Letter to Nuclear Development - Acceptance Letter to Review CP Transfer Application
ML19298A194
Person / Time
Site: Bellefonte  Tennessee Valley Authority icon.png
Issue date: 11/05/2019
From: Omid Tabatabai, Tabatabai-Yazdi O
NRC/NRR/DNRL/NRLB
To: Mccollum W
Nuclear Development
Tabatabai O / 415-6616
References
EPID L-2018-LLM-0004
Download: ML19298A194 (3)


Text

November 5, 2019 Mr. William R. McCollum, Jr.

Chief Executive Officer and Chief Nuclear Officer Nuclear Development, LLC 3 Bethesda Metro Center, Suite 515 Bethesda, MD 20814

SUBJECT:

BELLEFONTE NUCLEAR PLANT, UNITS 1 AND 2 - ACCEPTANCE OF APPLICATION FOR ORDER APPROVING CONSTRUCTION PERMIT TRANSFERS AND CONFORMING ADMINISTRATIVE CONSTRUCTION PERMIT AMENDMENTS (EPID NO. L-2018-LLM-0004)

Dear Mr. McCollum:

By letter dated November 13, 2018 (Agencywide Documents Access and Management System Accession No. ML18318A428), Nuclear Development, LLC (ND) submitted its application requesting that the U.S. Nuclear Regulatory Commission (NRC) consent to the transfer of Construction Permits (CP) CPPR-122 and CPPR-123 for the Bellefonte Nuclear Plant, Units 1 and 2, which are currently in deferred status and held by Tennessee Valley Authority (TVA), to ND. The purpose of this letter is to provide the results of the NRC staffs acceptance review of your application. The acceptance review was performed to determine if there is sufficient technical information, in scope and depth, to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff reviewed your application in accordance with the regulatory requirements set forth in Part 50, Domestic Licensing of Production and Utilization Facilities, of Title 10 of the Code of Federal Regulations (10 CFR). Specifically, 10 CFR 50.80(b)(1)(i) states that an application for transfer of a construction permit shall include as much of the information described in §§ 50.33 and 50.34 of this part with respect to the identity and technical and financial qualifications of the proposed transferee as would be required by those sections if the application were for an initial license.

The NRC staff has reviewed your application and concluded that it provides technical information that is sufficient in detail to enable the NRC staff to complete its technical review.

The staff will perform an independent assessment of the acceptability of the proposed construction permits transfer in terms of regulatory requirements and the protection of public health and safety and the environment. If the staff needs further information to complete its technical review, you will be advised by separate correspondence.

Based on the information provided in your submittal and discussions during the pre-licensing meetings, the NRC staff has estimated that this licensing request will take approximately 700 hours0.0081 days <br />0.194 hours <br />0.00116 weeks <br />2.6635e-4 months <br /> to complete. The NRC staff expects to complete this review by September 2020.

W. McCollum 2 These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated by the assigned project manager during routine interactions.

Please contact me if you have questions regarding this acceptance letter at (301) 415-6616 or Omid.Tabatabai@nrc.gov.

Sincerely,

/RA/

Omid Tabatabai, Senior Project Manager New Reactor Licensing Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation Docket Nos. 50-438 and 50-439 cc: Distribution via Listserv

ML19298A194 *via email NRR-104 OFFICE NRR/DNRL/NRLB: PM NRR/DNRL/NRLB: LA NRR/DNRL/NRLB: BC NRR/DRO/IQVB: BC NAME OTabatabai MMoore* MDudek* KKavanagh*

DATE 10/25/19 10/29/19 10/30/19 10/29/19 OFFICE NRR/DRO/IOLB NMSS/REFS/FAB OGC NRR/DNRL: D NAME CCowdrey* FMiller* KGamin* ABradford*

DATE 10/28/19 10/30/19 11/01/19 11/05/19