-11-13013 November 1987 Final Part 21 & Deficiency Rept Re Failure of LPSI Pump When Energized.Initially Reported on 840523.Results of C-E Analytical & Test Program Showed That Excessive Shaft Deflection Eliminated by Use of Larger Diameter Motor Shaft ML20215C3061987-06-11011 June 1987 Safety Evaluation Supporting Application of Modified Itt/ Grinnell Stiff Clamps for Use in safety-related Piping Sys ML20214M6471987-05-27027 May 1987 Final Deficiency Rept NY-QA-8 Re Atwood & Morrill Natural Frequency ASME III Active Valves,Identified During Ebasco Engineering Review.Initially Reported on 870515.Valves Will Be Reanalyzed & Modified.Not Reportable Per 10CFR50.55(e) ML20214E4681987-05-15015 May 1987 Deficiency Rept Re Natural Frequency of ASME III Active Valves.Initially Reported on 870413.Interim/final Rept Will Be Submitted by 870527 ML17278B1731986-12-31031 December 1986 Wppss Annual Rept 1986. ML20207F1031986-12-18018 December 1986 Final Deficiency Rept Re Four Elgar Corp Static Uninterruptible Power Supply Units That Could Potentially Result in Failure of Class 1E 120-volt Vital Ac Bus. Condition Not Reportable Per 10CFR50.55(e) ML20214W7711986-11-26026 November 1986 Interim Deficiency Rept Re Uninterruptible Power Supply Assembly Deficiencies.Initially Reported on 860708. Final Rept Will Be Provided by 870116 ML20215G5351986-10-10010 October 1986 Part 21 Rept Re Vendor Tests of air-operated Diaphragm Valves Revealing Natural Frequencies Less than Required Values of 33 Hz.Initially Reported on 841227.No Adverse Effects Noted During Testing ML20215G6801986-10-10010 October 1986 Part 21 Rept Re Vendor Tests of air-operated Diaphragm Valves Revealing Natural Frequencies Less than Required Values of 33 Hz.Initially Reported on 841227.No Adverse Effects Noted During Testing ML20211A8421986-09-0808 September 1986 Final Rept of Earthwork Module C3-01 of Facility Const Assurance Program of Facility Readiness Review Program ML20212N1371986-08-25025 August 1986 Part 21 Rept Re Potentially Defective Operation of Synchro-Start Products,Inc Synchronizing Speed Switches Used in Auxiliary Generating Equipment.Initally Reported on 860820.Next Rept Will Be Submitted by 860926 ML20205G0201986-08-0808 August 1986 Interim Deficiency Rept 64 Re Uninterruptible Power Supply Assembly Defects.Initially Reported on 860708.Cracked or Stressed Fuse Blocks Will Be Replaced by Nov 1986.Final Rept Anticipated by 861201 ML20203E6321986-06-30030 June 1986 Validation of Ebasco Foundation Spring Modeling for Elastic Half-Space Seismic Model ML20198N5431986-05-31031 May 1986 Addendum to CEN-315 Summary of Diversity Between Reactor Trip Sys & Auxiliary Feedwater Actuation Sys for C-E Plants ML20202H2271986-03-26026 March 1986 Part 21 & Final Deficiency Rept D/N 62 Re Potential Overspeed Trip in Diesel Generators Mfg by Colt Industries. Initially Reported on 860224.Vendor Forwarded Proposed Mods Whereby Air Will Be Positively Vented After Engine Started ML20140A7621986-02-28028 February 1986 Informs of Plans for Implementing Severe Accident Policy Statement & Regulatory Use of New source-term Info ML20151Y8141986-02-0404 February 1986 Part 21 Rept Re Colt-Pielstick Engine Tripping Out on High Speed When Started for Test Purposes at Seabrook.Caused by Source of Air Pressure Staying On.Engines Will Be Modified to Positively Vent Air from Rack Boost Cylinder ML17278A6141985-12-31031 December 1985 Wppss 1985 Annual Rept. W/860225 Ltr ML20137J4601985-12-27027 