2011/05/23 Watts Bar 2 OL - FW: NRC Bucket List and Sser 22/23 for 5/26/11
ML11165A141
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 05/23/2011
From:
Office of Nuclear Reactor Regulation
To:
Division of Operating Reactor Licensing
References
Download: ML11165A141 (17)


Text

1 WBN2Public Resource From: Poole, Justin Sent: Monday, May 23, 2011 10:12 AM To: Epperson, Dan Cc: WBN2HearingFile Resource

Subject:

FW: NRC Bucket List and SSER 22/23 for 5/26/11 Attachments:

NRC PM Open Items List 5-26-11.docx; U pdated SSER 22-23 Open Items Plan 5-23-11.docx JustinC.PooleProjectManagerNRR/DORL/LPWBU.S.NuclearRegulatoryCommission(301)4152048email:Justin.Poole@nrc.gov From: Crouch, William D [1]

Sent: Saturday, May 21, 2011 8:54 AM To: Poole, Justin; Milano, Patrick; Campbell, Stephen Cc: Adair, James G; Arent, Gordon; Beach, Charles D; Bryan, Robert H Jr; Detchemendy, Thomas F; Elliott, Walter L Jr; Elton, Thomas L; Freeman, Edwin E; Glover, Christopher Edmund; Helms, Douglas F; Hemmer, Gerald L Jr; Henrich, Nolan T Jr; Hilmes, Steven A; Johnson, Robert M; Jones, Dennis Michael; Knuettel, Edward Terry; Koontz, Frank A Jr; Metzler, Ernest Thomas; Miller, Lee R; Olson, Peter Edwin; Riedl, Christopher John; Schlessel, Jerry V; Shea, Joe; Smith, James D; Snyder, Laura L; Spink, Thomas E; Stephenson, Catherine L; Stinson, Kelly David Jr; Stockton, Rickey A; Tinley, Mary Darlene; Woods, Steven E

Subject:

NRC Bucket List and SSER 22/23 for 5/26/11 SeeattachedupdatedlistswithlatestforecastdatesWilliam D. (Bill) Crouch(423)365 2004WBN(256)777 7676Cell Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 385 Mail Envelope Properties (19D990B45D535548840D1118C451C74D83F07630B9)

Subject:

FW: NRC Bucket List and SSER 22/23 for 5/26/11 Sent Date: 5/23/2011 10:11:58 AM Received Date: 5/23/2011 10:12:00 AM From: Poole, Justin Created By: Justin.Poole@nrc.gov Recipients: "WBN2HearingFile Resource" <WBN2HearingFile.Resource@nrc.gov>

Tracking Status: None "Epperson, Dan" <Dan.Epperson@nrc.gov> Tracking Status: None Post Office: HQCLSTR02.nrc.gov

Files Size Date & Time MESSAGE 1118 5/23/2011 10:12:00 AM NRC PM Open Items List 5-26-11.docx 35574 Updated SSER 22-23 Open Items Pl an 5-23-11.docx 33270 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received:

Page 1 of 6 NRC PM Open Items List 5/26/11 (423) 751-6338 ID 657601 No. Description Status Additional Comments Resp Org/Person 1. Cyber Security Plan/Controls and Implementation Assess CDAs/Identify Mods 2/28/11A RAI Response 4/7/11A

Plan for Common Systems 6/7/11 Identify Required Exemptions

Scope Mods 5/31/11

TI issued

5/30/11 NRC Table Top/Pilot

Oct 2011

Procedures complete 9/30/11

Update Cyber Security Plan IAW NEI 08-09 Rev 6 per NRC letter dated 5/24/10. NRC Inspection in 2011

Provide update to change commitment for April ready for Inspection

Response to 3 Generic RAIs

Heinrich/Snyder (Bryan)

Page 2 of 6 No. Description Status Additional Comments Resp Org/Person Inspection Dec 2011 2. Instrumentation RAI List (Knuettel)

