Proposed Tech Specs 3.4.6.2,4.4.6.1 & 3.4-1,permitting Leak Testing of Valves in Mode 3 & Allowing Util 30 Days to Accumulate Data at Rated Sys Pressure to Establish Baseline Leakage Limits for RHR Sys Supply Line ValvesML19337A561 |
Person / Time |
---|
Site: |
Sequoyah |
---|
Issue date: |
09/24/1980 |
---|
From: |
TENNESSEE VALLEY AUTHORITY |
---|
To: |
|
---|
Shared Package |
---|
ML19337A552 |
List: |
---|
References |
---|
NUDOCS 8009290280 |
Download: ML19337A561 (5) |
|
|
---|
Category:TECHNICAL SPECIFICATIONS
MONTHYEARML20217F9701999-10-14014 October 1999 Proposed Tech Specs,Incorporating ARC for Axial Primary Water Stress Corrosion Cracking at Dented Tube Support Plate Intersections ML20217E4301999-10-12012 October 1999 Proposed Tech Specs,Revising Requirements for Containment Penetrations During Refueling Operations ML20211M7341999-08-30030 August 1999 Marked-up & Revised TS Pages,Providing Alternative to Requirement of Actually Measuring Response Times ML20211K1721999-08-30030 August 1999 Proposed Tech Specs,Providing Clarification to Current TS Requirements for Containment Isolation Valves ML20209B7731999-06-30030 June 1999 Proposed Tech Specs Updating Requirmements for RCS Leakage Detection & RCS Operational Leakage Specifications to Be Consistent with NUREG-1431 ML20196F2211999-06-24024 June 1999 Proposed Tech Specs Pages for Amend to Licenses DPR-77 & DPR-79,allowing Use of Fully Qualified & Tested Spare Inverter in Place of Any of Eight Required Inverters ML20196G4701999-06-24024 June 1999 Proposed Tech Specs Pages Re Amends to Licenses DPR-77 & DPR-79,revising TS to Be Consistent with Rev to ISTS Presently Submitted to NEI TSTF for Submittal as Rev to NUREG-1431 ML20196G7961999-06-22022 June 1999 Proposed Tech Specs Bases,Clarifying Proper Application of TS Requirements for Power Distribution Systems & Functions That Inverters Provide to Maintain Operability & Providing Updated Info on Cold Leg Injection Accumulators ML20195E9841999-06-0707 June 1999 Proposed Tech Specs,Increasing Max Allowed Specific Activity of Primary Coolant from 0.35 Microcuries/Gram Dose Equivalent I-131 to 1.0 Microcuries/Gram Dose Equivalent I-131 for Plant Cycle 10 (U2C10) Core ML20206E1391999-04-29029 April 1999 Proposed Tech Spec Change 99-03, Main Control Room Emergency Ventilation Sys Versus Radiation Monitors. Changes Add LCOs 3.3.3.1 & 3.7.7 to Address Inoperability of Radiation Monitoring CREVS & NUREG-1431 Recommendations ML20206E1611999-04-29029 April 1999 Proposed Tech Spec Change 99-04, Auxiliary Suction Pressure Low Surveillance Frequency Rev. Change Deletes Surveillance ML20204H4081999-03-19019 March 1999 Proposed Tech Specs,Relocating TS 3.8.3.1,3.8.3.2,3.8.3.3 & Associated Bases Associated with Electrical Equipment Protective Devices to Technical Requirements Manual ML20207D6011999-02-26026 February 1999 Proposed Tech Specs Relocating TS 3.7.6, Flood Protection Plan & Associated Bases from TS to Plant TRM ML20207D6331999-02-26026 February 1999 Proposed Tech Specs Providing for Consistency When Exiting Action Statements Associated with EDG Sets ML20206S0131999-01-15015 January 1999 Proposed Tech Specs 3.3.3.3, Seismic Instrumentation & Associated Bases,Relocated to Plant Technical Requirements Manual ML20199K6001999-01-15015 January 1999 Proposed Tech Specs Adding New Action Statement to 3.1.3.2 That Would Eliminate Need to Enter TS 3.0.3 Whenever Two or More Individual RPIs Per Bank May Be Inoperable,While Maintaining Appropriate