December 1985 Interim Deficiency Rept Re Rejectable Suction Nozzle Weld Defect on Ingersoll-Rand HPSI Pump.Initially Reported on 851127.C-E Performing Technical Review of Defect.Final Rept Will Be Submitted Upon Receipt of C-E Review Results ML20138D7281985-11-30030 November 1985 Draft SER Re Status of Staff Review of FSAR & Associated Submittals Until Const Delay Announced in 1983 ML20133E1111985-09-27027 September 1985 Final Part 21 & Deficiency Rept D/N 59 Re Possible Fractured or Cracked Welds on Louis Allis Emergency Standby Generators.Initially Reported on 850624.Item Not Reportable Per 10CFR50.55(e) ML20209H8381985-09-0404 September 1985 Final Part 21 & Deficiency Rept 58 Re Titus Products Tension Wires.Initially Reported on 850311.Tension Wires Replaced & Air push-on Locknuts Installed to Secure Wires to Shafts of Air Deflection Blades ML20132H0331985-07-31031 July 1985 Rev 1 to Evaluation of Itt/Grinnel Figure 215 Stiff Clamp Application on Safety-Related Piping Sys ML20133P1611985-07-24024 July 1985 Interim Part 21 & Deficiency Rept D/N 59 Re Cracked Welds on Diesel Generator Air Deflectors Supplied by Louis-Allis Co. Initially Reported on 850624.Corrective Actions Not Received from Vendor.Next Rept Expected by 850927 ML20128K1911985-07-0101 July 1985 Deficiency Rept D/N 52 Re LPSI Pump Failures.Pump Evaluation Necessary for Final Rept Not Yet Received.Final Rept to Be Provided as Soon as Info Received ML20115J9201985-04-0101 April 1985 Final Deficiency Rept Re Brown Boveri Voltage Balance Relays W/Excessive Operating Time.Initially Reported on 850227. Relays Removed from Control Panels & Returned to Vendor for Replacements.Item Not Reportable Per 10CFR50.55(e) ML20115D0491985-03-29029 March 1985 Interim Deficiency Rept (D/N 58) Re Titus Model 272 Grille Tension Wire Failing to Remain in Place.Initially Reported on 850311.Existing Tension Wires Will Be Replaced ML20112E6631985-03-0707 March 1985 Interim Deficiency Rept Re Failure of Borg-Warner 2-inch HPSI Header Isolation Valves.Initially Reported on 850204. Opening Torque Switch Light Bypassed & Valve Yoke Tack Welded to Valve Body ML20129A0631985-02-20020 February 1985 Rev 2 to Preservation of Assets Preventative Program ML17277B6301984-12-31031 December 1984 1984 Annual Rept. W/850222 Ltr ML20113A5381984-12-27027 December 1984 Final Part 21 & Deficiency Rept Re Damaged Wires on Westinghouse Ds/Dsl Circuit Breakers.Initially Reported on 841012.Damaged Wires Will Be Replaced & Addl Wire Ties Installed ML20101B1571984-12-0303 December 1984 Corrected Final Deficiency Rept (D/N 55) Re Foxboro N-2AC Module Fuse Pin Damage.Fabrication Dates for Defective Modules Should Be May 1981 - Jul 1982 1999-01-22
[Table view] |
Text
i l
WNP-4/5 TERMINATION PROGRAM DIRECTOR'S MONTHLY REPORT R. A. DE LORENZO PROGRAM DIRECTOR WNP-4/5 TERMINATION
!$R C 0 0 9 R PDR
k MONTHLY PROGRESS WASHINGTON PUBLIC POWER SUPPLY SYSTEM l DATE: 2 28tB2 REPORT 4l5 TERMINATION PROGHAM ; NAME: R. A. DELORENZO
{
t INTRODUCTION ON JANUARY 22,1982, THE BOARD OF DIRECTORS TERM'NATED THE WNP.4 AND WNP-5 PROJECTS. ONE WEEK LATER, THEY APPROVED AS A
" DRAFT," THE MANAGEMENT PLAN FOR TERMINATION OF WNP-4/5. THE PLAN REQUIRED ISSUANCE OF A MONTHLY STATUS REPORT PROVIDING AN UPDATE OF PROGRESS, RELATIVE TO BUDGET AND SCHEDULE, IN THE FINANCIAL, COMMERCIAL AND MATERIALS MANAGEMENT AREAS. THIS IS THE FIRST MONTHLY STATUS REPORT, AND COVERS THE PERIOD JANUARY l 22,1982 THROUGH FEBRUARY 28,1982.
