ML072970040

From kanterella
Revision as of 03:20, 22 October 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Brunswick July-August Exam 50-325, 324/2007301 Final Simulator Scenarios (Scenario 1 of 4) (Section 3 of 5)
ML072970040
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 01/31/2007
From:
- No Known Affiliation
To:
Office of Nuclear Reactor Regulation
References
0EOP-01-UG, 50-324/07-301, 50-325/07-301 50-324/07-301, 50-325/07-301
Download: ML072970040 (41)


See also: IR 05000325/2007301

Text

x S f (Ke4c!#,

KI/Cf(;,,.Hue/reef

CtJ"-!;,,,',.,pJ

m x<<C.OPERATOR ACTIONS 1.Control Operator Immediate Actions The control operator immediate actions are those actions which may be performed following a reactor scram prior to entering the scram procedure (EOP-01).These actions are not mandatory and shall not conflict with entering the scram procedure.

All the control operator immediate actions are located in the scram procedure flowchart.

There are no control operator immediate actions in EOP-02 through EOP-04.In the event the actions are not performed prior to entering the scram procedure, the scram procedure shall take precedence.

The control operator immediate actions which should be memorized by control operators, are defined as follows: a.Unit 2 Only: After steam flow is less than3x 10 6 lb/hr, PLACE the reactor mode switch to SHUTDOWN.Unit 1 Only: PLACE the reactor mode switch to SHUTDOWN.b.IF reactor power is below 2%(APRM downscale trip), THEN TRIP the main turbine.c.ENSURE the master reactor level controller

setpoint is+170".d.IF two reactor feed pumps are running, AND reactor vessel level is above+170" AND rising, THEN TRIP one.The EOP actions are those which are contained within EOP-01 through EOP-04.In the event the control operator immediate actions are not performed prior to entering EOP-01, these actions become EOP actions.Since the EOP actions are readily available to the control operator, there is no need to memorize them.The operator is not required to have the Operating Procedures

in hand while executing the EOPs, but may use any other procedure as necessary.

The following guidance applies to referencing

of supporting

material that is not included in the procedure but provides information

required in the performance

of a step (ERFIS, instructional

aids, Users'Guide, etc.).a.If the information

is available from several sources and a specific source is preferred, then that source is explicitly

referenced

at the point it is needed.b.If the information

is provided by a source which is not readily recognized

by the operator, then the source is explicitly

referenced

at the point it is needed.I OEOP-01-UG

Rev.47 Page 21 of 1381

(

SCRAM CARD*f-NSURE SCRAM VALVES ARE OPEN BY MANUAL-.'-SG-R*AM

OR ARI TRI P..,\*CONTROL REACTOR PRESSURE BETWE'EN 800 AND 1000 PSIG*CONTROL REACTOR VESSEL LEVEL BETWEEN+170 ,.AND+200 INCHES*INSERT NUCLEAR INSTRUMENTATION

  • PLACE RECrRC PUMP SPEED CONTROLLERS

TO 10%*ENSURE HEATER DRAIN PUMPS ARE TRIPPED*ENSURE TURBINE OIL SYSTEM OPERATING*PLACE SULCV IN SERVICE S/907

(

nvlv vt-'t:KA rlONS FOR EOPs MANUAL RCIC INJECTION (OP-16 SECTION 5.3)1.ENSURE THE F 0 L LOWINGVA LVES ARE 0 PEN:E51-V 8 (V A LV E PO SIT ION>.E51-V8 (ACTU AT 0 R PO SIT ION LAN 0E5 1-V9 2.OPENE5 1-F 04 6 3.START VAC U UM PUMP AND LEAVE SWITCH IN START.4.OPENE5 1-F045__'5.OPEN E51-F013..,'" 6.ENSURE RC I C TURBINE STARTS AND COMES UP TO SPEED AS DIRECTED BY RCIC FLOW CONTROLADJUST RC I C FLOW C ONTRO LLER TO OBTAIN DESIRED FLOW RATE.__:8.ENSUREE5 1-F0 19 IS CLOSED WITH FLOW ABOVE 80 G PM.__!, 9.ENSURE THE FOLLOWING VALVES ARE CLOSED: E51-F025.E51-F026.E51-F004.AND E51-F005'START S BGT (OP-10)1 t:'OPEN THESGT-V 8 ANDSGT-V9.__.l2.ENSURE BAROMETRIC

CNDSR CONDENSATE

PUMP OPERATES RCIC PRESSURE CONTROL (OP-16 SECTION 8.2)1.ENSURE THE F 0 L LOW IN G VA LVES ARE 0 PE N:E5 1-V 8 (VALVE POSITION>.

E51-V8 (ACTUATOR POSITION)AND E51-V9.2.OPENE5 1-F 04 6 3.START VACUUM PUMP AND LEAVE SWITCH IN START.4.ENSUREE5 1-F 013ISC LOS E 0 5.ENSURE E41-FOll IS OPEN 6.THROTTLE OPEN E51-F022 UNTIL DUAL INDICATION

IS OBTAINED 7.OPEN E51-F045 8.THROTTLE OPEN E51-F022 OR ADJUST Re IC FLOW CONTROL.E51-FIC-R600.