Ongoing 5/20/11A 6/8/11 6/17/11 6/3/11 RAI Responses Provide proprietary Westinghouse presentation Provide requested WINCISE Proprietary Documents Provide non-prop versions NRC review draft RAIs for deletions Eng/Hilmes (Smith) 3. Resolve Licensing Basis Preservation Self Assessment PERs (Crouch) 5/27/11 TVA to provide QA audit results Eng/Freeman (Smith) 4. Status of GSI 199 Eastern Seismicity (Crouch) 6/12/11 TVA/NRR 5. Complete Implementation (Hemmer)

RAI Response 3/29/11A RAI Clarification for Fuel Question 2 5/9/10A Diesel 6/1/11 Pump Relocation 6/17/11 Procedures Issued 6/30/11 Respond to RAI Implement two unit commitments.

Provide updated information for tables contained in the 6/29/07 and 7/1/10 letters.

Letter did not address Phase I commitments Hemmer (Smith)

Page 3 of 6 No. Description Status Additional Comments Resp Org/Person Inspection -

August 2011 Phase I commitments 8/1/11 6. Provide feedback on the status of NRC review of Integrated Safeguards Test submittal SSER 23 NRC to provide status of review in SSER 23 NRR 7. Document Control Issues for two letters 6/15/11 7/15, 10/5, 10/21 and 10/29 letters. NRC to reprint 7/15 letter and provide to NRC Document control.

TVA/Bechtel to provide non-proprietary version of documents that can be released to the public. TVA to provide revised letter that says non-prop once prop documents removed. NRC action to contact Kenny Nguyen, NRC Document Control regarding A102. Licensing/Boyd 8. Chapter 15.5 RAIs 12/10/10A RAI response 6/5/11 Additional question regarding meteorology data from 2008-2009 Wastrack (Bryan) 9. Fire Protection Report Questions regarding OMA 3/31/11A 5/6/11A 5/18/11A 6/17/11 5/27/11 6/7/11 TBD Justification Criteria Set 3 RAIs FPR Justifications Set 4A RAIs Set 4B RAIs Set 5 RAIs ENG/Hilmes (Crouch) 10. IST Tech Spec Change 5/27/11 TVA Corporate Licensing (Shea) 11. Environmental Phone call to discuss intake flow rate/velocity at IPS and 4/28/11A Responded to RAI and attached revised Impingement Report Environmental/

Hopping Page 4 of 6 No. Description Status Additional Comments Resp Org/Person SCCW in EIS versus NPDES. (Bryan) 12. Tech Spec Revisions from latest T/S markup and NRC Review comments 5/10/11A 6/10/11 Meeting Submittal Licensing/Elton (Bryan) 13. ASME III to XI transition Need NRC Letter When does ISI program begin with partial plant N-3?

Are repairs/mods after N-5 controlled under Section III or Section XI? The timing for the NIS-2 in the letter does not comply with the ASME Code . The NIS-2 must be before commercial operation. Eng/Helms (Crouch) 14. Chapter 15 RAI on Dose calc basis 5/26/11 Bechtel (Fredrick) preparing answer.

Eng/Koontz (Bryan) 15. Chapter 11/FSEIS RAIs 5/11/11A 5/20/11A 6/3/11 5/24/11 5/24/11 Public Meeting 5/11/11 Chapter 11/EIS Letter X/Q info in FSAR Chapter 11 RAI List X/Q to 50 miles Chem/Woods (Bryan) 16. Hydrology sand bag question 4/20/11A 5/11/11A 5/20/11A

5/23/11 Five RAI questions

NRC Visit to Knoxville/TVA dam

NRC Info Request

NRC Calc Request Corp/Selman 17. Letter to notify NRC when Vital Area Boundary returned to original location 5/31/11 Date for schedule Lic/Crouch 18. Part 70 License 6/10/11 4/29/11 NRC to issue Part 70 license.

NRC question related to dry versus wet storage.

TVA issued letter regarding placement of new Unit 2 fuel in new fuel vault and SFP.

