Letter Sequence Draft RAI |
---|
|
|
MONTHYEARML19211D2842019-08-20020 August 2019 Acceptance Review for Traveler TSTF-554, Revise Reactor Coolant Leakage Requirements Project stage: Acceptance Review ML19323D5342019-11-19019 November 2019 Draft RAIs TSTF-554, Revise Reactor Coolant Leakage Project stage: Draft RAI ML20304A1382020-10-30030 October 2020 TSTF-554 Draft Traveler Safety Evaluation Project stage: Request ML20168A3962020-10-30030 October 2020 Cover Letter Transmitting Draft SE of TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements Project stage: Draft Approval ML20154K6062020-10-30030 October 2020 Draft Safety Evaluation of TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements Project stage: Draft Approval ML20322A3612020-12-18018 December 2020 TSTF-554 Cover Letter for Final SE Project stage: Approval ML20322A0242020-12-18018 December 2020 Final SE of Traveler TSTF-554, Revise Reactor Coolant Leakage Requirements Project stage: Approval ML20324A0832020-12-18018 December 2020 Technical Specifications Task Force (TSTF)-554 Final Safety Evaluation Project stage: Request ML20353A2092020-12-21021 December 2020 Cover Letter Transmitting Draft Model TSTF-554, Revise Reactor Coolant Leakage Requirements Project stage: Draft Other ML20353A0742020-12-21021 December 2020 TSTF-554 Draft Model SE Project stage: Request ML20311A6642020-12-21021 December 2020 Draft Model Safety Evaluation of TSTF-554 Revise Reactor Coolant Leakage Requirements Project stage: Draft Approval ML21106A2392021-04-20020 April 2021 Final Model SE of TSTF 554, Revision 1, Revise Reactor Coolant Leakage Requirements Project stage: Other ML21106A2452021-04-20020 April 2021 Cover Letter Transmitting Final Model SE of TSTF 554, Revision 1, Revise Reactor Coolant Leakage Requirements Project stage: Other 2020-10-30
[Table View] |
|
---|
Category:Request for Additional Information (RAI)
MONTHYEARML24264A0232024-09-20020 September 2024 RAI TSTF-600, Rev. 0, Revise the Reactor Coolant System (RCS) Pressure Isolation Valve (PIV) Leakage Testing Frequency ML23222A2272023-08-10010 August 2023 Request for Additional Information Traveler TSTF-592, Revision 1, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML23010A2592023-01-11011 January 2023 Request for Additional Information Traveler TSTF-592, Revision 0, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML22272A5542022-10-0707 October 2022 Request for Additional Information Traveler TSTF-591, Revise Risk Informed Completion Time (RICT) Program ML22235A7382022-08-19019 August 2022 NRR E-mail Capture - Draft RAIs for TSTF-591 (L-2022-PMP-0003) ML22193A2372022-07-12012 July 2022 Request for Additional Information TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown ML21109A1352021-04-12012 April 2021 TSTF-576 NRC Comments on Draft Rev 1 and Draft RAI Response ML20308A6562020-11-0606 November 2020 Request for Additional Information Traveler TSTF-577, Revision 0, Revised Frequencies for Steam Generator Tube Inspections ML20132A1832020-05-11011 May 2020 Request for Additional Information TSTF-576, Revision 0, Revised Safety/Relief Valve Requirement ML20065J9902020-03-0505 March 2020 March 5 2020 TSTF Quarterly Meeting Handout, Agenda Item Iiib - Generic RAIs for LARs to Adopt TSTF-505 Rict ML19323D5342019-11-19019 November 2019 Draft RAIs TSTF-554, Revise Reactor Coolant Leakage ML18134A0752018-05-21021 May 2018 Request for Additional Information (RAI) Technical Specifications Task Force (TSTF) Traveler TSTF-569, Revise Response Time Testing Definition ML18127A4052018-05-0707 May 2018 Draft RAI TSTF-569, Revise Response Time Testing Definition. ML18122A1662018-04-27027 April 2018 Draft RAIs TSTF-568, Clarify Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3. ML18095A2292018-04-12012 April 2018 Request for Additional Information Traveler TSTF-564, Safety Limit MCPR ML18085A0252018-03-20020 March 2018 Traveler TSTF-564, Safety Limit MCPR, Draft RAIs ML18100A0942018-01-29029 January 2018 Draft RAIs from Apla TSTF-563, Revise Instrument Testing Definitions to Incorporate SFCP ML16215A1252016-08-0202 August 2016 Request for Additional Information for Technical Specifications Task Force TSTF-553, Revision 0, Add Action for Two Inoperable Control Room Emergency Air Temperature Control System Trains, CAC No. MF7061 ML16028A4532016-02-23023 February 2016 Request for Additional Information TSTF-553, Add Action for Two Inoperable Creatcs (Control Room Emergency Air Temperature Control