ML13242A012
ML13242A012 | |
Person / Time | |
---|---|
Site: | North Anna |
Issue date: | 08/23/2013 |
From: | Grecheck E Virginia Electric & Power Co (VEPCO) |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
12-162D, EA-12-049 | |
Download: ML13242A012 (20) | |
Text
VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 August 23, 2013 10 CFR 2.202 EA-1 2-049 Attention: Document Control Desk Serial No.: 12-162D U.S. Nuclear Regulatory Commission NL&OS/MAE: R3 Washington, D.C. 20555-0001 Docket Nos.: 50-338/339 License Nos.: NPF-4/7 VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION UNITS I AND 2 SIX-MONTH STATUS REPORT IN RESPONSE TO MARCH 12, 2012 COMMISSION ORDER MODIFYING LICENSES WITH REGARD TO REQUIREMENTS FOR MITIGATION STRATEGIES FOR BEYOND-DESIGN-BASIS EXTERNAL EVENTS (ORDER NUMBER EA-12-049)
References:
- 1. NRC Order Number EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond=Design-Basis External Events, dated March 12, 2012
- 2. NRC Interim Staff Guidance JLD-ISG-2012-01, Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, Revision 0, dated August 29, 2012
- 3. NEI 12-06, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide, Revision 0, dated August 2012
- 4. Virginia Electric and Power Company's Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated October 25, 2012 (Serial No. 12-162A)
- 5. Virginia Electric and Power Company's Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated February 28, 2013 (Serial No. 12-162B)
- 6. Virginia Electric and Power Company's Supplement to Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated April 30, 2013 (Serial No. 12-162C)
On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued an order (Reference 1) to Virginia Electric and Power Company (Dominion). Reference 1 was immediately effective and directs Dominion to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event. Specific requirements are outlined in Attachment 2 of Reference 1.
Serial No. 12-162D Docket Nos. 50-338/339 Six Month Status Report - Order EA-12-049 Page 2 of 3 Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (Reference 2) and an overall integrated plan pursuant to Section IV, Condition C. Reference 2 endorsed industry guidance document NEI 12-06, Revision 0 (Reference 3) with clarifications and exceptions. Reference 4 provided Dominion's initial status report regarding mitigation strategies, and Reference 5 provided Dominion's overall integrated plan. Reference 6 provided a supplement to Dominion's overall integrated plan.
Reference 1 requires submission of a status report at six-month intervals following submittal of the overall integrated plan. Reference 3 provides direction regarding the content of the status reports. The six-month status report (pursuant to Section IV, Condition C.2, of Reference 1) delineates the progress made in implementing the requirements of Reference 1 and is provided as an attachment to this letter. The attached report provides an update of milestone accomplishments since the supplement to the overall integrated plan (Reference 6) including any changes to the compliance method, schedule, or need for relief and the basis, if any.
If you have any questions, please contact Ms. Margaret Earle at (804) 273-2768.
Sincerely, Eugene S. Grecheck Vice President Nuclear Engineering and Development Attachment Commitments made by this letter: No new Regulatory Commitments COMMONWEALTH OF VIRGINIA COUNTY OF HENRICO The foregoing document was acknowledged before me, in and for the County and Commonwealth aforesaid, today by Eugene S. Grecheck who is Vice President Nuclear Engineering and Development of Virginia Electric and Power Company. He has affirmed before me that he is duly authorized to execute and file the foregoing document in behalf of the Company, and that the statements in the document are true to the best of his knowledge and belief.
Acknowledged before me this *. day of ,au. -.. ,2013.
My Commission Expires:-ecey*r31. ZV?,
CRAIG D SLY 4 Notary Public __
j Commonwealth of Virginia Reg. # 7518653 My Gommission Expires December 31, 20&1 No'1 blic bli
Serial No. 12-162D Docket Nos. 50-338/339 Six Month Status Report - Order EA-12-049 Page 3 of 3 cc: Director of Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 13H16M 11555 Rockville Pike Rockville, MD 20852-2738 U. S. Nuclear Regulatory Commission, Region II Regional Administrator Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 Dr. V. Sreenivas NRC Project Manager North Anna U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738 Ms. K. R. Cotton Gross NRC Project Manager Surry U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738 Ms. J. A. Kratchman U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 09 D2 11555 Rockville Pike Rockville, MD 20852-2738 NRC Senior Resident Inspector North Anna Power Station Mr. J. E. Reasor, Jr.