Milano 19. ACRS Topics Improvements, Inspection status, Refurb status, Construction Status, Japan, IST Re-Presentation, Page 5 of 6 No. Description Status Additional Comments Resp Org/Person Cyber Security 20. SAMDA RAIs 05/11/11A 05/13/11A 5/25/11 Meeting on 5/11/11 1st Submittal 2nd Submittal

21. SSER 22/23 Open Items Response 6/3/11 Addresses 15 Open Items - Need item 69 clarification
22. Chapter 12 RAI on Instrument Channel Operability Tests 6/24/11 ENG/Hilmes 23. Transient Analysis issues Overpressurization Boron Info Inadvertent SI CVCS Malfunction Steam line break Proprietary review of audit report Audit Report Response Audit Report Follow up Questions Additional Follow up Questions 4/1/11A 3/25/11A 4/29/11A 4/29/11A 5/13/11A 4/22/11A 5/13/11A 5/23/11 TBD ENG/Koontz WEC/Morgan 24. Sump Strainer Loads RAI 4/28/11A Eng/Helms (Bryan) 25. Sump Strainer Flow RAI 4/28/11A Eng/Helms (Bryan) 26. NRR/Region assign SSER 22 items 1, 4, 7, 9, 11, 19, 21, 38 5/17/11A Issue resolved at 5/17/11 NRC meeting Milano 27. FSAR A104 6/3/11 Lic/Stockton 28. IEB 88-02 SG Tube Cracking TBD What are the SG inspection plans in light of the experience with a French reactor exhibiting SG tube cracking early? Is TVA planning to change the Corp SG/ Webber ISI/Tinley Page 6 of 6 No. Description Status Additional Comments Resp Org/Person inspection plan due to this operating experience? 29. Develop list of planned License Conditions, Exemptions and Relief Requests (Crouch) 9/1/11 Review Unit 1 SER for exemptions. NRR/TVA (Bryan) 30. Submit final REP prior to fuel load (Spink) Complete Complete 10/1/11 NRR to determine if submittal has to occur before License rather than before fuel load.
1. Fix Section 6.0, Event 6.2 in Rev 92xx.
2. Submit Final REP and EPIPs 180 days prior to OL.

EP/ Detchemendy (Bryan) 31. Issue two Unit Offsite Dose Calculation Manual (Beach) Review TS Chapter 5 programs also 9/1/11 Chemistry/

Woods (Bryan) 32. Copy of Site Plan for NSR TBD Fire Ops/Sterchi 33. Issue Unit 2 Completion Letter (Crouch) 3/1/12 Licensing 34. Combined U1/U2 FSAR (Stockton) 3/1/12 Licensing 35. Submit final as-constructed FSAR figures 10/1/11 Licensing/ Stockton 36. Verify Tech Spec Setpoints match calcs 8/1/11 Eng/Hilmes (Bryan) 37. Letter to terminate Part 30/40 License after receipt of Part 50 License 4/1/12 Licensing (Crouch) 38. Discuss IPS velocity calc at 5/11 mtg 5/11/11A 5/19/11A Discussed at meeting Provide submittal to describe intake configuration Lic (Bryan) 39. Provide date of Unit 1 PASS T/S submittal and NRC SER date 5/3/11A Provide NRC SER to NRR via e-mail Licensing/ Stockton (Crouch) 40. Provide feedback on need to revise submittal regarding testing of non-EQ hand switches.

5/4/11A See e-mail from Crouch dated 5/2/11.

NRR reviewed determined no need to revise submittal or NRC July 2 letter.

Milano SSER 22/23 Open Item Plan 5/23/11 Items with the Organization s haded are inspection related Item Question/Issue Lead Action Plan (1) letter in folder Review evaluations and corrective actions associated with a power assisted cable pull. (NRC safety evaluation dated August 31, 2009, ADAMS Accession No.

