ML18110A321
ML18110A321 | |
Person / Time | |
---|---|
Site: | Brunswick |
Issue date: | 04/16/2018 |
From: | Eugene Guthrie Operator Licensing and Human Performance Branch |
To: | Hicks J Duke Energy Progress |
References | |
Download: ML18110A321 (3) | |
Similar Documents at Brunswick | |
---|---|
Category:Letter
MONTHYEARIR 05000324/20253012024-10-17017 October 2024
[Table view]Notification of Licensed Operator Initial Examination 05000325/2025301 and 05000324/2025301 IR 05000324/20244012024-10-15015 October 2024 Security Baseline Inspection Report 05000324/2024401 and 05000325/2024401 ML24297A6262024-10-11011 October 2024 PCA Letter to NRC Brunswick Potential Tropical Storm Eight IR 05000324/20240102024-09-10010 September 2024 Focused Engineering Inspection Commercial Grade Dedication Report 05000324-2024010 and 05000325-2024010 ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000324/20240052024-08-23023 August 2024 Updated Inspection Plan for Brunswick Steam Electric Plant, Units 1 and 2 (Report 05000324/2024005 and 05000325/2024005) IR 05000324/20240022024-08-0505 August 2024 Integrated Inspection Report 05000324/2024002 and 05000325/2024002 and 07200006/2024001 ML24206A1062024-07-30030 July 2024 2024 Brunswick Requal Inspection Corporate Notification Letter ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 IR 05000324/20244202024-07-0202 July 2024 – Security Baseline Inspection Report 05000324/2024420 and 05000325/2024420 ML24108A0702024-06-0505 June 2024 – Issuance of License Amendments to Revise the 10 CFR 50.69 Categorization Process to Reflect an Alternative Seismic Approach IR 05000324/20244022024-05-17017 May 2024 Plan Material Control and Accounting Program Inspection Report 05000324/2024402 and 05000325/2024402 - Cover Letter IR 05000324/20240012024-05-0909 May 2024 Integrated Inspection Report 05000324/2024001 and 05000325/2024001 05000325/LER-2024-002, Re Automatic Start of Emergency Diesel Generator Due to Emergency Bus De-energization2024-04-10010 April 2024 Re Automatic Start of Emergency Diesel Generator Due to Emergency Bus De-energization 05000325/LER-2024-001, Primary Containment Penetration Local Leak Rate Testing Failure2024-04-10010 April 2024 Primary Containment Penetration Local Leak Rate Testing Failure ML24066A0132024-03-0505 March 2024 Bru 2024-002 Radiation Safety Baseline Inspection Information Request ML24026A0982024-03-0101 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0057 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000324/20230062024-02-28028 February 2024 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 – NRC Inspection Reports 05000324/2023006 and 05000325/2023006 IR 05000324/20244032024-02-14014 February 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perm Inspection 05000325/2024403; 05000324/2024403 ML24032A1392024-02-12012 February 2024 Correction of Errors within Authorized Alternative Request RA-22-0308 IR 05000324/20230042024-02-0606 February 2024 Integrated Inspection Report 05000324/2023004 and 05000325/2023004 IR 05000324/20230112023-12-26026 December 2023 NRC Fire Protection Team Inspection - FPTI Report 05000324/2023011 and 05000325/2023011 IR 05000324/20234022023-12-14014 December 2023 Security Baseline Inspection Report 05000324-2023402 and 05000325-2023402 ML23297A0262023-11-27027 November 2023 – Proposed Alternatives to ASME Code Section XI Subsection IWE Requirements for Torus Metallic Liner Inspections ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000324/20230032023-11-0101 November 2023 Integrated Inspection Report 05000324/2023003 and 05000325/2023003 IR 05000324/20230102023-10-17017 October 2023 Biennial Problem Identification and Resolution Inspection Report 05000324/2023010 and 05000325/2023010 IR 05000325/20234012023-10-16016 October 2023 Security Baseline Inspection Report 05000324 and 05000325 2023401 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000324/20230052023-08-23023 August 2023 Updated Inspection Plan for Brunswick Steam Electric Plant, Units 1 and 2 (Report 05000324/2023005 and 05000325/2023005) IR 05000324/20230022023-08-0404 August 2023 Integrated Inspection Report 