Old Dominion Electric Cooperative Innsbrook Corporate Center, Suite 300 4201 Dominion Blvd.
Glen Allen, Virginia 23060
Serial No. 12-162D Docket Nos. 50-338/339 Order EA-12-049 Attachment Six Month Status Report for the Implementation of Order EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events North Anna Power Station Units 1 and 2 Virginia Electric and Power Company (Dominion)
Serial No. 12-162D Docket Nos. 50-338/339 Six Month Status Report - Order EA-12-049 Attachment Page 1 of 16 Six Month Status Report for the Implementation of Order EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events I Introduction Dominion developed an Overall Integrated Plan (OIP) (Reference 1) documenting the diverse and flexible strategies (FLEX) for North Anna Power Station in response to NRC Order Number EA-12-049 (Reference 2). This attachment provides an update of milestone accomplishments and open items since submittal of the OIP including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any.
2 Milestone Accomplishments The following milestone has been completed since the development of the Overall Integrated Plan, and is current as of July 31, 2013.
0 Submit Integrated Plan 3 Milestone Schedule Status The following table provides an update to Attachment 2A of the Overall Integrated Plan. The table provides the activity status of each item, and whether the expected completion date has changed. The dates are planning dates subject to change as design and implementation details are developed.
The revised milestone target completion dates for 'Develop Strategies' and 'Unit 1 Outage Implementation' do not impact the Order implementation date.
Target Activity Revised Target Milestone Completion Status Completion Date Date Submit Integrated Plan Feb 2013 Complete Develop Strategies July 2013 Started October 2013 Develop Modifications Feb 2014 Started Implement Modifications Sept 2014 Started Develop Training Plan Apr 2014 Started Implement Training Sept 2014 Not Started Issue FSGs and Associated Sept2014 Not Started Procedure Revisions Develop Strategies/ Contract with Regional Response Center (RRC) Apr 2014 Started
Serial No. 12-162D Docket Nos. 50-338/339 Six Month Status Report - Order EA-12-049 Attachment Page 2 of 16 Target Activity Revised Target Milestone Completion Status Completion Date Date Purchase Equipment Feb 2014 Started Procure Equipment* Aug 2014 Not Started Validation Walk-throughs or Demonstrations of FLEX Strategies Apr 2014 Not Started and Procedures*
Create Maintenance Procedures Aug 2014 Not Started Unit 1 Outage Implementation Mar 2015 Started April 2015 Unit 2 Outage Implementation Sept 2014 In Progress
- Refer to Section 8 for an explanation of Milestone changes.
4 Changes to Compliance Method By letter dated February 28, 2013, Dominion provided an Overall Integrated Plan (OIP) to address Beyond-Design-Basis (BDB) events at North Anna Power Station (North Anna) Units 1 and 2 (Reference 1) as required by Order Number EA-12-049, dated March 12, 2012 (Reference 2). The following are changes to the compliance method information provided in the North Anna OIP; however, the changes continue to meet NEI 12-06 (Reference 3):
a) Details of the connection strategy for RCS injection, as described in Section C.3 - PWR Portable Equipment Phase 3, have changed for North Anna Unit 2 only. The installed tie-in location has been moved from a position downstream of motor-operated valve (MOV) 2-SI-MOV-2890A [Safety Injection (SI) Train A] to a position downstream of 2-SI-MOV-2890B (SI Train B). Figure 4 of the OIP still reflects the connection strategy for Unit 1, only the associated valve numbers that reflect the opposite SI train are different for Unit 2. Therefore, since the change does not impact the connection strategy, OIP Figure 4 is not being revised.
b) Changes to the timing of the RCS injection strategy have been made. The strategy for RCS injection for inventory and reactivity control has been moved from a Phase 3 activity to a Phase 2 activity. The details and descriptions provided in Section C.3 of the OIP for RCS injection for the Phase 3 activity continue to be the same for the Phase 2 strategy for RCS injection, including the time at which natural circulation capability is lost, i.e., approximately 33 hours3.819444e-4 days <br />0.00917 hours <br />5.456349e-5 weeks <br />1.25565e-5 months <br /> based on WCAP-17601 (Reference 5) and ETE-NAF-2012-0150 (Reference 7). For conservatism and margin to account for uncertainty within the calculations and unanticipated deployment issues, a time of 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> has been chosen, which provides significant margin (by a factor of 2) prior to loss of natural circulation and the start of reflux boiling.
