MONTHYEARRS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-090, Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station2023-09-0707 September 2023 Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs RS-23-081, Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation2023-08-21021 August 2023 Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation RS-23-085, Supplemental Information Related to Request for Partial Site Release2023-08-0303 August 2023 Supplemental Information Related to Request for Partial Site Release RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-073, Request for Partial Site Release2023-06-0707 June 2023 Request for Partial Site Release RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-23-039, Request for License Amendment to Revise Technical Specifications Section 3.8.3, Diesel Fuel Oil, Lube Oil, and Starting Air2023-03-0101 March 2023 Request for License Amendment to Revise Technical Specifications Section 3.8.3, Diesel Fuel Oil, Lube Oil, and Starting Air RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 RS-23-002, Application to Adopt TSTF-332, ECCS Response Time Testing2023-01-13013 January 2023 Application to Adopt TSTF-332, ECCS Response Time Testing RS-22-126, Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2022-11-30030 November 2022 Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI RS-22-121, Notice of Intent to Pursue Subsequent License Renewal Applications2022-11-0909 November 2022 Notice of Intent to Pursue Subsequent License Renewal Applications RS-22-092, Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration2022-10-0303 October 2022 Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration RS-22-107, Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station2022-09-29029 September 2022 Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station RS-22-093, Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans2022-08-18018 August 2022 Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans RS-22-089, Additional Information Supporting Request for License Amendment to Revise the Secondary Containment Design Basis to Credit the Fuel Building Railroad Airlock2022-07-25025 July 2022 Additional Information Supporting Request for License Amendment to Revise the Secondary Containment Design Basis to Credit the Fuel Building Railroad Airlock RS-22-061, Request for License Amendment to Adopt TSTF-269, Revision 2, Allow Administrative Means of Position Verification for Locked or Sealed Valves2022-05-24024 May 2022 Request for License Amendment to Adopt TSTF-269, Revision 2, Allow Administrative Means of Position Verification for Locked or Sealed Valves RS-22-060, Request for License Amendment to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2022-05-24024 May 2022 Request for License Amendment to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling RS-22-068, Constellation Radiological Emergency Plan Addendum Revision2022-05-19019 May 2022 Constellation Radiological Emergency Plan Addendum Revision RS-22-055, Submittal of Preliminary Decommissioning Cost Estimate and Spent Fuel Management Plan2022-04-18018 April 2022 Submittal of Preliminary Decommissioning Cost Estimate and Spent Fuel Management Plan RS-22-051, Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists2022-04-12012 April 2022 Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists RS-22-020, Request for License Amendment to Revise the Secondary Containment Design Basis to Credit the Fuel Building Railroad Airlock2022-04-0707 April 2022 Request for License Amendment to Revise the Secondary Containment Design Basis to Credit the Fuel Building Railroad Airlock RS-22-049, Constellation Energy Generation, LLC, Supplemental Information to Correct Typographical Errors in Constellation'S Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for2022-04-0404 April 2022 Constellation Energy Generation, LLC, Supplemental Information to Correct Typographical Errors in Constellation'S Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for V RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations RS-22-023, Constellation Energy Generation, LLC, Executed Trust Fund Agreement Amendment and Subordinate Trust Agreement2022-02-23023 February 2022 Constellation Energy Generation, LLC, Executed Trust Fund Agreement Amendment and Subordinate Trust Agreement RS-22-027, Constellation, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated2022-02-23023 February 2022 Constellation, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated P RS-22-019, Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists2022-02-16016 February 2022 Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists RS-22-015, Notification of Completion of License Transfer and Request to Continue Processing Pending NRC Actions Previously Requested by Exelon Generation Company, LLC2022-02-0101 February 2022 Notification of Completion of License Transfer and Request to Continue Processing Pending NRC Actions Previously Requested by Exelon Generation Company, LLC RS-22-004, Supplement to Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements2022-01-0404 January 2022 Supplement to Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements RS-21-121, Proposed Changes to Decommissioning Trust Agreements and Master Terms2021-12-15015 December 2021 Proposed Changes to Decommissioning Trust Agreements and Master Terms RS-21-102, Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors2021-09-29029 September 2021 Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors RS-21-091, Implementation of Insider Threat Program Requirements Associated with the Voluntary Security Clearance Program and Advisement of Leadership Changes2021-09-13013 September 2021 Implementation of Insider Threat Program Requirements Associated with the Voluntary Security Clearance Program and Advisement of Leadership Changes RS-21-087, Additional Information Supporting Request for License Amendment to Revise Degraded Voltage Relay Allowable Values2021-08-31031 August 2021 Additional Information Supporting Request for License Amendment to Revise Degraded Voltage Relay Allowable Values RS-21-078, Response to Request for Additional Information for Application to Revise Technical Specification to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements, and TSTF-583-T, TSTF-582 Diesel2021-08-19019 August 2021 Response to Request for Additional Information for Application to Revise Technical Specification to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements, and TSTF-583-T, TSTF-582 Diesel RS-21-076, Application to Adopt TSTF-273, Safety Function Determination Program Clarifications2021-07-30030 July 2021 Application to Adopt TSTF-273, Safety Function Determination Program Clarifications RS-21-063, Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements2021-06-30030 June 2021 Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements RS-21-070, Proposed Alternative to Utilize Code Case N-8932021-06-30030 June 2021 Proposed Alternative to Utilize Code Case N-893 RS-21-069, Third Inservice Inspection Interval Relief Request I3R-182021-06-28028 June 2021 Third Inservice Inspection Interval Relief Request I3R-18 RS-21-054, Response to NRC Regulatory Issue Summary 2021-01, Preparation and Scheduling of Operator Licensing Examinations2021-04-29029 April 2021 Response to NRC Regulatory Issue Summary 2021-01, Preparation and Scheduling of Operator Licensing Examinations RS-21-039, Supplemental Information Regarding Application for Order Approving Transfers and Proposed Conforming License Amendments2021-03-25025 March 2021 Supplemental Information Regarding Application for Order Approving Transfers and Proposed Conforming License Amendments RS-21-037, Response to Request for Additional Information Regarding License Amendment Request to Adopt TSTF-505, Revision 22021-03-23023 March 2021 Response to Request for Additional Information Regarding License Amendment Request to Adopt TSTF-505, Revision 2 RS-21-028, Fitness for Duty Performance Data Reports - Annual 20202021-02-26026 February 2021 Fitness for Duty Performance Data Reports - Annual 2020 RS-21-032, Amended Decommissioning Trust Agreements2021-02-25025 February 2021 Amended Decommissioning Trust Agreements RS-21-030, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2021-02-24024 February 2021 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-21-014, License Amendment Request for One-Time Extension of the Containment Type a Integrated Leakage Rate Test Frequency2021-02-24024 February 2021 License Amendment Request for One-Time Extension of the Containment Type a Integrated Leakage Rate Test Frequency RS-21-005, Request for License Amendment to Revise Degraded Voltage Relay Allowable Values2021-01-20020 January 2021 Request for License Amendment to Revise Degraded Voltage Relay Allowable Values RS-21-002, Company - Update to Correspondence Addressees and Service Lists2021-01-0404 January 2021 Company - Update to Correspondence Addressees and Service Lists 2023-09-07
[Table view] Category:Request for Code Relief or Alternative
[Table view] |
Text
4300 Winfield Road Exelon Generation Warrenville, IL 60555 630 657 2000 Office RS-21-069 10 CFR 50.55a June 28, 2021 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Clinton Power Station, Unit 1 Facility Operating License No. NPF-62 NRC Docket No. 50-461
Subject:
Third Inservice Inspection Interval Relief Request I3R-18 In accordance with 10 CFR 50.55a, "Codes and standards," paragraphs (g)(5)(iv), Exelon Generation Company, LLC (EGC), requests NRC approval of the attached relief request associated with the third Inservice Inspection (ISI) Interval for Clinton Power Station, Unit 1 (CPS). Relief is requested due to the impracticality of satisfying the requirements of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code, Section XI, "Rules for Inservice Inspection of Nuclear Power Plant Components." The third ISI interval for CPS ended June 30, 2020. EGC requests approval of the request by June 28, 2022.
There are no regulatory commitments contained within this letter. Should you have any questions concerning this letter, please contact Mr. Kenneth M. Nicely at (630) 657-2803.
Respectfully, Patrick R. Simpson Sr. Manager Licensing
Attachment:
10 CFR 50.55a Request Number I3R-18 cc: NRC Regional Administrator, Region III NRC Senior Resident Inspector - Clinton Power Station
ATTACHMENT 10 CFR 50.55a Relief Request I3R-18 Relief Requested in Accordance with 10 CFR 50.55a(g)(5)(iv)
--Inservice Inspection Impracticality--
Revision 0 (Page 1 of 6)
- 1. ASME Code Component(s) Affected Code Class: 1
Reference:
IWB-2500 Code Case N-460 Component Number: RPV-C5 Examination Category: B-A Item Number: B1.30
Description:
Reactor Pressure Vessel (RPV) Shell to Flange Weld
- 2. Applicable Code Edition The third 10-year interval of the Clinton Power Station, Unit 1 (CPS) Inservice Inspection (ISI) Program ended on June 30, 2020, and complied with the 2004 Edition of American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code (Code),
Section XI, and No Addenda.
3. Applicable Code Requirement
Class 1 Reactor Pressure Vessel (RPV) Shell to Flange Weld examination requirements are given in Subsection IWB, Table IWB-2500-1, Examination Category B-A, Item Number B1.30. The method of examination is volumetric examination (ultrasonic examination, UT).
4. Impracticality of Compliance
Code required UT coverage is impractical for this weld due to the RPV Shell Flange configuration/geometry. The UT examination can only be performed from the shell side due to the flange configuration. Relief is requested from performing the required UT examination volume. To perform a full Code required UT examination of this weld, the RPV Shell Flange would have to be modified. The following describes the UT coverage:
- First 1/2 length of the weld (from 0 degrees to 180 degrees) - 62.8%
- Second 1/2 length of the weld (from 180 degrees to 360 degrees) - 72.9%
5. Burden Caused by Compliance
The RPV Shell Flange configuration/geometry does not allow CPS to perform UT examination from flange side. To perform a full Code required UT examination of this weld, the RPV Shell flange would have to be modified.
6. Proposed Alternative and Basis for Use
Proposed Alternative In accordance with 10 CFR 50.55a(g)(5)(iv), relief is requested from performing the required examination on essentially 100% of the examination area. Code Case N-460 (i.e.,
ATTACHMENT 10 CFR 50.55a Relief Request I3R-18 Relief Requested in Accordance with 10 CFR 50.55a(g)(5)(iv)
--Inservice Inspection Impracticality--
Revision 0 (Page 2 of 6)
Reference 1) allows a reduction in the examination area of up to 10%. This Code Case N-460 has been approved and incorporated into Regulatory Guide 1.147, "Inservice Inspection Code Case Acceptability, ASME Section XI, Division 1." The RPV Shell Flange configuration/geometry does not allow UT examination from the flange side. CPS proposes to perform the UT examination from the RPV Shell side only and perform UT examination on this weld to the maximum extent feasible. CPS evaluated the feasibility of using a remote auto UT system to potentially increase the examination volume. It was concluded that due to the size of the auto UT equipment the examination volume would have been less.
Basis for Use Performance of UT examination from the RPV Shell side only provides reasonable assurance of the structural integrity of the entire weld. CPS has performed UT examination on this weld to the maximum extent feasible. It should be noted that during initial plant construction, the entire weld was radiographed and the results were acceptable. The weld was also ultrasonically examined in accordance with the Preservice Inspection Plan, and the results of that examination were also acceptable.
Due to the bend radius on the flange side and the thickness of the flange, the following examination volumes can be scanned:
- From 0 deg to 180 deg -- Composite coverage of 62.8%
- From 180 deg to 360 deg -- Composite coverage of 72.9%
This weld was examined in two separate segments. The 0 to 180 degrees segment was examined in 2011, and the 180 to 360 degrees segment was examined in 2019. The lower coverage achieved in the 0 to 180 degrees scan (i.e., 62.8% coverage) was due to different procedures and equipment technical capabilities in place during the 2011 refueling outage.
The other half of this weld was examined in 2019 with superior results (i.e., 72.9%
coverage) due to advancements in both procedure and equipment. There was no indication identified during the examinations of the above two areas. As shown above, performance of the above examinations provides reasonable assurance of the structural integrity of the entire weld.
7. Duration of Proposed Alternative
Relief is requested for the CPS third 10-year ISI interval.
8. Precedents
Similar relief requests were approved for the first and second 10-year ISI intervals at CPS as Relief Request Numbers 4015 and 4218 as discussed in References 2 and 3.
ATTACHMENT 10 CFR 50.55a Relief Request I3R-18 Relief Requested in Accordance with 10 CFR 50.55a(g)(5)(iv)
--Inservice Inspection Impracticality--
Revision 0 (Page 3 of 6)
- 9. References
- 1. Code Case N-460, "Alternative Examination Coverage for Class 1 and Class 2 Welds, Section XI, Division 1"
- 2. Letter from A. J. Mendiola (U.S. NRC) to M. Reandeau (Clinton Power Station),
"Clinton Power Station - First 10-Year Interval Inservice Inspection Program Plan Requests for Relief Nos. 4014, 4015, 4016, and 4017, (TAC No. MA6192)," dated March 28, 2000
- 3. Letter from J. I. Zimmerman (U.S. NRC) to M. J. Pacilio (Exelon Generation Company, LLC), "Clinton Power Station, Unit No. 1 - Relief Requests (RRs) 4216, 4217, 4218, 4219, 4220, 4221, and 4222 Regarding Examination Coverage for the Second 10-Year Inservice Inspection (ISI) Interval (TAC Nos. ME4183, ME4184, ME4185, ME4186, ME4187, ME4188 andME4189)," dated June 17, 2011
ATTACH MENT 10 CFR 50.55a Relief Request I3R-18 Relief Request ed in Accorda nce with 10 CFR 50.SSa(g)(S)(iv)
--lnservi ce Inspectio n Impractic ality--
Revision 0 (Page 4 of 6)
Clinton Unit 1 RPV to Flange S6 60° Exam Volume ::; 56.9 Sq.. ll'l S4 Inner 15% T Exam Volume (6D"T & IRS) = 9.2 Sq. In S6 Go* T-Scan achieved = 47.9 SQ. In S4 60° T-Scan (Inner 15%T} achieved = 9.2 Sq. In r
- - - --'16.3 .
T-Scans T-Scans I r I
i RPV Shell Achieved Examina tion Coverage for '\Veld RPV -C5 Examine d 1/2 of \ Veld Length from O - 180 degrees Exam Perfonne d 2011 Figure 1a: RPV Shell-to-Flange Weld
ATTA CHME NT 10 CFR 50.SSa Relief Request I3R-18 Relief Requested in Acco rdanc e with 10 CFR 50.SSa(g)(S
)(iv)
--lnservice Inspection Impracticality--
Revis ion O (Page 5 of 6)
Achieved Exam inatio n Coverage for Weld RPV-C5 Examined 1/2 of Weld Length from 0 - 180 degrees Exam Performed 20 11 RPV Flange Clinton Unit 1 RPV to Flange S6 60' Exam Volume " 56.9 Sq. In S4 Inner 15%T Exam Volume (60"T & IRS) = 9.2 Sq. In S6 so: P-Scan achieved = 31.9 Sq. In n
S4 60 P-Scan (Inner 15% achieve d= 5.6 Sq. In
/ 1-4.5"1
/ P-ScaJs P-Scans I I I I I
I I
I I
I I
I 1----
i RPV Shell Figure 1b: RPV Shell- to-Fla nge Weld
ATTAC HMENT 10 CFR 50.55a Relief Request I3R-18 Relief Requested in Accordance with 10 CFR 50.SSa(g)(S)(iv)
--lnservice Inspection Impracticality--
Revision 0 (Page 6 of 6)
Clinton Unit 1 RPV to Flange so* S6 NS Exam Volume :: 11.0 Sq. In so* S6 FV Exam Volume = 45.9 Sq. In so* S4 Exam Volume = 9.2 Sq. In so* S6 NS p. scan Achieved = 5.6 Sq. In 60" 56 FV P- Scan Achieved= 26.3 Sq. In 60' S4 P-Scan Achieved = 5.6 Sq. In so* S6 NS T-Scan Achieved = 6.4 Sq In 60' S6 FV T-Scan Achieved = 43 .3 Sq. In so* S4 T-Scan Achieved = 9.2 Sq. In
/~ i==* **--- 116. J"*- --
( so* TIP I so*r NS so*r FV 11 I l I I \.
I
- ,i--1,i--r- - ~--
- , ,,;.---- -- - -.........;,-~
I -+--
I I
I I
I i----
Achieve d Examin ation CO\ erage for Weld RPV-C5 Examin ed 1/2 of Weld Length from 180 - 360 degrees Exam Perfo1med 2019 Figure 2: RPV Shell-to-Flange Weld