Overall Level of Protection ML20195H6111998-11-16016 November 1998 Proposed Tech Specs Revising EDG SRs by Adding Note That Allows SR to Be Performed in Modes 1,2,3 or 4 If Associated Components Are Already OOS for Testing or Maint & Removing SR Verifying Certain Lockout Features Prevent EDG Starting ML20154H7251998-10-0808 October 1998 Proposed Tech Specs Pages,Supplementing Proposed TS Change 96-08,rev 1 to Add CRMP to Administrative Controls Section & Bases of TS ML20238F1091998-08-27027 August 1998 Proposed Tech Specs Providing for Insertion of Limited Number of Lead Test Assemblies,Beginning W/Unit 2 Operating Cycle 10 Core ML20238F3001998-08-27027 August 1998 Proposed Tech Specs Replacing 72 H AOT of TS 3.8.1.1,Action b,w/7 Day AOT Requirement for Inoperability of One EDG or One Train of EDGs ML20236G5961998-06-29029 June 1998 Proposed Tech Specs Typed Pages for TS Change 95-19, Section 6 - Administrative Controls Deletions ML20249C6371998-06-26026 June 1998 Proposed Tech Specs Lowering Specific Activity of Primary Coolant from 1.0 Uci/G Dose Equivalent I-131 to 0.35 Uci/G Dose Equivalent I-131,as Provided in GL 95-05 ML20248F0051998-05-28028 May 1998 Proposed Tech Specs for Section 6, Administrative Controls Deletions ML20217N3511998-04-30030 April 1998 Proposed Tech Specs Pages,Modifying Surveillance Requirement 4.4.3.2.1.b to Change Mode Requirement to Allow PORV Stroke Testing in Modes 3,4 & 5 W/Steam Bubble in Pressurizer Rather than Only in Mode 4 ML20203J1681998-02-25025 February 1998 Proposed Tech Specs Pages,Revising EDG Surveillance Requirements to Delete Requirement for 18-month Insp IAW Procedures Prepared in Conjunction W/Vendor Recommendations & Modify SRs Associated W/Verifying Capability of DGs ML20202J7601998-02-13013 February 1998 Proposed Tech Specs Section 3.7.9 Re Relocation of Snubber Requirements ML20202J7141998-02-13013 February 1998 Proposed Tech Specs Adding New LCO That Addresses Requirements for Main Feedwater Isolation,Regulating & Bypass Valves ML20202J6961998-02-13013 February 1998 Proposed Tech Specs Incorporating MSIV Requirements to Be Consistent W/Std TS (NUREG-1431) ML20198T4311998-01-21021 January 1998 Proposed Tech Specs Re New Position Title & Update of Description of Nuclear Organization ML20199K4571997-11-21021 November 1997 Proposed Tech Specs Adding one-time Allowance Through Operating Cycle 9 to Surveillance Requirement 4.4.3.2.1.b to Perform Stroke Testing of PORVs in Mode 5 Rather than Mode 4,as Currently Required ML20211A3191997-09-17017 September 1997 Proposed Tech Specs Re Pressure Differential Surveillance Requirements for Containment Spray Pumps ML20137T0871997-04-0909 April 1997 Proposed Tech Specs Re Elimination of Cycle 8 Limitation for SG Alternate Plugging Criteria ML20137M8581997-04-0101 April 1997 Proposed Tech Specs 2.1 Re Safety Limits & TS 3/4.2 Re Power Distribution Limits ML20137C8421997-03-19019 March 1997 Proposed Tech Specs Re Conversion from Westinghouse Electric Corp Fuel to Framatome Cogema Fuel ML20136J0381997-03-13013 March 1997 Proposed Tech Specs Section 5.6.1.2,revising Enrichment of Fuel for New Fuel Pit Storage Racks ML20134P8631997-02-14014 February 1997 Proposed Tech Specs Requesting Discretionary Enforcement for 48 Hours Which Is in Addition to 72 Hours Allowed Outage Time Provided by TS Action 3.8.1.1.b ML20134K9981997-02-0707 February 1997 Proposed Tech Specs Revising TS Change Request 96-01, Conversion from W Electric Corp Fuel to Framatome