05000324/2023002 and 05000325/2023002 ML23201A2042023-07-28028 July 2023 Summary of Regulatory Audit in Support of Alternative Request RA-22-0308 for Inservice Inspection of the Torus Metallic Liner IR 05000324/20243012023-07-25025 July 2023 – Notification of Licensed Operator Initial Examination 05000325/2024301 and 05000324/2024301 05000324/LER-2023-001, Two Main Steam Line Safety Relief Valves Inoperable2023-07-17017 July 2023 Two Main Steam Line Safety Relief Valves Inoperable 05000325/LER-2023-001, Loss of Redundant Power Supply Operation Causes Turbine Trip and Subsequent Reactor Scram2023-06-15015 June 2023 Loss of Redundant Power Supply Operation Causes Turbine Trip and Subsequent Reactor Scram ML23146A0012023-05-24024 May 2023 EN 56538 - Engine Systems Inc and Brunswick ML23212A9502023-05-24024 May 2023 Engine Systems, Inc., Part 21 Report Re Woodward EGB-35P Governor/Actuator with Foreign Material ML23130A3902023-05-12012 May 2023 – Regulatory Audit Plan in Support of Alternative Request RA 22-0308 for Inservice Inspection of the Torus Metallic Liner IR 05000324/20230012023-05-10010 May 2023 – Integrated Inspection Report 05000324 2023001 and 05000325 2023001 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI IR 05000324/20220042023-04-0404 April 2023 Reissue - Brunswick Steam Electric Plant - Integrated Inspection Report 05000324/2022004 and 05000325/022004 ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000324/20220062023-03-0101 March 2023 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 – NRC Inspection Reports 05000324/2022006 and 05000325/2022006 ML23033A5252023-02-0808 February 2023 Integrated Inspection Report 05000324/2022004 and 05000325/2022004 IR 05000324/20223012023-02-0303 February 2023 NRC Operator License Examination Report 05000325/2022301 and 05000324/2022301 IR 05000324/20224022022-11-23023 November 2022 Security Baseline Inspection Report 05000324 2022402 and 05000325 2022402 ML22332A0132022-11-23023 November 2022 Operator Licensing Written Examination Approval 05000325/2022301 and 05000324/2022301 ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations 2024-09-04 Category:License-Operator MONTHYEARIR 05000324/20253012024-10-17017 October 2024
[Table view]Notification of Licensed Operator Initial Examination 05000325/2025301 and 05000324/2025301 RA-24-0093, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-04-0202 April 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations ML23065A0702023-03-0606 March 2023 Bru 2022301 2B Exam Administrative Items IR 05000324/20213642021-06-11011 June 2021 Exam Approval Letter 05000348/2021-301 and 05000324/2021-364 ML21034A6212021-02-0303 February 2021 301 2B (Normal Release) Exam Administrative Items ML21034A6222021-02-0303 February 2021 301 2A Exam Administrative Items (2 Year Delayed Release) ML21034A6252021-02-0303 February 2021 301 2A Exam Final Items (2 Year Delayed Release) ML21015A0162021-01-15015 January 2021 301 1A Final RO Written Exam (2-Year Delayed Release) ML21015A0202021-01-15015 January 2021 301 1A Final SRO Written Exam (2-Year Delayed Release) ML21019A3932021-01-11011 January 2021 1 GFE Annual Letter for Fy 2021 ML20339A4052020-11-30030 November 2020 Operator Licensing Examination Approval 05000325/2020301 and 05000324/2020301 RA-20-0075, Response to NRC Regulatory Issue Summary 2020-01 Preparation and Scheduling of Operator Licensing Examinations2020-03-16016 March 2020 Response to NRC Regulatory Issue Summary 2020-01 Preparation and Scheduling of Operator Licensing Examinations ML20007F7572020-01-0707 January 2020 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2020 ML19058A6322019-07-0101 July 2019 Issuance of Amendments to Revise Emergency Action Level Schemes to Incorporate Clarifications Provided by Emergency Preparedness FAQs RA-19-0237, Catawba Station, Shearon Plant, McGuire Station, Oconee Nuclear Station and H.B. Robinson Plant - Response to NRC Regulatory Issue Summary 2019-02 Preparation and Scheduling of Operator Licensing Examinations2019-05-15015 May 2019 Catawba Station, Shearon Plant, McGuire Station, Oconee Nuclear Station and H.B. Robinson Plant - Response to NRC