2011/09/21 Watts Bar 2 OL - NRC PM Open Items List 9-22-11.docx
ML11286A422
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 09/21/2011
From:
- No Known Affiliation
To:
Division of Operating Reactor Licensing
References
Download: ML11286A422 (7)


Text

1 WBN2Public Resource From: Boyd, Desiree L [dlboyd@tva.gov]

Sent: Wednesday, September 21, 2011 9:56 AM To: Poole, Justin; Milano, Patrick; Campbell, Stephen; Epperson, Dan Cc: Arent, Gordon; Smith, James D; Bryan, Rober t H Jr; Smith, James D; Boyd, Desiree L

Subject:

NRC PM Open Items List 9-22-11.docx Attachments:

NRC PM Open Items List 9-22-11.docx For next phone call.

Thank You, ~*~*~*~*~*~*~*~*~*~*~*~

Désireé L. Boyd WBN 2 Licensing Support Sun Technical Services dlboyd@tva.gov 423-365-8764

Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 549 Mail Envelope Properties (7AB41F650F76BD44B5BCAB7C0CCABFAF234279D3)

Subject:

NRC PM Open Items List 9-22-11.docx Sent Date: 9/21/2011 9:56:18 AM Received Date: 9/21/2011 9:56:20 AM From: Boyd, Desiree L Created By: dlboyd@tva.gov Recipients: "Arent, Gordon" <garent@tva.gov>

Tracking Status: None "Smith, James D" <jdsmith@tva.gov>

Tracking Status: None "Bryan, Robert H Jr" <rhbryan@tva.gov> Tracking Status: None "Smith, James D" <smith1jd@westinghouse.com> Tracking Status: None "Boyd, Desiree L" <dlboyd@tva.gov>

Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov> Tracking Status: None "Milano, Patrick" <Patrick.Milano@nrc.gov> Tracking Status: None "Campbell, Stephen" <Stephen.Campbell@nrc.gov>

Tracking Status: None "Epperson, Dan" <Dan.Epperson@nrc.gov> Tracking Status: None Post Office: TVANUCXVS2.main.tva.gov

Files Size Date & Time MESSAGE 244 9/21/2011 9:56:20 AM NRC PM Open Items List 9-22-11.docx 33644 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received:

Page 1 of 5 NRC PM Open Items List 9/22/11 (423) 751-7777 ID 4233652004#

No. Description Status Additional Comments Resp Org/Person 1. Cyber Security Plan/Controls and Implementation NRC TI issued TBD NRC Table Top/Pilot

Oct 2011 Procedures complete 9/30/11 Pre-inspection TBD

Inspection

Dec 2011 NRC Inspection in 2011 To be discussed at the next ACRS meeting (October

5 th - closed portion).

Follow-up meeting 9/21 Heinrich/Snyder (Bryan)

Page 2 of 5 No. Description Status Additional Comments Resp Org/Person 2. Instrumentation RAI List (Knuettel)

1. GA/ESI is preparing a report to document the conformance of their CGD program to NRC requirements based on NRC telecom on 8/30/11.

Draft scheduled for 9/9 is now TBD.

2. Updates based on schedule received from GA on 09/07/11 following conference call on document schedule.
3. Revise GA-ESI procedure for CGI dedication to address NRC comments.
4. Draft received for review 9/20/11.
5. Non-props & affidavits
6. WEC to provide demarcated proprietary, non-proprietary and affidavits for withholding for each item. 7. WEC to revise figure to remove connection from OM to printer to complete commitment.
8. WEC to agreed to produce a test report for the incore IITA.
9. WEC has the necessary documentation. WEC to produce a non-proprietary summary report and place the test reports in the WEC Rockville office for NRC audit.
1. TBD 2. Various - see status 3. 9/26/11 4. 10/1/11 5. 11/18/11 6. Various -

see status 7. TBD 8. TBD 9. TBD 1. Draft response TBD

2. 04038903-1SP: 9/30/11 04038903-2SP: 10/6/11 04038903-4SP: 10/21/11 04038903-QSR: 9/30/11 Non-props and affidavits due 11/18/11
3. OP-7.3-240: 9/26/11
4. Create new bridge document 04038800-1SP:

10/1/11 5. Provide NRC non-prop and affidavit for all remaining documents

6. WEC to provide the following documents:

CN-EQT-10-44: TBD DAR-ME-09-10: TBD EQ-EV-62-WBT: TBD EQLR-171: TBD EQ-QR-33-WBT: TBD EQ-QR-64-GEN: TBD WNA-SD-00250-WBT: TBD WNA-SD-00248-WBT: TBD WNA-TP-02988-WBT: TBD WNA-VR-00279-WBT: TBD WNA-PT-00138-WBT: TBD

7. WNA-AR-00189-WBT
8. IITA Incore EQ report
9. MI cable 600V test report Eng/Hilmes (Smith) 3. Verify MACCs values for SAMA Cost Benefit Evaluation 1. 9/8/11A 2. 9/16/11A 1. Non-conservatisms in some values identified. Discuss updated results with NRC 2. Submitted revised tables & revised RAI responses ENG/Koontz 4. Exemption to 10CFR50.49 for some Category II cables 9/23/11 Determine if exemption required. Check SSER 24.

Hilmes (Stockton)

Page 3 of 5 No. Description Status Additional Comments Resp Org/Person 5. Complete Implementation (Hemmer)

Pump Relocation 5/30/12 Bldg Plan 9/23/11 Inspection - June 2012 Phase I commitments 10/1/11 Additional clarification to Phase I actions will be needed. Fleet wide issue. Substantial building to complete and equipment in May. Provide document of mitigating equipment and location for unit 2. Hemmer (Smith) 6. Chapter 15.5 RAIs 9/21/11 9/15/11A Includes FHA calc. X/Q discussion for each accident, corrections to previously submitted dose calcs, and a complete 15.5 markup. Potential meeting following submittal. Look at splitting submittal up. Wastrack (Bryan) 7. Fire Protection Report Questions regarding OMA 1. 10/24-28/11 2.9/30/11 3.10/1/11 4. 11/4/11 5. 11/30/11

6. TBD 7. TBD 1. Audit 2. Group 7 RAI response 3. Receive Group 8 RAIs - if needed 4. Response to Group 8 - if needed 5. Submit As-designed U1/U2 FPR 6. Fire Protection Program Audit Frequency - add to group 7 response
7. Follow-up meeting ENG/Hilmes (Arent) 8. Tech Spec Revisions from latest T/S markup and NRC Review comments
1. 10/14/11
2. 10/14/11
3. 10/21/11
4. 10/21/11
1. CSST A & B - discretionary
2. I-131 DEI
3. Diesel Generator Frequency
4. Unit 1 AST FHA Licensing/Elton (Bryan) 9. ACRS Topics 10/5/11 Cyber, Chapter 15 except dose, Chapter 4 (Fuels), WINCISE, Hydrology, process for FSAR drawing documentation update, Gordon 10. SSER 22/23/24 Open Items Response 9/30/11 9/16 is the target date for the next SSER update. The expanded HH list and status is covered periodically. Licensing Page 4 of 5 No. Description Status Additional Comments Resp Org/Person 11. Transient Analysis issues Boron dilution RAI response 9/21/11 Question on RG revision and modes 3, 4, & 5. TVA to provide write up explaining NRC acceptance (CLB) of unit1 for modes 3, 4, & 5. See SSER OI 132. ENG/Koontz WEC/Morgan 12. FSAR A107 10/17/11 Current target date for A107 is 10/17/11.

How will note 4 & 5 on FSAR figure 9.2-23 change

for two unit operation when the CCS C-S and 2B pumps are realigned Lic/Stockton 13. Develop list of planned License Conditions, Exemptions and Relief Requests (Arent) 1. 11/1/112. TBD 3. TBD 1. Review Unit 1 SER for exemptions. Sand baskets, cyber security, physical security, PAD 4.0 2. NRR to review current exemptions 3. Verify required notifications made NRR/TVA (Bryan) 14. Verify Tech Spec Setpoints match calcs TS certification 1. 10/4/11

2. TBD 1. 3 SSDs remaining to be issued. Possible submittal if any number changes.
2. TS certification Eng/Hilmes (Bryan) 15. Issue two Unit Offsite Dose Calculation Manual (Beach) Review TS Chapter 5 programs also 3/1/12 Determine actual need date Chemistry/

Woods (Bryan) 16. Issue Unit 2 Completion Letter (Arent) 8/1/12 Licensing 17. Submit final as-constructed FSAR figures 7/1/12 Licensing/ Stockton 18. TMI action items 7/1/12 TVA to provide letter when TMI actions are field complete.

Licensing (Gordon) 19. ASME N-801 & N-802 code cases 11/30/11 NRC response to relief request submitted 9/1/11. NRR 20. ASME Section III N-3 reports 8/2012 0. Discretionary Actions

1. Letter to terminate Part 30/40 License after receipt of Part 50 License 4/1/12 Licensing (Arent) 2. Combined U1/U2 FSAR (Stockton) 3/1/13 Licensing 3. Status of GSI 199 Eastern Seismicity (Arent) Fall 2011 No action pending upcoming Generic Letter Related information on GSI 194 may need input TVA/NRR 4. Letter to notify NRC when Vital Area Boundary returned to original location 12/1/11 Security Plan Update - Boundary to be restored by 9/30/11 Lic/Arent Page 5 of 5 No. Description Status Additional Comments Resp Org/Person 5. IEB 88-02 SG Tube Cracking TBD Tubes are assumed locked in the WEC analysis. Waiting for NRC concurrence. When will the WEC analysis be submitted? NRC willing to review as a contingency.

Corp SG/ Webber ISI/Tinley