Cogema Fuel (MARK-BW-17), to Ensure That Core Analysis Computer Code Output Actions Are Consistent W/Hot Channel Factor SRs ML20134L9261996-11-0808 November 1996 Proposed Tech Specs Re Placing of Channel in Trip for Reactor Trip & Engineered Safety Feature Instrumentation Sys Solely to Perform Testing as Not Requiring Channel to Be Declared Inoperable ML20129D2661996-10-18018 October 1996 Proposed Tech Specs,Removing Existing Footnotes That Limit Application of Apc for Plant S/G Tubes to Cycle 8 Operation for Both Units ML20129G7301996-09-26026 September 1996 Proposed Tech Specs 3/4.3.3 Re Fire Detection instrumentation,3/4.7.11 Re Fire Suppression Systems & 3/4.7.12 Re Fire Protection Penetrations ML20113G2691996-09-20020 September 1996 Proposed Tech Specs Change 96-09, Clarification of Work Shift Durations for Overtime Limits ML20117J3391996-08-28028 August 1996 Proposed Tech Specs Revising Psv & MSSV Setpoint Tolerance from Plus or Minus 1% to Plus or Minus 3% ML20117D1651996-08-22022 August 1996 Proposed Tech Specs of SQN Units 1 & 2,deleting Table 4.8.1, DG Reliability, & Revising Section 3.8.1 to Allow Once Per 18 month,7 Day AOT for EDGs ML20117D3121996-08-22022 August 1996 Proposed Tech Specs,Lowering Minimum TS ice-basket Weight of 1,155 Lbs to 1,071 Lbs.Reduced Overall Ice Weight from 2,245,320 Lbs to 2,082,024 Lbs ML20117D3141996-08-21021 August 1996 Proposed TS 3.7.1.3 Re Condensate Storage Tank ML20117D3341996-08-21021 August 1996 Proposed Tech Specs Re Deletion of Surveillance Requirement 4.8.1.1.1.b ML20112H0431996-06-0707 June 1996 Proposed Tech Specs,Revising Section 6, Administrative Controls, to Be More Closely Aligned W/Requirements of STSs ML20101N7071996-04-0404 April 1996 Proposed Tech Specs,Allowing Conversion from Westinghouse Fuel to Fuel Provided by Framatome Cogema Fuels ML20096B3761996-01-0404 January 1996 Proposed Tech Specs Extending Radiation Monitoring Instrumentation Surveillance Period Per GL 93-05 ML20096C2481996-01-0303 January 1996 Proposed Tech Specs,Revising Bases Section 3/4.7.1.2 to Indicate Current Operational Functions of turbine-driven AFW Level Control Valves Modified During Unit 1 Cycle 7 Refueling Outage 1999-08-30
[Table view] Category:TECHNICAL SPECIFICATIONS & TEST REPORTS
MONTHYEARML20217F9701999-10-14014 October 1999 Proposed Tech Specs,Incorporating ARC for Axial Primary Water Stress Corrosion Cracking at Dented Tube Support Plate Intersections ML20217E4301999-10-12012 October 1999 Proposed Tech Specs,Revising Requirements for Containment Penetrations During Refueling Operations ML20211M7341999-08-30030 August 1999 Marked-up & Revised TS Pages,Providing Alternative to Requirement of Actually Measuring Response Times ML20211K1721999-08-30030 August 1999 Proposed Tech Specs,Providing Clarification to Current TS Requirements for Containment Isolation Valves ML20209B7731999-06-30030 June 1999 Proposed Tech Specs Updating Requirmements for RCS Leakage Detection & RCS Operational Leakage Specifications to Be Consistent with NUREG-1431 ML20196F2211999-06-24024 June 1999 Proposed Tech Specs Pages for Amend to Licenses DPR-77 & DPR-79,allowing Use of Fully Qualified & Tested Spare Inverter in Place of Any of Eight Required Inverters ML20196G4701999-06-24024 June 1999 Proposed Tech Specs Pages Re Amends to Licenses DPR-77 & DPR-79,revising TS to Be Consistent with Rev to ISTS Presently Submitted to NEI TSTF for Submittal as Rev to NUREG-1431 ML20196G7961999-06-22022 June 1999 Proposed Tech Specs