Letter Sequence RAI |
---|
TAC:MF7061, Revise or Add Actions to Preclude Entry Into LCO 3.0.3 - RITSTF Initiatives 6B and 6C, Add Action for Two Inoperable Creatcs Trains (Open) |
|
|
|
---|
Category:Letter
MONTHYEARML23325A2132023-12-18018 December 2023 Cover Letter for Final Model SE of TSTF-591, Revise Risk Informed Completion Time (RICT) Program ML23262B2292023-09-21021 September 2023 Cover Letter Transmitting Final SE of TSTF-591, Revision 0, Revise Risk-Informed Completion Time (RICT) Program ML23124A2212023-09-11011 September 2023 Cover Letter for Final SEs of TSTF-589, Eliminate Automatic Diesel Generator (DG) Start During Shutdown ML23206A1242023-07-31031 July 2023 TSTF-584 Cover Letter for Final SE ML23205A2342023-07-0606 July 2023 Draft TSTF-601, 'Extend Shield Building Completion Time After Refueling' ML23012A2812023-03-13013 March 2023 Draft SEs of TSTF-584, Eliminate Automatic RWCU System Isolation on SLC Initiation ML23059A3342023-02-28028 February 2023 TSTF-576 Open Issues Letter ML23010A2592023-01-11011 January 2023 Request for Additional Information Traveler TSTF-592, Revision 0, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML22272A5542022-10-0707 October 2022 Request for Additional Information Traveler TSTF-591, Revise Risk Informed Completion Time (RICT) Program TSTF-22-07, Transmittal of TSTF-592, Revision 0, Revise Automatic Depressurization System (ADS) Instrumentation Requirements2022-07-19019 July 2022 Transmittal of TSTF-592, Revision 0, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML22193A2372022-07-12012 July 2022 Request for Additional Information TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown TSTF-22-06, Technical Specifications Task Force - Request for a Workshop to Discuss the Interaction of Natural Phenomena Protection Design Features and Operability2022-07-0808 July 2022 Technical Specifications Task Force - Request for a Workshop to Discuss the Interaction of Natural Phenomena Protection Design Features and Operability ML22110A1712022-04-26026 April 2022 Acceptance for Review Regarding Traveler Tstf-584, Rev 0, Eliminate Automatic RWCU System Isolation on SLC Initiation TSTF-22-04, Technical Specifications Task Force - Transmittal of TSTF-591, Revision 0, Revise Risk Informed Completion Time (RICT) Program2022-03-22022 March 2022 Technical Specifications Task Force - Transmittal of TSTF-591, Revision 0, Revise Risk Informed Completion Time (RICT) Program ML21188A2782021-07-11011 July 2021 Cover Letter Transmitting Final SEs of CLIIP TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Operable RHR (Residual Heat Removal) Shutdown Cooling TSTF-21-03, TSTF Response to NRC Questions on TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements and Submittal of Revision 12021-06-23023 June 2021 TSTF Response to NRC Questions on TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements and Submittal of Revision 1 ML21054A2512021-05-26026 May 2021 Cover Letter Transmitting Draft SEs of CLIIP TSTF-580, RHR Shutdown Cooling System - Hot Shutdown ML21106A2452021-04-20020 April 2021 Cover Letter Transmitting Final Model SE of TSTF 554, Revision 1, Revise Reactor Coolant Leakage Requirements ML21098A2422021-04-14014 April 2021 Cover Letter for Final SEs of TSTF-577, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ML21068A4012021-03-24024 March 2021 Cover Letter for Draft SEs TSTF 577, Revision 1, Revised Frequencies for Steam Generator Tube Inspections TSTF-21-01, Transmittal of TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2021-01-26026 January 2021 Transmittal of TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML20322A3612020-12-18018 December 2020 TSTF-554 Cover Letter for Final SE ML20308A6562020-11-0606 November 2020 Request for Additional Information Traveler TSTF-577, Revision 0, Revised Frequencies for Steam Generator Tube Inspections ML20168A3962020-10-30030 October 2020 Cover Letter Transmitting Draft SE of TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements ML20265A1152020-10-0909 October 2020 Cover Letter Transmitting Model SE of TSTF-582 and TSTF-583-T ML20133J8832020-07-29029 July 2020 Letter Transmitting Draft SE of Traveler TSTF-582, Revision 0, RPV WIC Enhancements TSTF-20-04, Technical Specifications