ML092151155) Const Complete - Addressed by Maximo Commitment Closure package 10181059

(2) letter in folder Conduct appropriate inspection activities to verify cable lengths used in calculations and analysis match as-installed configuration. (NRC safety evaluation dated August 31, 2009, ADAMS Accession No. ML092151155) Elec Provide NRC Residents access to as-constructed ICRDS database and associated calcs.

Due date:02/29/2012 (Khan)

Note: Pending completion of the cable pull effort and updating ICRDS for as-installed cable lengths by construction.

(4) letter in folder Conduct appropriate inspection activities to verify that TVA's maximum SWBP criteria for signal level and coaxial cables do not exceed the cable manufacturers maximum SWBP criteria. (NRC safety evaluation dated August 31, 2009, ADAMS Accession No. ML092151155)

Elec/ Const Complete - Close to Inspection Report 20100604 (7) letter in folder Verify commitment completion and review electrical design calculations. (TVA letter dated October 9, 1990, ADAMS Accession No. ML073551056) Elec See commitments in TVA Letter.

Provide NRC Residents a copy of related electrical calculation procedures

and provide NRC access to calculations

Due date: 8/1/11 (Khan)

(9) pg 13-2 Confirm that education and experience of management and principal supervisory positions down through the shift supervisory level conform to Regulatory Guide 1.8. (Section 13.1.3)

Lic Obtain education and experience information from WBN Human Resources and provide info to NRC Residents.

Due date: 7/15/11 (Elton)

(10) pg 13-2 Confirm that TVA has an adequate number of licensed and non-licensed operators in the training pipeline to support the preoperational test program, fuel loading, and dual unit operation. (Section 13.1.3)

Ops Provide submittal that confirms we have adequate personnel in the pipeline.

Due date: 7/15/11 (Wallace)

(11) pg 13-2 The plant administrative procedures should clearly state that, when the Assistant Shift Engineer assumes his duties as Fire Brigade Leader, his control Ops Provide NRC Residents copy of procedure that provides the controls of this function.

room duties are temporarily assumed by the Shift Supervisor (Shift Engineer), or by another SRO, if one is available. The plant administrative procedures should clearly describe this transfer of control room duties. (Section 13.1.3)

Due date: 7/15/11 (Wallace)

(12) pg 25-3 TVA's implementation of NGDC PP-20 and EDCR Appendix J is subject to future NRC audit and inspection. (Section 25.9) LIC Provide self assessment related PER closure packages to Licensing for NRR review.

Due date: 6/15/11 (Smith)

(13) pg 3-11 TVA is expected to submit an IST program and specific relief requests for WBN Unit 2 nine months before the projected date of OL issuance. (Section 3.9.6) ISO Provide submittal addressing IST program and relief requests.

Due date: 7/15/11 (Tinley)

(16) pg 3-12 3-13 Based on the uniqueness of EQ, the NRC staff must perform a detailed inspection and evaluation prior to fuel load to

determine how the WBN Unit 2 EQ

program complies with the requirements of 10 CFR 50.49. (Section 3.11.2) Elec Provide NRC Residents copies of EQ documents as requested for the onsite inspections.

Due date: Ongoing Inspection (Khan)

(17) pg 3-13 The NRC staff should verify the accuracy of the WBN Unit 2 EQ list prior to fuel load. (Section 3.11.2.1) Elec Provide NRC Residents copies of EQ documents as requested for the onsite inspections.

Due date: Ongoing Inspection (Khan)

(19) pg 3-14 The NRC staff should complete its review of TVA's EQ Program procedures for

WBN Unit 2 prior to fuel load. (Section 3.11.2.2.1) Elec Provide NRC Residents copies of EQ documents as requested for the onsite inspection Complete - Expect NRC to close in next inspection report

(21) pg 3-14 The NRC staff should confirm that the Electrical Penetration Assemblies (EPAs) are installed in the tested configuration, and that the feedthrough module is manufactured by the same company and is consistent with the EQ test report for the

EPA. (Section 3.11.2.2.1) Elec Provide NRC Residents copies of EQ documents as requested for the onsite inspection

Due date: 5/20/11 (Khan)

(25) pg 22-1 Prior to the issuance of an operating license, TVA is required to provide satisfactory documentation that it has obtained the maximum secondary liability insurance coverage pursuant to 10 CFR 140.11(a)(4), and not less than the

amount required by 10 CFR 50.54(w) with respect to property insurance, and the

NRC staff has reviewed and approved the documentation. (Section 22.3) Lic Provide Insurance coverage submittal.