l l
[
I I _ _ , .___ _. .. . _ _ _ , _ . _ _ _ _ _ . _ . . . _ _ _ _ _ . _ _ . _ _ . . _ .
MONTHLY PROGRESS DATE: 2l2Bl82 l WASHINGTON PUBLIC POWER SUPPLY SYSTEM REPORT NAME: R. A. DELORENZO 4l5 TERMINATION PROGRAM l
PROGRAM DIRECTOR'S
SUMMARY
WITH THE ISSUANCE OF THE MANAGEMENT PLAN, THE MANAGING DIREC-TOR FORMED THE TERMINATION PROGRAM OFFICE. R. A. DELORENZO WAS APPOINTED PROGRAM DIR2CTOR. OUR INITIAL EFFORTS WERE RELATED TO ESTABLISHMENT OF A PROGRAM TEAM, WHICH WOULD BE RESPONSIBl.E FOR IMPLEMENTATION OF THE PLAN. THAT TEAM HAS BEEN FORMED.
IN THE FIRST WEEK OF FEBRUARY INITIAL DIRECTION WAS PROVIDED TO SUPPLY SYSTEM PERSONNEL REGARDING SUSPENSION OF ANY ONGOING WORK. ALL CONTRACTOR WORK WAS SUSPENDED (STOPPED) EXCEPT WHERE A DEFINITE DECISION TO CONTINUE WORK COULD BE MADE FOR ONE OR MORE OF THE FOLLOWING REASONS:
- TO CONTINUE IN FORCE THE LICENSES FOR WNP-4 AND WNP-5
- CONTINUATION OF WORK RESULTS IN LESS NET COST TO THE PROJECT THAN TERMINATION.
- FOR MAINTENANCE OF SAFETY-RELATED OR LONG-LEAD-TIME MAJOR ITEMS
- TO PERFORM RECEIVING INSPECTIONS AND STORAGE.
- TO CONTINUE DEMOBILIZATION OR CONTRACT CLOSEOUT ALREADY IN PROCESS.
'e. .:.
MONTHLY PROGRESS ! WASHINGTON PUBLIC POWER SUPPLY SYSTEM OATE: 212 818 2 REPORT 4l5 TERMINATION PROGRAM NAME: R. A. DELORENZO l
9
?
PROGRAM DIRECTOR'S
SUMMARY
(CONTINUED)
FURTHER DIRECTION WAS PROVIDED SHORTLY THEREAFTER REGARDING ISSUANCE OF NOTICES OF TERMINATION TO CONTRACTORS AND VENDORS.
NOTICES ARE TO BE ISSUED FOR ALL CONTRACTS EXCEPTWHERE WORK IS TO CONTINUE FOR THE ABOVE REASONS, OR:
- LEAD TIME FOR PROCUREMENT OF THE TERMINATED EQUIPMENT, MATERIAL OR WORK UNDER A NEW OR REISSUED CONTRACT WOULD CRITICALLY IMPACT RESUMPTION OF CONSTRUCTION BY A NEW OWNER.
- TO PERFORM MAINTENANCE OR OTHER WORK ACTIVITIES REQUIRED DURING THE TERMINATION PROGRAM, CONTRACTS TO BE TERMINATED ARE BEING DIVIDED INTO TWO CATEGORIES.
- CATEGORY 1: THOSE CONTRACTS TO BE TERMINATED IMMEDIATELY.