Task Force - Transmittal of TSTF-577, Revision 0, Revised Frequencies for Steam Generator Tube Inspections2020-06-0808 June 2020 Technical Specifications Task Force - Transmittal of TSTF-577, Revision 0, Revised Frequencies for Steam Generator Tube Inspections ML20133J8152020-05-13013 May 2020 Letter Transmitting Revised Final SE of Traveler TSTF-564, Revision 2, Safety Limit MCPR, Using the Consolidated Line Item Improvement Process ML20132A1832020-05-11011 May 2020 Request for Additional Information TSTF-576, Revision 0, Revised Safety/Relief Valve Requirement TSTF-20-01, Transmittal of TSTF-IG-20-02, Guidance on Evaluating One-Time Surveillance Frequency Changes Under the Surveillance Frequency Control Program (TSTF-425M SFCP)2020-04-0909 April 2020 Transmittal of TSTF-IG-20-02, Guidance on Evaluating One-Time Surveillance Frequency Changes Under the Surveillance Frequency Control Program (TSTF-425M SFCP) TSTF-19-14, Technical Specifications Task Force - TSTF Response to NRC Questions on TSTF-582, RPV WIC Enhancements2020-02-12012 February 2020 Technical Specifications Task Force - TSTF Response to NRC Questions on TSTF-582, RPV WIC Enhancements TSTF-19-11, TSTF Response to NRC Questions on TSTF-554, Revise Reactor Coolant Leakage Requirements2020-01-16016 January 2020 TSTF Response to NRC Questions on TSTF-554, Revise Reactor Coolant Leakage Requirements ML19325C4362019-12-17017 December 2019 Cover Letter Transmitting Final SEs of Traveler TSTF-568, Revision 2, Revise Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2 TSTF-19-09, Technical Specifications Task Force - Transmittal of TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements2019-12-13013 December 2019 Technical Specifications Task Force - Transmittal of TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements ML19323E9282019-12-10010 December 2019 Cover Letter Transmitting Final SEs of Traveler TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position TSTF-19-13, Technical Specifications Task Force - Updated TSTF Membership and Distribution2019-12-0303 December 2019 Technical Specifications Task Force - Updated TSTF Membership and Distribution TSTF-19-12, TSTF Comments on Draft Safety Evaluations for Traveler TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position.2019-11-0505 November 2019 TSTF Comments on Draft Safety Evaluations for Traveler TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position. TSTF-19-10, Transmittal of Errata Changes to TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2019-08-28028 August 2019 Transmittal of Errata Changes to TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML19176A1892019-08-14014 August 2019 Cover Letter Transmitting Final Safety Evaluations of Traveler TSTF-569, Revision 2, Revise Response Time Testing Definition TSTF-19-03, Request for Fee Exemption for TSTF-554, Revision 0, Revise Reactor Coolant Leakage Requirements - Letter2019-07-0808 July 2019 Request for Fee Exemption for TSTF-554, Revision 0, Revise Reactor Coolant Leakage Requirements - Letter TSTF-19-08, Draft of Traveler TSTF-582, Revision 0, RPV WIC Enhancements.2019-07-0303 July 2019 Draft of Traveler TSTF-582, Revision 0, RPV WIC Enhancements. TSTF-19-06, TSTF Comments on Draft Safety Evaluations for Traveler TSTF-569, Revision 1, Revise Response Time Testing Definition2019-06-25025 June 2019 TSTF Comments on Draft Safety Evaluations for Traveler TSTF-569, Revision 1, Revise Response Time Testing Definition TSTF-19-07, TSTF Handout for October 16, 2019, Meeting: Elimination of Commitment to Adopt TSTF-4932019-06-18018 June 2019 TSTF Handout for October 16, 2019, Meeting: Elimination of Commitment to Adopt TSTF-493 TSTF-19-05, Transmittal of TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2019-06-18018 June 2019 Transmittal of TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML19017A2222019-05-29029 May 2019 Letter Transmitting Draft Safety Evaluations of Technical Specifications Task Force Traveler TSTF-569, Revision 1, Revise Response Time Testing Definition ML19028A2852019-02-21021 February 2019 Final SEs of TSTF-566, Revision 0, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems (Transmittal Letter) TSTF-19-01, TSTF Comments on Draft Safety Evaluations for Traveler TSTF-566, Revision 0, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems2019-01-17017 January 2019 TSTF Comments on Draft Safety Evaluations for Traveler TSTF-566, Revision 0, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems ML19007A2252019-01-15015 January 2019 Letter Transmitting Final SEs of Traveler TSTF-557, Revision 1, Spent Fuel Storage Rack Neutron Absorber Monitoring Program. ML18284A3772018-12-31031 December 2018 Incorporation of Technical Specifications Task Force (TSTF) Traveler TSTF-565, Revision 1, Revise the LCO 3.0.2 and LCO 3.0.3 Bases, Into the Next Revision of the Standard Technical Specifications TSTF-18-13, TSTF Comments on Draft Safety Evaluation for Traveler TSTF-557, Revision 1, Spent Fuel Storage Rack Neutron Absorber Monitoring Program.2018-12-20020 December 2018 TSTF Comments on Draft Safety Evaluation for Traveler TSTF-557, Revision 1, Spent Fuel Storage Rack Neutron Absorber Monitoring Program. 2023-09-21
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML23222A2272023-08-10010 August 2023 Request for Additional Information Traveler TSTF-592, Revision 1, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML23010A2592023-01-11011 January 2023 Request for Additional Information Traveler TSTF-592, Revision 0, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML22272A5542022-10-0707 October 2022 Request for Additional Information Traveler TSTF-591, Revise Risk Informed Completion Time (RICT) Program ML22235A7382022-08-19019 August 2022 NRR E-mail Capture - Draft RAIs for TSTF-591 (L-2022-PMP-0003) ML22193A2372022-07-12012 July 2022 Request for Additional Information TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown ML21109A1352021-04-12012 April 2021 TSTF-576 NRC Comments on Draft Rev 1 and Draft RAI Response ML20308A6562020-11-0606 November 2020 Request for Additional Information Traveler TSTF-577, Revision 0, Revised Frequencies for Steam Generator Tube Inspections ML20132A1832020-05-11011 May 2020 Request for Additional Information TSTF-576, Revision 0, Revised Safety/Relief Valve Requirement ML20065J9902020-03-0505 March 2020 March 5 2020 TSTF Quarterly Meeting Handout, Agenda Item Iiib - Generic RAIs for LARs to Adopt TSTF-505 Rict ML19323D5342019-11-19019 November 2019 Draft RAIs TSTF-554, Revise Reactor Coolant Leakage ML18134A0752018-05-21021 May 2018 Request for Additional Information (RAI) Technical Specifications Task Force (TSTF) Traveler TSTF-569, Revise Response Time Testing Definition ML18127A4052018-05-0707 May 2018 Draft RAI TSTF-569, Revise Response Time Testing Definition. ML18122A1662018-04-27027 April 2018 Draft RAIs TSTF-568, Clarify Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3. ML18095A2292018-04-12012 April 2018 Request for Additional Information Traveler TSTF-564, Safety Limit MCPR ML18085A0252018-03-20020 March 2018 Traveler TSTF-564, Safety Limit MCPR, Draft RAIs ML18100A0942018-01-29029 January 2018 Draft RAIs from Apla TSTF-563, Revise Instrument Testing Definitions to Incorporate SFCP ML16215A1252016-08-0202 August 2016 Request for Additional Information for Technical Specifications Task Force TSTF-553, Revision 0, Add Action for Two Inoperable Control Room Emergency Air Temperature Control System Trains, CAC No. MF7061 ML16028A4532016-02-23023 February 2016 Request for Additional Information TSTF-553, Add Action for Two Inoperable Creatcs (Control Room Emergency Air Temperature Control System) Trains. ML15322A2842016-02-0404 February 2016 Request for Additional Information TSTF-537, Revision 0, Increase CIV Completion Time; Update of TSTF-373. ML15322A2702016-01-12012 January 2016 Request for Additional Information Regarding Traveler TSTF-454, Revision 3, Extend PCIV Completion Times (NEDC-33046). ML15293A1612015-12-0808 December 2015 Request for Additional Information (RAI) TSTF 542, Rev. 1, Reactor Pressure Vessel Water Inventory Control, ML15281A2912015-11-18018 November 2015 Request for Additional Information Regarding TSTF-551, Revision 1, Revise Secondary Containment Surveillance Requirements. ML15208A2872015-08-13013 August 2015 Request for Additional Information Traveler TSTF-541, Rev 0, Add Exceptions to Surveillance Requirements When the Safety Function Is Being Performed ML15033A1082015-06-0202 June 2015 Draft Request for Additional Information Traveler TSTF-529, Revision 2, Clarify Use and Application Rules TSTF-14-17, Technical Specification Task Force - Response to NRC Request for Additional Information Regarding TSTF-454, Revision, Extend PCIV Completion Times (NEDC-33046) and Submittal of TSTF-454, Revision 32015-03-31031 March 2015 Technical Specification Task Force - Response to NRC Request for Additional Information Regarding TSTF-454, Revision, Extend PCIV Completion Times (NEDC-33046) and Submittal of TSTF-454, Revision 3 ML15057A2482015-02-26026 February 2015 Notice of Forthcoming Public Meeting Between the U.S. Nuclear Regulatory Commission and the Technical Specifications Task Force TSTF-551 ML14310A3442014-11-0606 November 2014 Draft RAI from Srxb TSTF-547, Clarification of Rod Position Requirements. ML14196A4142014-07-0707 July 2014 TSTF Handout from 7/10/14 Meeting TSTF Concerns with TSTF-505 RAIs ML13045A8602013-03-0404 March 2013 Request for Additional Information Traveler TSTF-537, Revision 0, Increase CIV (Containment Isolation Valve) Completion Time; Update of TSTF-373 ML12279A2082012-10-19019 October 2012 TSTF-531 RAIs ML12279A1342012-10-19019 October 2012 TSTF-454, Rev 2, RAIs ML12158A5472012-06-13013 June 2012 TSTF-523 Acceptance Letter and RAIs ML1108908172011-04-12012 April 2011 Request for Additional Information Regarding TSTF-508, Revision 1, Revise Control Room Habitability Actions to Address Lessons Learned from TSTF-448 Implementation ML1020402322010-07-27027 July 2010 Request for Additional Information Regarding TSTF-505, Revision 0, on Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML1015304012010-07-0707 July 2010 Acceptance for Review and Request for Additional Information for TSTF-432, Revision 0, Change in Technical Specifications End States (WCAP-16294). ML0914704322009-06-11011 June 2009 Request for Additional Information Regarding TSTF-514 on Reactor Coolant System Leakage Detection ML0906808132009-04-17017 April 2009 Request for Additional Information Regarding TSTF-508, Revision 0, Revise Control Room Habitability Actions to Address Lessons Learned from TSTF-448 Implementation ML0828004842008-11-0404 November 2008 Evaluation of TSTF Responses to NRC Staff Request for Additional Information (RAI) Regarding Traveler TSTF-493, Revision 2, Clarify Application of Setpoint Methodology for LSSS Functions. ML0820406052008-08-13013 August 2008 RAI for Review of TSTF-506, Rev 0 ML0812101752008-06-0404 June 2008 Request for Additional Information Regarding TSTF-500, Rev. 0, DC Electrical Rewrite - Update to TSTF-360. ML0810400032008-05-0505 May 2008 Request for Additional Information Regarding TSTF-501, Revision 0, Relocate Stored Fuel Oil and Lube Oil Values to Licensee Control ML0721206302007-10-0202 October 2007 Request for Additional Information (RAI) Regarding TSTF Traveler 425, Revision 1, Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5. ML0627700892006-11-0909 November 2006 Request for Additional Information Regarding TSTF-478, Revision 0, BWR Technical Specification Changes That Implement the Revised Rule for Combustible Gas Control 2023-08-10
[Table view] |
Text
February 23, 2016 Technical Specifications Task Force 11921 Rockville Pike, Suite 100 Rockville, MD 20852
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION RE: TRAVELER TSTF-553, REVISION 0, ADD ACTION FOR TWO INOPERABLE CREATCS TRAINS (TAC NO. MF7061)
Dear Members of the Technical Specifications Task Force:
By letter dated October 31, 2015 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML15304A002), you submitted to the U.S. Nuclear Regulatory Commission (NRC) Traveler TSTF-553, Revision 0, Add Action for Two Inoperable CREATCS
[Control Room Emergency Air Temperature Control System] Trains. Upon review of the information provided, the NRC staff has determined that additional information is needed to complete the review. On February 22, 2016, Brian Mann, Vice President of Industry Programs, EXCEL Services Corporation, and I agreed that the NRC staff will receive your response to the enclosed request for additional information (RAI) questions within 60 calendar days of the date of this letter (or the next business day if 60 days falls on a weekend).
The review schedule below that was provided in the acceptance letter, dated December 15, 2015 (ADAMS Accession No. ML15328A367), is still valid.
MILESTONE ORIGINAL DATE Issue Draft Safety Evaluation August 26, 2016 Issue Final Safety Evaluation October 31, 2016 If you have any questions regarding the enclosed RAI questions, please contact me at 301-415-1774 or via e-mail at Michelle.Honcharik@nrc.gov.
Sincerely,
/RA/
Michelle C. Honcharik, Senior Project Manager Licensing Processes Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Project No. 753
Enclosure:
As stated cc: See next page
ML15328A367), is still valid.
MILESTONE ORIGINAL DATE Issue Draft Safety Evaluation August 26, 2016 Issue Final Safety Evaluation October 31, 2016 If you have any questions regarding the enclosed RAI questions, please contact me at 301-415-1774 or via e-mail at Michelle.Honcharik@nrc.gov.
Sincerely,
/RA/
Michelle C. Honcharik, Senior Project Manager Licensing Processes Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Project No. 753
Enclosure:
As stated cc: See next page DISTRIBUTION:
See next page ADAMS Accession No.: ML16028A453 *concurred via e-mail
NAME MHoncharik DHarrison (ABaxter for) SWeerakkody DATE 2/9/16 2/11/16 1/21/16 OFFICE DSS/SCVB** DPR/PLPB* DPR/PLPB NAME RDennig (ASallman for) KHsueh MHoncharik DATE 2/8/15 2/18/16 2/23/16 Letter to Technical Specifications Task Force dated February 23, 2016
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION RE: TRAVELER TSTF-553, REVISION 0, ADD ACTION FOR TWO INOPERABLE CREATCS TRAINS (TAC NO. MF7061)
DISTRIBUTION:
Project No. 753 PUBLIC RidsNrrOd RidsNrrDpr RidsOgcMailCenter RidsOpaMail RidsAcrs_MailCTR RidsNrrPMMHoncharik RidsNrrLADHarrison RidsNrrDprPlpb RidsNrrDssStsb RKuntz EMiller MHamm NKaripineni RidsNrrDssScvb VHuckabay SMazumdar RidsNrrDraApla RidsNrrDraAphb RidsNrrDeEicb
Technical Specifications Task Force Project No. 753 cc:
Technical Specifications Task Force c/o EXCEL Services Corporation 11921 Rockville Pike Suite 100 Rockville, MD 20852 Attention: Brian D. Mann E-mail: brian.mann@excelservices.com James R. Morris Diablo Canyon Power Plant Building 104/5/21A P.O. Box 56 Avila Beach, CA 93424 E-mail: JY1E@pge.com Joseph A. Clark Entergy Nuclear South 5485 Highway 61 St. Francisville, LA. 70775 E-mail: jclark@entergy.com Otto W. Gustafson Entergy Nuclear Operations, Inc.
Palisades Nuclear Power Plant 27780 Blue Star Memorial Highway Covert, MI 49043 E-mail: ogustaf@entergy.com Michael K. Leisure Duke Energy 526 S. Church Street Mail Code EC2ZF Charlotte, NC 28202 E-mail: mike.leisure@duke-energy.com
REQUEST FOR ADDITIONAL INFORMATION TSTF-553, REVISION 0, ADD ACTION FOR TWO INOPERABLE CREATCS TRAINS (TAC NO. MF7061)
By letter dated October 31, 2015 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML15304A002), the Technical Specifications Task Force (TSTF) submitted to the U.S. Nuclear Regulatory Commission (NRC) for review Traveler TSTF-553, Revision 0, Add Action for Two Inoperable CREATCS [Control Room Emergency Air Temperature Control System] Trains.
TSTF-553 proposes to revise the current Technical Specification (TS) 3.7.11, to modify the TS Actions for two inoperable CREATCS trains. The revised Action provides 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to restore a CREATCS train to operable status, provided the control room area temperature is maintained below a plant-specific limit. TSTF-553 is applicable to all Babcock & Wilcox and Westinghouse plants (NUREG-1430 and NUREG-1431).
Question #1 is from the Probabilistic Risk Assessment Operations and Human Factors Branch (APHB). Questions #2 through #5 are from the Containment and Ventilation Branch (SCVB).
RAI #1:
Appendix A, General Design Criteria for Nuclear Power Plants, to Title 10 of the Code of Federal Regulations (10 CFR), Part 50, Domestic Licensing of Production and Utilization Facilities, Criterion 19 - Control room, states, in part: A control room shall be provided from which actions can be taken to operate the nuclear power unit safely under normal conditions and to maintain it in a safe shutdown condition under accident conditions, including loss-of-coolant accidents.
NUREG-0700, Human-System Interface Design Review Guidelines, Revision 2, Section 12, Workplace Design, Subsection 12.1.2.1, Temperature and Humidity, Guideline 12.1.2.1-1, Comfort Zone, states: The climate control system should maintain temperatures of 68-75°F in winter and 73-79°F in summer and relative humidity levels between 30% and 60%. Further, the additional information accompanying this guideline, states, in part: The temperature ranges given are based on the ASHRAE [American Society of Heating, Refrigerating and Air-Conditioning Engineers] 55-1992.
While the above guidance addresses the temperature comfort zone in the control room, it does consider maximum allowable temperatures and associated stay times (action times), to ensure control room habitability. Related guidance for heat stress exposure is found in NUREG-0700, Revision 2, Section 12, Subsection 12.2.5.1, Heat, Guideline 12.2.5.1-1, Heat Stress, which states: The level of physical activity and required protective clothing, as well as temperature and humidity, should be considered when assessing the danger of heat exposure. Further, the additional information accompanying this guideline, states: Important considerations are the amount of metabolic heat being generated by the worker and the restriction of evaporative heat loss associated with protective clothing. Workers abilities to withstand heat will also differ Enclosure
based on their physical conditioning and degree of acclimatization. While this guidance is provided for Local Control Stations and not Control Rooms, it addresses the effects of heat stress for workers with low metabolism (which is characterized as light work, such as actively monitoring spatially distributed equipment, walking, retrieving procedures or manuals, etc.) and work clothes. Table 12.7, Stay times for different WBGTs [Wet-bulb globe temperatures],
illustrates that, for example, the stay time for WBGT of 93°F for an individual in work clothes with low metabolism is limited to 3 to 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />, whereas the stay time for WBGT of 97°F for the same individual would be limited to 2 to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.
With both CREATCS trains being inoperable, the effects of heat stress due to the rising temperature, under some circumstances, may impede the operators ability to take actions required to safely operate the nuclear power unit.
TSTF-553, Revision 0, Section 2.4, Description of the Proposed Change, states, in part: The proposed Required Actions require verification that control room temperature is less than a plant-specific limit every 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> and restoration of one CREATCS train to operable status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. Further, Section 3, Technical Evaluation, states, in part: The four-hour monitoring frequency of control room area temperature is adequate given the indications available in the control room, the time required for a significant increase in control room air temperature, and NRC acceptance of this interval in similar Technical Specifications for other plant designs.
Provide additional information to clarify why the proposed temperature monitoring frequency is set at 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />, and does not vary with the plant-specific maximum temperature limit. In the response, identify what industry standard(s) or guidance (such as, for example, EPRI TR-109445, Heat Stress Management Program for Power Plants), or other data were used in determining the acceptable stay times, based on varying temperature and humidity levels.
RAI #2 Page 2 of TSTF-553, Revision 0, second paragraph states:
Depending on the plant design, the CREATCS and the CREVS [Control Room Emergency Ventilation System] or CREFS [Control Room Emergency Filtration System] may share components, such as ductwork, dampers, or doors.
Inoperability of the CREATCS or of the CREVS or CREFS would not affect the operability of the other system unless a shared component, such as ductwork, is affected.
The last sentence, although not incorrect, is limited to passive components only. Depending on the system configuration, many plants are designed to have flow in series through active components such as fans in CREVS and CREATCS. In such cases, there is a potential for an inoperable CREATCS fan to render the CREVS also inoperable. On the other hand, an inoperable chiller or a chilled water pump in CREATCS may not have an impact on CREVS operability. In this regard, the NRC staff requests additional discussion in the Traveler as to how these situations regarding CREVS operability would be implemented/handled in the TS, including possible entry into limiting condition for operation (LCO) 3.7.10.F.
RAI #3 Page 3 of TSTF-553, Revision 0, and first bullet under the paragraph starting The requirements are not consistent . . . states:
NUREG-1432, the ISTS [improved standard technical specifications] for Combustion Engineering plants, TS 3.7.11, provides 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to restore one of two inoperable control room cooling trains provided mitigating actions are implemented and the Reactor Coolant System (RCS) Specific Activity TS Limiting Condition for Operation (LCO) is met. This allowance was approved by the NRC on May 30, 2013 as TSTF-426, Revision 5, Revise or Add Actions to Preclude Entry into LCO 3.0.3 - RITSTF Initiatives 6b & 6c [. . .]. To date, this traveler has been adopted by four of the eight Combustion Engineering plants.
The referenced TS 3.7.11 is incorrect for control room cooling trains. The information in TS 3.7.12 applies to control room cooling trains. The reference to RCS Specific Activity TS LCO is also incorrect. It applies to Control Room Emergency Air Cleanup System (TS 3.7.11),
not the control room cooling trains. Revise the references and the discussion to convey its intended purpose and use in TSTF-553.
RAI #4 Section 3, Technical Evaluation, second paragraph, last sentences states:
This evaluation may credit compensatory actions, such as use of normal ventilation systems, opening of cabinet doors, use of fans or ice vests, and opening control room doors or ventilation paths. If the control room envelope boundary is breached in order to provide cooling, the Actions of TS 3.7.10 (CREVS/CREFS) would also apply. This evaluation is performed for normal operating conditions including the availability of normal electrical power based on the small likelihood of an event requiring the CREATCS during the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Completion Time.
In addition to what was stated in RAI #2, this is one area of the interdependency between CREATCS and CREVS. It brings out a conflict between the proposed compensatory actions under the TS for CREATCS and the existing mitigating actions under TS 3.7.10 for CREVS/CREFS. Opening the control room doors would compromise the control room boundary thus placing the plant in TS 3.7.10 Action Statement B.1, requiring immediate initiation of action to implement mitigating actions. Opening control room doors intentionally, in effect, could also render both trains of CREVS/CREFS to be inoperable due to inoperable control room boundary in MODE 1, 2, 3, or 4 during the 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, along with both trains of CREATCS. Why is this acceptable? What would then be the immediate mitigating actions that can be initiated under TS 3.7.10 Action Statement B.1? The Traveler should address this issue in more detail, and also provide guidance to licensees to address this condition in their plant-specific submittals.
RAI #5 The last paragraph in Attachment 2 - Justification of the Control Room Area Temperature Limit states:
This evaluation is performed for normal operating conditions including the availability of normal electrical power based on the small likelihood of an event requiring the CREATCS during the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Completion Time.
This statement made here and other places in the Traveler, also needs to consider control room habitability, not only from temperature view point but also from other aspects applicable to the plant such as hazardous chemicals, smoke, etc. The CREFS plays a larger role in protecting the control room operators under such conditions. How does temperature mitigating actions such as opening control room doors impact the readiness of CREFS to protect control room habitability from other aspects applicable?