Regulatory Issue Summary 2019-02 Preparation and Scheduling of Operator Licensing Examinations ML19115A2282019-04-25025 April 2019 Exam 2019-301, Exam Administrative Items (Normal Release) ML19018A0882019-01-17017 January 2019 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2019 ML19004A3402019-01-0303 January 2019 Operator Licensing Examination Approval 05000325/2019301 and 05000324/2019301 ML18239A4532018-08-27027 August 2018 302 Exam Administrative Items (ADAMS-2D)- Delay Release 2 Yrs ML18239A4522018-08-27027 August 2018 302 Exam Administrative Items (ADAMS-2C)- Delay Release 2 Yrs ML18239A4482018-08-27027 August 2018 302 Exam Final Items (ADAMS-2B)- Delay Release 2 Yrs ML18239A4462018-08-27027 August 2018 302 Examination Draft Items (ADAMS-2A)- Delay Release 2 Yrs RA-18-0049, Operating Test Outline, Written Examination Outline, and Reference Materials for Licensed Operator Initial Examination 50-325/2018-301 and 50-324/2018-3012018-06-25025 June 2018 Operating Test Outline, Written Examination Outline, and Reference Materials for Licensed Operator Initial Examination 50-325/2018-301 and 50-324/2018-301 IR 05000324/20183012018-06-25025 June 2018 Operating Test Outline, Written Examination Outline, and Reference Materials for Licensed Operator Initial Examination 50-325/2018-301 and 50-324/2018-301 ML18110A3212018-04-16016 April 2018 March 2018 - Brunswick NRC Generic Fundamentals Examination Results ML18086B0442018-02-16016 February 2018 Facility Cover Letter - Rii - March 2018 - GFE BSEP 17-0121, Post-Examination Documentation and Comments for Operator Retake Initial Examination2017-12-14014 December 2017 Post-Examination Documentation and Comments for Operator Retake Initial Examination IR 05000324/20173022017-12-12012 December 2017 (Retake) Operator Licensing Examination Approval 05000325/2017302 and 05000324/2017302 ML17298B1312017-10-25025 October 2017 05000325/2017-301 and 05000324/2017-301 Exam Draft Items ML17298B1612017-10-25025 October 2017 05000325/2017-301 and 324/2017-301 Exam Final Items ML17298B1732017-10-25025 October 2017 05000325/2017-301 and 324/2017-301 Exam Administrative Items ML17263A6012017-09-20020 September 2017 Final RO Written as Given and Answer Sheet - Delay Release 2 Yrs ML17263A6222017-09-20020 September 2017 Reactor Operator and Senior Reactor Operator License Post-Examination Documentation and Comments 05000325/2017301 and 05000324/2017301 Post Exam Comments ML17263A6042017-08-0808 August 2017 Final SRO Written as Given and Answer Sheet - Delay Release 2 Yrs ML17201B5072017-07-18018 July 2017 Operator Licensing Written Examination Approval 050003252017301 and 050003242017301 ML17181A3862017-06-30030 June 2017 Exam Draft Items 2A - Delay Release ML17181A3952017-06-30030 June 2017 Exam Final Items 2B - Delay Release ML17181A4012017-06-30030 June 2017 Exam Administrative Items 2C - Delay Release ML17181A3342017-06-30030 June 2017 Brunswick 2015301 ADAMS 2D - Exam Admin Items ML17032A2792017-01-27027 January 2017 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2017 ML17017A3892017-01-27027 January 2017 Post-Exam Comment - Delay Release 2 Yrs ML17017A3852017-01-27027 January 2017 Final SRO Written Exam - Delay Release 2 Years ML17012A3042017-01-27027 January 2017 Final RO Written Exam - Delay Release 2 Yrs ML16334A5322016-11-21021 November 2016 Operator Licensing Written Examination Approval 05000325/2016301 and 05000324/2016301 ML16007A2122016-01-0707 January 2016 Initial Exam 2015-301 Post Exam Comments BSEP 15-0105, Reactor Operator and Senior Reactor Operator License Post-Examination Documentation and Comments2015-12-21021 December 2015 Reactor Operator and Senior Reactor Operator License Post-Examination Documentation and Comments BSEP 15-0018, Updated Information Regarding Operator Licensing Examinations2015-03-0505 March 2015 Updated Information Regarding Operator Licensing Examinations ML14350A1252014-12-16016 December 2014 Initial Exam 2014-301 Draft RO Written Exam ML14350A1312014-12-16016 December 2014 Initial Exam 2014-301 Draft SRO Written Exam ML14350A1342014-12-16016 December 2014 Initial Exam 2014-301 Draft Simulator Scenarios 2024-04-02 Category:Part 55 Examination Related Material MONTHYEARIR 05000324/20253012024-10-17017 October 2024