- CATEGORY 2: THOSE CONTRACTS TO BE TERMINATED LATER DURING TERMINATION PHASE I.
CONTRACTS TO REMAIN IN EFFECT ARE CONTAINED IN A SINGLE CATEGORY.
- CATEGORY 3: THOSE CONTRACTS TO REMAIN IN EFFECT DURING PHASE I TO PRESERVE THE ASSETS / LICENSES OR TO ALLOW POSSIBLE SALE OF THE COMPLETE PLANT TO A PROSPECTIVE OWNER.
l
{
i
~ ~ - -
um ~ --
-- . _ _ _ , n MONTHLY PROGRESS WASHINGTON PUBLIC POWER SUPPLY SYSTEM DATE: 212 818 2 REPORT 415 TERMINATION PROGRAM NAME: R. A. DELORENZO C
MAJOR MILESTONES COMPLETED IN FEBRUARY:
- TERMINATION PROGRAM OFFICE ESTABLISHED: TEAM MEMBERS APPOINTED.
- ADMINISTRATIVE AND GENERAL BUDGET AND WBS PROGRAMS DEVELOPED AND FUNCTIONAL.
- NOTIF! CATION OF TERMINATION SENT TO OUTSIDE PARTIES.
- REVIEW / APPROVAL REQUIREMENTS DEFINED FOR COMMERCIAL ACTIONS.
- GARDINlER FUELS CONTRACT SETTLEMENT COMPLETED.
TO BE COMPLETED IN MARCH:
- APPROVAL OF " FINAL" MANAGEMENT PLAN.
- CON.PLETION OF SITE TERMINATION PLANS.
- !DENTIFICATION OF CATEGORY 1, 2, & 3 CONTRACTS.
I l
4 MONTHLY PROGRESS WASHINGTON PUBLIC POWER SUPPLY SYSTEM DATE: 213Bl83 NAME: R. A. DELORENZO REPORT 415 TERMINATION PROGRAM
' i 1
., 0 i
i
! CRITICAL ITEMS.
CRITICAL ITEMS
- PARTICIPANT COMMITMENT TO $70.5 MILLION IN TERMINATION PRO-GRAM LOANS.
- RESOLUTION OF PACIFIC POWER & LIGHT INTERFACE.
l-i i
i i
L
.~. . . . _ . . _ . _ . . _ _ _ .. . . _, . _ _ . - . _ _ _ _ . . _ . _ _ _ _ . _ _ . . - _ , . . - . . . _ - -. . _ _ -
_ . , _ . - , . ~ . .
CONTHLY PROGRESS WASHINGTON PUBLIC POWER SUPPLY SYSTEM OATE: 3l31182 REPORT WNP 415 TERMINATION PROGRAM NAME: R. A. DE LORENZO PROGRAM DIRECTOR'S
SUMMARY
This is the second monthly status report for the WNP-4/5 Termination Program, and covers the period March 1 through March 31,1982. During that period, the Participants fully committed to the $70.5 milion Termination Program loans; executed notes have been provided to the lending Participants. No further action by the Supply System is necessary to make the loan agreements effective.
With the issuance of " Guidelines for WNP-4/5 Contract Termination Settlements,"
and the Program Directive for the "WNP-4/5 Business Action Approval Process,"
the internal Supply System methodology for contract termination and settlement has been established. On-going efforts to identify review and approval requirements by the Participants and Pacific Power & Light Company should lead to revision of the Termination Management Plan, incorporating those re-quirements. In the meantime, negotiations are in process with both the Par-ticipants and PP&L.
The Termination Program Team is in the process of developing a detailed Pro-gram Budget for the termination period (Phase I and Phase 11). Upon completion of budget preparation, the budget will be submitted for internal approval, through the Supply System Board of Directors, and then to the Participants' Committee and PP&L. At this time, there have been no projected expenditures' identified which would cause the total $343 million Termination Budget to be exceeded.
