10/01/2018 Vogtle Readiness Group (Vrg) Update (Presentation)
ML18271A216
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 10/01/2018
From: Odunayo Ayegbusi, Victor Hall
Division of Construction Inspection and Operational Programs
To:
Webb M
References
Download: ML18271A216 (7)


Text

CIP Public MeetingOctober 1, 2018Vogtle Readiness Group (VRG) UpdateAyo AyegbusiVictor HallNRO/DCIP VogtleReadiness Group

-VRG serves as the focal point for project status and for coordination among Region II, NRO, NRR, NSIR, and OGC through commercial operation of Vogtle Units 3 and 4. Oversee the VogtleUnits 3 and 4 Transition to Operations

-In addition, the VRG serves as the hub for communications with the Commission, the Executive Director for Operations and its office direct reports, the licensee, and other external stakeholders

-Identify and resolve any licensing, inspection, or regulatory challenges or gaps that could impact the schedule for completion of VogtleUnits 3 and 4.

2 Integrated Project Plan

-VRG directed the formation of an internal NRC working group to develop an Integrated Project Plan (IPP) scheduling tool-The IPP lists the regulatory milestones for the transition of Vogtle'sconstruction to operations 3

Integrated Project Plan

-The tool will allow the working group to map the milestones' inter

-dependencies and ties to NRC's inspection schedule

-The VRG will use the IPP to track scheduled activities and identify potential critical path areas related to the completion of construction 4

Integrated Project Plan

-Innovative and technology driven

  • First of a kind at NRC
  • Uses Primavera software

-Enhances communication

  • Internal and external

-Reduces project risks

  • NRC internal processes are known
  • Increases stakeholder confidence 5

IMC 2503IMC 2504IMC 2514Fuel Load10/14/2020Current NRCStatusUpcoming NRC Schedule Items

  • Continue to inspect construction activities
  • Finalize 103(g) sequence of events
  • Complete development of IMC 2514IPP, VogtleU3 Status

-2018 Q3 Questions?