Serial No. 12-162D Docket Nos. 50-338/339 Six Month Status Report - Order EA-12-049 Attachment Page 3 of 16 c) Details of the strategy for the portable diesel generators (DGs) used to re-power the 120VAC vital bus circuits, as described in Section F1.2 - PWR Portable Equipment Phase 2, have changed for North Anna Units 1 and 2. A single 120/240VAC DG per unit will be sized to accommodate the necessary electrical loads for that unit and will power both BDB distribution panels for that unit. Thus, the deployment of two 120/240VAC DGs per unit as shown in Figure 7 of the previously submitted OIP is no longer being pursued, and a revised Figure 7 is attached. Figure 8 is revised to show the location of the single 120/240VAC DG for each unit and the location of the associated unit's connection receptacles and is also attached. Figure 10 was a typical schematic of the connections from one of two 120/240VAC DGs. A revised Figure 10 showing the current connections for the 120/240VAC DG (Unit 1 only) is attached. A spare 120/240VAC DG will be purchased; however, as stated in the OIP, the 480VAC DG is considered the alternate re-powering source for instrumentation.
d) The quantities of BDB equipment stated in OIP Table 1, PWR Portable Equipment Phase 2, and OIP Table 2, PWR Portable Equipment Phase 3, have changed. Per Footnote 1 to Table 1, the quantities were based on the assumption that two storage buildings would be available to store BDB equipment pending completion of the study to determine the details of the BDB Storage Building(s). Open Item No. 6 has been completed, and the decision to have one storage building is documented in Section 6 of this update. A revised Table 1 is attached.
As discussed in the previous item b), North Anna will purchase and store BDB RCS Injection Pumps for use in the Phase 2 RCS Inventory strategy. These pumps are being added to the revised Table 1 for Phase 2 equipment.
5 Need for Relief/Relaxation and Basis for the Relief/Relaxation Dominion expects to comply with the Order implementation date and no required relief/relaxation has been identified at this time.
6 Open Items from Overall Integrated Plan The following table provides a summary of the open items documented in Attachment 28 of the OIP and the status of each item.
Overall Integrated Plan Open Item 01 # Description Status Verify response times listed in timeline and perform staffing Not started.
1 assessment. Scheduled completion date: April 2014 Preliminary analyses have been performed to determine the time Complete.
to steam generator overfill without operator action to reduce AFW (Reference 4) 2 flow, time to steam generator dryout without AFW flow, and time to depletion of the useable volume of the ECST. The final durations will be provided when the analyses are completed.
Serial No. 12-162D Docket Nos. 50-338/339 Six Month Status Report - Order EA-12-049 Attachment Page 4 of 16 Overall Integrated Plan Open Item 01 # Description Status Preliminary analyses have been performed to determine the Class Complete.
3 1E battery life based on implementation of load stripping actions. (Reference 4)
The final battery life duration will be provided when the analyses are completed.
The Phase 3 coping strategy to maintain containment integrity is Started.
under development. Methods to monitor and evaluate Scheduled completion 4 containment conditions and depressurize/cool containment, if date is revised from necessary, will be provided in a future update. December 2013 to October 2013 **
Analyses will be performed to develop fluid components Started.
5 performance requirements and confirm fluid hydraulic-related Scheduled completion strategy objectives can be met. date: September 2013 A study is in progress to determine the design features, site Complete.
location(s), and number of equipment storage facilities. The final A single 10,000 sq. ft.
design for BDB equipment storage will be based on the guidance Type 1 building will be contained in NEI 12-06, Section 11.3, Equipment Storage. A constructed at North supplement to this submittal will be provided with the results of the Anna for storage of BDB equipment storage study. equipment. The building will be designed to meet the plant's design basis for the Safe Shutdown Earthquake, high wind hazards, snow, ice and cold conditions, and will 6 be located above the flood elevation from the most recent site flooding analysis. The BDB Storage Building will be sited in theOwner Controlled Area in the parking lot west of Warehouse #5. This update provides the supplemental information referred to in this open item.
FLEX Support Guidelines (FSGs) will be developed in accordance Started.
with PWROG guidance. Existing procedures will be revised as Scheduled completion necessary to implement FSGs. date: September 2014.
Serial No. 12-162D Docket Nos. 50-338/339 Six Month Status Report - Order EA-12-049 Attachment Page 5 of 16 Overall Integrated Plan Open Item 01 # Description Status EPRI guidance documents will be used to develop periodic testing Not started.
and preventative maintenance procedures for BDB equipment. Scheduled completion 8 Procedures will be developed to manage unavailability of date: September 2014 equipment such that risk to mitigating strategy capability is minimized.
An overall program document will be developed to maintain the Started.
9 FLEX strategies and their bases and provide configuration control Scheduled completion and change management for the FLEX Program. date: September 2014 The Dominion Nuclear Training Program will be revised to assure Started.
personnel proficiency in the mitigation of BDB events is developed Scheduled completion 10 and maintained. These programs and controls will be developed date: September 2014 and implemented in accordance with the Systematic Approach to Training (SAT).
Complete the evaluation of TDAFW pump long term operation with Complete.
< 290 psig inlet steam pressure. TDAFW pump operation and adequate AFW flow 11 to the SGs at SG pressures < 290 psig have been confirmed.
(Reference 8)
Plant modifications will be completed for permanent plant changes Started.
12 required for implementation of FLEX strategies. Scheduled completion date: See Milestone Schedule.
Details of the ventilation strategy are under development and will Started.
13 conform to the guidance given in NEI 12-06. The details of this Scheduled completion strategy will be provided at a later date. date: September 2013 Complete installation of N-9000 RCP seals in 2 of 3 RCPs in each Not started.
unit. Scheduled completion 14 date is revised from September 2014 to April 2015**
Analyses will be performed to develop electrical components Started.
performance requirements and confirm electrical loading-related Scheduled completion 15 strategy objectives can be met. date is revised from September 2013 to December 2013**
16 An evaluation of all BDB equipment fuel consumption and required Not started.
Serial No. 12-162D Docket Nos. 50-338/339 Six Month Status Report - Order EA-12-049 Attachment Page 6 of 16 Overall Integrated Plan Open Item 01 # Description Status re-fill strategies will be developed. Scheduled completion date: June 2014 A lighting study will be performed to validate the adequacy of Started.
17 supplemental lighting and the adequacy and practicality of using Scheduled completion portable lighting to perform FLEX strategy actions. date: June 2014 A communications study will be performed in accordance with the Started.
statements made in response to Recommendation 9.3 of the Scheduled completion 10 CFR 50.54(f) letter dated March 12, 2012 in Dominion letter date: Consistent with 18 S/N 12-207F dated October 29, 2012.** Rec. 9.3 implementation dates.
Preferred travel pathways will be determined using the guidance Started.
19 contained in NEI 12-06. The pathways will attempt to avoid areas Scheduled completion with trees, power lines, and other potential obstructions and will date: June 2014 consider the potential for soil liquefaction.
The equipment listed in Table 1 will be procured.** Not started.
20 Scheduled completion date revised from June 2014 to August 2014**
- Refer to Section 8 for an explanation of changes to Open Items.
7 Potential Draft Safety Evaluation Impacts There are no potential impacts to the Draft Safety Evaluation identified at this time.
8 Supplemental Information This supplemental information provides details of changes identified in the status updates above and addresses the following topics: a) Open Item No. 4, b) Open Item No. 15, c) Open Item No. 18, d) Open Item No. 20, e) North Anna Milestone 'Procure Equipment', and f) the addition of Milestone "Validation Walk-throughs or Demonstration of FLEX Strategies and Procedures."
a) North Anna, Open Item 4: The Open Item completion date is revised to October 2013 to be consistent with the revised completion date for the Milestone "Develop Strategies."
b) North Anna, Open Item 14: The Open Item completion date is revised to April 2015 to be consistent with the revised completion date for the Milestone "Unit 1 Outage Implementation."
Serial No. 12-162D Docket Nos. 50-338/339 Six Month Status Report - Order EA-12-049 Attachment Page 7 of 16 c) North Anna, Open Item 15: The Open Item completion date is revised to December 2013. Additional time is required to complete the loading/sizing calculations for North Anna Unit 2.
d) North Anna, Open Item 18: The revision to the wording more accurately reflects the planned activities to determine and validate that adequate communications are available to implement FLEX strategies in all phases of the response to an ELAP/LUHS event. The revised Open Item 18 is as follows:
A comprehensive study of communication capabilities is being performed in accordance with the statements made in Dominion letter S/N 12-207F dated October 29, 2012 in response to Recommendation 9.3 of the 10 CFR 50.54(f) letter dated March 12, 2012. The results of this study will identify the communication means available or needed to implement command and control of the FLEX strategies at North Anna. Validation of communications required to implement FLEX strategies will be performed as part of Open Item No. 1.
e) North Anna, Open Item 20: The revision to the wording more accurately reflects the equipment that will be purchased and delivered to the site. The updated completion schedule accurately reflects the Milestone schedule. The revised Open Item and revised completion schedule are as follows:
Open Item 20: The equipment listed in Table 1 will be received on site.
Completion Schedule: August 2014 f) North Anna Milestone 'Procure Equipment': The revision to the wording more accurately reflects the actual tasks as they occur in sequence. The revised milestone task is the successor to 'Purchase Equipment'. The revised Milestone Task is as follows:
Milestone Task: Receive Equipment g) North Anna Milestone 'Validation Walk-throughs or Demonstration of FLEX Strategies and Procedures': This milestone was added for consistency with template and industry formats. It corresponds to the activity previously identified in Open Item No. 1. The scheduled milestone date is the same as the open item completion date. By this date, sufficient FLEX equipment will be available to perform the walk-throughs and procedures will be in a near final form and will rely on the walk-throughs for validation prior to final issuance.
Serial No. 12-162D Docket Nos. 50-338/339 Six Month Status Report - Order EA-1 2-049 Attachment Page 8 of 16 9 References The following references support the updates to the Overall Integrated Plan described in this attachment.
- 1. Dominion's Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)," Serial No. 12-162B, dated February 28, 2013.
- 2. NRC Order Number EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," dated March 12, 2012.
- 3. NEI 12-06, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide, Revision 0, dated August 2012.
- 4. Dominion letter 12-162C, "Supplement to Overall Integrated Plan in Response to March 21, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis Events (Order Number EA-12-049)," dated April 30, 2013.
- 5. WCAP-17601, "Reactor Coolant System Response to the Extended Loss of AC Power Event for Westinghouse, Combustion Engineering and Babcock & Wilcox NSSS Designs", August 2012.
- 6. Engineering Technical Evaluation, ETE-CPR-2012-0012, "Beyond Design Basis - FLEX Strategy Overall Integrated Plan Basis Document," Revision 1, August 2013.
- 7. Engineering Technical Evaluation, ETE-NAF-2012-0150, "Evaluation of Core Cooling Coping for Extended Loss of AC Power (ELAP) and Proposed Input for Dominion's Response to NRC Order EA-12-049 for Dominion Fleet," Revision 0, January 2013.
- 8. Dominion Calculation ME-0968, "Evaluation of the TDAFW Pump Performance at Low Steam Generator Pressures," August 2013.
Serial No. 12-162D Docket Nos. 50-338/339 Six Month Status Report - Order EA-12-049 Attachment Page 9 of 16 Table I - PWR Portable Equipment Phase 21 [Open Item 20]
Use and (potential/ flexibility) Diverse Uses Performance Maintenance Criteria List portable Core Containment SFP Instrumentation Accessibility Maintenance / PM equipment [Open Item 4] requirements BDB High Capacity Will follow EPRI pump 4 (2) and assoc. X X 1200 gpm template hoses and fittings requirements BDB AFW pump 4 (3) Will follow EPRI and assoc. hoses X 300 gpm template and fittings requirements BDB RCS Injection Will follow EPRI pump, (2) and assoc. X 40 gpm template hoses and fittings requirements 120/240 VAC Will follow EPRI generators 3' 5 (3) and template associated cables, requirements connectors and X 35 kW switchgear (DGs to re-power instrumentation)
Serial No. 12-162D Docket Nos. 50-338/339 Six Month Status Report - Order EA-12-049 Attachment Page 10 of 16 Table I - PWR Portable Equipment Phase 21 [Open Item 20]
Use and (potential/ flexibility) Diverse Uses Performance Maintenance Criteria List portable Core Containment SFP Instrumentation Accessibility Maintenance / PM equipment [Open Item 4] requirements 120/240 VAC Will follow EPRI generators2', (8) and template associated cables, requirements connectors and X 5-6.5 kW switchgear (DGs to provide power to support equipment) 480 VAC Will follow EPRI generators3'5 (2) and template associated cables, requirements connectors and X 300-350 kW switchgear (re-power battery chargers, inverters, and vital buses)