[Table view]Notification of Licensed Operator Initial Examination 05000325/2025301 and 05000324/2025301 RA-24-0093, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-04-0202 April 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations ML23065A0702023-03-0606 March 2023 Bru 2022301 2B Exam Administrative Items IR 05000324/20213642021-06-11011 June 2021 Exam Approval Letter 05000348/2021-301 and 05000324/2021-364 ML21034A6222021-02-0303 February 2021 301 2A Exam Administrative Items (2 Year Delayed Release) ML21034A6252021-02-0303 February 2021 301 2A Exam Final Items (2 Year Delayed Release) ML21034A6212021-02-0303 February 2021 301 2B (Normal Release) Exam Administrative Items ML21015A0202021-01-15015 January 2021 301 1A Final SRO Written Exam (2-Year Delayed Release) ML21015A0162021-01-15015 January 2021 301 1A Final RO Written Exam (2-Year Delayed Release) ML21019A3932021-01-11011 January 2021 1 GFE Annual Letter for Fy 2021 ML20339A4052020-11-30030 November 2020 Operator Licensing Examination Approval 05000325/2020301 and 05000324/2020301 RA-20-0075, Response to NRC Regulatory Issue Summary 2020-01 Preparation and Scheduling of Operator Licensing Examinations2020-03-16016 March 2020 Response to NRC Regulatory Issue Summary 2020-01 Preparation and Scheduling of Operator Licensing Examinations RA-19-0237, Catawba Station, Shearon Plant, McGuire Station, Oconee Nuclear Station and H.B. Robinson Plant - Response to NRC Regulatory Issue Summary 2019-02 Preparation and Scheduling of Operator Licensing Examinations2019-05-15015 May 2019 Catawba Station, Shearon Plant, McGuire Station, Oconee Nuclear Station and H.B. Robinson Plant - Response to NRC Regulatory Issue Summary 2019-02 Preparation and Scheduling of Operator Licensing Examinations ML19115A2282019-04-25025 April 2019 Exam 2019-301, Exam Administrative Items (Normal Release) ML19004A3402019-01-0303 January 2019 Operator Licensing Examination Approval 05000325/2019301 and 05000324/2019301 ML18239A4532018-08-27027 August 2018 302 Exam Administrative Items (ADAMS-2D)- Delay Release 2 Yrs ML18239A4522018-08-27027 August 2018 302 Exam Administrative Items (ADAMS-2C)- Delay Release 2 Yrs ML18239A4482018-08-27027 August 2018 302 Exam Final Items (ADAMS-2B)- Delay Release 2 Yrs ML18239A4462018-08-27027 August 2018 302 Examination Draft Items (ADAMS-2A)- Delay Release 2 Yrs IR 05000324/20183012018-06-25025 June 2018 Operating Test Outline, Written Examination Outline, and Reference Materials for Licensed Operator Initial Examination 50-325/2018-301 and 50-324/2018-301 RA-18-0049, Operating Test Outline, Written Examination Outline, and Reference Materials for Licensed Operator Initial Examination 50-325/2018-301 and 50-324/2018-3012018-06-25025 June 2018 Operating Test Outline, Written Examination Outline, and Reference Materials for Licensed Operator Initial Examination 50-325/2018-301 and 50-324/2018-301 ML18110A3212018-04-16016 April 2018 March 2018 - Brunswick NRC Generic Fundamentals Examination Results BSEP 17-0121, Post-Examination Documentation and Comments for Operator Retake Initial Examination2017-12-14014 December 2017 Post-Examination Documentation and Comments for Operator Retake Initial Examination IR 05000324/20173022017-12-12012 December 2017 (Retake) Operator Licensing Examination Approval 05000325/2017302 and 05000324/2017302 ML17298B1312017-10-25025 October 2017 05000325/2017-301 and 05000324/2017-301 Exam Draft Items ML17298B1732017-10-25025 October 2017 05000325/2017-301 and 324/2017-301 Exam Administrative Items ML17298B1612017-10-25025 October 2017 05000325/2017-301 and 324/2017-301 Exam Final Items ML17263A6222017-09-20020 September 2017 Reactor Operator and Senior Reactor Operator License Post-Examination Documentation and Comments 05000325/2017301 and 05000324/2017301 Post Exam Comments ML17263A6012017-09-20020 September 2017 Final RO Written as Given and Answer Sheet - Delay Release 2 Yrs ML17263A6042017-08-0808 August 2017 Final SRO Written as Given and Answer Sheet - Delay Release 2 Yrs ML17201B5072017-07-18018 