Bases,Clarifying Proper Application of TS Requirements for Power Distribution Systems & Functions That Inverters Provide to Maintain Operability & Providing Updated Info on Cold Leg Injection Accumulators ML20196G8071999-06-22022 June 1999 Revs to Technical Requirements Manual ML20195E9841999-06-0707 June 1999 Proposed Tech Specs,Increasing Max Allowed Specific Activity of Primary Coolant from 0.35 Microcuries/Gram Dose Equivalent I-131 to 1.0 Microcuries/Gram Dose Equivalent I-131 for Plant Cycle 10 (U2C10) Core ML20206E1611999-04-29029 April 1999 Proposed Tech Spec Change 99-04, Auxiliary Suction Pressure Low Surveillance Frequency Rev. Change Deletes Surveillance ML20206E1391999-04-29029 April 1999 Proposed Tech Spec Change 99-03, Main Control Room Emergency Ventilation Sys Versus Radiation Monitors. Changes Add LCOs 3.3.3.1 & 3.7.7 to Address Inoperability of Radiation Monitoring CREVS & NUREG-1431 Recommendations ML20204E8501999-03-21021 March 1999 Plant,Four Yr Simulator Test Rept for Period Ending 990321 ML20204H4081999-03-19019 March 1999 Proposed Tech Specs,Relocating TS 3.8.3.1,3.8.3.2,3.8.3.3 & Associated Bases Associated with Electrical Equipment Protective Devices to Technical Requirements Manual ML20207D6331999-02-26026 February 1999 Proposed Tech Specs Providing for Consistency When Exiting Action Statements Associated with EDG Sets ML20207D6011999-02-26026 February 1999 Proposed Tech Specs Relocating TS 3.7.6, Flood Protection Plan & Associated Bases from TS to Plant TRM ML20206S0131999-01-15015 January 1999 Proposed Tech Specs 3.3.3.3, Seismic Instrumentation & Associated Bases,Relocated to Plant Technical Requirements Manual ML20199K6001999-01-15015 January 1999 Proposed Tech Specs Adding New Action Statement to 3.1.3.2 That Would Eliminate Need to Enter TS 3.0.3 Whenever Two or More Individual RPIs Per Bank May Be Inoperable,While Maintaining Appropriate Overall Level of Protection ML20195H6111998-11-16016 November 1998 Proposed Tech Specs Revising EDG SRs by Adding Note That Allows SR to Be Performed in Modes 1,2,3 or 4 If Associated Components Are Already OOS for Testing or Maint & Removing SR Verifying Certain Lockout Features Prevent EDG Starting ML20154H7251998-10-0808 October 1998 Proposed Tech Specs Pages,Supplementing Proposed TS Change 96-08,rev 1 to Add CRMP to Administrative Controls Section & Bases of TS ML20238F1091998-08-27027 August 1998 Proposed Tech Specs Providing for Insertion of Limited Number of Lead Test Assemblies,Beginning W/Unit 2 Operating Cycle 10 Core ML20238F3001998-08-27027 August 1998 Proposed Tech Specs Replacing 72 H AOT of TS 3.8.1.1,Action b,w/7 Day AOT Requirement for Inoperability of One EDG or One Train of EDGs ML20209J1631998-08-0707 August 1998 Rev 41 to Sequoyah Nuclear Plant Odcm ML20236G5961998-06-29029 June 1998 Proposed Tech Specs Typed Pages for TS Change 95-19, Section 6 - Administrative Controls Deletions ML20249C6371998-06-26026 June 1998 Proposed Tech Specs Lowering Specific Activity of Primary Coolant from 1.0 Uci/G Dose Equivalent I-131 to 0.35 Uci/G Dose Equivalent I-131,as Provided in GL 95-05 ML20248F0051998-05-28028 May 1998 Proposed Tech Specs for Section 6, Administrative Controls Deletions ML20217N3511998-04-30030 April 1998 Proposed Tech Specs Pages,Modifying Surveillance Requirement 4.4.3.2.1.b to Change Mode Requirement to Allow PORV Stroke Testing in Modes 3,4 & 5 W/Steam Bubble in Pressurizer Rather than Only in Mode 4 ML20203J1681998-02-25025 February 