Due date: 10/1/11 (Smith)

(29) pg 8-8 Provide a detailed description of the transmission system grid conditions and the operating characteristics of the offsite power supply at the Watts Bar Hydro (for dual-unit operation), including the operating voltage range, post contingency voltage drops (including bounding values and post-unit trip values), and operating frequency range. Provide the design operating voltage range of the shutdown boards (minimum and maximum voltage) and information regarding how low the

Watts Bar Hydro Station voltage could drop (assuming operation of the LTCs) while still supplying the worst-case shutdown board loads at the minimum design voltage of the shutdown boards.

The summary of the grid studies should address dual-unit operation, the transmission network interface available fault current changes, and the impact on the switchyard and plant switchgear and cabling. (Section 8.2.2) Elec Provide response for submittal to NRR

Due date: 7/15/11 (Hilmes)

(30) pg 8-10 TVA should confirm that all other safety-related equipment (in addition to the Class 1E motors) will have adequate starting and running voltage at the most limiting safety related components (such as motor operated valves, contactors, solenoid

valves or relays) at the degraded voltage

relay setpoint dropout setting. TVA should also confirm that the final Technical Specifications are properly derived from these analytical values for the degraded voltage settings. (Section 8.3.1.2) Elec Provide response for submittal to NRR.

Due date: 8/1/11 (Hilmes)

Note: This issue is with Corporate Licensing to resolve on Unit 1. Unit 2 resolution will be the same as it is for

Unit 1. (32) pg 8-14 TVA should provide to the NRC staff the details of the administrative limits of EDG voltage and speed range, and the basis for its conclusion that the impact is negligible, and describe how it accounts for the administrative limits in the Technical Specification surveillance

requirements for EDG voltage and frequency. (Section 8.3.1.14)

Elec Provide response for submittal to NRR.

Due date: 8/1/11 (Hilmes)

(35) pg 10-9 TVA should provide information to the NRC staff that the CCS will produce feedwater purity in accordance with BTP MTEB 5-3 or, alternatively, provide justification for producing feedwater purity to another acceptable standard. (Section

10.4.6) Mech/ Chem Complete - A104 Update received (37) pg 13-8 The NRC staff will review the combined WBN Unit 1 and 2 Appendix C prior to issuance of the Unit 2 OL to confirm (1) that the proposed Unit 2 changes were incorporated into Appendix C, and (2) that changes made to Appendix C for Unit 1 since Revision 92 and the changes made to the NP-REP since Revision 92 do not affect the bases of the staff's findings in this SER supplement. (Section 13.3.2) REP Submit final Unit 1/2 REP to NRC

Due date: October 1, 2011 (38) pg 13-14 The NRC staff will confirm the availability and operability of the ERDS for Unit 2 prior to issuance of the Unit 2 OL. (Section

13.3.2.6) REP The Emergency Response Data System software has previously been modified and tested for the Watts Bar Unit 2 addition. This unit can be selected from the ERDS menu to send data to the

NRC at this time. In addition, the

software has been developed and tested to send data from the WBN PEDS to the CECC. However, the official list of points for Watts Bar Unit 2 has not been provided by Unit 2 Design Engineering and, until this has been completed and submitted to the Computer Engineering Group for addition to the ERDS software, official testing of the software for this unit

cannot be completed with the NRC in order to declare the WBN ERDS Unit 2 operational. This list is derived from the official Data Point List. Once developed, Unit 2 Licensing submits the data to the NRC. Once this list has been

received by the NRC, it would require one month to add the list to the NRC data systems, write the test, schedule the test with TVA/NRC, run the test, and TVA submit the results.

