KP-NRC-2206- 014

June 30, 2022 Docket No. 50-7513

US Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

Subject:

Kairos Power LLC Transmittal of Changes to Construction Permit Application

References:

1. Letter, Kairos Power LLC to Document Control Desk, Submittal of the Preliminary Safety Analysis Report for the Kairos Power Fluoride Salt-Cooled, High Temperature Non-Power Reactor (Hermes), September 29, 2021 (ML21272A376)
2. Letter, Kairos Power LLC to Document Control Desk, Submittal of the Environmental Report for the Kairos Power Fluoride Salt-Cooled, High Temperature Non-Power Reactor (Hermes), October 31, 2021 (ML21306A132)

Kairos Power submitted a Preliminary Safety Analysis Report (PSAR) (Reference 1) and an Environmental Report (ER) (Reference 2), comprising the Construction Permit Application (CPA) for the Hermes non-power reactor. Subsequent to the initial submittal of these doc uments, Kairos Power made a decision to switch from the 2019 version of the ASME BPVC Section III, Division 5 code to the 2017 version, which is the version that NRC has currently endorsed. This change impacts Chapters 3, 4, and 6 of the PSAR and Chapter 2 of the ER. Changes to the pages of the PSAR and ER are provided in Enclosures 1 and 2, respectively. Kairos Power requests NRC review of these changes as part of the continued review of the Hermes CPA.

If you have any questions or need any additional information, please contact Delaney Simmons at simmons@kairospower.com or (605) 838-5132, or Darrell Gardner at gardner@kairospower.com or (704) 769-1226.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on June 30, 2022

Sincerely,

Peter Hastings, PE Vice President, Regulatory Affairs and Quality

Enclosures:

1) Changes to PSAR Chapters 3, 4, and 6
2) Changes to ER Chapter 2

Kairos Power LLC www.kairospower.com 707 W Tower Ave, Suite A 5201 Hawking Dr SE, Unit A 2115 Rexford Rd, Suite 325 Alameda, CA 94501 Albuquerque, NM 87106 Charlotte, NC 28211

KP-NRC-2206- 014 Page 2

xc (w/enclosure):

William Kennedy, Acting Chief, NRR Advanced Reactor Licensing Branch Benjamin Beasley, Project Manager, NRR Advanced Reactor Licensing Branch Edward Helvenston, Project Manager, NRR Advanced Reactor Licensing Branch Samuel Cuadrado de Jesus, NRR Advanced Reactor Licensing Branch