System) Trains. ML15322A2842016-02-0404 February 2016 Request for Additional Information TSTF-537, Revision 0, Increase CIV Completion Time; Update of TSTF-373. ML15322A2702016-01-12012 January 2016 Request for Additional Information Regarding Traveler TSTF-454, Revision 3, Extend PCIV Completion Times (NEDC-33046). ML15293A1612015-12-0808 December 2015 Request for Additional Information (RAI) TSTF 542, Rev. 1, Reactor Pressure Vessel Water Inventory Control, ML15281A2912015-11-18018 November 2015 Request for Additional Information Regarding TSTF-551, Revision 1, Revise Secondary Containment Surveillance Requirements. ML15208A2872015-08-13013 August 2015 Request for Additional Information Traveler TSTF-541, Rev 0, Add Exceptions to Surveillance Requirements When the Safety Function Is Being Performed ML15033A1082015-06-0202 June 2015 Draft Request for Additional Information Traveler TSTF-529, Revision 2, Clarify Use and Application Rules TSTF-14-17, Technical Specification Task Force - Response to NRC Request for Additional Information Regarding TSTF-454, Revision, Extend PCIV Completion Times (NEDC-33046) and Submittal of TSTF-454, Revision 32015-03-31031 March 2015 Technical Specification Task Force - Response to NRC Request for Additional Information Regarding TSTF-454, Revision, Extend PCIV Completion Times (NEDC-33046) and Submittal of TSTF-454, Revision 3 ML15057A2482015-02-26026 February 2015 Notice of Forthcoming Public Meeting Between the U.S. Nuclear Regulatory Commission and the Technical Specifications Task Force TSTF-551 ML14310A3442014-11-0606 November 2014 Draft RAI from Srxb TSTF-547, Clarification of Rod Position Requirements. ML14196A4142014-07-0707 July 2014 TSTF Handout from 7/10/14 Meeting TSTF Concerns with TSTF-505 RAIs ML13045A8602013-03-0404 March 2013 Request for Additional Information Traveler TSTF-537, Revision 0, Increase CIV (Containment Isolation Valve) Completion Time; Update of TSTF-373 ML12279A2082012-10-19019 October 2012 TSTF-531 RAIs ML12279A1342012-10-19019 October 2012 TSTF-454, Rev 2, RAIs ML12158A5472012-06-13013 June 2012 TSTF-523 Acceptance Letter and RAIs ML1108908172011-04-12012 April 2011 Request for Additional Information Regarding TSTF-508, Revision 1, Revise Control Room Habitability Actions to Address Lessons Learned from TSTF-448 Implementation ML1020402322010-07-27027 July 2010 Request for Additional Information Regarding TSTF-505, Revision 0, on Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML1015304012010-07-0707 July 2010 Acceptance for Review and Request for Additional Information for TSTF-432, Revision 0, Change in Technical Specifications End States (WCAP-16294). ML0914704322009-06-11011 June 2009 Request for Additional Information Regarding TSTF-514 on Reactor Coolant System Leakage Detection ML0906808132009-04-17017 April 2009 Request for Additional Information Regarding TSTF-508, Revision 0, Revise Control Room Habitability Actions to Address Lessons Learned from TSTF-448 Implementation ML0828004842008-11-0404 November 2008 Evaluation of TSTF Responses to NRC Staff Request for Additional Information (RAI) Regarding Traveler TSTF-493, Revision 2, Clarify Application of Setpoint Methodology for LSSS Functions. ML0820406052008-08-13013 August 2008 RAI for Review of TSTF-506, Rev 0 ML0812101752008-06-0404 June 2008 Request for Additional Information Regarding TSTF-500, Rev. 0, DC Electrical Rewrite - Update to TSTF-360. ML0810400032008-05-0505 May 2008 Request for Additional Information Regarding TSTF-501, Revision 0, Relocate Stored Fuel Oil and Lube Oil Values to Licensee Control ML0721206302007-10-0202 October 2007 Request for Additional Information (RAI) Regarding TSTF Traveler 425, Revision 1, Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5. ML0627700892006-11-0909 November 2006 Request for Additional Information Regarding TSTF-478, Revision 0, BWR Technical Specification Changes That Implement the Revised Rule for Combustible Gas Control 2024-09-20
[Table view] |
Text
REQUEST FOR ADDITIONAL INFORMATION TECHNICAL SPECIFICATIONS TASK FORCE TRAVELER TSTF-554, "REVISE REACTOR COOLANT LEAKAGE REQUIREMENTS (EPID L-2019-PMP-0181))
RAI - 1
Background
Section 2.3, Reason for the Proposed Change, states the following:
There is disagreement on what is required for isolation. The industry has historically held that isolation must be within the expected capabilities of the isolation device and some normal leakage past the isolation device is acceptable.