Due date: 10/1/11 (39) pg 13-14 The NRC staff will confirm the adequacy of the communications capability to

support dual unit operations prior to issuance of the Unit 2 OL. (Section

13.3.2.6) REP Provide NRC Residents copies of related documents as requested for the onsite inspection. This item is covered

by the response to Item 38

Due date: See Item 38 (40) pg 13-15 The NRC staff will confirm the adequacy of the emergency facilities and equipment to support dual unit operations prior to issuance of the Unit 2 OL. (Section

13.3.2.8) REP Perform self assessment to verify processes and materials in main control room, TSC, OSC, EOF and local recivery facility. Provide NRC Residents copies of self assessment documents for the onsite inspection.

Due date: 10/1/11 (41) pg 13-16 TVA committed to (1) update plant data displays as necessary to include Unit 2, and (2) to update dose assessment models to provide capabilities for assessing releases from both WBN units. The NRC staff will confirm the adequacy of these items prior to issuance of the Unit 2 OL. (Section 13.3.2.9)

Computer Eng REP 1) Provide demonstration of capability of SPDS, ICS and PEDS data system displays for Unit 2.

Due date:

2) Submit EPIP-13. Describe RED, FRED and BRED data systems..

Due date: 10/1/11 (42) pg 13-16 The NRC staff will confirm the adequacy of the accident assessment capabilities to support dual unit operations prior to issuance of the Unit 2 OL. (Section

13.3.2.9)

Computer Eng Covered by Item 41 (1)

Due date: See Item 41(1)

(43) pg 13-23 Section V of Appendix E to 10 CFR Part 50 requires TVA to submit its detailed implementing procedures for its emergency plan no less than 180 days before the scheduled issuance of an

operating license. Completion of this requirement will be confirmed by the NRC staff prior to the issuance of an operating license. (Section 13.3.2.18) REP Submit Unit 1/2 REP implementing procedures (EPIP-1 thru EPIP-17) to NRC Due date: October 1, 2011 (Detchemendy)

(47) pg 6-12 The NRC staff noted that TVA's changes to Section 6.2.6 in FSAR Amendment 97, regarding the implementation of Option B of Appendix J, were incomplete, because several statements remained regarding

performing water-sealed valve leakage tests "as specified in 10 CFR [Part] 50, Appendix J." With the adoption of Option B, the specified testing requirements are no longer applicable; Option A to Appendix J retains these

requirements. The NRC discussed this discrepancy with TVA in a telephone conference on September 28, 2010. TVA stated that it would remove the inaccurate reference to Appendix J for specific water

testing requirements in a future FSAR amendment. (Section 6.2.6) Lic Complete - A104 Update received (48) pg 6-15 The NRC staff should verify that its conclusions in the review of FSAR Section 15.4.1 do not affect the conclusions of the staff regarding the acceptability of Section 6.5.3. (Section

6.5.3) LIC Complete - No TVA action Licensing to address in next SSER update letter (49) letter in folder The NRC staff was unable to determine how TVA linked the training qualification

requirements of ANSI N45.2-1971 to TVA

Procedure TI-119. Therefore, the implementation of training and qualification for inspectors will be the subject of future NRC staff inspections.

(NRC letter dated July 2, 2010, ADAMS Accession No. ML101720050) Mech Provide NRC Residents how the refurb training requirements are linked to the ANSI standard. Provide the training records for refurb inspectors.

Due date: June 15, 2011 (Moll)

(50) letter in folder TVA stated that about 5 percent of the anchor bolts for safety-related pipe supports do not have quality control documentation, because the pull tests have not yet been performed. Since the documentation is still under development, the NRC staff will conduct inspections to follow-up on the adequate implementation of this construction refurbishment program requirement. (NRC letter dated July 2, 2010, ADAMS Accession No.

