RS-14-207, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)

From kanterella
Revision as of 18:50, 5 February 2020 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)
ML14248A231
Person / Time
Site: Clinton Constellation icon.png
Issue date: 08/28/2014
From: Kaegi G
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
EA-12-049, RS-14-207
Download: ML14248A231 (47)


Text

Amor Exelon Generation Order No. EA-12-049 RS-14-207 August 28, 2014 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Clinton Power Station, Unit 1 Facility Operating License No. NPF-62 NRC Docket No. 50-461

Subject:

Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)

References:

1. NRC Order Number EA-12-049, "Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," dated March 12, 2012
2. NRC Interim Staff Guidance JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," Revision 0, dated August 29, 2012
3. NEI 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide,"

Revision 0, dated August 2012

4. Exelon Generation Company, LLC's Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated October 25, 2012
5. Exelon Generation Company, LLC Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated February 28, 2013 (RS-13-019)
6. Exelon Generation Company, LLC First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA 049), dated August 28, 2013 (RS-13-117)
7. Exelon Generation Company, LLC Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA 049), dated February 28, 2014 (RS-14-009)

U.S. Nuclear Regulatory Commission Integrated Plan Report to EA-12-049 August 28, 2014 Page 2

8. NRC letter to Exelon Generation Company, LLC, Clinton Power Station, Unit 1 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) (TAC No. MF0901), dated December 17, 2013 On March 12, 2012, the Nuclear Regulatory Commission ("NRC" or "Commission") issued an order (Reference 1) to Exelon Generation Company, LLC (EGC). Reference 1 was immediately effective and directs EGC to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event. Specific requirements are outlined in of Reference 1.

Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (Reference 2) and an overall integrated plan pursuant to Section IV, Condition C. Reference 2 endorses industry guidance document NEI 12-06, Revision 0 (Reference 3) with clarifications and exceptions identified in Reference 2. Reference 4 provided the EGC initial status report regarding mitigation strategies. Reference 5 provided the Clinton Power Station, Unit 1 overall integrated plan.

Reference 1 requires submission of a status report at six-month intervals following submittal of the overall integrated plan. Reference 3 provides direction regarding the content of the status reports. References 6 and 7 provided the first and second six-month status reports, respectively, pursuant to Section IV, Condition C.2, of Reference 1 for Clinton Power Station.

The purpose of this letter is to provide the third six-month status report pursuant to Section IV, Condition C.2, of Reference 1, that delineates progress made in implementing the requirements of Reference 1. The enclosed report provides an update of milestone accomplishments since the last status report, including any changes to the compliance method, schedule, or need for relief and the basis, if any. The enclosed report also addresses the NRC Interim Staff Evaluation Open and Confirmatory Items contained in Reference 8.

This letter contains no new regulatory commitments. If you have any questions regarding this report, please contact David P. Helker at 610-765-5525.

I declare under penalty of perjury that the foregoing is true and correct. Executed on the 28th day of August 2014.

Respectfully submitted, len T. Kaegi Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC

Enclosure:

1. Clinton Power Station, Unit 1 Third Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events

U.S. Nuclear Regulatory Commission Integrated Plan Report to EA-12-049 August 28, 2014 Page 3 cc: Director, Office of Nuclear Reactor Regulation NRC Regional Administrator - Region III NRC Senior Resident Inspector Clinton Power Station, Unit 1 NRC Project Manager, NRR Clinton Power Station, Unit 1 Ms. Jessica A. Kratchman, NRR/JLD/PMB, NRC Mr. Jack R. Davis, NRR/DPR/MSD, NRC Mr. Eric E. Bowman, NRR/DPR/MSD, NRC Mr. Jeremy S. Bowen, NRR/DPR/MSD/MSPB, NRC Mr. Robert L. Dennig, NRR/DSS/SCVB, NRC Mr. John P. Boska, NRR/DPR/MSD/MSPB, NRC Illinois Emergency Management Agency - Division of Nuclear Safety

Enclosure Clinton Power Station, Unit 1 Third Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (43 pages)

Enclosure Clinton Power Station's Third Six Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events 1 Introduction Clinton Power Station developed an Overall Integrated Plan (Reference 1), documenting the diverse and flexible strategies (FLEX), in response to Reference 2. This enclosure provides an update of milestone accomplishments since submittal of the Overall Integrated Plan, including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any.

2 Milestone Accomplishments None 3 Milestone Schedule Status The following provides an update to Attachment 2 of the Overall Integrated Plan. It provides the activity status of each item, and whether the expected completion date has changed. The dates are planning dates subject to change as design and implementation details are developed.

Original Target Activity Status Completion Date

{Include date changes in this column}

Submit 60 Day Status Report Complete Submit Overall Integrated Complete Implementation Plan Contract with National SAFER Complete Response Center Aug 2013 Submit 6 month update Complete Feb 2014 Submit 6 month update Complete Aug 2014 Submit 6 month update Complete with this submittal Feb 2015 Submit 6 month update Not Started Modification Development Mar 2014

  • Phase 2 modifications Started Dec 2014 National SAFER Response Center Started Operational Procedure development Page 1 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Feb 2015 Strategy procedures Started Feb 2015 Validate Procedures (NEI 12-06, Sect. Not Started 11.4.3)

May 2015 Maintenance procedures Not Started Feb 2015 Staffing analysis Not Started Modification Implementation May 2015

  • Phase 2 modifications Started May 2015 Storage plan and construction Started May 2015 FLEX equipment acquisition Started May 2015 Training completion Started May 2015 Unit 1 Implementation date Not Started 4 Changes to Compliance Method Change 1 Maintain Core Cooling - BWR Portable Equipment Phase 2 - Storage/ Protection of Equipment Reason for Change: Engineering issues associated with staging both FLEX diesel generators in the same room required changing the N+1 FLEX generator storage plan.

Change: A table addressing the guidance in NEI 12-06 Sections 6 through 9 is included in Attachment 1.

Storage / Protection of Equipment:

Describe storage / protection plan or schedule to determine storage requirements Seismic List how equipment is protected or schedule to protect Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section 11.3 and Section 5.3.1.

Schedule to construct permanent buildings is contained in Section 3 of this document, and will satisfy the site compliance date. Temporary locations will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to Clinton Power Station.

With respect to a seismic event, the storage plan does not require clearing debris from a haul path since the portable FLEX pumps and primary FLEX generator are pre-staged near their connection points. FLEX cables, hoses and permanent plant equipment used in the mitigating strategies are all designed to be protected from the seismic event, or will be analyzed or Page 2 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28. 2014 upgraded to ensure their survival.

The N+1 FLEX generator will be mounted on a trailer and stored in the seismically robust FLEX Storage Building. A truck capable of debris removal will also be staged in the FLEX Storage Building, should a condition arise requiring the N+1 generator to be deployed.

Flooding List how equipment is protected or schedule to protect Note: if stored below current Structures to provide protection of FLEX equipment will be constructed to flood level, then ensure meet the requirements of NEI 12-06 Section 11.3 and Section 6.2.3.1.

procedures exist to move Schedule to construct permanent buildings is contained in Section 3 of this equipment prior to exceeding document, and will satisfy the site compliance date. Temporary locations flood level will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to Clinton Power Station.

With respect to flooding, the storage building housing the portable FLEX pumps and portable N+1 FLEX generator will not be protected up to the PMF elevation. Sufficient time will be available to relocate the FLEX pumps and generator to a higher elevation in advance of the rising lake level. The haul path for relocating the FLEX pump will not be affected by the flood.

Since the FLEX pump connection will be submerged, hoses with sufficient capacity to provide the required flow rate will be deployed with the FLEX pump. The hoses will connect to the Diesel Generator Building FLEX manifold to supply the required flow for the mitigating strategies. Station procedures governing high lake level will contain guidance for maintaining ELAP response capability during a flooding event.

Severe Storms with List how equipment is protected or schedule to protect High Winds Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section 11.3 and Section 7.3.1.

Schedule to construct permanent buildings is contained in Section 3 of this document, and will satisfy the site compliance date. Temporary locations will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to Clinton Power Station.

Snow, Ice, and List how equipment is protected or schedule to protect Extreme Cold Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section 11.3 and Section 8.3.1.

Schedule to construct permanent buildings is contained in Section 3 of this document, and will satisfy the site compliance date. Temporary locations will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the Page 3 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 external hazards applicable to Clinton Power Station.

With respect to snow, ice, and extreme cold, the storage plan does not require clearing snow or ice from a haul path since the portable FLEX pumps and primary generator are prestaged near their connection points.