This position is consistent with other uses of the term isolate in Standard Technical Specifications and in Section XI of the ASME Code. The NRC position has been that isolation must be complete with no leakage past the isolation device.
Request State the basis for how Section XI of the ASME Code supports the historical industry position of some normal leakage past the isolation device being acceptable or delete and in Section XI of the ASME Code.
RAI - 2
Background
Section 2.4 Description of the Proposed Change, states in part that:
The new Condition A provides a clear action to follow if pressure boundary leakage exists. The Bases for Required Action A.1 states that normal leakage past the isolation device is acceptable and it is included in identified or unidentified LEAKAGE and subject to the TS limits. The Bases also state that if there is no available isolation device or if the flaw cannot be isolated from the RCS due to physical or operational reasons, then Condition C (an immediate plant shutdown) applies.
Leakage past the isolation device is acceptable because the isolated flaw is no longer part of the RCS pressure boundary and any further degradation would not have any significant effect on the RCS. Other considerations, such as boric acid deposition in pressurized water reactors, effects of the leakage on other plant systems, and correction of the flaw, are addressed by existing plant programs, such as the corrective action process and the operability determination process.
Normal leakage may be evaluated using engineering judgement, historical performance, or other means, and does not imply that a limit on normal leakage must be established.
Allowed leakage past the isolation device is permitted as described in each model technical specification change, ACTIONS A.1. However, aside from the clause in the definition of IDENTIFIED LEAKAGE which states that leakage cannot interfere with the operation of leakage detection systems, the change does not define limits on the allowable amount of leakage. The NRC staff is concerned that extensive leakage beyond the isolation device could lead to further degradation that could potentially compromise the structural support function of the pipe during a seismic event.
Take for example a flaw downstream of a closed isolation device that is leaking. Though the pipe has a pressure boundary function that is known to no longer be functional, it may still need to function as a link in the structural support system. Leakage beyond the isolation device may result in continued degradation of the downstream flaw and resultantly cause the pipe to fail its structural support function.
Request Define normal leakage past the isolation valve and state the basis for why leakage past the isolation device could not lead to further degradation of the flawed area such that the structural support function of the component could challenge the structural support of the isolation device. Commented [HM1]: Brian Mann had a lot to say about this RAI. Did his commentary clear up the issue? Do we still RAI - 3 need this RAI? Do we want to revise the request? If we keep this RAI, what would be consider an acceptable definition for normal leakage?
Background
BASES, ACTIONS A.1 of the Babcock & Wilcox, Westinghouse, Combustion Engineering, and AP1000 Standard Technical Specifications states in part that:
If there is no available isolation device or if the flaw cannot be isolated from the RCS due to physical or operational reasons, then Condition C applies.
Similarly, BASES, ACTIONS A.1 of the General Electric BWR/4 and General Electric BWR/6 Standard Technical Specifications states in part that:
If there is no available isolation device or if the flaw cannot be isolated from the RCS due to physical or operational reasons, then Condition D applies.
These statements, though captured in the BASES, are not reflected in the in the Technical Specifications (TS) changes in the Action tables. The proposed TS changes only assign a COMPLETION TIME of "Immediately" and the REQUIRED ACTION states Initiate action to isolate affected component, pipe, or vessel from the RCS by use of a closed manual valve, closed and de-activated automatic valve, blind flange, or check valve. The NRC staff has raised concern in the usage of the term Initiate Action in lieu of Isolate There is no completion time for isolation of the flaw. For example, initiating action can be the installation of a blind flange, which will require a significant engineering, planning, and work execution effort without any intermediate isolation of leakage.
Requests
- a. Provide the bases for why the requirements to enter Conditions C.1 and C.2 or D.1 and D.2 when there is no available isolation device or if the flaw cannot be isolated from the RCS are not being captured in the Technical Specification changes.
State the bases for the need for the term Initiate action andExplain why the Required Action statement does not start with Isolate Initiation of an action could potentially be followed by a long period of time where the flaw continues to leakhave a completion time for isolation of the flaw.
RAI - 4 Commented [HM2]: Ravi, Please discuss with Vic on Friday or Monday. His door was shut Thursday afternoon, Background so I was not able to talk with him after you left.
Section 2.2 states (emphasis added):
Note that the Reactor Coolant System pressure boundary considered in the RCS Operational LEAKAGE TS and the corresponding definitions are not equivalent to the reactor coolant pressure boundary as defined in 10 CFR [50.2],
"Definitions.
The NRC staff doesnt believe the definitions in 10 CFR 50.2 and the STS are meant to imply a difference. They are complementary to one another because any RCPB leakage requires a shutdown period. The only way the licensee can avoid the shutdown is to isolate the leakage in accordance with the definition in 10 CFR 50.2 (i.e., isolating the fault from the RCS by closing two valves between the fault and the RCS). The valves must remain closed as indicated in the definition, and Action required per the TS.
Request Clarify why the definitions are not the same or remove the sentence.