1998 Proposed Tech Specs Pages,Revising EDG Surveillance Requirements to Delete Requirement for 18-month Insp IAW Procedures Prepared in Conjunction W/Vendor Recommendations & Modify SRs Associated W/Verifying Capability of DGs ML20202J7651998-02-13013 February 1998 Technical Requirements Manual ML20202J7141998-02-13013 February 1998 Proposed Tech Specs Adding New LCO That Addresses Requirements for Main Feedwater Isolation,Regulating & Bypass Valves ML20202J6961998-02-13013 February 1998 Proposed Tech Specs Incorporating MSIV Requirements to Be Consistent W/Std TS (NUREG-1431) ML20202J7601998-02-13013 February 1998 Proposed Tech Specs Section 3.7.9 Re Relocation of Snubber Requirements ML20198T4311998-01-21021 January 1998 Proposed Tech Specs Re New Position Title & Update of Description of Nuclear Organization ML20199F8231997-11-30030 November 1997 Cycle 9 Restart Physics Test Summary, for 971011-971130 ML20199K4571997-11-21021 November 1997 Proposed Tech Specs Adding one-time Allowance Through Operating Cycle 9 to Surveillance Requirement 4.4.3.2.1.b to Perform Stroke Testing of PORVs in Mode 5 Rather than Mode 4,as Currently Required ML20211A3191997-09-17017 September 1997 Proposed Tech Specs Re Pressure Differential Surveillance Requirements for Containment Spray Pumps ML20203B9731997-08-0505 August 1997 Rev 1 to RD-466, Test & Calculated Results Pressure Locking ML20217J5581997-07-31031 July 1997 Cycle Restart Physics Test Summary, for Jul 1997 ML20210J1671997-04-30030 April 1997 Snp Unit 1 Cycle 8 Refueling Outage Mar-Apr 1997,Results of SG Tube ISI as Required by TS Section 4.4.5.5.b & Results of Alternate Plugging Criteria Implementation as Required by Commitment from TS License Condition 2C(9)(d) ML20137T0871997-04-0909 April 1997 Proposed Tech Specs Re Elimination of Cycle 8 Limitation for SG Alternate Plugging Criteria ML20137M8581997-04-0101 April 1997 Proposed Tech Specs 2.1 Re Safety Limits & TS 3/4.2 Re Power Distribution Limits ML20137C8421997-03-19019 March 1997 Proposed Tech Specs Re Conversion from Westinghouse Electric Corp Fuel to Framatome Cogema Fuel ML20136J0381997-03-13013 March 1997 Proposed Tech Specs Section 5.6.1.2,revising Enrichment of Fuel for New Fuel Pit Storage Racks ML20134P8631997-02-14014 February 1997 Proposed Tech Specs Requesting Discretionary Enforcement for 48 Hours Which Is in Addition to 72 Hours Allowed Outage Time Provided by TS Action 3.8.1.1.b ML20134K9981997-02-0707 February 1997 Proposed Tech Specs Revising TS Change Request 96-01, Conversion from W Electric Corp Fuel to Framatome Cogema Fuel (MARK-BW-17), to Ensure That Core Analysis Computer Code Output Actions Are Consistent W/Hot Channel Factor SRs ML20138F2581997-01-17017 January 1997 Rev 39 to Sequoyah Nuclear Plant Odcm ML20134L9261996-11-0808 November 1996 Proposed Tech Specs Re Placing of Channel in Trip for Reactor Trip & Engineered Safety Feature Instrumentation Sys Solely to Perform Testing as Not Requiring Channel to Be Declared Inoperable ML20129D2661996-10-18018 October 1996 Proposed Tech Specs,Removing Existing Footnotes That Limit Application of Apc for Plant S/G Tubes to Cycle 8 Operation for Both Units ML20129G7301996-09-26026 September 1996 Proposed Tech Specs 3/4.3.3 Re Fire Detection instrumentation,3/4.7.11 Re Fire Suppression Systems & 3/4.7.12 Re Fire Protection Penetrations ML20134J9991996-09-23023 September 1996 Fuel Assembly Insp Program 1999-08-30
[Table view] |
Text
. _ _ - - _ - - - ____ _
' *
. ,
. .