As part of the contract classification efforts, those contracts have been identified which must remain active to preserve the assets, maintain the licenses, and pro-vide for possible resale to another owner. The monthly costs for these contracts have been estimated. Additionally, the costs for Architect / Engineer, Construction Manager, and Owner's Administrative and General expenses have been reviewed to determine an upper bound for these costs. (This is an upper bound because it includes all costs during Phase I in these categories, not just preservation costs).
As a result of these efforts, the following estimated costs reflect the " upper bound" on the costs to preserve the assets / retain the licenses during Phase 1. It should be noted that transition from Phase I to Phase 11 would not eliminate all of these costs.
WNP-4 WNP-5 Total
($ in thousands)
Mar-Dec 1982 (10 Months) $5,066 $6,082 $11,148 Monthly (Average) $ 507 $ 608 $ 1,115 Annualized $6,080 $7,300 $13,380 nm
5 . .
MONTHLY PROGRESS WASHINGTON PUBLIC POWER SUPPLY SYSTEM DATE: 313 118 2 REPORT WNP 415 TERMINATION Pil0 GRAM NAME: R. A. DE LORENZO PROGRAM DIRECTOR'S
SUMMARY
(continued)
Preparation of the Termination Budget will segregate the A/E, CM and Owner's A&G costs for preservation of the assets / retention of the licenses from other Phase '_
I costs. When segregation of those costs allows evaluation of the reduced costs strictly required to preserve the assets / retain the licenses, the revised cost estimates will be published. -
Efforts to sell the projects in their entirety are in the preliminary stages. Actions in-clude establishment of an advisory committee of the Board of Directors (including representatives of the participants and PP&L) and drafting of a summary descrip-tion of the projects for sales purposes, as well as maintenance of the construction permits and preservation of key contracts and assets.
Insufficient information is currently available to determine whether there is a reasonable chance of sale of the plants at a reasonable price, and it would not be justified to foreclose that option until that information becomes known. The most significant item since termination is the independent Review of WNP-4 and WNP-5 mandated by the 1981 Legislature, issued March 22,1982, which recommends that every effort be made to preserve the option of completing the plants.
Sales of component assets and transfers to other Supply System projects are limited to date, in compliance with the guidelines of the Management Plan for Ter-mination. Only one significant disposition, transfer of a $600,000 computer from WNP-4 to WNP-1 has occurred.
(
At this time, the Termination Program Office believes it is prudent to continue to sell non-essential assets (as defined in the Management Plan) and to preserve the assets and retain the licenses, while continuing those efforts directed toward the sale of the complete plants. As further information becomes available the Program Office will continue to review whether it is prudent to continue efforts to sell the projects as complete units and will make appropriate recommendations to the Par-ticipants and PP&L.
b' L
5 M 66 M
u o. ~ . m._ _ __ -. s
. l MONTHLY PROGRESS WASHINGTON PUBLIC POWER SUPPLY SYSTEM DATE: 313 118 2 REPORT WNP 415 TERMINATION PROGRAM NAME: R. A. DE LORENZO 4
g MAJOR MILESTONES COMPLETED IN MARCH:
- PARTICIPANTS' COMMITMENT TO $70.5 MILLION IN CONTROLLED TERMINATION LOAN FUNDS.
- IDENTIFICATION OF CATEGORY 1,2 & 3 CONTRACTS.
- DRAFTS OF SITE TERMINATION PLANS COMPLETE.
SUMMARY
PROJECT DESCRIPTIONS PREPARED FOR SALE OF PLANTS.
TO BE COMPLETED IN APRIL:
- APPROVAL OF " FINAL" MANAGEMENT PLAN.
- APPROVAL OF " FINAL" SITE TERMINATION PLANS.
- PREPARATION OF FY '83 BUDGET.
- ESTABLISHMENT OF SALES TEAM FOR ASSETS DISPOSA.I..
CRITICAL ITEMS
- RESOLUTION OF PACIFIC POWER & LIGHT INTERFACE 6.M F A