TO OBTAIN DESIRED SYSTEM PARAMETERS

AND REACTOR PRESSURE.9.ENSUREE5 1-F 019 IS C LOS ED WIT H FLOW ABOVE 80 G PM.10.ENSURE THE FOLLOWING VALVES ARE CLOSED: E51-F025.E51-F026.E51-F004.AND E51-F005.11.START SBGT (OP-10)12.OPEN THE SGT-V8 AND SGT-Y9 13.ENSURE BAR 0 MET RIC C NOS R CON DEN SATEPUM POP E RATES I=OR

RFI=FR TO OP-1h

(

.-*II"".1I'i'-'Cv I IUN IN EOPs (OP-19 SECTION 5.3)1.ENSURE AUXILIARY OIL PUMP IS NOT RUNNING 2.ENSURE E41-V9 AND E41-V8 ARE CLOSED 3.OPEN E41-F05g-*

4""START VACUUM PUMP AND LEAVE IN START 5.OPEN E41-FOOl 6.START AUXILIARY OIL PUMP AND LEAVE IN START 7.OPEN E41-F006.IMMEDIATELY

AFTER E41-V8 HAS DUAL INDICATION

8.l;NSURE E41-V9 AND E41-V8 ARE OPEN 9.ENSURE HPCI TURBINE COMES UP TO SPEED 10.ADJUST HPCI FLOW CONTROL.E41-FIC-R600

TO OBTAIN DESIRED FLOW RATE 11.ENSURE E41-F012 IS CLOSED WHEN FLOW HAS INCREASED ABOVE 800 GPM 12.ENSURE FOLLOWING E41 DRAIN VALVES ARE CLOSED: F025.AND F026 13.START SBGT (OP-10)AND OPEN SGT-V8 AND SGT-V9 14.ENSURE BAROMETRIC

CNDSR CONDENSATE

PUMP IS OPERATING.

_**_._.....I lVI'll 11'4 I:: V I"'5 TRANSFER TO PRESSURE CONTROL FROM LEVEL CONTROL (OP-19 SECTION 8.3)1.ENSURE H PC IIS NOT NEEDED FOR LEVEL CONTROL 2.ENSURE H PCII NITIAT IONSIGNA LIS RESET 3.ENSUREE51-F 02 2ISC LOS ED....-4.TRANSFER HPCI FLOW CONTROL TO MANUAL (M)5..REDUCE H PC ITU RBI N ESP E EDT 0 BE T WEE N 3000 AND 3300 RPM 6.OPEN E 41-F 011 7.CLOSE E41-F006 8.WHEN E41-F006 IS CLOSED.THEN THROTTLE OPENE4 1-F 008 UN TIL FLO W IS G REA TERT HAN 1000 GPM 9.ENSUREE4 1-F 012ISC LOSED 10.ADJUST SETPOINT AND TRANSFER HPCI FLOW CONTROL TO AUTOMATIC CA}11.MAINTAIN REACTOR PRESSURE BY THROTTLING

E41-F008 OR VARYING HPC I Ft.:OW USING THE FLOW CONTROLLER

TRANSFER TO LEVEL CONTROL FROM PRESSURE CONTROL (OP-19 SECTION 8.4)__.,1.IF NECESSARY.

TRANSFER HPCI FLOW CONTROL TO MANUAL (M)2.REDUCE H PC I TURBI NE SPEED TO BETWEEN 3000 AND 3300 RPM 3.CLOSE E41-F008 4.OPEN E41-F006 5.ADJUST SETPOINT AND TRANSFER HPCI FLOW CONTROL TO AUTOMATIC (A)6.ADJUST HPC I FLOW CONTROL SETPOINT FOR DESIRED FLOW RATE 7.ENSURE E 41-Fa 12 IS CLOSED 8.IF DESIRED.THEN CLOSE E41-F011.---

(,.(

Y::)UPPRESSION

POOL COOLING START AHR SW A LOOP (CONV)RHR SW A LOOP (NUCl: OPEN SW-V101: CLOSE SW-V143: If LOCA SIGNAL IS PRESENT PLACE Rffl SW BOOSTER PlM'SA&C LOCA OVERRIDE SWITCH TO MANUAL OVERRIDE_: START Rffl SW PtvP_: ADJUST Ell-POV-F068A

SUPPLY CLG WTR TO VITAL H)R:OPEN SW-V105:CLOSE SW-V143_:OPEN SW-V102 lOCA SIGNAL IS PRESENT.PLACE Rtfl SW BOOSTER PUMPS A&C LOCA OVERRIDE SWITCH TO MANUAL OVERRIDE: START RHR SW PMP: ADJUST ETI-POV-F068A
SUPPLY CLG WTR TO VITAL HOR START RHA LOOP A: If LOCA SIGNAL IS PRESENT.VERIFY SPRAY LOGIC IS MADE UP_:If ETI-F015A IS OPEN.THEN CLOSE ETI-F017 A: START LOOP A RHR PMP: OPEN Ell-F028A: TtflOTTLE Ell-F024A: TfflOTTLEETI-F048A

REFERENCE OP-17 AND OP-43 S/106?

__S.'q--s;i1;

POOL COOLING START RHR SW LOOP (NUC)RHR SW BLOOP (CONV)_: OPEN SW-V105_: ClOSE_;If LOCA SIGNAL IS PRESENT PlACE RHR SW BOOSTER PUMPS*B&0 LOCA OVERRIDE SWITCH TO MANUAL OVERRDE*: START RHR SW PMJ: ADJUST Ell:-POV-f0688

SUPPlY ClG WTR TO VITAL H)R:OPEN SW-V10l._:CLOSE SW-Vl43_:OPEN SW-V102_:IF LOCA*SlGNAL

IS PRESENT PlACE RHR SW BOOSTER PUMPS*B&0 LOCA OVERRDE SWITCH TO MANUAL OVERRDE_: START RHR SW PMP___: ADJUST ETI-POV-f068B_: SUPPLY Cl6 WTR TO VITAL H)R START RHR LOOP B.._: If LOCA SIGNAL IS PRESENT.VERIfY...SPRA Y LOGIC IS MADE UP_:If En-F015B.1S

OPEN.THEN CLOSE Ell-f0178_: START lOOP B RHR PMP: OPEN Ell-F0288._": THROTTLE En-f024B_: THROTTLE ETI-f0488 REFERENCE OP-17 AND

5/1064

((c

___

'.'\., ,t l REACTOR SCRAM PROCEDURE BNP

VI 2EOp*01*RSP REVISION NO;9 UNIT 2 ONLY"/j1[0/',*1,160'00 I 1,100 200 400 600 600 , ,000 REACTOR PRESSURE (PSIG)tLQI!WHfN

PIIEUURf'6 THAN 60 PliO.use INDICATeDII'llO'NCHes, 200 FIGURE 1 REACTOR WN"ER LEVEL AT MSL..PEURMINATION

USINQ

MOM (Nom,)OR Ll21.L.I*R6061UN.02Zilltii...'5 z 0:-.J W m I**0....,0lI'OlJAL 10 tH" Q{q'l.IQ W"..1I1"OW ,...::___.,--______________________II'0....'___.------.L.-

, j..

-,..1..v'OOWI1

"","14OV',OIlO/f**OIT.lt.M+H'O,l'

"'01111.'1'Qfoll

"'OT'UL"'I'.......III'TtO...0 fWlOlll.I'loUJooI..CUH'I'II\OI.

II.0QI W\TMO!UW"'I

'fO Il-O'ITION

U oUI0....0'"O....,,,Ol."ou WITHOAAW)of IIOIITION n..'."L.lvtV'OWU

COWT.l.CI."

"....*.-!ll..

.......

........'-'f:..........

'/'MAT Tkt<.-'IIII...CTQIIl, Wll.I.Il'Ill4>>!

."",TOOM!>'l'**'---------..,

-'" lULl'.0/....'"'" III...*"'01*.1Il......COHnNVO\l"H'VIli.Tl0.U,.""-Yl....V...

VUOfI''O

uou.",,, I n...lun...'LO....lU4UIO't'o'Il'olOIol'

0111110-;'

0'nil'OU.O'MNO.....nfWl':.."'I f\lU"'lt....,...._f.*.111"''''''1,.111'

OJU,IfII'*"01<:...,.,.......".,'..,']I..yll.**""".....o11IoIO*,otIflCKU

I'I"ITll OHIO-: MOfl'0'THI ,OI,LOWlttQ

""III"*OOHO....hn"..ow.u."*"CHI*"'*CI-----_.." ,-, ,-'-

.-'1,,1....L**

>>""".0,---,'l'OV"ll//.".......T*'-r--......

H9..........Wl1'W"\JHrttM\itCOWN" ,.....----------------

no'/1"....no vunOtlINlTW'1

A/llYOI'f)l1

1l0UoO'f'l1lo!O.OT'lONf WWI¢M llolOUL.o.....04""""101*Oi't)WI'\X.lnoH'

  • ,OC'IHIf'lAf'IOjIt
  • ..OlI..LOIHI.....TOlIl..",TOIT.:#I;T

..*"ACM....

0'"V..".oua*l'OJI*.,...,OI\.....'_'1'11#j i Ut

Jon\[

STEP 013 NO 013 STEP BASES: This step requires the operator to evaluate plant conditions

a*nd determine the status of actual reactor water level and its indications.

This critical step will direct the operator to the Reactor Vessel Control Procedure or level/Power

Control should level instrumentation

indicate that vessel level recovery actions are necessary.

1001-37.3 Rev.8 Page 14 of 381

STEP 014 STEP BASES: If reactor water level cannot be maintained

above+170 inches, additional

level control measures must be taken.These additional

measures will be taken once the operator enters the Reactor Vessel Control Procedure or Level/Power

Control procedure.

1001-37.3 Rev.8 Page 15 of 381

STEPS 015 through 017.;.., YES STEP BASES: These steps are used to determine if an entry condition exists for the Reactor Vessel Control Procedure or the Level/Power

Control procedure.

The parameters

selected are RPS Scram setpoints or critical parameters, which indicate that an emergency condition exists which requires the use of the above referenced

procedures.

It also directs entry to the EPG based procedures

if required to scram by Containment

Control procedures

or the Radioactivity

Release Control Procedure.

1001-37.3 Rev.8 Page 16 of 381

STEPS 018 through 021 f'/'f?'" S ft,{J/1/'1/>',7//TABLE 1 YES ARE ALL CONTROL RODS INSERTeD TO OR BEYOND POSITION 00 018 HAS IT BEEN DETERMINED

THAT THE REACTOR WILL REMAIN SHUTDOWN UNDER ALL CONDmONS WITHOUT BORON TABLE 1 019 PERFORM"REACTOR VESSEL CONTROL PROCEDURE" (EOP.01*RVCPI AND EXECUTE IT CONCURRENT\.

