MONTHYEARML23304A1422024-02-0101 February 2024 Issuance of Environmental Scoping Summary Report Associated with the U.S. Nuclear Regulatory Commission Staffs Review of the Oconee Nuclear Station, Units 1, 2, & 3, Subsequent License Renewal Application ML24005A2492024-01-24024 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) IR 05000269/20243012024-01-11011 January 2024 Notification of Licensed Operator Initial Examination 05000269/2024301, 05000270/2024301, and 05000287/2024301 ML23331A7982023-12-14014 December 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report (01R32) ML23262A9672023-12-13013 December 2023 Alternative to Use RR-22-0174, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section XI, Division 1 ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000269/20230032023-11-14014 November 2023 Integrated Inspection Report 05000269/2023003, 05000270/2023003, and 05000287/2023003; and IR 07200040/2023001; and Exercise of Enforcement Discretion ML23219A1402023-10-10010 October 2023 Audit Report Proposed Alternative to Use ASME Code Case N-752, Risk Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems XI, Division 1 ML23269A1102023-10-0606 October 2023 Letter to Steven Snider-Revised Schedule for the Environmental Review of the Oconee Nuclear Station, Unit 1, 2, and 3, Subsequent License Renewal Application ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000269/20230112023-08-25025 August 2023 Comprehensive Engineering Team Inspection Report 05000269/2023011 and 05000270/2023011 and 05000287/2023011 IR 05000269/20230052023-08-25025 August 2023 Updated Inspection Plan for Oconee Nuclear Station Units 1, 2 and 3 (Report 05000269/2023005, 05000270/2023005, and 05000287/2023005) IR 05000269/20230022023-07-28028 July 2023 Integrated Inspection Report 05000269/2023002, 05000270/2023002 and 05000287/2023002 ML23208A0972023-07-27027 July 2023 Subsequent License Renewal List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected IR 05000269/20230102023-07-19019 July 2023 Biennial Problem Identification and Resolution Inspection Report 05000269/2023010 and 05000270/2023010 and 05000287/2023010 and Notice of Violation ML23178A0682023-07-0303 July 2023 Audit Plan Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 & 3 Systems Section XI, Division 1 ML23132A2392023-06-0101 June 2023 Summary of the April 2023 Remote Environmental Audit Related to the Review of the Subsequent License Renewal Application ML23144A0192023-05-25025 May 2023 Review of the Spring 2022 Steam Generator Tube Inspection Report (O3R31) IR 05000269/20230012023-05-12012 May 2023 Integrated Inspection Report 05000269/2023001 and 05000270/2023001 and 05000287/2023001 ML23121A0552023-05-0303 May 2023 Acknowledgement of Withdrawal Request to Revise TS 5.5.2 Containment Leakage Rate Testing Program ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML23117A0432023-04-20020 April 2023 Framatome, Inc., Part 21 Notification of Existence of a Defect ML23075A0732023-04-0505 April 2023 License Renewal Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application Supplement (EPID Number L-2021-SLE-0002) ML23045A1332023-03-15015 March 2023 Request for Scoping Comments Concerning the Supplemental Environmental Review of Oconee Nuclear Station, Units 1, 2, and 3, Subsequent License Renewal Application - Achp Letter ML23045A1402023-03-15015 March 2023 Request for Scoping Comments Concerning the Supplemental Environmental Review of Oconee Nuclear Station, Units 1, 2, and 3, Subsequent License Renewal Application - Shpo Letter ML23045A1432023-03-15015 March 2023 Request for Scoping Comments Concerning the Supplemental Environmental Review of Oconee Nuclear Station, Units 1, 2, and 3, Subsequent License Renewal Application - State Tribe Letter ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility ML23069A1102023-03-10010 March 2023 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML23061A1772023-03-0303 March 2023 Notification of Oconee Nuclear Station Comprehensive Engineering Team Inspection - NRC Inspection Report 05000269/2023011, 05000270/2023011 and 05000287/2023011 IR 05000269/20220062023-03-0101 March 2023 Annual Assessment Letter for Oconee Nuclear Nuclear Station, Units 1, 2 and 3 (NRC Inspection Report 05000269/2022006, 05000270/2022006, and 05000287/2022006) ML23039A1632023-02-0808 February 2023 Requalification Program Inspection ML23037A0772023-02-0606 February 2023 402 Cyber Notification and RFI Letter Final IR 05000269/20220042023-02-0202 February 2023 Integrated Inspection Report 05000269 2022004 and 05000270/2022004 and 05000287/2022004 ML22363A3942023-01-12012 January 2023 Subsequent License Renewal Environmental Report Supplement - Proposed Review Schedule ML22356A0512022-12-14014 December 2022 Curtiss-Wright Nuclear Division, Letter Regarding Potential Efect in a Configuration of the 11/2 Inch Quick Disconnect Connector Cable Assemblies Supplied to Duke Energy (See Attached Spreadsheet) for a Total of 460 of Connectors Only Suppl ML22321A0492022-12-0808 December 2022 Issuance of Amendment Nos. 426, 428 and 427, Additional Mode Change Limitations Applicable to the Adoption of TSTF- 359, Revision 9, Increase Flexibility in Mode Restraints ML22329A1042022-11-29029 November 2022 Review of the Fall 2021 Steam Generator Tube Inspection Report ML22321A1582022-11-22022 November 2022 Summary of Conference Call Regarding the Fall 2022 Steam Generator Tube Inspections ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 IR 05000269/20220032022-11-0707 November 2022 Integrated Inspection Station 05000269/2022003 and 05000270/2022003 and 05000287/2022003 ML22301A0112022-11-0303 November 2022 Request for Withholding Information from Public Disclosure Regarding the SLR Application - September 2, 2022 ML22298A0752022-10-27027 October 2022 Request for Withholding Information from Public Disclosure Regarding the Subsequent License Renewal Application Duke Energy Letter Dated July 25, 2022 ML22264A0322022-10-20020 October 2022 _Request for Withholding Information from Public Disclosure Regarding the Subsequent License Renewal Application - Duke Energy Letter Dated July 8, 2022 IR 05000269/20220112022-09-26026 September 2022 NRC Inspection Report 05000269/2022011 and 05000270/2022011 and 05000287/2022011 ML22258A0302022-09-15015 September 2022 Evacuation Time Estimate Reports ML22222A0072022-09-14014 September 2022 Request for Withholding Information from Public Disclosure Regarding the Subsequent License Renewal Application ML22231B1362022-09-0101 September 2022 Review of the Draft Environmental Assessment and Findings of No Significant Impact for Catawba Nuclear Station, H.B. Robinson Steam Electric Plant, and Oconee Nuclear Station Independent Spent Fuel Storage Installation Decommissioning Fundi ML22234A0062022-08-30030 August 2022 SLRA - Closed Public Meeting Summary - August 18, 2022 2024-02-01
[Table view] |
Text
Scott L. Batson DUKEG Vice President ENERGY. Oconee Nuclear Station Duke Energy ON01VP I 7800 Rochester Hwy.Seneca, SC 29672 o: 864.873.3274 f: 864.873.4208 Scott. Batson@duke-energy.com May 15, 2013 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
SUBJECT:
Duke Energy Carolinas, LLC (Duke Energy)Oconee Nuclear Station (Oconee), Units 1, 2 and 3 Docket Nos. 50-269, 50-270 and 50-287 Closure Options for Generic Safety Issue (GSI)-191, "Assessment of Debris Accumulation on Pressurized-Water Reactor Sump Performance" in resolution of final Issues related to Generic Letter (GL) 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors" By letter dated February 29, 2008, Duke Energy submitted a supplemental response to NRC Generic Letter 2004-02 regarding the status of GL 04-02 Requests for Additional Information (RAIs) and inspection questions.
Included in this letter was a commitment to "Evaluate and Respond to NRC Conditions and Limitations of WCAP 16793-NP, rev. 0, 90 days after receipt of final NRC Conditions and Limitations." By letter dated July 1, 2008, the NRC issued a response to Duke Energy's February 29, 2008 summary of the GL 04-02 program. In this letter, the NRC stated: "We have no further questions at this time regarding your completion of corrective actions for Generic Letter (GL) 2004-02. In large part this conclusion is based on the very low potential debris loading at Oconee, as discussed in your supplemental response." In a subsequent paragraph, the July 1, 2008, letter from the NRC stated the following: "As you may be aware, we have not yet issued a final safety evaluation (SE) on WCAP 16793 NP. "Evaluation of Long-Term Cooling Considering Particulate, Fibrous, and Chemical Debris in the Recirculating Fluid." We believe that the likelihood of unacceptable in-vessel debris impact for Oconee is very low because of the low debris loading. However, because your GL 2004-02 response refers to and relies on this topical report, we plan to defer issuance of a closure letter to Oconee for the GL until uncertainties regarding the remaining issues with WCAP-1 6793 are reduced. You may wait for the issue to be resolved through the WCAP process or may demonstrate that in-vessel downstream effects issues are resolved for Oconee by demonstrating without reference to WCAP-16793 or the NRC staff SE that in-vessel downstream effects have been addressed at Oconee." aLt www.duke-energy.corn U. S. Nuclear Regulatory Commission May 15, 2013 Page 2 Based on the above statement, Duke Energy has chosen to wait until issues associated with WCAP-16793-NP were resolved through the WCAP process to address in-vessel downstream effects evaluation commitment for Oconee.Duke Energy has selected GSI-191 Closure Option 1 from SECY-12-0093 because it has determined that Oconee Nuclear Station, Units 1, 2, and 3, meets the requirements of 10 CFR 50.46, "Acceptance Criteria for Emergency Core Cooling Systems for Light-Water Nuclear Power Reactors," based on approved models for analysis and strainer head loss testing. In addition, Duke Energy expects to demonstrate compliance with recently approved models for analysis of in-vessel downstream effects.Based on the aforementioned statement from the July 1, 2008, letter concerning WCAP-16793-NP and telephone discussions between Duke Energy personnel and NRC staff on April 30, 2013, Duke Energy's understanding is that there are two methods available to Duke Energy to address Closure Option 1 and close-out GSI-191 for Oconee. Duke Energy can;1) evaluate Oconee against WCAP-1 6793-NP, revision 2 and associated Safety Evaluation (ML1 3084A1 54) limits and restrictions, or 2) demonstrate compliance with 'Clean Plant Criteria'(with additional NRC considerations and clarifications) as reviewed by the NRC in a letter to the Nuclear Energy Institute (NEI) dated May 2, 2012 (ML120730181).
Duke Energy is currently evaluating both methods and will clarify the method utilized to closeout GSI-191 in the follow-up letter noted in Attachment 1.There are no new commitments made herein; however, the completion date for the outstanding commitment to address WCAP 16973-NP and associated NRC SE is revised to July 31, 2013, to allow time for the appropriate documentation of the in-vessel downstream effects analysis.If any questions arise or additional information is needed, please contact Bob Meixell of the Oconee Regulatory Affairs Group at (864) 873-3279.I declare under penalty of perjury that the foregoing is true and correct.Executed on May 15, 2013 Very truly yours, Scott L. Batson Vice President Oconee Nuclear Station
Attachment:
- 1. Oconee Nuclear Station -Generic Letter 2004-02 Supplemental Response, Commitments U. S. Nuclear Regulatory Commission May 15, 2013 Page 3 xc (with Attachment):
Mr. Victor McCree U.S. Nuclear Regulatory Commission, Region II Marquis One Tower 245 Peachtree CenterAve., NE, Suite 1200 Atlanta, GA 30303-1257 Mr. John P. Boska (electronic copy only)Oconee Project Manager, NRR/DORL U.S. Nuclear Regulatory Commission 11555 Rockville Pike Mail Stop O-8G9A Rockville, MD 20852-2746 Ed Crowe NRC Senior Resident Inspector Oconee Nuclear Station Ms. Susan E, Jenkins Manager, Infectious and Radioactive Waste Management Bureau of Land and Waste Management Department of Health & Environmental Control 2600 Bull Street, Columbia, SC 29201 Attachment 1 Oconee Nuclear Station Generic Letter 2004-02 Supplemental Response Commitments May 15, 2013 Attachment 1 Generic Letter 2004-02 Supplemental Response May 15, 2013 Commit. Commitment Due Date 1 Oconee will address the in-vessel downstream July 31, 2013 effects issue in subsequent correspondence.
Page 1 of 1