All operator actions during the first hours of the event are performed indoors; either inside the plant or inside the FLEX storage building at the Screen House. The one exception is the foot travel from the plant to the storage building containing the FLEX pumps.

High Temperatures List how equipment is protected or schedule to protect Structures to provide protection of FLEX equipment will be constructed to meet the requirements of NEI 12-06 Section 11.3 and Section 9.3.1.

Schedule to construct permanent buildings is contained in Section 3 of this document, and will satisfy the site compliance date. Temporary locations will be used until building construction completion. Procedures and programs will be developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the external hazards applicable to Clinton Power Station.

Change 2 Safety Functions Support - BWR Portable Equipment Phase 2 Deployment Conceptual Design Reason for Change: This discussion is updated to describe the deployment methods for electrical and mechanical connections.

Change:

Deployment Conceptual Design Strategy Modifications Protection of connections Identify Strategy including Identify modifications Identify how the connection is how the equipment will be protected deployed to the point of use.

Electrical Support (Figure 4)

The primary FLEX

  • A permanently staged primary Phase 2 generator will be 480 VAC generator able to The FLEX electrical connections permanently staged and supply necessary portions of will be completed inside the does not require the 480 VAC distribution Diesel Generator, Control, and deployment. The N+1 system to repower the Division Auxiliary Buildings, which are generator will be housed 1 battery charger or the swing battery charger and other protected from all external in a storage structure that needed AC loads, hazards.

meets NEI 12-06 Rev.0 storage requirements. A

  • Two independent electrical Phase 3 strategies with connection Page 4 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28. 2014 heavy duty truck capable points able to supply necessary The electrical connection for an of clearing debris will be portions of the 480 VAC external generator from the stored in the same distribution system from an National SAFER Response Center location. external source to repower the to the required portions of the Division 1 battery charger or installed 480 VAC system will be Pre-staged cabling will be the swing battery charger to deployed, if needed, from within deployed from the FLEX supply DC MCC 1A, and other the Diesel Generator Building generator to the Unit needed AC loads, through an engineered opening Substations that supply

  • Pre-routed and pre-staged in external wall to the outside the components needed cabling with cam-lock "A2" staging area.

to meet the FLEX timeline. connectors,

  • Installed 480 VAC bus panel inserts to simplify external electrical connections.

Cooling/Makeup Water Support (Figure 3)

The diesel driven pumps

  • One external water connection Phase 2 will be housed in a ties to the Unit 2 robust SX The FLEX mechanical connections storage structure that piping, will be completed inside the meets NEI 12-06 Rev.0
  • One internal water manifold for Diesel Generator, Control, and storage requirements. A cooling/makeup water Auxiliary Buildings, which are heavy duty truck capable distribution, capable of being protected from all external of clearing debris will be supplied from a separate hazards.

stored in the same external pump, location.

  • Various pipe branch Phase 3 connections and valve Water will be routed The mechanical connection for an installations to support from the UHS to the plant external pump from the National manifold distribution, via the unused seismically SAFER Response Center, if
  • Pre-staged hoses with Storz robust Unit 2 SX piping. needed, to the SX system will be fittings to support manifold to branch and valve connections. inside a robust building on the Unit 2 side of the Screen House adjacent to the "Al" staging area.

An alternate connection will be deployed from within the Diesel Generator Building through an engineered opening in the external wall to the outside "A2" staging area using a hose pre-staged for this purpose inside the protected Diesel Generator Building.

Change 3 A - Sequence of Events Timeline Page 5 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28. 2014 Reason for Change:

The timeline for "FLEX pump available for RPV makeup" was improved. This change ensures that the FLEX pump is available for RPV makeup when suppression pool temperature reaches 190°F (the threshhold established for elevated risk to the RCIC system) at approximately to + 6.6 hrs. This change is also responsive to Confirmatory Item 3.2.1.3.A.

Item 25 on the timeline is reworded from "Connect Div 1 Day Tank 120 VAC portable pump" to "Commence FLEX generator and pump refueling operations" to more accurately state the task that requires future validation.

The time to commence lining up the FLEX pump should be at to + 1 hr to ensure the subsequent time constraints can be met.

Changes:

1. The time "FLEX pump available for RPV makeup" occurs on the timeline at to + 6 hrs, and is identified as a time constraint,
2. Reworded item 25 on the timeline,
3. Changed the Elapsed Time value for Item 10 "Commence UHS Pump Deployment" to 1 hr.

Time Remarks / Applicability Action Elapsed Action Constraint (if blank then no change from 01P item Time Y/N submittal) 0 Event starts, Scram, Recirc Pumps Trip NA Level 2 1 RCIC has started and begins to inject NA

+30 sec 2 10 min Control level and pressure per procedures Y 3 29 min Bypass RCIC leak detection isolation logic Y Defeat Low RCIC Steam Supply Pressure 4 1 hr Isolation per CPS 4410.01C001, Defeating N RCIC Interlocks Initiate CPS 4200.01C003, Monitoring CNMT 5 1 hr N Temperatures During A SBO Complete CPS 4200.01C002, DC Load 6 1 hr Y Shedding During A SBO 7 1 hr Initiate Beyond Design Basis FLEX Strategies Y Begin RPV depressurization to 150 psig with 8 1 hr SRVs at 507/hr. Control RPV pressure Y between 150 and 250 psig.

9 1 hr Commence Lining Up FLEX generator N Page 6 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28. 2014 10 1 hr Commence UHS Pump Deployment N Place ADS Backup Air Bottles in service per 11 2 hr Y CPS 3101.01, Main Steam (MS, IS & ADS).

12 5.5 hr Energize MCC 1A3 N 13 5.5 hr Open the SPMU valves Y 14 5.5 hr Energize MCC 1A1 N Startup Div 1 Battery Charger and supply DC 15 5.5 hr Y MCC 1A Energize Hydrogen Igniter Distribution Panel 16 5.5 hr N (MCC 1A1)

Energize DG MCC 1A and Standby Lighting 17 5.5 hr N Cabinet 1LL70EA Confirmatory Item 3.2.1.3.A.

18 6 hr FLEX pump available for RPV makeup Y Improved from previous update.

19 6 hr Open RCIC room doors Y Place FLEX suppression pool cooling strategy 20 8 hr Y in service 21 8 hr Makeup to Suppression Pool as needed Y Initiate supplemental MCR ventilation per 22 12 hr N CPS 4200.01C001, MCR Cooling During A SBO Commence Spent Fuel Pool makeup (>86 23 12 hr Y gpm) as needed 24 12 hr Establish Fuel Bldg steam vent path N Commence FLEX generator and pump 25 14 hr Y refueling operations Commence recharging the ADS backup air 26 24 hr Y bottles with a FLEX air compressor First piece of National SAFER Response 27 24 hr N Center equipment arrives at the staging area Establish RCIC Pump Room compensatory 28 30 hr Y action (portable fan)

Page 7 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Continue to maintain critical functions of core cooling (via RCIC), containment (via alternate suppression pool cooling) and SFP 29 24-72 hr N cooling (FLEX pump injection to SFP). Utilize initial National SAFER Response Center equipment in spare capacity.

Change 4 Attachment 2 BWR Portable Equipment Phase 3 Reason for Change: Phase 3 portable equipment listed in the 01P needed to be updated.

Change:

Brought the Phase 3 portable equipment listing up to date with the National SAFER Response Center Equipment Technical Requirements Manual.

Change 5 Attachment 3 Conceptual Sketches Reason for Change: Changes to deployment plan and system alignments required updated sketches.

Color versions of the figures are available on the ePortal.

Change:

Updated Figures 2 through 5 to reflect advances in the ongoing engineering design.

5 Need for Relief/Relaxation and Basis for the Relief/Relaxation Clinton Power Station expects to comply with the order implementation date and no relief/relaxation is required at this time.

6 Open Items from Overall Integrated Plan and Draft Safety Evaluation The following tables provide a summary of the open items documented in the Overall Integrated Plan or the Draft Safety Evaluation (SE) and the status of each item.

Overall Integrated Plan Open Item Status Initial calculations were used to determine the fuel pool timelines. Formal [Not Started]

calculations will be performed to validate this information during development of the spent fuel pool cooling strategy detailed design, and will be provided in a future six (6) month update.

Page 8 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Analysis of deviations between Exelon's engineering analyses and the See the February 2014 01P Update analyses contained in BWROG document is expected to be completed, for closure information.

documented on Attachment 1B, and provided to the NRC in the August 2013

[Complete]

six (6) month status update.

The times to complete actions in the Events Timeline are based on operating [Not Started]

judgment, the conceptual designs, and the current supporting analyses. The final timeline will be time validated once detailed designs are completed, procedures are developed, and the results will be provided in a future six (6) month update.

Identification of storage locations and creation of the administrative [Started]

program are open items. Closure of these items will be documented in a six (6) month update.

Habitability conditions will be evaluated and a strategy will be developed to Will be tracked under Confirmatory maintain Main Control Room habitability. The strategy and associated Items 3.2.4.2.6 and 3.2.4.6.A.

support analyses will be submitted in a future six (6) month update.

[Closed]

Battery room conditions will be evaluated and a strategy will be developed Will be tracked under Confirmatory to maintain acceptable conditions. The strategy and associated support Item 3.2.4.2.A.

analyses will be submitted in a future six (6) month update.

[Closed]

Inverter room conditions will be evaluated and a strategy will be developed Will be tracked under Confirmatory to maintain acceptable conditions. The strategy and associated support Item 3.2.4.2.C.

analyses will be submitted in a future six (6) month update.

[Closed]

The need for further analysis of fuel building conditions during an Will be tracked under Confirmatory ELAP/LUHS and mitigating actions is an open item. Closure of this item will Item 3.2.2.A.

be documented in a future six (6) month update.

[Closed]

Procedures and programs will be developed to address storage structure Corporate Program Document, CC-requirements, haul path requirements, and FLEX equipment requirements AA-118 drafted.

relative to the external hazards applicable to Clinton Power Station.

[Started]

Draft Safety Evaluation Open Items Item Description Status Number 3.1.4.2.0 No information was provided in the Integrated Plan to The FLEX pump will take suction from address the ultimate heat sink and the potential that the an existing opening on the Screen flow path may be affected by ice blockage or formation of House deck that was designed for a frazil ice due to extreme low temperatures. Unit 2 Shutdown Service Water (SX)

Pump. This location bypasses the Unit 1 traveling screens and is not susceptible to frazil ice.

Page 9 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 It is not susceptible to ice blockage since the inlet to the Screen House is at elevation 670', 5 feet below the design water level of the UHS. The occurrence of an estimated ice thickness of 10" in the intake area when the water level is at elevation 675' would not block the flow into the Screen House. The availability of the FLEX pump water supply will not be affected by ice formation in the Screen House area.

Additional protection against any probable ice blockage in the intake area is provided with the installation of a warming line at the inlet to the Screen House, designed to maintain a minimum water temperature of 40°F during winter operation.

[Complete - Revised]

3.2.4.8.A On page 6 of their six-month update, dated August 28, 2013 See Change 1 in this document.

(Agencywide Documents Access and Management System

[Complete - Revised]

(ADAMS) ML13241A241), the licensee states that they are proposing to pre-stage both the primary and alternate FLEX generator in the Unit 2 side of the Control/Diesel Generator building. This use of pre-staged generators appears to be an alternative to NEI 12-06.1n a future submittal update the licensee will need to document the proposed method as an alternate to NEI 12-06, along with a stronger justification addressing how the approach maintains the flexibility to respond to an undefined event and provide power to the necessary equipment.

Draft Safety Evaluation Confirmatory Items Item Description Status Number 3.1.1.1.A Each section of the Integrated Plan describing protection of See Attachment 1 of this document.

equipment from the hazards makes reference to NEI 12-06,

[Complete - Revised]

Section 11 rather than to the protection guidance described in NEI 12-06 for the applicable hazard; that is 6.2.3.1 for floods, 7.3.1 for wind, etc. The licensee's proposed protection strategy needs to be specific for each Page 10 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 hazard.

3.1.1.2.A The Integrated Plan did not provide sufficient information See the February 2014 01P Update for to conclude that for each mitigation strategy discussed, closure information.

operators would have access only through seismically

[Complete]

robust structures to deploy the strategy. As an example, on page 27 of the Integrated Plan, the deployment plan describes using hoses to connect the FLEX alternate suppression pool cooling pump to the suppression pool and RHR heat exchanger connections. Licensee needs to address this issue generically.

3.1.1.2.B It was not evident from the review of the Integrated Plan See the February 2014 01P Update for whether or not electrical power would be necessary to closure information.

move or to deploy mitigation strategies (e.g., to open the

[Complete]

door from a storage location). If necessary, provisions would be necessary to provide that power source.

3.1.1.3.A The licensee should develop a reference source that See the February 2014 01P Update for provides approaches for obtaining necessary instrument closure information.

readings for instruments in addition to the existing

[Complete]

guidance for the suppression pool temperature instrument.

The suppression pool cleanup and transfer pumps will require a strategy to provide control power to the pump motor supply breakers.

3.1.1.3.B The licensee discussed how internal flooding is mitigated Calculation 3C10-0485-001, Internal for ECCS pump cubicles, but it is not clear whether or not Flooding Analysis, evaluates flooding in other mitigation strategies may be susceptible to the various areas throughout the station internal flooding hazard. due to postulated failures of moderate and high energy systems. One area of particular concern is the 702' elevation of the Control Building where Unit Substations 1F & 1G are located. These busses provide power to Suppression Cooling and Cleanup pumps 1SFO1PA/B which will be used to establish suppression Pool cooling during the extended loss of AC event.

From Calculation 3C10-0485-001 Revision 8 and 8A Internal Flooding Analysis (Reference 6) the flood level in the area of unit subs 1F & 1G is < 6" (specifically 5.8"). The unit substations are mounted on pads that are high, so based on the calc flooding in 702' would impact these busses. It Page 11 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28. 2014 should be noted that this calculation of flood level at 702 is conservative in that no credit is taken for floor drain sumps that are in the vicinity of the Unit Subs.

The small amount of water intrusion that Unit Substations 1F and 1G could experience by the flooding described above would not impact the internal bus bars. Re-energizing the bus would still be possible after the occurrence of the design internal flooding event.

[Complete]

3.1.1.4.A With regard to the use of off site resources, no information Refer to Figure 7. The B Staging Area is was provided regarding the identification of the local arrival shown on the north side of the staging area or a description of the methods to be used to property. Two access routes into the deliver the equipment to the site. During the audit process, protected area are shown, and each of the licensee stated that information will be provided in a those routes can reach the A Staging future 6-month update to address the issue. Areas (Al for UHS access and primary water connection, A2 for an external electrical and water connection).

[Complete - Revised]

3.1.2.1.A On page 4, in the section of its Integrated Plan regarding FLEX pumps and associated equipment key assumptions associated with implementation of FLEX and the N+1 FLEX generator will be strategies, the licensee explained that primary and stored in a robust structure at the Unit secondary storage locations for FLEX equipment have not 2 side of the Screen House.

been selected. Storage locations must be selected that The primary FLEX generator and protect FLEX equipment from all hazards.

associated cabling will be stored in the robust Diesel Generator, Control, and Auxiliary buildings.

[Complete - Revised]

3.1.2.2.A With regard to deployment during flood conditions, the See the February 2014 01P Update for licensee stated that transportation routes from the closure information.

equipment storage area to the FLEX staging areas are not

[Complete]

yet identified. The licensee also stated that the identification of storage areas is part of a self identified open item.

3.1.2.2.B The Integrated Plan did not address the potential need to 120 VAC submersible pumps will be remove accumulated water from structures in the event stored in the robust Control Building.

that installed sump pumps are not available. Accumulated water can be pumped to the unused Unit 2 Diesel Generator Fuel Oil Storage Tank rooms in the Page 12 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28. 2014 Diesel Generator Building basement.

[Complete - Revised]

3.1.2.3.A The administrative program and procedures for The administrative program and deployment from storage and staging areas in flood procedures for deployment from conditions or after a tornado are not yet developed, storage and staging areas in flood conditions or after a tornado will be described in a future 6-month update.

[Started]

3.1.4.2.A The licensee does not address the effects of snow, ice, and In the primary strategy, all manual extreme cold on the ability of plant personnel to perform actions in the early hours of the event manual operations. are performed indoors, either in the plant or in the FLEX storage building.

Appropriate clothing will be pre-staged for outdoor actions, such as refueling the FLEX DG and pump.

In the event the N+1 generator is used, it will be transported from the FLEX storage building at the Screen House to the A2 staging area outside the Diesel Generator building and connected to the in-plant electrical distribution system using cables deployed from within the Diesel Generator Building. Appropriate clothing will be pre-staged for outdoor actions.

[Complete - Revised]

3.1.4.2.13 Although debris removal and haul requirements are The following was added to the site addressed as previously discussed in this report, there is snow removal plan:

insufficient information in the Integrated Plan to conclude New Fukushima Requirements the licensee will conform to guidance with respect to the NEI 12-06, Rev 0, August 2012, removal of snow and ice from haul pathways and staging Diverse and Flexible Coping areas. Strategies (Flex) Implementation Guide, Section 8.3.2.2 states: "For sites exposed to extreme snowfall and ice storms, provision should be made for snow/ice removal, as needed to obtain and transport FLEX equipment from storage to its location for deployment."

In order to address this requirement, Clinton will make provisions for Page 13 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 maintaining these areas open for vehicle and foot traffic during extreme weather events:

1. the area immediately south of the DG building,
2. the area around the FLEX building and its access doors on the Unit 2 side of the Screen House,
3. the vehicle and foot access routes between the DG building and the FLEX building,
4. the National SAFER Response Center staging area in the north contractor parking lot.
5. vehicle access route from the National SAFER Response Center staging area to the Screen House and area south of the DG Building.

[Complete - Revised]

3.2.1.1.A Need benchmarks to demonstrate that the Modular Information that validates the use of Accident Analysis Program (MAAP4) is the appropriate code MAAP4 is contained in document for simulation of ELAP. Forwarding of Clinton MAAP Justification for ELAP Analysis Acceptability (Attachment 4) and is available on the ePortal.

[Complete]

3.2.1.1.6 Collapsed level must remain above Top of Active Fuel and Information that validates the use of cool down rate must meet technical specifications. MAAP4 is contained in document Forwarding of Clinton MAAP Justification for ELAP Analysis Acceptability (Attachment 4) and is available on the ePortal.

[Complete]

3.2.1.1.0 MAAP4 use must be consistent with June 2013 position Information that validates the use of paper. MAAP4 is contained in document Forwarding of Clinton MAAP Justification for ELAP Analysis Acceptability (Attachment 4) and is available on the ePortal.

[Complete]

3.2.1.1.D In using MAAP4, the licensee must identify and justify the Information that validates the use of subset of key modeling parameters cited from Tables 4-1 MAAP4 is contained in document Page 14 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 through 4-6 of the "MAAP4 Application Guidance, Desktop Forwarding of Clinton MAAP Reference for Using MAAP4 Software, Revision 2" (Electric Justification for ELAP Analysis Power Research Institute Report 1 020236). Acceptability (Attachment 4) and is available on the ePortal.

[Complete]

3.2.1.1.E The specific MAAP4 analysis case that was used to validate Information that validates the use of the timing of mitigating strategies in the Integrated Plan MAAP4 is contained in document must be identified and should be available on the ePortal Forwarding of Clinton MAAP for NRC staff to view. Alternately, a comparable level of Justification for ELAP Analysis information may be included in the supplemental response. Acceptability (Attachment 4) and is available on the ePortal.

The Clinton MAAP analysis report, CL-MISC-009 R3 MAAP Analysis to Support Initial FLEX Strategy (Reference 5), is available on the ePortal. Case 17 in the report was used to validate the timeline described in the February 2014 01P update.

[Cornplete]

3.2.1.3.A The sequence of events timeline is not final. The licensee Results of timeline validation will be stated that the final sequence of events timeline will be included in a future 6-month update.

time validated once detailed designs are completed and

[Not Started]

procedures are developed. The licensee stated that the results will be provided in a future 6-month update.

Also, the final sequence of events timeline needs to identify FLEX pump availability for RCIC backup when the FLEX pump is staged to supply backup for RCIC. included in Change 3 of this document.

[Complete - Revised]

3.2.1.4.A The licensee has not yet completed the analyses to FLEX pump hydraulic analysis is in demonstrate adequate head and flow will be provided by calculation IP-M-0809. Rev. 0 is the FLEX pumps for cooling strategies. approved but is based on a higher flow/head requirement. Rev. 1 will document the current 3000 gpm. This revision will be part of EC 392339 Rev.

1 and will be placed on the ePortal upon approval.

[Started]

3.2.1.4.B The concerns related to raw water injection by FLEX See the February 2014 01P Update for strategies are being addressed by the Boiling Water closure information.

Reactor Owners Group and the resulting evaluation will be

[Complete]

included in a future 6-month update.

Page 15 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 3.2.1.5.4 Additional information is needed to address the associated Item 1 - In reference to part 1 relating measurement tolerances/accuracy of instrumentation used to the concern that electrical to monitor portable/FLEX electrical power equipment to equipment remains protected (from an ensure that: 1) the electrical equipment remains protected electrical power standpoint e.g.,

(from an electrical power standpoint- e.g., power power fluctuations), the protection of fluctuations) and 2) the operator is provided with accurate the equipment is not altered from the information to maintain core cooling, containment, and original design. The equipment will be spent fuel cooling. provided power through protective relays at the source, unit substation breakers. The power source, the FLEX DG, is a 500kW Cummins diesel generator set QSX15 series engine model DFEK. The units are equipped with a "PowerCommand" control, which is an integrated generator set control system that provides governing, voltage regulation, engine protection and operator interface functions. This includes a "Integral AmpSentry Protective" relay which provides a full range of alternator protection functions that are matched to the alternator. In addition, a three phase sensing, full wave rectifier voltage regulation system is included which provides a control of the FLEX DG output for stable operation with all load types.

Item 2 The FLEX strategy provides for uninterrupted operation of the Division 1 Nuclear System Protective System (NSPS). This system provides power to the level and pressure instruments listed in the 01P for the RPV, containment, and suppression pool, as well as RCIC system parameters. These parameters can be monitored directly in the main control room.

Suppression pool, containment, and drywell temperature indications are correlated from RTD resistance readings taken in the main control room. The FLEX strategy restores AC power to those instrument loops from Page 16 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 the FLEX generator, once it is placed in service.

[Complete]

3.2.2.A The licensee stated that evaluation of the spent fuel pool Evaluation of Spent Fuel Pool Area for area for steam and condensation had not yet been steam and condensation will be performed. The results of this evaluation and the vent path included in a future 6-month update.

strategy, if needed, will be provided in a future 6-month

[Started]

update.

3.2.3.A The licensee plans to circulate suppression pool water The plan to restore and maintain the through the shell side of an RHR heat exchanger using RHR piping to operable status will be abandoned RHR steam condensing mode piping. It is not provided in a future 6-month update.

clear how the abandoned RHR piping used will be returned

[Not Started]

to an operable status. The licensee stated the plan to restore and maintain the RHR piping to operable status will be provided in a future 6-month update.

3.2.3.6 It is not clear from the licensee's Integrated Plan that The plan for maintenance and testing current maintenance and testing for the suppression pool for the suppression pool cleanup and cleanup and transfer pumps would conform to the transfer pumps to conform to the standards for FLEX equipment because the pumps are not standards for FLEX equipment will be currently relied upon to mitigate accidents or transients or included in a future 6-month update.

the consequences of a beyond-design-basis event.

[Not Started]

3.2.3.0 The expected peak temperatures predicted by MAAP4 The potential for wetwell air space calculations are 185.06 degrees F for the wetwell air space temperatures exceeding the 185°F and 253.8 degrees F for the drywell. The wetwell air space design limit will be included in a future peak is marginally above the 185 degree F limit for the 6-month update.

containment. Because there are unresolved concerns with

[Started]

the MAAP4 analyses, the licensee will need to address the potential for wetwell air space temperatures exceeding the 185 degree F design limit.

3.2.4.2.A The information provided in the Integrated Plan regarding Battery room ventilation information battery room ventilation did not address potential regarding temperature and hydrogen temperature increases/decreases on the station batteries concerns will be provided in a future 6-due to loss of battery ventilation resulting from an ELAP. A month update.

discussion is also needed on hydrogen limits in battery

[Started]

room while charging the batteries during Phase 2 and 3.The licensee stated that battery room ventilation information will be provided in a future 6-month update.