Y WITH THIS PROCEDURE 020 NO SHUTDOWN WITHOUT BORON ONLY ONE CONTROL ROD NOT FULLY INSERTED NO MORE THAN 10 CONTROL RODS WITHDRAWN TO POSmON 02 AND NO CONTROl ROO WITHDRAWN BEYOND POSmON 02 AS DETERMINED

BY REACTOR ENGINEERING

Gom"LEVEUPOWER

CONTROL" (EOP*01*LPCI 021 STEP BASES:Thesesteps

determine whether entry to the Reactor Vessel Control Procedure or the Level/Power

Control procedure is required based on whether or not a cold shutdown control rod configuration

exists.If cold shutdown is not assured on control rods alone, then entry to the Level/Power

Control procedure is directed where the required actions to control reactor water level, pressure, and power and to insert control rods are found.If cold shutdown is assured, then entry to the Reactor Vessel Control Procedure, where guidance on the control of reactor water level and pressure are found, is directed.Execution of the Reactor Vessel Control Procedure and the remainder of the Reactor Scram Procedure are then performed concurrently.

Positive confirmation

that the reactor will remain shut down under all conditions

is best obtained by determining

that no control rod is withdrawn beyond the Maximum Subcritical

Bank Withdrawal

Position, of position 00.Table 1 has been added to provide a listing of those conditions

for the reactor being shutdown under all conditions

without boron.This was added specifically

for condition where 10 control rods could be withdrawn to position 02 as long as no control rod is withdrawn beyond position 02.On a loss of UPS or any other condition where control rod position can not be determined, then entry to the Level/Power

Control procedure is required.1001-37.3 Rev.8 Page 17 of 381

(

PRIMARY CONTAINMENT

CONTROL PROCEDURE'liI'

.. UO\II,,.,Oft,UOW

'....._."'OUffO no_BNPVI OEOP*02*PCCP REVISION NO: 10 1'/.",.--II-<,.,/'

.,................

HIL:W./'-

I.....................

r*:--*...........tII+<11 r'"

,-_-'L::''--:"\

'.*"COJI."

.....

C.QlolU.OI.WH

....tJON'OQl,.*"'UlMl,,,,,,t,, Nt.or,.Loo-G

I",nlill 1IrC.tfI1l.A'r'UCl'l1Ofl

''01110"1

t.t,HIC/lH*"1

r'""...,**.*.---**1-.-***.*******, tf>"*l'

""'1UI"ClOlll""'

iIKh 11<:1'1011I

01"0"'*11: I'**ll..'l'Wtll*.....'.ovt 1,7"14*ll'IJ_U.-otf1'000.

W"l'I11 l.miloO......"llK;llf.{,"tn'lINCH'1I

...'" r..IVfLlhOW.1

1-..c",.(.I.,n&'IWCHIII

'*"'''''''C,,"HtlI'I\.lt*ItQIQIoI,t,flCQIII.(OOUItQ.AAlW!l'O

on-.tt#l......

JAO¥w.-eu

'"-.u.JlYct""uelf'1

UIOIIIIOIIOWlutetlOff.n.,.,....*...lIOcI\O._*

"\"WII'I1U.OtI",l".".J

.."",...-----+6 INCHES

"""V"'Ol'-tlo'lt'ot!

'Jlc:l1',,,,lIl'Ul11l1" UQl.MtO'OA

oloO.QIJ,/lTl(ONlCCXlUM).Vc.e>>mH\IOU.I.I!'1I,uTlOll

"'V'Cll.oot

{....NfI O\llheTM."1Wf1

j

J

....

">__,"'>:.....OUIIII.D ,.............*.....1..1-,.........L.-.,----_<J

......................

,...........,1'(..." ,...6

.........0""+88.5 FEET

IlI\.W'Mtt"'/t

."nowIOf 10f'.".""'" D<<¥'WIu.HI'NIU.4e"'"'C1'\,,1l*c.A,.._

il,lIl: U"",.fll",UMO,f"kt/""_., ItO I)WIf."


ClWI'r.,.

3.0 STEP BASES STEPS PCCP-1 and PCCP-2 ENTRY CONomONS:*SUPPRESSION

POOL TEMP ABOVE 951'Q.B ABOVE 105'F WHEN DUE TO TESTING*DRYWELLAVERAGE

AIR TEMP ABOVE 15O"F*ORYWELL PRESS ABOVE 1.7PSlG*SUPPRESSION

POOL WATER LEVEL ABOVE*27 INCHES (-2 FEET&3 INCHES)*SUPPRESSION

POOL WATER LEVEL BELOW-31 INCHES (-2 FEET&T INCHES)*PRIMARY eTm H2 CONCENTRATION

ABOVE 1.5°,4 STEP BASES: The conditions

which require entry into the Primary Containment

Control Procedure are symptomatic

of an emergency or conditions

which, if not corrected, could degrade into an emergency.

This set of entry conditions

is sufficient

to assure that procedures

will be entered for transients

and accidents, which are within the design and licensing basis for BWRs and for additional

events which have been evaluated as significant

with respect to emergency response actions.Similar to the rationale which formed the basis for selecting the Reactor Control Guideline entry condition parameters

and setpoints, setpoints for the Primary Containment

Control Procedure entry condition parameters

are simple, unambiguous, operationally

significant, readily identifiable, and familiar to plant operators.

For example, each of the entry conditions

is typically one or more of the following:

a.Scram setpoint b.Annunciator

alarm setpoint 1001-37.8 Rev.4 Page 4 of 581

STEPS PCCP-1 and PCCP-2 (continued}

c.Technical specification

limit d.ECCS automatic initiation

logic trip setpoint The entry condition setpoints are specified so as to provide advance warning to operators of potential emergency conditions, allowing action to be taken sufficiently

early to prevent more severe consequences.

1001-37.8 Rev.4 Page 5 of 581

STEPS PCCP-5 and PCCP-6 PCCP-6 NO STEP BASES: If performing

the actions specified in the Primary Containment

Control Procedure restores the entry condition(s)

to normal, and this procedure is no longer required to control primary containment

parameters.

then the operator may exit this procedure since primary containment

will no longer be threatened

at this point.EOP-01-SEP-08

is entered to ensure all jumpers and inhibits used during execution of PCCP are restored to normal and all safety systems are returned to normal.1001-37.8 Rev.4 Page 7 of 581

STEPS SPIT-01 through SPIT-04 MONITOR AND CONTROL SUPPRESSION

POOL TEMP BELOW 95"F START AVAILABLE IUlR LOOPS IN SUPPRESSION

POOL COOLING MODE AS NECESSARY TO MAINTAIN TEMP BELOW 95"F IOP*H)SPIT-04 STEP BASES: The initial action taken to control suppression

pool temperature

employs the same method typically used during normal plant operations:

monitoring

its status and placing available suppression

pool cooling in operation, as required, to maintain temperature

within technical specification

limits.These steps thus provide a smooth transition

from general plant procedures

to the Emergency Operating Procedures

and assure that the normal method of suppression

pool temperature

control is attempted in advance of initiating

more complex actions to terminate rising suppression

pool temperature.

As long as suppression

pool temperature

remains below the value of the most limiting suppression

pool temperature

LCO, no further operator action is required in this section of the procedure other than continuing

to monitor and control suppression

pool temperature

using available suppression

pool cooling systems.The NPSH (Net Positive Suction Head)limits are defined to be the highest suppression

pool temperature

which provides adequate net positive suction head for pumps taking suction on the pool.The NPSH Limits are functions of pump flow and suppression

chamber overpressure (airspace pressure plus the hydrostatic

head of water over the pump suction).It is utilized to preclude pump damage from cavitation.

It should be 1001-37.8 Rev.4 Page 9 of 581

STEPS SPIT-01 through SPIT-04 (continued)

noted that containment

pressurization

of up to 5 psig is credited for maintaining

NPSH margins for BNP.Therefore, as actions are taken that reduce suppression

chamber pressure (Le.suppression

pool cooling, containment

sprays), pump NPSH requirements

should be considered, and closer attention directed towards observing the performance

of the RHR and Core Spray pumps for signs of NPSH problems.The vortex limits are defined to be the lowest suppression

pool water level above which air entrainment

is not expected to occur in pumps taking suction on the pool.These levels are functions of ECCS flow.Exceeding the limits can lead to air entrainment

at the pump suction strainers.

The NPSH and vortex limits are addressed through a caution for the following reasons: a.It is difficult to define in advance exactly when the limits should be observed and when pumps should be operated irrespective

of the limits.b.Pumps to which the limits apply are used in more than one parameter control path, or in different procedures.

RHR pumps, for example, may be used in the Reactor Vessel Control Procedure, the Level/Power

Control procedure, or the Primary Containment

Control Procedure.

Authorizing

operation of the pumps"irrespective

of NPSH and vortex limits" in one path may conflict with instructions

in another path where flow would normally be controlled

below the limits.The identified

systems should be operated within the NPSH and vortex limits if possible.If the situation warrants, however, the limits may be exceeded.A judgment as to whether a pump should be operated beyond its limits in a particular

event should consider such factors as: a.The availability

of other systems b.The current trend of plant parameters

c.The anticipated

time such operation will be required d.The degree to which the limit will be exceeded e.The sensitivity

of the pump to operation beyond the limit f.The consequences

of not operating the pump beyond the limit Immediate and catastrophic

failure is not expected if a pump is operated beyond the NPSH or vortex limit.1001-37.8 Rev.4 Page 10 of 581

STEPS SPIT-05 and SPIT-06 START AU AVAILABlE RHR LOOPS IN SUPPRESSION

POOl COOLING MODE EXCEPT RHR PUMPS REQUIRED FOR ADEQUATE CORE COOLING BY CONTINUOUS

OPERATION IN lPClMODE SPfT*06 STEP BASES: When it is determined

that suppression

pool temperature

cannot be maintained

below the value of the most limiting suppression

pool temperature

lCO, a conclusion

that may be reached in advance of suppression

pool temperature

actually reaching this value, the general direction of Step SPIT-04 is supplemented

with the explicit instruction

to place into operation all available methods by which Suppression

Pool Cooling can be effected.Step SPIT-06 assures adequate core cooling takes precedence

over maintaining

suppression

pool temperature

below the lCO since catastrophic

failure of the primary containment

is not expected to occur at this temperature.

In addition, further action still remains available for reversing a rising suppression

pool temperature

trend.Therefore, only if continuous

operation of a RHR pump in the LPCI mode is not required to assure adequate core cooling is it permissible

to use that pump for Suppression

Pool Cooling.This step, however, does permit alternating

the use of RHR pumps between LPCI injection and Suppression

Pool Cooling as the need for each occurs and so long as adequate core cooling is able to be maintained.

1001-37.8 Rev.4 Page 11 of 581

STEPS DWIT-01 through DWIT-03 Dwrr DWIT*01 MONITOR AND CONTROL DRYWELL AVERAGE AIR TEMP BELOW 15O"F STEP BASES: The initial action taken to control drywell temperature

employs the same method typically used during normal plant operations:

monitoring

its status and placing available drywell cooling in operation, as required, to maintain temperature

within specified normal operating limits (below drywell average air temperature

LeO of 150°F).Thesesteps

provide a smooth transition

from general plant procedures

to the Emergency Operating Procedures, and assure that the normal method of drywell temperature

control is attempted in advance of initiating

more complex actions to terminate rising drywell temperature.

As long as drywell temperature

remains below normal operating limits no further operator action is required in this section of the EOP other than continuing

to monitor and control drywell temperature

using available drywell cooling.1001-37.8 Rev.4 Page 15 of 581

STEPS o WIT-04 through DWIT-08 START AlL AVAILABLE ORYWEU COOLERS, DEFEATING DRYWELL COOLER INTERLOCKS

IF NECESSARY PER"CIRCUIT ALTERATION

PROCEDURE" (EOP-01-SEP*10)DW/T*08 STEP BASES: When it is determined

that drywell temperature

cannot be maintained

below the drywell average temperature

LCO limit of 150°F, a conclusion

that may be reached prior to drywell temperature

actually reaching this value, the general direction of Step DWIT-03 is supplemented

with the explicit instruction

to place into operation all available methods by which drywell cooling can be effected as indicated in Step DWIT-07.A note is added to inform the operator at Step DWIT-06 that the drywell coolers are tripped and locked out on a LOCA signal.1001-37.8 Rev.4 Page 16 of 581

STEPS DWIT-04 through DWIT-08 (continued)

All available drywell coolers should be started in an effort to reduce drywell average temperature, unless actual LOCA conditions

exist in the drywell.Step DWIT-07, through EOP-01-SEP-10, allows inhibiting

of the LOCA signal-drywell

cooler lockout if reactor water level is low.Defeating of interlocks

recognizes

that concurrent

actions by other procedures (Le.Level/Power

Control)may otherwise preclude normal drywell cooler operation.

RBCCW pressure and temperatures

should be verified to ensure proper system operation.

If the Reactor Building is accessible, additional

RBCCW heat exchangers

and/or SW to the RBCCW heat exchangers

can be placed in service.In addition, nonessential

equipment serviced by RBCCW can be taken out of service and isolated.Step DW IT-05 is used to alert the operator that elevated drywell temperatures

may adversely affect reactor level instrumentation.Adetailed discussion

of this caution is contained within the EOP User's Guide.If drywell temperature

can be maintained

below 150°F, then the operator is directed back into Step DW IT-02 so that he can continue to monitor and control drywell temperatures

until they reach the normal operating value.1001-37.8 Rev.4 Page 17 of 581

STEPS PC/P-01 through PC/P-03 PC/P*01 PC/P*03 PC/P VENT THE DRYWB.L USING SBGT lOP*10).AS REQUIRED STEP BASES: These steps provide the initial action taken to control primary containment

pressure which employs the same methods typically used during normal plant operations:

monitoring

its status and using containment

and drywell pressure control systems (including

Standby Gas Treatment System), as required, to maintain containment

pressure below the high drywell pressure scram setpoint.These steps thus provide a smooth transition

from general plant operating procedures

to the Emergency Operating Procedures, and assure that normal methods of primary containment

pressure control are attempted in advance of initiating

more complex actions to terminate rising primary containment

pressure.1001-37.8 Rev.4 Page 24 of 581

STEPS PC/P-04 through PC/P-07 1.7 PSIG 11.5 PSIG CAN PRIMARY CTMT PRESS BE MAINTAINED

BELOW 1.7PSIG SUPPRESSION

CHAMBER PRESS REACHES 11.5 PSIG INITIATE SUPPRESSION

POOL SPRAY PER EOP*01*SEP*03 EXCEPT RHR PUMPS REQUIRED FOR ADEQUATE CORE COOLING BY CONTINUOUS

OPERATION IN LPCI MODE YES____----'----..:..P""CIP.06

IF SUPPRESSION

CHAMBER PRESS DROPS TO LESS THAN 2.5 PSIG, THEN TERMINATE SUPPRESSION

POOL SPRAYS pc/p*O?STEP BASES: Operation of suppression

pool sprays reduces primary containment

pressure by condensing

steam that may be present in the suppression

chamber airspace, and by absorbing heat energy from the enclosed atmosphere

through the processes of evaporative

and convective

cooling.1001-37.8 Rev.4 Page 25 of 581

STEPS PC/P-04 through PC/P-07 (continued)

The Suppression

Chamber Spray Initiation

Pressure is defined to be the lowest suppression

chamber pressure which can occur when 95%of the noncondensibles

in the drywell have been transferred

to the airspace of the suppression

chamber.This pressure is utilized to preclude chugging: the cyclic condensation

of steam at the downcomer openings of the drywell vents.When a steam bubble collapses at the exit of the downcomers, the rush of water filling the void (some of it drawn up into the downcomer pipe)induces a severe stress at the junction of the downcomer and the vent header.Repeated application

of this stress can cause these joints to experience

fatigue failure (Le., crack)thereby creating a pathway which bypasses the pressure suppression

function of the containment.

Subsequent

steam discharges

through the downcomers

would directly pressurize

the suppression

chamber airspace rather than being discharged

to and condensed in the suppression

pool.Scale model tests have demonstrated

that chugging will not occur so long as the drywell atmosphere

contains at least 1%noncondensibles.

To preclude the occurrence

of conditions

under which chugging may happen, the Suppression

Chamber Spray Initiation

Pressure is conservatively

defined by specifying

5%noncondensibles.

Although operation of suppression

pool sprays may not, by itself, preclude chugging, suppression

pool sprays are initiated before reaching the Suppression

Chamber Spray Initiation

Pressure (11.5 psig)to assure that operation of this system is attempted for reducing primary containment

pressure before operation of drywell sprays is directed.The operation of suppression

pool sprays is terminated

when suppression

chamber pressure decreases to 2.5 psig to assure that primary containment

pressure is not reduced below atmospheric.

Maintaining

a positive suppression

chamber pressure precludes air from being drawn in through the vacuum relief system to deinert the primary containment, and also assures that a positive margin to the negative design pressure of the primary containment

exists.It is acceptable

to use drywell pressure instead of suppression

chamber if the suppression

chamber instruments

are not available.

It should be noted however that during transient conditions;

Le., a steam leak in drywell, drywell pressure may be significantly

higher than suppression

chamber pressure.The NPSH (Net Positive Suction Head)limits are defined to be the highest suppression

pool temperature

which provides adequate net positive suction head for pumps taking suction on the pool.TheNPSH Limits are functions of pump flow and suppression

chamber overpressure (airspace pressure plus the hydrostatic

head of water over the 1001-37.8 Rev.4 Page 26 of 581

STEPS PC/P-04 through PC/P-07 (continued}

pump suction).It is utilized to preclude pump damage from cavitation.

It should be noted that containment

pressurization

of up to 5 psig is credited for maintaining

NPSH margins for BNP.Therefore, as actions are taken that reduce suppression

chamber pressure (Le.suppression

pool cooling, containment

sprays), pump NPSH requirements

should be considered, and closer attention directed towards observing the performance

of the RHR and Core Spray pumps for signs of NPSH problems.The NPSH limit is addressed through a caution for the following reasons: a.It is difficult to define in advance exactly when the limits should be observed and when pumps should be operated irrespective

of the limits.b.Pumps to which the limits apply are used in more than one parameter control path, or in different procedures.

RHR pumps, for example, may be used in the Reactor Vessel Control Procedure, the Level/Power

Control procedure, or the Primary Containment

Control Procedure.

Authorizing

operation of the pumps irrespective

of NPSH in one path may conflict with instructions

in another path where flow would normally be controlled

below the limits.The identified

systems should be operated within the NPSH and vortex limits if possible.If the situation warrants, however, the limits may be exceeded.A judgment as to whether a pump should be operated beyond its limits in a particular

event should consider such factors as: a.The availability

of other systems b.The current trend of plant parameters

c.The anticipated

time such operation will be required d.The degree to which the limit will be exceeded e.The sensitivity

of the pump to operation beyond the limit f.The consequences

of not operating the pump beyond the limit Immediate and catastrophic

failure is not expected if a pump is operated beyond the NPSH or vortex limit.Suppression

chamber sprays are initiated per Suppression

Pool Spray Procedure (EOP-01-SEP-03).

1001-37.8 Rev.4 Page 27 of 581

STEPS PC/P-08 through PC/P-13 NO NO NO INmATE DRYWEU SPRAYS PER EOP-01-SEP*02

EXCEPT RHR PUMPS REQUIRED FOR ADEQUATE CORE COOUNG BY CONTINUOUS

OPERATION INLPCIMODE

PC/P*i2 IF DRYWEU PRESSURE DROPS TO lESS THAN 2.5 PSlG THEN TERMINATE DRYWELL SPRAY PC/P*i3 STEP BASES: If suppression

pool sprays could not be initiated or if their operation was not effective in reversing the rising trend of primary containment

pressure, as evidenced by suppression

chamber pressure exceeding the Suppression

Chamber Spray Initiation

Pressure (11.5 psig), drywell sprays are initiated to effect the desired pressure reduction.

The Suppression

Chamber Spray Initiation

Pressure is described in the discussion

of Step PC/P-06.1001-37.8 Rev.4 Page 28 of 581

STEPS PC/P-08 through PC/P-13 (continued}

The NPSH (Net Positive Suction Head)limits are defined to be the highest suppression

pool temperature

which provides adequate net positive suction head for pumps taking suction on the pool.The NPSH Limits are functions of pump flow and suppression

chamber overpressure (airspace pressure plus the hydrostatic

head of water over the pump suction).It is utilized to preclude pump damage from cavitation.

It should be noted that containment

pressurization

of up to 5 psig is credited for maintaining

NPSH margins for BNP.Therefore, as actions are taken that reduce suppression

chamber pressure (Le.suppression

pool cooling, containment

sprays), pump NPSH requirements

should be considered, and closer attention directed towards observing the performance

of the RHR and Core Spray pumps for signs of NPSH problems.The initiation

of drywell sprays is conditioned

on the following restrictions

on the plant.First, the recirculation

pumps and drywell cooling fans are required to be secured prior to the initiation

of drywell sprays.These actions are covered in EOP-01-SEP-02.

A second restriction

on the initiation

of drywell sprays is for suppression

pool water level to be below+21 inches.This provides protection

for the operation of the suppression

chamber-to-drywell

vacuum breakers.The vacuum breakers will not function as designed if any portion of the valve is covered with water.The specified water level assures that no portion of the drywell side of the valve is submerged for any drywell below wetwell differential

pressure less than or equal to the valve opening differential

pressure.Spray operation with vacuum breakers inoperable (Le., with no drywell vacuum relief capability)

may cause the containment

differential

pressure capability

to be exceeded and is therefore not permitted.

Step PC/P-12 assures adequate core cooling takes precedence

over initiating

drywell spray in this case since catastrophic

failure of the primary containment

is not expected under the conditions

for which spray requirements

are established.

The wording of the stepdoespermit

alternating

between reactor vessel injection and drywell spray modes as the need for each occurs, provided adequate core cooling can be maintained.

Drywell sprays are secured if drywell pressure drops to 2.5 psig.This is a backup step to the automatic securing of the sprays during a LOCA condition when the spray permissive

interlock drops out.This precludes air from being drawn in through the vacuum relief system to de-inert the primary containment

and also provides a positive margin to the negative design pressure of the primary containment.

The drywell sprays are actuated in accordance

with EOP-01-SEP-02.

1001-37.8 Rev.4 Page 29 of 581

STEPS PC/P-14 through PC/P-16 PSP EMERGEHCYOEPRESSURUE

TliE REACTOR PER THE RCIP SECTION OF EOP*01 PC/P*16 STEP BASES: If suppression

pool and/or drywell sprays could not be initiated or if operation was not effective in reversing the rising trend of primary containment

pressure, as evidenced by not being able to maintain suppression

chamber pressure below the Pressure Suppression

Pressure, the reactor is depressurized

to minimize further release of energy from the reactor vessel to the primary containment.

This action serves to terminate, or reduce as much as possible, any continued primary containment

pressure rise.The Pressure Suppression

Pressure is defined to be the lesser of either (1)the highest suppression

chamber pressure which can occur without steam in the suppression

chamber airspace or (2)the highest suppression

chamber pressure at which initiation

of reactor depressurization

will not result in exceeding Primary Containment

Pressure Limit A before reactor pressure drops to the Minimum Reactor Flooding Pressure, or (3)the highest suppression

chamber pressure which can be maintained

without exceeding the suppression

pool boundary design load if SRVs are opened.This pressure is a function of primary containment

water level, and it is utilized to assure the pressure suppression

function of the containment

is maintained

while the reactor is at pressure.(For additional

information

about the Pressure Suppression

Pressure see the EOP User's GUide.)1001-37.8 Rev.4 Page 30 of 581

STEPS PC/P-14 through PC/P-16 (continued)

A note is added to remind the operator that rapid depressurization

per the reactor pressure control guidance of the Reactor Vessel Control Procedure may be allowed prior to the direction to Emergency Depressurize.

See discussion

on Step SPIT-11.1001-37.8 Rev.4 Page 31 of 581

STEPS PC/H*01 through PC/H*04 PC/H MONITOR AND CONTROL PRIMARY CTMT HYDROGEN AND OXYGEN CONCENTRATIONS

H2 AND 02 READINGS ARE COMPENSATED

BY ERFIS.H2 AND 02 READINGS ON CAC*AT.4409 AND 4410 MUST BE COMPENSATED

FOR PRIMARY CTMT CONDITIONS

USING ATTACHMENT

12 OF"USERS GUIDE" (EOP*01*UG)STEP BASES: The primary containment

hydrogen control (PC/H)section of the Primary Containment

Control Procedure specifies appropriate

actions for controlling

combustible

gas concentration

in containment.

Hydrogen and oxygen must both be present and in sufficient

concentration

for combustion

to occur.Measurable

levels of hydrogen could appear in the primary containment

from the following sources: a.The high temperature

reaction of metal (typically

zirconium)

with water to produce hydrogen gas and metal oxide b.Radiolysis

of water to produce hydrogen and oxygen c.Feedwater injection of hydrogen to control reactor water chemistry 1001-37.8 Rev.4 Page 49 of 581

,.VW"M STEPS PC/H-01 through PC/H-04 (continued)

Elevated concentrations

of oxygen are not expected during normal power operations

except during brief periods at startup and shutdown of the plant when the containment

atmosphere

is being inerted and deinerted.

However, oxygen may be generated due to the radiolysis

of water, and oxygen could enter the containment

from leaks in the instrument

air system and from operation of Reactor Building-to-suppression

pool vacuum breakers.Oxygen concentration

is routinely monitored and controlled

during reactor operation in accordance

with Technical Specification

requirements.

These steps are included to ensure the monitors are placed in service as required.Step PC/H-04 alerts the operator of the need to compensate

for H2/02 based on primary containment

conditions.

1001-37.8 Rev.4 Page 50 of 581