ML101720050) Const Notify NRC Residents of anchor bolt pull tests. Due date: July 1, 2011 (Adair)

(51) letter in folder The implementation of TVA Procedure TI-119 will be the subject of NRC follow-up inspection to determine if the construction refurbishment program requirements are being adequately implemented. (NRC letter dated July 2, 2010, ADAMS Accession No. ML101720050) Mech Provide NRC Residents the results of the refurb program.

Due date: Ongoing Inspection (Moll) 52 draft TVA should provide an update to the FSAR replacing Table 12.2-3 with the expected source strength val ues of the freshly irradiated IITAs. (Section 12.3)

I&C Complete - A104 Update received

53 draft TVA should provide an update to the FSAR reflecting the information provided in its letter dated October 4, 2010, regarding the WBN radiation protection design features, including controlled access areas, decontamination areas, and onsite laboratories and counting rooms. (Section 12.4) Rad Pro Provide update to FSAR based on 10/4/10 letter to NRC.

Due Date: June 15, 2011 (Grim) 54 draft TVA should provide adequate technical justification to the staff to relax the frequency of the radiation monitor channel quarterly operability tests. TVA should provide sufficient information to the staff to determine that the protable airborne radiation monitors comply with the requirements of 10 CFR 20.1501. TVA should provide sufficient information for the staff to determine that the licensing or TVA program requirements for the calibration and

operability testing of ar ea radiation monitors are sufficient to meet the regulatory I&C Provide requested info using correct methodology

Due Date: June 30, 2011 (Hilmes) requirements of 10 CFR 20.1501. (Section 12.4) 55 draft TVA should provide sufficient information to the staff to demonstr ate that the two area radiation monitors for the Spent Fuel Pit comply with the requirements of 10 CFR 70.24 and 10 CFR 50.68 for radiation monitoring in areas where fuel is handled or stored. (Section 12.4)

Lic Complete - Info provided by Question 27 of 2/25/11 letter

56 draft TVA should update the FSAR to reflect the information regarding the dose assessment program provided in its letter the NRC dated June 3, 2010. (Section 12.5)

Lic Complete - TVA does not believe an FSAR update is warranted. The info in the 6/3/10 letter is merely confirming

that the WBN Unit 1/2 history meets the requirements of the FSAR.

57 draft TVA should update the FSAR to reflect the qualification standards of the RPM as provided in its letter to the NRC dated October 4, 2010. (Section 12.6)

Lic Develop FSAR change from 10/4/10 submittal - Question 12-13.

Due Date: 5/27/11 (Stockton) 58 draft The staff has insufficient information to conclude that TVA has taken appropriate actions to reduce radiation levels and

increase the capabilit y of operators to control and mitigate the consequences of an accident at WBN Unit 2, in accordance with the guidance of NUREG-0737, Item II.B.2, or can maintain occupational doses to plant operators within the requirements of GDC 19. Therefore, the staff cannot conclude that the plant shielding for WBN Unit 2 is

acceptable. (Section 12.7.1)

Lic Discussion in progress with NRC regarding this item versus Item 53 (apparent contradiction in the questions).

Provide requested info

Due Date:

59 draft The staff's evaluation of the compatibility of the ESF system materials with containment sprays and core cooling water in the event of a LOCA is incomplete pending resolution of GSI-191 for WBN Unit 2. (Section 6.1.1.4)Mech Complete - Addressed by TVA letter dated 3/4/11, question 3.o.1 60 draft TVA should amend the FSAR description of the design and operation of the spent fuel pool cooling and cleanup system in FSAR Section 9.1.3 as proposed in its December

21, 2010, letter to the NRC. (Section 9.1.3) Lic Complete - A103 provided update 61 draft TVA should provide information to the NRC staff to demonstrate that PAD 4.0 can conservatively calculate the fuel temperature and other impacted variables, such as stored energy, given the lack of a fuel thermal conductivity degradation model.