3.2.4.2.B The licensee stated on page 41 regarding phase 2 main Main Control Room cooling control room cooling that further analysis is needed to information will be provided in a develop strategies. These strategies and supporting analysis future 6-month update.

are to be provided in a future 6-month update

[Started]

Page 17 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 3.2.4.2.0 On page 41, in the section of the Integrated Plan regarding Inverter Room cooling information will safety function support, phase 2, the licensee stated that be provided in a future 6-month inverter room conditions will be evaluated and a strategy update.

will be developed to maintain acceptable conditions. The

[Started]

strategy and associated support analyses will be submitted in a future 6-month update 3.2.4.2.D In general, the discussion of ventilation in the submittal The impact of elevated temperature provides insufficient information on the impact of elevated on equipment credited as part of the temperatures, as a result of loss of ventilation and/or [LAP strategies will be included in a cooling, on the support equipment being credited as part of future 6-month update.

the ELAP strategies (e.g., electrical equipment in the RCIC

[Not Started]

pump rooms). As an example, there is no discussion regarding whether the initial temperature condition assumed the worst-case outside temperature with the plant operating at full power. No list was provided or referenced of electrical components located in the pump rooms that are necessary to ensure successful operation of required pumps. Also, no information was provided regarding the qualification level for temperature and pressure for these electrical components for the duration that the pumps are assumed to perform its mitigating strategies function. During the audit process, the licensee explained that these issues will be addressed by providing information in a 6-month update.

3.2.4.4.A Confirm upgrades to communication system that resulted Upgrades to communication systems from the licensee communications assessment. Reference that resulted from the communications assessment correspondence (ADAMS Accession Nos. ML assessment will be confirmed in a 12306A 199 and ML13056A135). future 6-month update.

[Started]

3.2.4.6.A On page 41 of the Integrated Plan, in the section describing Main Control Room habitability safety function support for phase 2, the licensee stated that information will be provided in a habitability conditions will be evaluated and a strategy will future 6-month update.

be developed to maintain Main Control Room habitability.

[Not Started]

3.2.4.8.8 On page 50, in the Integrated Plan, the submittal includes a The 500 KW "Low Voltage Diesel table that lists additional equipment, "Medium Voltage and Generator" will be connected to an Low Voltage Diesel Generators", for phase 3; however, this external electrical connection point equipment is not discussed in the body of the Integrated and will supply the 480 VAC electrical Plan. It is not clear from the information presented in the distribution system as shown in Figure plan regarding; when and how the "Medium Voltage and 4. The generator will serve as a Low Voltage Diesel Generators" identified in the table redundant source to the primary and would be used, what loads would be served, or what N+1 generators staged at the site.

generating capacity would be provided. The licensee stated [Complete]

the strategies for the deployment of phase 3 equipment Page 18 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 would be developed and incorporated into pre-planned Guidance for deployment of planned guidance. The guidance will provide flexible and diverse "Medium Voltage Diesel Generator" (4 direction for the acquisition, deployment, connection, and kV) generators will be included in a operation of the equipment. future 6-month update.

[Not Started]

3.2.4.8.0 The Integrated Plan does not provide information or The FLEX generator sizing calculation references regarding sizing calculations for the FLEX EAD-FLEXGEN-1 (Reference 4) is generators to demonstrate they can adequately provide included on the ePortal.

power to the assumed loads. The licensee's response

[Complete]

addressed this issue by stating that the FLEX generator sizing calculations will be submitted in a future 6-month update.

3.2.4.9.A The licensee did not address assessing and maintaining fuel Fuel oil quality concerns will be quality for fuel oil supplies to the FLEX equipment. addressed in a future 6-month update.

[Not Started]

Also, the licensee did not address a concern with regard to See the February 2014 01P Update for providing an indefinite fuel supply. closure information.

[Complete]

3.4.A The Integrated Plan failed to provide any information as to See the February 2014 01P Update for how conformance with NEI 12-06, Section 12.2 guidelines 2 closure information.

through 10 will be met regarding the capabilities of the off

[Complete]

site resources.

7 Potential Draft Safety Evaluation Impacts There are no potential impacts to the Draft Safety Evaluation identified at this time.

8 References The following references support the updates to the Overall Integrated Plan described in this enclosure.

1. Clinton Power Station's Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)," dated February 28, 2013.
2. NRC Order Number EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," dated March 12, 2012.
3. Clinton Power Station MAAP Justification for ELAP Analysis Acceptability (Response to Letter Dated October 13, 2013 from Jack R. Davis, Director Mitigating Strategies Directorate, Office of Nuclear Reactor Regulation, regarding endorsement of MAAP Code)
4. EAD-FLEXGEN-1 Electrical Loading and Rating in KW for the FLEX Generator Page 19 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014

5. CLMISC-009 R3 MAAP Analysis to Support Initial FLEX Strategy
6. 3C10-0485-001 Revision 8 and 8A Internal Flooding Analysis
7. Clinton Power Station's First Six Month Update for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, dated August 28, 2013.
8. Clinton Power Station's Second Six Month Update for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, dated February 28, 2014.

9 Attachments

1. FLEX Equipment Protection per NEI 12-06 (Revised)
2. BWR Portable Equipment Phase 3
3. Conceptual Sketches
4. Forwarding of Clinton Power Station MAAP Justification for ELAP Analysis Acceptability 10 Figures
1. RCIC Operation During Phase 2
2. Suppression Pool Cooling and Low Pressure RPV Makeup from Suppression Pool (Revised)
3. Supply from Ultimate Heat Sink (Revised)
4. Electrical Strategy (Revised)
5. FLEX ADS Air Supply (Revised)
6. FLEX Fuel Oil Supply
7. FLEX Deployment Conceptual Sketch Page 20 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Attachment 1 FLEX Equipment Protection per NEI 12-06 5.3.1 Protection of FLEX Equipment (Seismic)

1. FLEX equipment should be stored in one or more of following three configurations:
a. In a structure that meets the plant's design basis for the Safe Shutdown Earthquake (SSE)(e.g., FLEX equipment will be stored in existing safety-related structure). structures designed to survive a SSE.
b. In a structure designed to or evaluated equivalent to ASCE 7-10, Minimum Design Loads for NA Buildings and Other Structures.
c. Outside a structure and evaluated for seismic interactions to ensure equipment is not damaged by NA non-seismically robust components or structures.
2. Large portable FLEX equipment such as pumps and power supplies should be secured as appropriate FLEX pumps and generators will be to protect them during a seismic event (i.e., Safe Shutdown Earthquake (SSE) level), stored to survive a SSE.
3. Stored equipment and structures should be evaluated and protected from seismic interactions to FLEX equipment will be protected and ensure that unsecured and/or non-seismic components do not damage the equipment. stored in areas where the potential for seismic interactions with unsecured and/or non-seismic equipment is minimal.

6.2.3.1 Protection of FLEX Equipment (Flooding)

These considerations apply to the protection of FLEX equipment from external flood hazards:

1. The equipment should be stored in one or more of the following configurations:
a. Stored above the flood elevation from the most recent site flood analysis. The evaluation to FLEX equipment will be stored above determine the elevation for storage should be informed by flood analysis applicable to the site the PMF elevation with the exception from early site permits, combined license applications, and/or contiguous licensed sites. of the FLEX pumps and associated equipment, the N+1 generator, and the haul/debris removal vehicle.
b. Stored in a structure designed to protect the equipment from the flood. NA
c. FLEX equipment can be stored below flood level if time is available and plant FLEX pumps and associated equipment, procedures/guidance address the needed actions to relocate the equipment. Based on the timing the N+1 generator, and the haul/debris of the limiting flood scenario(s), the FLEX equipment can be relocated to a position that is removal vehicle will be stored below protected from the flood, either by barriers or by elevation, prior to the arrival of the potentially the PMF elevation. Procedures damaging flood levels. This should also consider the conditions on-site during the increasing flood governing high lake level will include levels and whether movement of the FLEX equipment will be possible before potential inundation guidance for relocating this equipment occurs, not just the ultimate flood height. ahead of rising lake level.

Page 21 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014

2. Storage areas that are potentially impacted by a rapid rise of water should be avoided. Rapid rise in lake level is not a credible event.

7.3.1 Protection of FLEX Equipment (Wind)

These considerations apply to the protection of FLEX equipment from high wind hazards:

1. For plants exposed to high wind hazards, FLEX equipment should be stored in one of the following configurations:
a. In a structure that meets the plant's design basis for high wind hazards (e.g., existing safety- FLEX equipment will be stored in related structure). structures that will survive the design basis wind.

. In storage locations designed to or evaluated equivalent to ASCE 7-10, Minimum Design Loads for Buildings and Other Structures given the limiting tornado wind speeds from Regulatory Guide 1.76 or design basis hurricane wind speeds for the site. Given the FLEX basis limiting tornado or hurricane wind speeds, building loads would be computed in accordance with requirements of NA ASCE 7-10. Acceptance criteria would be based on building serviceability requirements not strict compliance with stress or capacity limits. This would allow for some minor plastic deformation, yet assure that the building would remain functional.

  • Tornado missiles and hurricane missiles will be accounted for in that the FLEX equipment will be stored in diverse locations to provide reasonable assurance that N sets of FLEX equipment will remain deployable following the high wind event. This will consider locations adjacent to NA existing robust structures or in lower sections of buildings that minimizes the probability that missiles will damage all mitigation equipment required from a single event by protection from adjacent buildings and limiting pathways for missiles to damage equipment.
  • The axis of separation should consider the predominant path of tornados in the geographical location. In general, tornadoes travel from the West or West Southwesterly direction, diverse locations should be aligned in the North-South arrangement, where possible. Additionally, in NA selecting diverse FLEX storage locations, consideration should be given to the location of the diesel generators and switchyard such that the path of a single tornado would not impact all locations.
  • Stored mitigation equipment exposed to the wind should be adequately tied down. Loose equipment should be in protective boxes that are adequately tied down to foundations or slabs to prevent protected equipment from being damaged or becoming airborne. (During a NA tornado, high winds may blow away metal siding and metal deck roof, subjecting the equipment to high wind forces.)
c. In evaluated storage locations separated by a sufficient distance that minimizes the probability NA Page 22 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 that a single event would damage all FLEX mitigation equipment such that at least N sets of FLEX equipment would remain deployable following the high wind event. (This option is not applicable for hurricane conditions).

  • Consistent with configuration b., the axis of separation should consider the predominant path NA of tornados in the geographical location.
  • Consistent with configuration b., stored mitigation equipment should be adequately tied NA down.

8.3.1 Protection of FLEX Equipment (Snow, Ice, Cold)

These considerations apply to the protection of FLEX equipment from snow, ice, and extreme cold hazards:

1. For sites subject to significant snowfall and ice storms, portable FLEX equipment should be stored in one of two configurations:
a. In a structure that meets the plant's design basis for the snow, ice and cold conditions (e.g., FLEX equipment will be stored in existing safety-related structure). structures that will survive the design basis for snow, ice, and cold.
b. In a structure designed to or evaluated equivalent to ASCE 7-10, Minimum Design Loads for NA Buildings and Other Structures for the snow, ice, and cold conditions from the site's design basis.
c. Provided the N FLEX equipment is located as described in a. or b. above, the N+1 equipment may be stored in an evaluated storage location capable of withstanding historical extreme weather NA conditions and the equipment is deployable.
2. Storage of FLEX equipment should account for the fact that the equipment will need to function in a FLEX pumps and generators and their timely manner. The equipment should be maintained at a temperature within a range to ensure its storage location will include likely function when called upon. For example, by storage in a heated enclosure or by direct heating appropriate heating.

(e.g., jacket water, battery, engine block heater, etc.).

9.3.1 Protection of FLEX Equipment (High Temperature)

The equipment should be maintained at a temperature within a range to ensure its likely function when called FLEX pumps, generators, and the upon. haul/debris removal vehicle, and their storage locations will include appropriate cooling such that the equipment will run without overheating.

Page 23 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Attachment 2 BWR Portable Equipment Phase 3 BWR Portable Equipment Phase 3 Generic Equipment Use and (potential / flexibility) diverse uses Performance Criteria Notes Note: The equipment listed is the generic equipment list provided by the National SAFER Response Center and even though we may not require this equipment in our plan it will be available and could be utilized in the phase 3 time period. The Phase 3 portable equipment table will be updated once all of the equipment has been procured and paced in inventory.

List portable Core Containment SFP Instrumentation Accessibility equipment Medium Voltage X X X X X 1 MW output at 4160 Vac, Diesel Generator three phase "el-Low Voltage X X X X X 1100 kW output at 480 Diesel Generator Vac, three phase Note '

High Pressure X 2000 psi shutoff head, 60 Injection Pump gpm capacity SG/RPV Makeup X 500 psi / 500 gpm Pump Low Pressure / X X X 300 psi shutoff head, 2500 Medium Flow gpm max flow Pump Low Pressure / X X 150 psi shutoff head, 5000 High Flow Pump gpm max flow Cable / Electrical X X X Various as determined by AREVA document # 51 -

9199717 - 005 Hose! X X X Various as determined by Mechanical AREVA document # 51 -

Connections 9199717 - 005 Page 24 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 BWR Portable Equipment Phase 3 Generic Equipment Use and (potential / flexibility) diverse uses Performance Criteria Notes Note: The equipment listed is the generic equipment list provided by the National SAFER Response Center and even though we may not require this equipment in our plan it will be available and could be utilized in the phase 3 time period. The Phase 3 portable equipment table will be updated once all of the equipment has been procured and p aced in inventory.

List portable Core Containment SFP Instrumentation Accessibility equipment Lighting Towers X 40,000 lumens Diesel Fuel 500 gallon air-lift container Transfer Diesel Fuel 264 gallon tank, with Transfer Tank mounted AC/DC pumps Portable Fuel 60 gpm after filtration Transfer Pump Electrical 4160 V, 250 MVA, Distribution 1200 A System Note 1: 1 MW is the individual generator output, and 2 MW is the total standard output to be supplied by the Phase 3 MV generators to satisfy identified load demands. The total output is created by connection of several smaller generators in parallel. Loads in excess of 2 MW are planned to be addressed as additional generators classified as non-generic equipment (see Section 8.4).

Note 2: The 1100 kW unit is derated to 1000 kW.

Page 25 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Phase 3 Response Equipment/Commodities Item Notes Radiation Protection Equipment The National SAFER Response Center will not stock this type of equipment but this equipment will be requested from site to site and utility to utility on an as required basis.

  • Survey instruments
  • Dosimetry
  • Off-site monitoring/sampling Commodities The National SAFER Response Center will not stock these commodities but they will be requested
  • Food from site to site and utility to utility on an as required basis.
  • Potable water BWR Portable Equipment Phase 3 Site Specific Use and (potential / flexibility) diverse uses Performance Criteria Notes List portable Core Containment SFP Instrumentation Accessibility equipment 2500/5000 GPM X X X The Suction Booster Lift Suction Booster Pump will assist in Pumps providing 26 feet of suction lift to the Low Pressure Medium Flow Pumps and the Low Pressure High Flow Pumps.

Page 26 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Attachment 3 Conceptual Sketches Figure 1 - RCIC Operation During Phase 2 MaIn Stearn HPV 711-Coml. Lippe Cnmt 1E51 rol ZEI 101 iO45 ADC (S1 RIM From RHR-A Sp ay Pool DC IA Pump Keep Fill ROC 1E12 rosAEO ID 1E1: 8407 11:11E1IF82IA 1E1: 10410 A

1E12 rolls 1E12 70684 X01E1240144 Suppression Pool Page 27 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Figure 2 - Suppression Pool Cooling and Low Pressure RPV Makeup from Suppression Pool Cnmt Upper Cnmt LPCI Sp ay Pool From RHR-A IA Pump Feedwater A A Keep-Fill A

A 1E12-F051A 1E12-F047A 1E12-F115 1E12-F053A lEEI X-0 1E12-F497 1 01E12-F028A 1E12-F037A To RHR B 11111 1E12-F048A 1E12-F052B 1E12-F052A 1E12-F087A RHR HX-A IA 1500 RCIC gpm 1E12-F003A 1E12-F027A 1E12-F042A Suction 1E12-F026A 1E12-1065A 2000 gpm S O 1E12-F024A Hose Z0 1E12-F068A 3 31E12-1014A UHS Div 1SX Supply To Radwaste Bldg (Filter Demins)

To Turbine Bldg

(".1" Polisher) 15F009 15F010A 1SFO1FA 15F005A 1SFO1PA 1>1 15F004 15F003 Suppression Pool 15F010B 1SFO1FB 15F005B 15F01PB Page 28 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Figure 3 - Supply from Ultimate Heat Sink ri 1512.1088 1E124021 Suppression Pool Cooling Suppression Pool Cooling From RHR-C Pump From LPCS Pump 1E21-F374

  • 4 CV Flush Une
  • UHS Suppression Pool 1121-F012 A

1E21-FOOS

.. LPCS Injection to RPV lEi2-1014h 1E12-F0680 1512-50680 1E12-F014e Black lines depict permanent plant equipment AM Red lines depict FLEX modifications Spent Fuel Pool Jap eaH AiddnS XSI Dotted lines depict manually deployed hoses 1000:68 15X0168 LPCS/RHR-C Div 1/Div 2 makeup to RPV/

Suppression Pool rl * "..

15)(35413 SFP Spray I Flooding Water Supply

  • 1SX354A

!.I * ,

43 Opening to Outside 1FX001.13 i.FX001C 1F00010 I.

"r.

1F0003 PXI:07A 1

Unit 2 Div 2 SX Buried 30" Supply Une Page 29 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Figure 4 =Eectrical Strategy

  • .1c DC Bldg ..... Outside DG Bldg Existing Plant Equipment 1FX01KB Alternate FLEX RRC Generator Pre-Installed Cable Runs
  • 1FX01KA Primary FLEX
  • Generator *
  • Cable Spools Generator 0 1 11011. I Spooled Cable Runs 44,41,0
  • r"-- r* Fry U. Unit Sub Cubicle Inserts S.. -4 as 60 mem
  • 14 & Ib 4 00 S. 6 444 Pre-Installed Terminal Boxes *1.. *1 sea 14.1 Primary RRC Connection 411)

Primary Strategy Alternate Strategy DO Bldg 762 Engineered Wall Opening 4160 VAC Swgr 1A1 480 VAC Bus Panel Insert 4160 VAC Sw r 1B1 For Cable Connection 4160/480 VAC 4160/480 VAC 4160/480 VAC 4160/480 VAC 480 VAC Unit Sub 1A 480 VAC Unit Sub A 480 VAC Unit Sub B 480 VAC Unit Sub 16 nmt Ind. d26 West

. RCIC, SM, NSPS SM, NSPS 1FX05E 1FX06E*

6900 VAC Swgr IA 6900 VAC Swgr 1B 6900/480 VAC 6900/480 VAC 6900/480 VAC 6900/480 VAC 480 VAC Unit Sub 1F 480 VAC Unit Sub 1L 480 VAC Unit Sub 1M 480 VAC Unit Sub 1G 1FX04E


77171-(717:7 to DC MCC 1A West Stairweli Page 30 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Figure 5 - FLEX ADS Air Supply 1DG168 1DG154 1DGO2MA 1DG011B 100150 Removed 1DGO1CA \ 1DGO4TA

-N-1DG 151 Air Dryers Bypassed Division 1 (Division 2 Similar)

X 100625 To DG Air Start Motors 100011A 1DG169 1DG155 10002MB 100152 1DGO1CB \ 10004TB 11 04 1170153 Outside Fill Connection 1IA828A 11A830A ON 11A828B 11A073 11A830B 1IA1154 11A074 11A828C 1 tA830C 11A076A 11A075A 11A0758 1iA076B 0 N 1IA828D zx 11A8300 ADS Backup ADS Backup Air Bottles 1IA828E 11A830E Air Bottles 11A 170A 11A171A 1B21-F041B 1B21-F041F 11A830F 1IA828F To SRVs 1B21-F041D 1IA044A 1IA013A 1621-F051D 11A828G 11A830G 1B21-F051C 1A170B 0_04_ 1B21-F051G 1621-F047A H 11A830H 11A828H 1621-F047C 11A012A 1 A044B 11321-F041C Q0'1 Page 31 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Figure 6 - FLEX Fuel Oil Supply

  • Day Tank supplied from the DG Fuel Oil Storage Tank using the installed Fuel Oil Transfer Pump, powered from the FLEX DG Unit 1 Div 1 DG Room Unit 1 Div 2 DG Room Unit 2 Div 1 DG Room Unit 2 Div 2 DG Room Portable 120 VAC Pump (using receptacle repowered from FLEX DG)

External connection deployed from FLEX DG on Connection to FLEX 762'elevation Truck Fuel Tanks Page 32 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28. 2014 Figure 7 - FLEX Deployment Conceptual Sketch

  • Al Staging Area Storage building housing the prestaged FLEX pumps, hose trailers, and F-750 truck used for debris removal. Operators need to travel on foot to this location to gain access to the building to lineup the FLEX pump.
  • A2 Staging Area External water and electrical connection used for National SAFER Response Center redundant equipment, and is the location of the source of fuel oil to refill the FLEX pumps.
  • Pedestrian Travel Route -

Personnel travelling on foot to the Al Staging Area follow a route that includes areas 3, 4, 5, and 1. The primary or alternate vehicle routes can be used as well.

  • Phase 2 Primary Vehicle Travel Route The primary travel route between Al and A2 Staging Area includes areas 1, 2, 3, and 4.
  • Phase 2 Alternate Vehicle Travel Route I. 41.

The alternate travel route between Al and A2 Staging Area includes areas 1, 5, 6, 2, 3, and 4.

  • B Staging Area The laydown area for Phase 3 equipment arriving from the National SAFER Response Center or other locations.
  • Phase 3 Primary Vehicle Travel Route The primary travel route from the B staging area to the Al and A2 staging areas includes area 7 before it connects to the on-site deployment route.
  • Phase 3 Alternate Vehicle Travel Route Mb OP The alternate travel route from the B staging area to the Al and A2 staging areas includes area 8 before it connects to the on-site deployment route.

Page 33 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Attachment 4 FORWARDING OF CLINTON POWER STATION MAAP JUSTIFICATION FOR ELAP ANALYSIS ACCEPTABILITY Enclosed is a completed ELAP response template for the Clinton Power Station (CPS) to justify the use of MAAP4 for the determination of the ELAP timeline.

The following restrictions and limitations apply to the template:

  • No containment vent is included in the ELAP response
  • The prescribed strategy for ELAP response (including portable pump flow rates) was provided by Exelon in the February 2013 Beyond Design Basis External Event Integrated Plan submittal No check has been made regarding the procedural adequacy, the timing for alignment, or flow curves for the portable pump The operability of RCIC for the calculated plant conditions is not justified by this template.

Separate justification needs to be provided for the RCIC operability under the calculated RPV and containment conditions, e.g., as part of this evaluation, RCIC NPSH has not been verified to be adequate over the duration of the MAAP analysis.

Page 34 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28. 2014 Clinton Power Station Response In response to the letter of October 3, 2013 from Jack Davis (NRR) to Joe Pollock (NEI), the following responses have been developed regarding the use of the Modular Accident Analysis Program (MAAP) for estimating accident progression timing in support of the Overall Integrated Plan for Clinton.

(1) From the June 2013 position paper, benchmarks must be identified and discussed which demonstrate that MAAP4 is an appropriate code for the simulation of an ELAP event at your facility.

Response to item 1:

Generic response provided by EPRI BWR Roadmap "Technical Basis for Establishing Success Timelines in Extended Loss of AC Power Scenarios in Boiling Water Reactors Using MAAP4,"

(EPRI Product ID 3002002749).

(2) The collapsed level must remain above Top of Active Fuel (TAF) and the cool down rate must be within technical specification limits.

Response to item 2: A of the Clinton Integrated Plan (Feb 2013) states that the operators would commence a cooldown of the RPV at 1 hr at a rate of 50 °F/hr which is within the technical specifications limit of 100°F/hr. The following plot of the RPV pressure from the MAAP analysis confirms this cooldown rate for the supporting MAAP calculation.

Page 35 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 1200

< 1000 C/)

--z (0 800 600 400 cc 200 4 6 8 10 TIME, HOURS MAAP Calculation of RPV Pressure During RPV Depressurization For the representative MAAP run (Case 17), the collapsed RPV water level inside the shroud remains above TAF for the duration of the analysis. The plot below shows that the lowest RPV level, calculated by MAAP, is approximately -10" below instrument zero. (TAF is located at -162" relative to instrument zero(1).) As shown in the following plot, the collapsed RPV water level remains at least 12' above TAF for the duration of the analysis.

(') Instrument zero is at +521" above vessel zero.

Page 36 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 80 cc w 70 I- 60

  • 50 0

CC 40

-I 30

_1 20 cc 1 10

  • 0 cc

-10 0 10 20 30 40 50 60 70 80 TIME, HOURS MAAP Calculation of Collapsed RPV Water Level Inside the Shroud (3) MAAP4 must be used in accordance with Sections 4.1, 4.2, 4.3, 4.4, and 4.5 of the June 2013 position paper.

Response to item 3:

MAAP analysis performed for Clinton was carried out in accordance with Sections 4.1, 4.2, 4.3, 4.4, and 4.5 of the June 2013 position paper, EPRI Technical Report 3002001785, "Use of Modular Accident Analysis Program (MAAP) in Support of Post-Fukushima Applications".

(4) In using MAAP4, the licensee must identify and justify the subset of key modeling parameters cited from Tables 4-1 through 4-6 of the "MAAP4 Application Guidance, Desktop Reference for Using MAAP4 Software, Revision 2" (Electric Power Research Institute Report 1020236). This should include response at a plant-specific level regarding specific coding options and parameter choices for key models that would be expected to substantially affect the ELAP analysis performed for that licensee's plant. Although some suggested key phenomena are identified below, other parameters considered important in the simulation of the ELAP event by the vendor / licensee should also be included.

a. Nodalization
b. General two-phase flow modeling
c. Modeling of heat transfer and losses
d. Choked flow Page 37 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014

e. Vent line pressure losses
f. Decay heat (fission products / actinides / etc.)

Response to item 4:

a. The reactor vessel nodalization is fixed by the MAAP code and cannot be altered by the user, with the exception of the detailed core nodalization. The Clinton MAAP 4.0.5 parameter file divides the core region into 5 equal volume radial regions (See NCHAN) and 13 axial regions (See NAXNOD). The axial nodalization represents 10 equal-sized fueled nodes (see NROWS), 1 unfueled node at the top (see NNFT), and 2 unfueled nodes at the bottom (see NNFB). The figure below, taken from the MAAP Users Manual, illustrates the vessel nodalization scheme.

SR LOCA 4 Upperl Head 4-.17=1 to 0 LOCA 3 Key Standprpes Separators 11- -1

( Gas Flow Path No.

Ot E A Heat Sink Surface No.

2 5 Shroud Head Upper =3 Heat Sir*

Down-COrtlef 0 , Generakzed rA "P Opening 1 Generalized 1 Core 0 --0. Opening 2 Generakzed ci Lower Dovmcorner Opening 3 4s ts, 8 Reese LOCA Loop ot I 7 Lower Head A 4 i+ (Flow Path 8 Not Aopitcable for GE BWR's)

.1149+4174=R Containment nodalization is defined by the user. The standard nodalization scheme is used in the Clinton MAAP 4.0.5 parameter file and represents the following individual compartments:

1. Reactor pedestal region
2. Drywell
3. Drywell vents to suppression chamber
4. Suppression chamber (wetwell)
5. Containment chimney
6. Containment dome Page 38 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014

7. Containment middle compartment
8. Upper containment pool The figure below illustrates the Clinton containment nodalization along with an identification of containment flow junctions.

Junction Description 1 Pedestal to Drywell Connection 2 Drywell to Vent/Downcomer Leakage/Failure 3 Lower Downcomer Vent to Wetwell 4 Middle Downcomer t 14 Vent to Wetwell 5 Upper Downcomer 12 Vent to Wetwell Containment Dome --> 6 Drywell to Mid Containment Pedestal Upper Vacuum Breakers A Pool 7 Wetwell to Mid Containment 9 Mid Containment to 1 Chimney Mid 71 13 10 Chimney Chimney to Dome Containment 11 Mid Containment to 6,15 Dome 12 Dome to Upper 7 Pool Drywell 13 Upper Pool to 16 Wetwell Wetwell 14 Dome Downcomer Leakage/Failure to Environment 2 4,5 15 Drywell Leakage to Containment 16 Drywell to Wetwell Hydrogen Mixing

b. General two-phase flow from the reactor vessel is described in the EPRI BWR Roadmap. In the case of the scenario outlined in the integrated plan, flow can exit the RPV via the open SRV(s) and from the assumed recirculation pump seal leakage. Flow from SRV will be single-phase steam and flow from the recirc pump seal or other RPV leakage will be single-phase liquid due to the location of the break low in the RPV with RPV level continued to be maintain above TAF. Upon exiting the RPV, the seal leakage will flash a portion of the flow to steam based on saturated conditions in the drywell, creating a steam source and a liquid water source to the drywell. As described in the BWR Roadmap (EPRI Product ID 3002002749) there are two parameters that can Page 39 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 influence the two-phase level on the RPV. The following table confirms that the parameter values match the recommended values as outlined in the roadmap.

Page 40 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Value Used in the EPRI Parameter Name Clinton MAAP Analysis Recommended Value FCO 1.5248 1.5248 FCHTUR 1.53 1.53

c. Modeling of heat transfer and losses from the RPV are described in the EPRI BWR Roadmap. The parameters that control these processes, as defined in the Roadmap, are provided below with the values selected to represent Clinton.

Value Used in the Parameter Name Clinton MAAP Analysis Comment QCO not-thru-insulation 3.42E6 BTU/hr Plant specific value based on drywell heat transfer from RPV heat removal to coolers during during normal operation. normal operation. Typical values range between 1-2 MW (3.4E6 to 6.8E6 BTU/hr).

FIN PLT number of plates 2 Plant-specific value in reflective insulation XTINS average reflective 0.25 ft Plant-specific value insulation thickness At the request of the NRC, the following information, as used in the MAAP analysis, is provided.

Parameter Value Used in the Parameter Definition Name in MAAP Clinton MAAP Analysis Power level, MWth QCRO 3473 MWth Initial CST water volume, gal VCSTO (ft3) 126,241 gal Initial CST water temperature, F HCST (enthalpy) 91.4°F Initial suppression pool water mass, Calculated from input 8,067,000 lbm Initial suppression pool water level, XWRBO(i), where i is node 19.42 ft ft number for wetwell Initial suppression pool water TWRBO(i), where i is node 95.0°F temperature, F number for wetwell Drywell free volume, ft3 VOLRB(i), where I is node 214,663 ft3 number for drywell Wetwell free volume, ft3 VOLRB(i) volume of 287,805 ft3 suppression pool water from initial pool mass Containment vent pressure, psia Refer to MAAP analysis N/A document (containment is not vented)

RCIC max flow rate, gpm WVRCIC 600 gpm Max FLEX pump flow rate, gpm Refer to MAAP analysis 2000 gpm document Lowest set SRV flow rate, lb/hr Derived from SRV area, ASRV 924,933 lb/hr Lowest set SRV pressure, psia PSETRV 1117.31 psia Recirc pump seal leakage, gpm Value that was used to define 100 gpm LOCA area, ALOCA Total leakage used in the transient, Value that was used to define 100 gpm gpm LOCA area, ALOCA Page 41 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014

d. Choked flow from the SRV and the recirculation pump seal leakage is discussed in the EPRI BWR Roadmap. The parameters identified that impact the flow calculation are listed below with input values identified.

Value Used in the EPRI Parameter Name Clinton MAAP Analysis Recommended Value ASRV effective flow area 0.1181 ft2 Plant-specific value for relief valve (based on rated flow at pressure)

ALOCA seal leakage 1.55E-3 ft2 Plant-specific value area (100 gpm at normal conditions)

FCDBRK discharge 0.75 0.75 coefficient for seal leakage

e. Vent line pressure loss can be represented in two ways. The actual piping flow area can be input along with a discharge coefficient (FCDJ). An alternative method would be to calculate the effective flow are given the estimated piping losses, and input a loss coefficient of 1.0. For the Clinton MAAP analysis, no venting of containment is modeled.
f. Decay heat in MAAP is discussed in the EPRI BWR Roadmap (EPRI Product ID 3002002749). Input parameters used to compute the decay heat are identified in the roadmap and are listed in the following table along with their values used in the Clinton analysis.

Page 42 of 43

Clinton Power Station's Third Six Month Status Report for the Implementation of FLEX August 28, 2014 Value used in the Parameter Name Clinton MAAP analysis EPRI recommended value FENRCH normal fuel enrichment 0.0369 Plant-specific value EXPO average exposure 14,550 MW-day/ton Plant-specific value FCR total capture rate of U-238 / 0.324 Plant-specific value total absorption rate FFAF total absorption rate / total 2.37 Plant-specific value fission rate FQFR1 fraction of fission power due 0.476 Plant-specific value to U-235 and PU-241 FQFR2 fraction of fission power due 0.437 Plant-specific value to PU-239 FQFR3 fraction of fission power due 0.087 Plant-specific value to U-238 TIRRAD average effective 26,280 hours0.00324 days <br />0.0778 hours <br />4.62963e-4 weeks <br />1.0654e-4 months <br /> Plant-specific value irradiation time for entire core (5) The specific MAAP4 analysis case that was used to validate the timing of mitigating strategies in the integrated plan must be identified and should be available on the ePortal for NRC staff to view. Alternately, a comparable level of information may be included in the supplemental response. In either case, the analysis should include a plot of the collapsed vessel level to confirm that TAF is not reached (the elevation of the TAF should be provided) and a plot of the temperature cool down to confirm that the cool down is within tech spec limits.

Response to item 5:

The MAAP analysis performed in support of the Clinton Integrated Plan is documented in calculation CL-MISC-009 Rev. 3 and is available on the ePortal. Case 17 was the specific MAAP run selected to represent the scenario as described in the February 2014 NRC OIP update.

Page 43 of 43