.
s%
-
ENCLOSURE 1 PROPOSED CllANGES TO SEQUOYAH NUCLEAR PLANT UNIT 1 .
TECHNICAL SPECIFICATIONS
-
8 0 0 9 :2 9 0 %
.
o
.
.
OPERATIONAL LEAKAGE LIVITING CONDITION FOR OPERATION
.
3.4.6.2 Reactor Coolant System leakage shall be limited to:
- a. No PRES 5URE BOUNDARY LEAKAGE,
- b. 1 GPM UNIDENTIFIED LEAKAGE,
- c. 1 GPM total primary-to-secondary leakage through all steam generators and 500 gallons per day through any one steam generator,
- d. 10 GPM IDENTIFIED LEAKAGE from the Reactor Coolant System,
- e. 40 GPM CONTROLLED LEAKAGE at a Reactor Coolant System pressure of 2235 + 20 psig.
- f. 1 GPM leakage from any Reactor Coolant System Pressure Isolation Valve specified in Table 3.4-1.*
APPLICABILITY: MODES 1, 2, 3 and 4 ACTION:
- a. With any PRESSURE BOUNDARY LEAKAGE, be in at least HOT STANDBY within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
- b. With any Reactor Coolant System leakage greater than any one of the above limits, excluding PRESSURE BOUNDARY LEAKAGE, and leakage from Reactor Coolant System Pressure Isolation Valves, reduce the leakage rate to within limits within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
- c. With any Reactor Coolant System Pressure Isolation Valve leakage greater than the above limit, isolate the high pressure portion of the affected system from the low pressure portion within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> by use of at least two closed manual or deactivated automatic valves, or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
SURVEILLANCE REQUIREMENTS 4.4.6.1 Reactor Coolant System leakages shall be demonstrated to be within each of the above limits by:
l
- Specific exceptions to the 1 GPM leakage limit and the MODE 3 and 4 l applicability are listed on Table 3.4-1.
SEQUOYAH - UNIT 1 3/4 4-14 l
-
.
. .
.
TABLE 3.4-1 REACTOR COOLANT SYSTEM PRESSURE ISOLATION VALVES VALVE NUMBER FUNCTION 63-586 Baron Injection 63-587 Boron Injection 63-588 Boron Injection 63-589 Baron Injection 63-581 Boron Injection 63-560 f 63-561 Accumulator Accumulator Discharge l) (l)
Discharge 63-562 Accumulator Discharge (l)63-563 Accumulator Discharge (l)63-622 Accumulator Discharge 63-623 Accumulator Discharge 63-624 Accumulator Discharge 63-625 Accumulator Discharge 63-551 Safety Injection (Cold Leg)63-553 Safety Injection (Cold Leg)63-557 Safety Injection (Cold Leg)63-555 Safety Injection (Cold Leg) .63-632 Residual Heat Removal (Cold Leg)(1)63-633 Residual Heat Removal (Cold Leg)(1)63-634 Residual Heat Removal (Cold Leg)(1)63-635 Residual Heat Removal (Cold Leg)(1)63-641 Residual Heat Removal / Safety Injection (Hot Leg)63-644 Residual Heat Removal / Safety Injection (Hot Leg)63-558 Safety Injection (Hot Leg)63-559 Safety Injection (Hot Leg)63-543 Safety Injection (Hot Leg)63-545 Safety Injection (Hot Leg)63-547 Safety Injection (Hot Leg)
- 63-549 Safety Injection (Hot Leg) 63-640- Residual Heat Removal (Hot Leg)63-643 Residual Heat Removal (Hot Leg)87-558 . Upper Head Injection 87-599 Upper Head Injection 87-560 Upper Head Injection 87-561 Upper Head Injection 87-562 Upper Head Injection 87-563 Upper Head Injection FCV-74-1 Residual Heat Removal (1)(2)
FCV-74-2 Residual Heat Removal (1)(2)
(1) These valves must be tested prior to entering MODE 2.
