MONTHYEARCP-202400030, License Renewal Application Revision 0 - Supplement 3, Revision 12024-01-31031 January 2024 License Renewal Application Revision 0 - Supplement 3, Revision 1 IR 05000445/20230042024-01-29029 January 2024 Integrated Inspection Report 05000445/2023004 and 05000446/2023004 CP-202400034, (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1)2024-01-29029 January 2024 (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1) ML24024A2102024-01-29029 January 2024 Summary of Regulatory Audit Regarding a License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors ML24025A0052024-01-25025 January 2024 Review of the Spring 2023 Steam Generator Tube Inspection Report ML24023A0242024-01-24024 January 2024 Correction to Amendment Nos. 185 and 185 Regarding Implementation of Full Spectrum Loss-of-Coolant Accident Methodology ML24018A1072024-01-18018 January 2024 Notification of Commercial Grade Dedication Inspection (05000445/2024012 and 05000446/2024012) and Request for Information ML23159A2082023-12-20020 December 2023 Request for Withholding Information from Public Disclosure ML23319A3872023-12-20020 December 2023 Issuance of Amendment Nos. 185 and 185 Regarding Implementation of Full Spectrum Loss-of-Coolant Accident (Fsloca) Methodology ML23348A2392023-12-19019 December 2023 Nonacceptance of License Amendment Request to Relocate Technical Specification 3.9.3, Nuclear Instrumentation, to the Technical Requirements Manual CP-202300575, (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 22023-12-13013 December 2023 (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 2 ML23333A0872023-12-13013 December 2023 Transmittal of Dam Safety Inspection Report - Public CP-202300566, (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation2023-12-12012 December 2023 (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation CP-202300494, License Renewal Application Revision 0, Supplement 32023-12-0606 December 2023 License Renewal Application Revision 0, Supplement 3 ML23313A0732023-12-0606 December 2023 Issuance of Amendment Nos. 184 and 184 Regarding Revision to Technical Specifications to Implement WCAP-17661-P-A, Rev. 1, Improved Roac and CAOC Fq Surveillance Technical Specifications ML23291A4382023-11-30030 November 2023 Notice of Availability of the Draft Plant-Specific Supplement 60, to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Comanche Peak Nuclear Power Plant, Unit Numbers 1 and 2, License Renewal Applica ML23325A0182023-11-30030 November 2023 Schedule Revision for the License Renewal Application Review IR 05000445/20234022023-11-30030 November 2023 NRC Security Inspection Report 05000445/2023402 and 05000446/2023402 CP-202300349, License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation2023-11-20020 November 2023 License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation ML23308A0032023-11-17017 November 2023 Letter to R. Nelson, Executive Director; Achp; Re., Comanche Peak Draft Environmental Impact Statement ML23308A0022023-11-17017 November 2023 Letter to M. Wolfe, Executive Director; Shpo; Re., Comanche Peak Draft Environmental Impact Statement ML23317A3002023-11-13013 November 2023 Letter to R. Sylestine, Chairman, Alabama-Coushatta Tribe of Texas Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2972023-11-13013 November 2023 Letter to R. Martin, President, Tonkawa Tribe of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2872023-11-13013 November 2023 Letter to J. Garza, Chairman, Kickapoo Traditional Tribe of Texas Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2832023-11-13013 November 2023 Letter to D. Dotson, President, Delaware Nation Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2852023-11-13013 November 2023 Letter to E. Martinez, President, Mescalero Apache Tribe Regarding Comanche Peak Draft Environmental Impact Statement ML23306A0302023-11-13013 November 2023 Letter to J. Cernek, Chairman; Coushatta Tribe of Louisiana Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2902023-11-13013 November 2023 Letter to M. Pierite, Chairman, Tunica Biloxi Tribe of Louisiana Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2982023-11-13013 November 2023 Letter to R. Morrow, Town King, Thlopthlocco Tribal Town Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2842023-11-13013 November 2023 Letter to D. Kaskaske, Chairman, Kickapoo Tribe of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2822023-11-13013 November 2023 Letter to D. Cooper, Chairman, Apache Tribe of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2962023-11-13013 November 2023 Letter to M. Woommavovah, Chairman, Comanche Nation Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2812023-11-13013 November 2023 Letter to C. Hoskin, Principal Chief, Cherokee Nation; Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2862023-11-13013 November 2023 Letter to J. Bunch, Chief, United Keetoowah Band of Cherokee Indians Regarding Comanche Peak Draft Environmental Impact Statement ML23317A3032023-11-13013 November 2023 Letter to W. Yargee, Chief, Alabama-Quassarte Tribal Town Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2882023-11-13013 November 2023 Letter to L. Johnson, Chief, Seminole Nation of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A3012023-11-13013 November 2023 Letter to S. Yahola, Mekko, Kialegee Tribal Town Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2792023-11-13013 November 2023 Letter to B. Gonzalez, Chairman, Caddo Nation Regarding Comanche Peak Draft Environmental Impact Statement ML23317A3022023-11-13013 November 2023 Letter to T. Parton, President, Wichita and Affiliated Tribes Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2892023-11-13013 November 2023 Letter to L. Spottedbird, Chairman, Kiowa Indian Tribe Regarding Comanche Peak Draft Environmental Impact Statement ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23360A6312023-10-26026 October 2023 FEMA, Submittal of Radiological Emergency Preparedness Final Report for the Comanche Peak Nuclear Power Plant Medical Services Drill Evaluated on August 23, 2023 CP-202300416, Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements2023-10-12012 October 2023 Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements CP-202300432, Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 42023-10-0404 October 2023 Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 4 ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23263A0242023-09-21021 September 2023 Revision of Schedule for the Environmental Review of the Comanche Peak Nuclear Power Plant Units 1 and 2 License Renewal Application 2024-01-31
[Table view] |
Text
Rafael Flores Senior Vice President& Chief Nuclear Officer rafael.flores@luminant.com Luminant Power P 0 Box 1002 6322 North FM 56 Glen Rose, TX 76043 Luminant T 254 897 5550 C 817 559 0403 F 254 897 6652 CP-201101107 TXIX-11099 Ref: 1OCFR50.54(a)
August 10, 2011 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555
SUBJECT:
COMANCHE PEAK NUCLEAR POWER PLANT (CPNPP)DOCKET NOS. 50-445 AND 50-446 RESPONSE TO A REQUEST FOR ADDITIONAL INFORMATION RELATED TO THE REQUEST FOR A CHANGE TO THE QUALITY ASSURANCE PLAN INVOLVING A REDUCTION IN COMMITMENT
REFERENCES:
- 1. Letter logged TXX-11014, dated May 3, 2011, from Rafael Flores of Luminant Power to the NRC requesting a change to the Quality Assurance Plan.2. Request for Additional Information from Balwant Singal, NRR, via e-mail dated July 11, 2011.
Dear Sir or Madam:
In reference 1 above, Luminant Generation Company LLC (Luminant Power) requested a change to the Quality Assurance (QA) Program, as provided in FSAR Chapter 17.The proposed QA Program change revises FSAR section 17.2.15, "Nonconforming Material, Parts, or Components," and an associated commitment, to allow use of a conditional release to install a nonconforming item in the plant, and declare the affected component operable per Technical Specifications, provided that an evaluation of the nonconforming condition supports Technical Specification operability.
Reference 2 provided Luminant Power with a request for additional information from the Nuclear Regulatory Commission that is needed to review the QA Program change request. This letter provides the additional information requested in reference 2 in an attachment.
In accordance with 1OCFR50.4(b)(7), a copy of this correspondence, with attachment, is being provided to the NRC Region IV Office and the CPNPP NRC Resident Inspectors.
This communication contains no new commitments.
Should have any questions regarding this submittal, please contact Tom Daskam at (254) 897-0348.QOOL/
U.S. Nuclear Regulatory Commission TXX- 11099 Page 2 of 4 8/10/2011 I state under penalty of perjury that the foregoing is true and correct.Executed on August 10, 2011.Sincerely, Luminant Generation Company, LLC Rafael Flores By: Mitch Lucas Site Vice President Attachment
-RESPONSE TO A REQUEST FOR ADDITIONAL INFORMATION RELATED TO THE REQUEST FOR A CHANGE TO THE QUALITY ASSURANCE PLAN INVOLVING A REDUCTION IN COMMITMENT c -E. E. Collins, Region IV Balwant Singal, NRR Resident Inspectors, CPNPP U.S. Nuclear Regulatory Commission TXX- 11099 Page 3 of 4 8i10/2011 ATTACHMENT to TXX-11099 RESPONSE TO A REQUEST FOR ADDITIONAL INFORMATION RELATED TO THE REQUEST FOR A CHANGE TO THE QUALITY ASSURANCE PLAN INVOLVING A REDUCTION IN COMMITMENT U.S. NucLear ReguLatory Commission TXX- 11099 Page 4 of 4 811012011 NRC Request for Additional Information:
Appendix B to Title of Code of Federal regulations (10 CFR), Part 50, Criterion 15, states in part,"measures shall be established to control materials, parts, or components which do not conform to requirements in order to prevent their inadvertent use or installation." Clarify how installing, testing and allowing for a nonconformity item to be declared operable based on Technical Specification operability satisfies the requirements of Appendix B to 10 CFR Part 50.CPNPP Response: The proposed change to the FSAR, section 17.2.15, "Nonconforming Materials, Parts, or Components," affects only subsection 5 on conditional releases, and does not alter the other 17.2.15 subsections, which address various measures for controlling nonconforming items, including:
identification, tagging, segregation, documentation, re-inspection, testing, operability review, and disposition of the nonconformance, among others. The current FSAR, section 17.2.15, subsection 5, addresses conditional releases of nonconforming items, and this section contains some of the program controls to prevent inadvertent use or installation of nonconforming items. The proposed change to FSAR, section 17.2.15, subsection 5, as discussed further below, continues to provide adequate controls to prevent inadvertent use or installation of nonconforming items. CPNPP FSAR section 17.2.15 currently satisfies 10CFR50, Appendix B, Criterion 15, and the proposed FSAR section 17.2.15, if approved, will continue to satisfy this 10CFR50 requirement.
The proposed change to FSAR, section 17.2.15, subsection 5, would revise the current conditional release provision and allow for a conditional release of a nonconforming item from the warehouse for installation, testing, and operation, and allow taking Technical Specification credit for use of the nonconforming item, provided that: 1) resolution of the nonconforming condition is tracked in the Corrective Action Program, and 2) an Operability evaluation that meets the NRC Part 9900 Technical Guidance for assessing degraded or nonconforming conditions for potential impact on Operability is completed prior to taking Technical Specification credit for the nonconforming item. This change in the conditional release program allows Technical Specification credit to be taken for use of a nonconforming item, where the nonconformance does not adversely impact those characteristics required for SSC Operability.
With the additional requirement to complete a satisfactory Operability evaluation prior to taking Technical Specification credit for the nonconforming item, the proposed FSAR program for conditional release of nonconforming items is comparable to the current FSAR program requirements.
The change will also provide additional plant operational flexibility, and may prevent unnecessary plant mode changes and shutdowns.