Issue date | Title | Topic | |
---|---|---|---|
ML18043A490 | 31 January 1979 | Reactor Internals Noise Monitoring Tests for Period Apr- Oct 1978 (First 6 Full Months of Core 3) | |
ML18043A799 | 2 July 1979 | Request for Change to Tech Specs of License DPR-20,re Heatup & Cooldown Curves | Shutdown Margin Hydrostatic |
ML18043A865 | 26 July 1979 | Application for Amend to Tech Specs Authorizing Change from Coordinated Phosphate to Volatile Chemistry Control for Secondary Side of Steam Generators.Change Will Reduce Corrosion Rate to Essentially Zero | |
ML18043A896 | 31 July 1979 | Request for Change to Tech Specs of License DFR-20 Re Auxiliary Feedwater Sys Operability | |
ML18044A195 | 31 October 1979 | Cycle 4,Startup Physics Test Program. | |
ML18044A208 | 6 November 1979 | Page Changes for Proposed Changes to Tech Specs 3.1 Re Primary Coolant Sys Heatup & Cooldown Rates & Min Conditions for Criticality | Shutdown Margin Hydrostatic |
ML18044A343 | 30 November 1970 | Containment Bldg Structural Integrity Test. | |
ML18044A344 | 5 October 1970 | Deformation Measurements During Containment Pressure Test. | |
ML18044A374 | 6 December 1979 | Const Specs for Outside Containment Portion of Pressurizer Relief Valve Position Indication Sys | |
ML18044A376 | 13 November 1979 | Const Specs for Inside Containment Portion of Pressurizer Relief Valve Position Indication Sys | |
ML18044A378 | 28 February 1979 | Rept of Seismic Vibration Testing of Various Electrical Items for B&W Under Purchase Order 033788LG. | |
ML18044A380 | 12 November 1979 | Installation & Checkout Procedures C-010-00 for Valve Monitoring Sys. | |
ML18044A480 | 31 January 1980 | Proposed Pages 3-99,3-101,4-79,3-96,3-100,4-75 & Table 3.22.1 to Tech Specs Re Fire Protection Equipment | Hydrostatic Fire Protection Program Fire Watch |
ML18044A484 | 1 February 1980 | Proposed Page 6-3 to Tech Specs Re Plant Organization | Fire Protection Program |
ML18044A536 | 11 February 1980 | Rept on Insp & Testing Program for Concrete Expansion Anchors Per IE Bulletin 79-02 & Revisions for CPC Facility in South Haven,Mi. | |
ML18044A539 | 11 February 1980 | Results of Insp & Testing Program in Response to IE Bulletin 79-02 & Revisions (for Interim Plant Operations) for CPC Facility in South Haven,Mi, Revision 0 | High Radiation Area |
ML18044A540 | 31 January 1980 | Results & Evaluation of Tests on Phillips Red Head Self- Drilling Expansion Anchors for CPC Facility in South Haven, Mi. | Breakaway torque Earthquake |
ML18044A589 | 29 February 1980 | Facility Steam Generator Repair Rept, Revision 5 | Safe Shutdown Boric Acid Operating Basis Earthquake Finite Element Analysis Earthquake Scaffolding |
ML18044A595 | 26 February 1980 | Page Changes for Proposed Tech Specs Change for License DPR-20,adding Addl Radical Peaking Factor | Shutdown Margin |
ML18044A758 | 11 April 1980 | Feedwater Line Water Hammer Test. | |
ML18044A836 | 5 May 1980 | Revised Pages 3.10,3.10.1,3.10.2 & 3.10.3 for Proposed Change to Tech Specs Re Shutdown Margin Requirements | Shutdown Margin |
ML18044A846 | 5 May 1980 | Tech Specs 3.2.1,3.2.2 & 3.2.3 Re Concentrated Boric Acid Tank Level | Boric Acid |
ML18044A894 | 14 May 1980 | Tech Spec Change Request Re Tech Specs 3.10 & 3.11 for Control Rod & Power Distribution Limits & in-core Instrumentation | |
ML18044A898 | 14 May 1980 | Tech Spec Change Request,Clarifying Implementation,Providing Editorial Changes & Deleting Redundant Requirements.Proposed Revised Pages to Sections 2.3.7,2.3,3.3,4.6,3.17 & Revised Tables 3.17.4,4.1.1 & 4.1.2 Encl | Shutdown Margin Hydrostatic |
ML18044A960 | 14 May 1980 | Emergency Procedure,Card 8,for Plant Health Physicist, Revision 5 | |
ML18044A961 | 29 April 1980 | Determination of Extent of Core Damage. | |
ML18044A962 | 26 April 1980 | Emergency High Range Effluents Monitor. | |
ML18044A963 | 29 April 1980 | In-plant Airborne Iodine Monitoring & Thyroid Blocking Agent Administration Under Accident Conditions. | |
ML18044A964 | 24 April 1980 | Sampling & Analysis of High Activity Reactor Coolant. | |
ML18044A965 | 30 April 1980 | Sampling & Analysis of High Activity Containment Atmosphere. | |
ML18044A966 | 21 April 1980 | Offsite Accident TLD Procedure. | |
ML18044A967 | 30 April 1980 | Offsite Airborne Iodine Monitoring Under Accident Conditions. | |
ML18045A222 | 30 November 1979 | Reactor Internals Noise Monitoring Tests Nov 1978-Nov 1979. | |
ML18045A293 | 1 July 1980 | Rept on Endurance Testing of Auxiliary Feedwater Pumps. | |
ML18045A338 | 3 July 1980 | Changes to Tech Specs 3.9 for Effluent Release & 4.11 for Environ Monitoring Program | |
ML18045A480 | 31 July 1980 | Cpco Hot License Program-Reactor Operator. | Shutdown Margin |
ML18045A539 | 21 August 1980 | Tech Specs Change Request Redefining Operability. | |
ML18045A548 | 31 July 1980 | Physics Testing Rept for Core 4 Startup. | |
ML18045A839 | 31 October 1980 | Emergency Operating Procedures 1-12 | |
ML18046A188 | 24 November 1980 | Proposed Tech Spec Changes in Response to NRC 790606 Request Re Undervoltage Protection Requirements.Changes Consist of Limiting Conditions for Operation & Setting Limits for Preferred Relays | |
ML18046A191 | 24 November 1980 | Application for Tech Spec Changes to License DPR-20 Re Containment Spray Initiation Time | |
ML18046A208 | 3 December 1980 | Proposed Changes to Tech Specs,Section 6.0 for Administrative Controls | Safe Shutdown Fire Protection Program |
ML18046A613 | 5 May 1981 | Proposed Revisions to Tech Spec Tables 1 & 2 Re Steam Generator Insp | |
ML18046A818 | 21 July 1981 | Proposed Revisions to Tech Spec Sections 1.0 & 3.10, Specifying New Limits for Radial Peaking Factors & Allowable Linear Heat Rates & Implementation of Excore Detectors for Use in Core Power Distribution Monitoring | Shutdown Margin Fuel cladding |
ML18046A853 | 6 July 1981 | Control Rod Drive Mechanism Dynamic Analysis Rept. | Earthquake |
ML18046B012 | 15 May 1980 | Operation Procedure 0540-001-02 Revision 1, Palisades Nuclear Station-High Energy Line Break Evaluation Phase III, Procedures for Determining Jet Impingement Forces & Pipe Whip Energies. | |
ML18046B013 | 6 June 1980 | Operation Procedure 0540-001-03,Revision 2, Palisades Nuclear Station-High Energy Line Break Evaluation Phase III, Procedures for Evaluating Structural Response of Piping Targets to Pipe Rupture Loadings. | |
ML18046B056 | 12 November 1981 | Proposed Tech Spec Page 4-82 Re Integrity of Sys Outside Containment Likely to Contain Radioactive Fluids | |
ML18046B080 | 31 October 1981 | Containment Bldg Post-Accident Sys 10-Yr Surveillance Rept. | |
ML18046B081 | 24 June 1981 | Surveillance Procedure for Containment Bldg Post-Tensioning Sys. |