Sufficient size and length of pre-terminated cable for connection of 4kV generator to station bus (4 sets)
Serial No. 12-162D Docket Nos. 50-338/339 Six Month Status Report - Order EA-12-049 Attachment Page 11 of 16 Table 1 - PWR Portable Equipment Phase 21 [Open Item 20]
Performance Manenc Use and (potential/ flexibility) Diverse Uses Criteria Maintenance List portable Core Containment SFP Instrumentation Accessibility Maintenance / PM equipment [Open Item 4] requirements Portable boric acid Will follow EPRI batching tanks (2) X template requirements Light plants 2 (4) Will follow EPRI X template requirements Front end loader2 (1) Will follow EPRI X template requirements Tow vehicles 2 (2) Will follow EPRI X template requirements Hose trailer or utility Will follow EPRI vehicle 2 (2) X template requirements Fans / blowers 2 (10) Will follow EPRI X template requirements Air compressors 2 (6) Will follow EPRI X template requirements
Serial No. 12-162D Docket Nos. 50-338/339 Six Month Status Report - Order EA-12-049 Attachment Page 12 of 16 Table 1 - PWR Portable Equipment Phase 21 [Open Item 20]
Use and (potential/ flexibility) Diverse Uses Performance Maintenance Criteria List portable Core Containment SFP Instrumentation Accessibility Maintenance / PM equipment [Open Item 4] requirements Fuel carts 2 with Will follow EPRI transfer pumps (2) X template requirements Communication Will follow EPRI equipment 6 X template requirements Misc. debris removal Will follow EPRI equip. 2 (2 sets) X template requirements Misc. support Will follow EPRI equipment 2 (2 sets) X template requirements NOTES:
- 1. This table is based on one BDB Storage Building.
- 2. Support equipment. Not required to meet N+1.
- 3. 480 VAC generators are an alternate strategy to the 120/240 VAC generators. Therefore, only N is required.
- 4. Preliminary performance criteria. Final performance criteria will be determined by the hydraulic analyses performed in accordance with the design process. [Open Item 5]
- 5. Preliminary performance criteria. Final performance criteria will be determined by the electrical loading analyses performed in accordance with the design process. [Open Item 15]
- 6. Equipment purchased in response to the results of the study performed for Recommendation 9.3 of the 1OCFR50.54(f) letter dated March 12, 2012
Serial No. 12-162D Docket Nos. 50-338/359 Six Month Status Report - Order EA-12-049 Attachment Page 13 of 16 Table 2 - PWR Portable Equipment Phase 3 Use and (potential/ flexibility) Diverse Uses Performance Notes Criteria List portable Core Containment SFP Instrumentation Accessibility equipment [Open Item 2]
4kV generators 1 (2) and associated cables, connectors and switchgear NOTE:
- 1. Preliminary performance criteria. Final performance criteria will be determined by the electrical loading analyses performed in accordance with the design process. [Open Item 15] RRC equipment will meet the required performance criteria.
Serial No. 12-162D Docket Nos. 50-338/339 Six Month Status Report - Order EA-12-049 Attachment Page 14 of 16
iRA LInr Z~. m EF i
Serial No. 12-162D Docket Nos. 50-338/339 Six Month Status Report - Order EA-12-049 Attachment Page 15 of 16
. . .
....
......
......
. Lj....::s::v.rzsr..a 41
/ s =3 ...... ..... I
..........
m*
A,
/
'9
..............
....
........... .. j (C2
-7.-.!.*..* -*=.--*
- r< 1 sa ~s rco sC.i-; xc,;nrSU. * ~ COe~WC. FIWIURE 8 (AIJGIS'r 2013 UPDAl ;)
~ a'r+LEn flCI1~%.CSSFt~ ThE- C.3~
(C*CCr 1201240AND 480 VAC ELECTRICAL. GENERATIOR DEPLOYMEN" LAYOUT NOR'rITI ANNA POWER STATION
Serial No. 12-162D Docket Nos. 50-338/339 Six Month Status Report - Order EA-12-049 Attachment Page 16 of 16 LIGHTING PANEL NORMALFEED LIGHTING PANEL NORMALFEED KEY, HCR - MAIN CONTROL ROOM 0 BOB MODIFICATION NOTE. UNIT 2 SIMILAR FIGURE 10 (AUGUST 2013 UPDATE) 120/240 VAC GENERATOR ELECTRICAL CONNECTIONS NORTH ANNA POWER STATION