July 2017 Operator Licensing Written Examination Approval 050003252017301 and 050003242017301 ML17181A4012017-06-30030 June 2017 Exam Administrative Items 2C - Delay Release ML17181A3342017-06-30030 June 2017 Brunswick 2015301 ADAMS 2D - Exam Admin Items ML17181A3952017-06-30030 June 2017 Exam Final Items 2B - Delay Release ML17181A3862017-06-30030 June 2017 Exam Draft Items 2A - Delay Release ML17032A2792017-01-27027 January 2017 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2017 ML17012A3042017-01-27027 January 2017 Final RO Written Exam - Delay Release 2 Yrs ML17017A3852017-01-27027 January 2017 Final SRO Written Exam - Delay Release 2 Years ML17017A3892017-01-27027 January 2017 Post-Exam Comment - Delay Release 2 Yrs ML16334A5322016-11-21021 November 2016 Operator Licensing Written Examination Approval 05000325/2016301 and 05000324/2016301 ML16007A2122016-01-0707 January 2016 Initial Exam 2015-301 Post Exam Comments BSEP 15-0018, Updated Information Regarding Operator Licensing Examinations2015-03-0505 March 2015 Updated Information Regarding Operator Licensing Examinations ML14350A1682014-12-16016 December 2014 Initial Exam 2014-301 Final Simulator In-Plant JPMs ML14350A1732014-12-16016 December 2014 Initial Exam 2014-301 Final Administrative JPMs ML14350A1612014-12-16016 December 2014 Initial Exam 2014-301 Final Simulator Scenarios ML14350A1582014-12-16016 December 2014 Initial Exam 2014-301 Final Administrative Documents ML14350A1552014-12-16016 December 2014 Initial Exam 2014-301 Draft Administrative JPMs ML14350A1372014-12-16016 December 2014 Initial Exam 2014-301 Draft Simulator In-plant JPMs ML14350A1342014-12-16016 December 2014 Initial Exam 2014-301 Draft Simulator Scenarios ML14350A1312014-12-16016 December 2014 Initial Exam 2014-301 Draft SRO Written Exam 2024-04-02 |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 April 16, 2018 Duke Energy Progress, Inc.
ATTN: Mr. Jonathan L. Hicks Manager, Training Brunswick Steam Electric Plant P. O. Box 10429 Southport, NC 28461-0429
SUBJECT:
BRUNSWICK - NRC GENERIC FUNDAMENTALS EXAMINATION RESULTS
Dear Mr. Hicks:
On March 7, 2018, the U.S. Nuclear Regulatory Commission (NRC) administered the generic fundamentals examination (GFE) section of the written operator licensing examination to employees of your facility. Enclosed with this letter are copies of both forms of the examination including the answer keys, the grading results for your facility, and copies of individual answer sheets for each of your employees. Please forward the results to the individuals along with the copies of their respective answer sheets. A PASS in the RESULTS column indicates that the individual achieved a passing grade of 80 percent or better on the GFE, while a FAIL indicates that the individual failed the examination.
Copies of the administered BWR and PWR GFEs and their answer keys will be available for review in the NRCs Agencywide Documents Access and Management System (ADAMS) immediately after administration of the second subsequent GFE. The NRC will also update its GFE Web Page, http://www.nrc.gov/reactors/operator-licensing/generic-fundamentalsexaminations.html.
If you have any questions concerning this examination, please contact me at (404) 997-4662.
Sincerely,
/RA by Phillip G. Capehart for/
Eugene F. Guthrie, Chief Operations Branch 2 Division of Reactor Safety Docket Nos.: 50-325, 50-324 License Nos.: DPR-71, DPR-62
Enclosures:
(See Page 2)
J. Hicks 2
Enclosures:
- 1. Examination Forms A and B with answers
- 2. Examination Results Summary for Brunswick
- 3. Individual Answer Sheets
- 4. NRC Response to Facility Comment on the March 2018 GFE cc w/o encls.:
Duke Energy Progress, Inc.
ATTN: Mr. William R. Gideon Site Vice President Brunswick Steam Electric Plant P. O. Box 10429 Southport, NC 24861-0429 Duke Energy Progress, Inc.
ATTN: Mr. Karl Moser Plant General Manager Brunswick Steam Electric Plant P. O. Box 10429 Southport, NC 28461-0429
ML18110A321 SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRS RII:DRS SIGNATURE JHK PGC for NAME JKIRBY EGUTHRIE DATE 4/12/2018 4/16/2018 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO