MONTHYEARML24261C0092024-09-16016 September 2024 Kairos Power LLC - Charlotte Office Address ML24155A0612024-06-0303 June 2024 Kairos Power LLC, Presentation Materials for the Kairos Power Meeting with the Nuclear Regulatory Commission on the Hermes Foundation Design ML24150A2442024-05-29029 May 2024 Kairos Power, LLC - Presentation Materials for Kairos Power Briefing to the Advisory Committee on Reactor Safeguards, Kairos Power Subcommittee on Hermes 2 Preliminary Safety Analysis Report, Chapters 2, 3, 5, 9, and 13 ML24150A2172024-05-28028 May 2024 Kairos Power, LLC - Request for Documents Related to Non-Power Security ML24136A2542024-05-15015 May 2024 Kairos Power LLC - Transmittal of Changes to Hermes 2 Construction Permit Application - PSAR Chapter 9 ML24109A2952024-04-16016 April 2024 Kairos Power, LLC - Slides to Support April 22, 2024, Public Meeting About Hermes Physical Security ML23268A0092023-11-0303 November 2023 Kairos Power, LLC - Approval of Kairos Power Safeguards Information Protection Plan ML23102A2392023-04-11011 April 2023 Kairos Power LLC, Presentation Materials for Briefing to the Advisory Committee on Reactor Safeguards, Kairos Power Subcommittee on Hermes Preliminary Safety Analysis Report Section 12.9 and Chapter 13 ML23089A3872023-03-30030 March 2023 Kairos Power LLC, Submittal of the Environmental Report for the Kairos Power Fluoride Salt-Cooled, High Temperature Non-Power Reactor (Hermes), Revision 1 ML23062A7342023-03-13013 March 2023 Transmittal Letter for Final Safety Evaluation of Graphite Material Qualification for the KP-FHR ML23062A7302023-03-13013 March 2023 Transmittal Letter for Final Safety Evaluation of Metallic Material Qualification for the KP-FHR ML22181B0542022-06-30030 June 2022 Kairos Power, LLC - Transmittal of Changes to Construction Permit Application - PSAR Chapter 7 ML22181B1582022-06-30030 June 2022 Kairos Power LLC, Transmittal of Changes to Construction Permit Application ML22181B1752022-06-30030 June 2022 Kairos Power, LLC - Transmittal of Changes to Construction Permit Application - PSAR Chapter 4 ML22181B1122022-06-27027 June 2022 Kairos Power, LLC - Transmittal of Changes to Construction Permit Application - PSAR Chapter 3 ML21342A2412021-12-0808 December 2021 Kairos Power LLC, Presentation Materials for the December 14, 2021 Pre-Submittal Meeting on the Atlas Fuel Fabrication Facility Application ML20188A1112020-07-13013 July 2020 Verification Letter for Kairos Power LLC PDC Topical Report ML20014E6422020-02-0606 February 2020 Kairos Power, LLC Online Reference Portal Information Access Agreement ML20029E9302020-01-29029 January 2020 Withholding Proprietary Information from Public Disclosure - Kairos Power LLC Topical Report Submittal, Scaling Methodology for the Kairos Power Testing Program (Revision 1) ML19336B2702019-12-0909 December 2019 Withholding Proprietary Information from Public Disclosure - Kairos Power, LLC Topical Report Submittal, Reactor Coolant for the Kairos Power Fluoride Salt-Cooled, High Temperature Reactor ML19310E8702019-11-0606 November 2019 Withholding Proprietary Information from Public Disclosure - Kairos Power Regulatory Engagement Plan ML19303C1592019-11-0404 November 2019 Withholding Proprietary Information from Public Disclosure -Presentation Materials for Kairos Power Pre-Application Engagement Plans ML19304C4652019-11-0404 November 2019 Withholding Proprietary Information from Public Disclosure - Presentation Slides for Kairos Nuclear Fuel Overview ML19297E4342019-10-25025 October 2019 Withholding Proprietary Information from Public Disclosure - Presentation Materials for Kairos Power Pre-Submittal Meeting on Risk-Informed Performance-Based Licensing Basis Development Topical Report ML19297G2502019-10-25025 October 2019 Withholding Proprietary Information from Public Disclosure -Presentation Slides for Kairos Power High Temperature Materials Overview ML19294A1102019-10-25025 October 2019 Withholding Proprietary Information from Public Disclosure - Presentation Materials for Kairos Power Pre-Submittal Meeting on Reactor Coolant and Scaling Methodology Topical Reports ML19294A0942019-10-25025 October 2019 Withholding Proprietary Information from Disclosure- Presentation Materials for Kairos Power Pre-submittal Meeting on Principal Design Criteria and Regulatory Gap Analysis ML19284D7672019-10-23023 October 2019 Kairos Power LLC - Acceptance of KP-FHR Risk-Informed performance-Based Licensing Basis Development Methodology Topical Report (CAC No. 000431) ML19275E2812019-10-21021 October 2019 Withholding Proprietary Information from Public Disclosure - Presentation Materials for Kairos Power Pre-Submittal Meeting on Fuel Performance and Discussion of Fuel Qualification Plan ML19267A2202019-09-30030 September 2019 Withholding Proprietary Information from Public Disclosure - Kairos Power, LLC Topical Report Submittal, Regulatory Analysis for the Kairos Power Fluoride Salt-Cooled High Temperature Reactor ML19255H2342019-09-17017 September 2019 Confirmation of Revision to Kairos Power LLC Regulatory Analysis for the Kairos Power Fluoride Salt-Cooled, High Temperature Reactor Topical Report (CAC No. 000431) ML19221B5852019-08-0909 August 2019 Kairos Power, LLC - Acceptance of Reactor Coolant for the Kairos Power Flouride Salt-Cooled High Temperature Reactor Topical Report (CAC No. 000431) ML19189A2972019-07-15015 July 2019 Withholding Proprietary Information from Public Disclosure - Kairos Power LLC Topical Report Submittal, Principal Design Criteria for the Kairos Power Fluoride Salt-Cooled, High Temperature Reactor ML19184A2382019-07-0808 July 2019 Confirmation of Revision to Kairos Power LLC, Principal Design Criteria for the Kairos Power Fluoride Salt-Cooled, High Temperature Reactor Topical Report (CAC No. 000431) ML19150A2752019-06-0505 June 2019 Acceptance for Review of Kairos Power LLC, Scaling Methodology for the Kairos Power Testing Program Topical Report (CAC No. 000431) ML19059A3772019-03-0606 March 2019 Acceptance for Review of Kairos Power LLC, Regulatory Analysis for the Fluoride Salt-Cooled, High Temperature Reactor Topical Report (CAC No. 000431) ML19059A3552019-03-0606 March 2019 Acceptance for Review of Kairos Power LLC, Principal Design Criteria for the Kairos Power Fluoride Salt-Cooled, High Temperature Reactor Topical Report (CAC No. 000431) 2024-09-16
[Table view] |
Text
October 23, 2019 Mr. Peter Hastings Vice President, Regulatory Affairs and Quality Kairos Power LLC 707 W Tower Ave Alameda, CA 94501
SUBJECT:
KAIROS POWER LLC - ACCEPTANCE OF KP-FHR RISK-INFORMED PERFORMANCE-BASED LICENSING BASIS DEVELOPMENT METHODOLOGY TOPICAL REPORT (CAC NO. 000431)
Dear Mr. Hastings:
By letter dated August 6, 2019, Kairos Power LLC (Kairos) submitted for U.S. Nuclear Regulatory Commission (NRC) staff review, KP-FHR Risk-Informed Performance-Based Licensing Basis Development Methodology Topical Report, (Agencywide Documents Access and Management System Accession No. ML19217A420). The NRC staff has performed an acceptance review of the topical report and found that it contains sufficient information to enable the staff to complete a detailed technical review. Notwithstanding the acceptance review, the NRC staff may require additional information to complete the detailed technical review.
If needed, the NRC staff will request this information by separate correspondence by November 2019.
Based on the acceptance review, the NRC staff expects to issue a safety evaluation by July 2020. This date could change due to several factors, including the need for and timeliness of responses to requests for additional information; unanticipated changes to the scope of the review; and unsolicited supplements to the topical report. Additionally, the Advisory Committee for Reactor Safeguards (ACRS) will be notified of this topical report and may choose to discuss the report at an ACRS meeting which could impact the schedule for issuing the final safety evaluation to Kairos.
If the forecasted completion date changes, the NRC staff will notify you in writing of the new date and an explanation of the reason for the change. The NRC staff estimates that the review will require approximately 400 staff hours, including project management time.
Section 170.21 of Title 10 of the Code of Federal Regulations requires approvals and preapplication/licensing activities, including topical reports, to be subject to fees based on the full cost of the review. Kairos did not request a fee waiver for the cost of this review, therefore, NRC staff hours will be billed to Kairos accordingly.
The review schedule milestones, estimated level of effort, and associated review costs were discussed and agreed upon during a phone call between James Tomkins, Project Manager for Kairos and Stewart Magruder, Senior Project Manager, Advanced Reactor Licensing Branch, NRC on September 30, 2019.
P. Hastings 2 If you have questions regarding this matter, please contact Stewart Magruder at (301) 348-5766 or Stewart.Magruder@NRC.gov.
Sincerely,
/RA/
Benjamin Beasley, Chief Advanced Reactor Licensing Branch Division of Advanced Reactors and Non-Power Production and Utilization Facilities Office of Nuclear Reactor Regulation Project No. 99902069
P.Hastings 3
SUBJECT:
KAIROS POWER LLC - ACCEPTANCE OF KP-FHR RISK-INFORMED PERFORMANCE BASED LICENSING BASIS DEVELOPMENT METHODOLOGY TOPICAL REPORT (CAC NO.000431) - DATED October 23, 2019 DISTRIBUTION:
Public JMonninger SMagruder LCandelario BBeasley WWang RidsAcrsAcnw_MailCTRResource RidsOgcMailCenterResource RIdsOpaMailResource ADAMS Accession Number: ML19284D767 NRR-106 OFFICE NRR/DANU NRR/DANU NAME SMagruder BBeasley DATE 10/15/2019 10/23/2019 OFFICIAL RECORD COPY