Callaway Plant - NRC Material Control and Accounting Program Inspection Report 05000483-12-405
ML12279A317
Person / Time
Site: Callaway Ameren icon.png
Issue date: 10/05/2012
From: Drake J F
NRC/RGN-IV/DRS/PSB-2
To: Heflin A C
Union Electric Co
References
IR-12-405
Download: ML12279A317 (5)


Text

" " October 5, 2012

Mr. Adam C. Heflin, Senior Vice President and Chief Nuclear Officer Union Electric Company P.O. Box 620 Fulton, MO 65251

SUBJECT: CALLAWAY PLANT - NRC MATERIAL CONTROL AND ACCOUNTING PROGRAM INSPECTION REPORT 05000483/2012405

Dear Mr. Heflin:

On August 30, 2012, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Callaway Plant. The inspection covered a key attribute of the Security Cornerstone of the NRC's Reactor Oversight Process, Material Control and Accounting of Special Nuclear Material. The enclosed inspection report documents the inspection results, which were discussed on August 30, 2012, with Mr. L. Graessle, Director of Plant Support, and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, the material enclosed herewith contains security-related information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. If security-related information is necessary to provide an acceptable response, please mark your entire response security-related information in accordance with 10 CFR 2.390(d)(1)

and follow the instructions for withholding in 10 CFR 2.390(b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.

Sincerely,/RA/ Louis Carson II for James F. Drake, Acting Chief Plant Support Branch 2 Division of Reactor Safety Docket Nos.: 50-483 License Nos.: NPF-30 Nonpublic

Enclosure:

NRC Inspection Report 05000483/2012405

w/attachments:

1. Supplemental Information 2. Information Request for Inspection Activities Documented in IP 71130.11 cc: Electronic Distribution w/o enclosure

cc w/enclosure:

Eric Olson Security Manager Callaway Plant, Unit 1 5 Miles North of Hwy 94 Portland, MO 65067