(2) The leakage limit for these valves is 3 GPM. This value will be finalized within 30 days of issuance of this amendment.
I SEQUOYAH - UNIT 1 3/4 4-15a
.
=
~. ,
- .
ENCLOSURE 2 REASONS AND JUSTIFICATIONS FOR PROPOSED CHANGES TO SEQUOYAH NUCLEAR PLANT UNIT 1 TECHNICAL SPECIFICATIONS c
.
<
l l
. .s
. . . .
- 1. Specification 3.4.6.2.f. Page 3/4 4-14 Add a festnote to this specification to note that there are exceptions to the one GPM leakage limit and the requirement to test before enter-ing MODE 4. These exceptions are identified in Table 3.4-1.
- 2. Table 3.4-1, Page 3/4 4-15a The leakage test procedure for the cold leg injection line check
,
valves requires that the Reactor Coolant System (RCS) pressure be greater than the cold leg accumulator pres.ure. The plant must be in MODE 3 to achieve this pressure. The specific test procedures were discussed with A. Schwencer of the NRC staff by telephone on September 23, 1980. The affected check valves are:
63-560, -561, -562, -563 Cold Leg Injection Line 63-632, -633, -634, -635 RHR Cold Leg The Residual Heat Removal (FHR) pumps or two Reactor Coolant Pumps (RCP) must be operating in MODE 5. This is a requirement of technical specification 3.4.1 3 In order to test the RHR supply line valves, the RHR system must be isolated. Two RCP's must be started. The pump heat from the RCP's will cause the RCS to heat up and exceed MODE 5.
TVA proposes to test the valves before entering MODE 2 to allow for normal plant heatup and isolation of the RHR system. The affected valves are:
FCV-74-1 and FCV-74-2 RHR Supply Line The present specification imposes a one GPM leakage limit on the RHR supply line valves FCV-74-1 and FCV-74-2. The baseline extrapolation, based on an ASME low to high pressure test correlation, for FCV-74-1 resulted in an projected leakage of 1.84 GPM at rated system pressure.
TVA believes that the test correlation is overly conservative. We request that the leakage limits for FCV-74-1 and FCV-74-2 be increased to three GPM for 30 days. During this period, TVA would make leakage measurements at low pressure and at rated system pressure.
Aftar the data has been analyzed, TVA would like to meet with the
'm r . a dis;ueo the results and establish a final baseline leakage value for these valves. ~Without the waiver, the plant would be pro-hibited from starting up and collecting data at rated system pressure.
Section 5.2.6.1 of Safety Evaluation Report (SER) Supplement No. 2 for Sequoyah states in part that "(L)eakage rates higher than one GPM may be considered acceptable if the leak rate changes are below one GPM above the previous test leak rate." TVA's proposal of a three GPM valve is consistent with the SER statement. The fact that these
....
....
valves are gate valves in which valve position is known and that the leakage will be limited to one GPM above a preliminary baseline
, provides reasonable assurance that the design pressure of the RHR system will not be exceeded thus reducing the probability of an occur-rence of an intersystem LOCA. In addition, TVA believes valuable data will be collected which can be used to establish a more effective technical specification.
!
1 i
- :
'
i
. - - . -- . ..
- . -
.- . _ . -