(Section 4.2.2.1) Lic Complete - This will be addressed by a License Condition 62 draft Confirm TVA's change to FSAR Section 10.4.9 to reflect its intention to operate with each CST isolated from the other. (Section 10.4.9) Lic Complete - A103 provided update 63 draft TVA should confirm to the NRC staff that testing prior to Unit 2 fuel load has demonstrated that two-way communications is impossible with the Eagle 21

communications interfac

e. (Section 7.2.1.1) I&C Provide requested info

Due Date: 6/16/11 for plan 64 draft TVA stated that, "Post modification testing will be performed to verify that the design change corrects the Eagle 21, Rack 2 RTD accuracy issue prior to WBN Unit 2 fuel load." The issue is open pending NRC staff review of the testing results. (Section

7.2.1.1) I&C Provide requested info Due Date: Need FDCN date from Westinghouse 65 draft TVA should provide justification to the staff regarding why different revisions of WCAP-13869 are referenced in WBN Unit 1 and Unit 2. (Section 7.2.1.1) I&C Provide requested info Due Date: 6/15/11 (Hilmes) 66 draft TVA should clarify FSAR Section 9.2.5 to add the capability of t he UHS to bring the non accident unit to cold shutdown within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. (Section 9.2.5) Lic Complete - A102 provided update to FSAR Section 9.2.2.4 to cover this question for both ERCW and CCS.

67 draft TVA should confirm, and the NRC staff should verify, that the component cooling booster pumps for Unit 2 are above PMF level. (Section 9.2.2) Civil Provide EDCR closure documentation for installation of CCS thermal barrier booster pump dike.

Due Date:

68 draft TVA should clarify to the NRC staff how the CSS complies with GDC 5. (Section 9.2.2) Lic Complete - A102 provided update 69 draft The WBN Unit 2 RCS vent system is acceptable, pending verification that the

RCS vent system is installed. (Section 5.4.5) Mech Provide EDCR closure documentation for installation of ECCS vents. EDCR numbers 52637 (RHR) [P3 Completion Date 6/7/11], 53311 (SI) [P3 Completion

Date 8/25/11]

Due Date: See above 70 draft TVA should provide the revised WBN Unit 2 PSI program ASME Class 1, 2, and 3 Supports "Summary Tables," to include numbers of components so that the NRC

staff can verify that the numbers meet the reference ASME Code. (Section 3.2.3 of Appendix Z of this SSER) ISO Provide requested info

Due Date: 11/1/11 (Tinley) 71 draft TVA should confirm to the staff the replacement of the current Unit 2 clevis insert bolts to the latest design, which uses an X-750 alloy with an HTH process, rolled threads, and a larger radius on the undercut of the cap screw he ad. (Section 3.9.5) Lic Complete - Letter issued 4/21/11 72 draft Based on its review, the staff asked TVA several questions regarding the ICC instrumentation. TVA responded to the staff questions by letter dated October 26, 2010 (ADAMS Accession No. ML103020322). Lic Open pending NRC review The NRC staff has not completed the review of the additional information provided by TVA. The staff will provide its evaluation after completion of that review. (Section

4.4.8) 73 draft The NRC staff will inspect to confirm that TVA has completed the WBN Unit 2 EOPs

prior to fuel load. (Section 7.5.3) Ops Provide copies of EOPs for inspection.

Due Date: (Wallace) 74 draft The NRC staff will verify installation of the acoustic-monitoring system for the power-operated relief valve (PORV) position indication in WBN Unit 2 before fuel load.

(Section 7.8.1) I&C Provide EDCR closure documentation for installation of acoustic monitors.

Panels installed 5/18/11 Probes not installed

Due Date:

75 draft The NRC staff will verify that the test procedures and qualification testing for auxiliary feedwater initiation and control and flow indication are completed in WBN Unit 2 before fuel load. (Section 7.8.2) PreOp Provide copies of test procedures for inspection.

Due Date: (Olson) 76 draft The NRC staff will verify that the derivative time constant is set to zero in WBN Unit 2 before fuel load. (Section 7.8.3) I&C Provide EDCR closure documentation for setting of time constant.

Due Date: