MONTHYEARML15205A2872015-07-15015 July 2015 License Amendment Request - Cyber Security Plan Implementation Schedule Project stage: Request ML16105A0492016-04-13013 April 2016 E-mail Planned Issuance of NRC License Amendment for Pilgrim - Revision of the Cyber Security Plan Implementation Schedule Milestone 8 Project stage: Other ML16082A4602016-06-0606 June 2016 Issuance of Amendment Cyber Security Plan Implementation Schedule Project stage: Approval ML17101A6082017-03-30030 March 2017 License Amendment Request - Cyber Security Plan Implementation Schedule Project stage: Request 2016-04-13
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML22335A2802022-11-0404 November 2022 11-4-2022 Email Transmitting Draft Questions Pertaining to Pilgrim ISFSI Exemption Request ML22270A0422022-09-26026 September 2022 Acknowledgement Email for Holtecs Request for Reporting Exemption with Regards to the Pilgrim ISFSI Annual Radioactive Effluent Release Report (Docket No. 05000293) ML22154A1622022-05-26026 May 2022 Letter and Email from Save Our Bay/Diane Turco Regarding Irradiated Water Release from Pilgrim ML22007A2602021-12-0606 December 2021 E-mail from P. Obrien, Holtec, to A. Snyder, NRC, on Pilgrim Effluent Discharge ML21287A6192021-10-14014 October 2021 E-mail from S. Phillips, MEMA, to A. Snyder, NRC, Pilgrim Nuclear Power Station, Commonwealth of Massachusetts Consultation Response to Amendment Review for Emergency Preparedness ML21266A2512021-09-23023 September 2021 Consultation with Commonwealth of Massachusetts Regarding Proposed Amendment Application for Emergency Plan and Emergency Action Levels ML21266A2772021-09-23023 September 2021 HDI Clarification of Exemption Requested from 10 CFR 20, Appendix G, Section Iii.E ML21267A0012021-09-23023 September 2021 E-mail from A. Snyder, NRC, to A. Sterdis, Holtec, - Pilgrim Nuclear Power Station - Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E Acceptance Review ML21257A3832021-09-15015 September 2021 E-mail from A. Snyder, NRC, to A. Sterdis, Holtec, - Pilgrim Nuclear Power Station - Follow-on Request Re Request for Additional Information 2 Pilgrim - License Amendment Request Independent Spent Fuel Storage Installation Only Emergency Pl ML21211A5912021-07-22022 July 2021 Consultation Response from Commonwealth of Massachusetts Regarding Proposed Pilgrim ISFSI Only Technical Specifications ML21211A5162021-07-22022 July 2021 Consultation Response from Commonwealth of Massachusetts Regarding Proposed Pilgrim ISFSI Only Physical Security Plan ML21200A2352021-07-13013 July 2021 Consultation Request to Commonwealth of Massachusetts Regarding Proposed Pilgrim ISFSI Only Technical Specifications ML21200A1522021-07-13013 July 2021 Consultation Request to Commonwealth of Massachusetts Regarding Proposed Pilgrim Isfi Only Physical Security Plan ML21176A1842021-06-25025 June 2021 Email from HDI Regarding Pilgrim Nuclear Power Station Training ML21180A0582021-06-17017 June 2021 Email from Region I Regarding Pilgrim Nuclear Power Station Inspection - EA-13-132 ML21097A0402021-04-0606 April 2021 E-Mail Consult with Commonwealth of Mass Re - Amendment Application - Physical Security Plan for the Pilgrim Nuclear Power Station L-20-092, Email Pilgrim Nuclear Power Station-Exemption from Annual Force-On-Force Exercise Requirements of 10 CFR Part 73, Appendix B,2020-12-10010 December 2020 Email Pilgrim Nuclear Power Station-Exemption from Annual Force-On-Force Exercise Requirements of 10 CFR Part 73, Appendix B, L-20-096, Supplemental Information to Support Physical Security Plan Revision and License Amendment Request to Incorporate Alternate Measures - Holtec Email Dated December 10, 20102020-12-10010 December 2020 Supplemental Information to Support Physical Security Plan Revision and License Amendment Request to Incorporate Alternate Measures - Holtec Email Dated December 10, 2010 ML20328A2982020-11-16016 November 2020 Response from Commonwealth of Massachusetts on No Significant Hazard for Pilgrim ISFSI Amendment to Address ISFSI II Dated November 16, 2020 ML20297A2372020-10-22022 October 2020 Request for Additional Information - HDI Fleet Decommissioning Quality Assurance Program ML20266G4032020-09-22022 September 2020 Acceptance Review Email - Request for Approval of HDI Fleet Decommissioning Quality Assurance Program, Revision 0 ML20163A6802020-06-11011 June 2020 Confirmation of the Scope of the Requested Regulatory Relief for Pilgrim Security Qualifications ML20280A1912020-04-17017 April 2020 Request for Additional Information- Clarifying Information for Pilgrim ISFSI Physical Security Amendment Application ML20269A3542020-03-0505 March 2020 CFR 26.717 Reports 2019 Transmittal Email ML19336A0302019-11-27027 November 2019 OEDO-15-00479 - Re 2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding ML19336A0332019-11-26026 November 2019 OEDO-15-00479 - E-mail to Petitioner - 2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding (CAC No. MF6460; EPID L-2015-CRS-0002)- Issuance of Final Director'S Decision ML19331A1952019-11-21021 November 2019 NRR E-mail Capture - (External_Sender) Pilgrim Nuclear Power Station - Commonwealth Consultation Response - Amendment Regarding Site Emergency Plan and Emergency Action Level Scheme ML19331A1732019-11-12012 November 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station -Consult with Commonwealth - Amendment Regarding Cyber Security Plan ML19331A1642019-11-0505 November 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station -Consult with Commonwealth - Amendment Regarding Site Emergency Plan and Emergency Action Level Scheme ML19331A1792019-11-0505 November 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - EA and Fonsi for Pilgrim Emergency Planning Exemption CY-19-007, LTR-19-0441 Henrietta Cosentino, E-mail SECY-19-0078 Request by Entergy Nuclear Operations Inc. for Exemptions from Certain Emergency Planning Requirements for the Pilgrim Nuclear Power Station2019-11-0404 November 2019 LTR-19-0441 Henrietta Cosentino, E-mail SECY-19-0078 Request by Entergy Nuclear Operations Inc. for Exemptions from Certain Emergency Planning Requirements for the Pilgrim Nuclear Power Station ML19275H1962019-09-24024 September 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Consult with Commonwealth - Amendment Regarding Permanently Defueled Technical Specifications (PDTS) ML19239A0372019-08-26026 August 2019 E-mail from Entergy Dated August 26, 2019, Notification of Pilgrim License Transfer ML19239A0262019-08-23023 August 2019 LTR-19-0330 Janet Azarovitz, E-mail a Plea for More Time and Reasonable Discussion Including the Citizens of the Commonwealth in the Sale of the Pilgrim Nuclear Power Station ML19234A2072019-08-20020 August 2019 LTR-19-0328 Lawrence Delafield, President, Six Ponds Improv Assoc., Plymouth, Ma, Ltr Requests NRC to Postpone Consideration of Transferring the Licenses for the Pilgrim Nuclear Power Until the NRC Has Answered Concerns by Pilgrim Watch, Se ML19232A4032019-08-20020 August 2019 LTR-19-0322 Diane Turco, Director, Cape Downwinders, Massachusetts, Letter/E-mail Requests Suspension of the Pilgrim License Transfer from Entergy to Holtec Until the Adjudicatory Hearing Is Held and Raised Contentions Are Resolved ML19308A9942019-08-19019 August 2019 Entergy Nuclear Operations, Inc. Confirmatory Order Rescission Supplemental Information ML19226A3912019-08-14014 August 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - EA and Fonsi for Pilgrim Decommissioning Trust Fund Exemption (Holtec) ML19226A3962019-08-14014 August 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station -Consult with Commonwealth - Conforming Amendment in Support of Pilgrim License Transfer Application ML19226A1212019-08-13013 August 2019 OEDO-15-00479-2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding - Status (CAC No. MF6460; EPID L-2015-CRS-0002) ML19227A1032019-08-0707 August 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Draft Wording for Potential Condition of License Transfer Order ML19207B3662019-07-26026 July 2019 NRR E-mail Capture - Pilgrim - RAI Direct and Indirect Transfer of Lic.; Conforming Lic. Amend.; Req. for Exemption 10 CFR 50.82(A)(8)(I)(A) for Holtec Decom. International, Llc ML19176A3452019-06-25025 June 2019 2.206 Petition Regarding Pilgrim Nuclear Power Station'S Current Licensing Basis for Flooding - Information (OEDO-15-00479) (CAC No. MF6460; EPID L-2015-CRS-0002) ML19154A0652019-06-0303 June 2019 NRR E-mail Capture - Pilgrim - Permanent Cessation of Power Operations ML19154A5242019-06-0303 June 2019 NRR E-mail Capture - RAI - Pilgrim Post-Decommissioning Technical Specifications (PDTS) License Amendment Request (LAR) ML19161A2122019-05-20020 May 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Acceptance of License Amendment Request to Remove Cyber Security Plan Requirements ML19123A0332019-05-0101 May 2019 NRR E-mail Capture - Logbook Entry: 05/01/2019 Endangered Species Report Regarding a Confirmed Sighting of North Atlantic Right Whale(S) (Balaena Glacialis) ML19122A4912019-04-29029 April 2019 NRR E-mail Capture - Logbook Entry: 04/29/2019 Regarding the Confirmed Sighting of Ten North Atlantic Right Whales (Balaena Glacialis) ML19108A2372019-04-18018 April 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Acceptance of Requested Licensing Action, Proposed Exemptions from 10 CFR 50.54(w)(1) - On-Site Property Damage Insurance ML19108A2362019-04-18018 April 2019 NRR E-mail Capture - Pilgrim Nuclear Power Station - Acceptance of Requested Licensing Action, Proposed Exemptions from 10 CFR 140.11(a)(4) - Primary and Secondary Liability Insurance 2022-09-26
[Table view] |
Text
From:Giarrusso, John (CDA)To:Venkataraman, BoomaCc:McNamara, Nancy; Tifft, Doug
Subject:
[External_Sender] RE: Planned issuance of NRC License Amendment for Pilgrim- Revision of the Cyber Security Plan implementation schedule Milestone 8 (CAC NO. MF6517)Date:Wednesday, April 13, 2016 1:35:20 PMThank you Booma I have no other questions John
John Giarrusso, Jr Planning, Nuclear & Preparedness Section Chief Massachusetts Emergency Management Agency Work - 508-820-2040 Cell - 603-817-0560 From: Venkataraman, Booma [1] Sent: Wednesday, April 13, 2016 12:46 PMTo: Giarrusso, John (CDA)Cc: McNamara, Nancy; Tifft, Doug
Subject:
RE: Planned issuance of NRC License Amendment for Pilgrim- Revision of the Cyber Security Plan implementation schedule Milestone 8 (CAC NO. MF6517) John,Thanks for your questions on this LAR. I provide the answers to your questions below. Let me know if you have any questions.
Question 1: Has Pilgrim provided any reason for the extension?
Currently, Milestone 8 of the Pilgrim Cyber Security Plan (CSP) requires the licensee to fully implement the CSP by June 30, 2016. By letter dated July 15, 2015, the licensee proposed to modify the Milestone 8 completion date to December 15, 2017. The licensee provided the following information pertinent to some of the criteria identified in the NRC guidance memorandum dated October 24, 2013. 1) Identification of the specific requirement or requirements of the cyber security plan that the licensee needs additional time to implement: The licensee stated that the requirements of the CSP that needed additional time to implement are Section 3, "Analyzing Digital Computer Systems and Networks" and Section 4, "Establishing, Implementing and Maintaining the Cyber Security Program." It further noted that these sections describe requirements for application and maintenance of cyber security controls and described the process analyzing security controls to determine their applicability in a particular circumstance. 2) Detailed justification that describes the reason the licensee requires additional time to implement the specific requirement or requirements identified: The licensee stated it had hosted a "pilot" Milestone 8 inspection at the Indian Point Energy Center in March 2014.
During the pilot, insight was gained into the NRC perspective on how to apply the cyber security controls listed in NEI 08-09, "Cyber Security Plan for Nuclear Power Reactors", Revision 6, dated April 2010 (ADAMS Accession No. ML101180437). During the pilot inspection, the NRC team and Entergy reviewed several examples of critical digital assets (CDAs), describing the level of detail and depth expected in the technical analyses for cyber security controls referenced in NEI 08-09. Based on this review, it is evident to Entergy that the detail and depth of the technical analysis exceeds its prior understanding and requires a considerably greater effort to achieve than initially anticipated. Additionally during 2015, each operating Entergy licensee had an inspection of compliance with interim Milestones 1 through 7. The preparation for and support of these inspections has required a significant commitment of time from Entergy's most knowledgeable subject matter experts on nuclear cyber security, exceeding the estimate previously developed and thereby, drawing those resources away from Milestone 8 implementation activities. 3) The licensee stated in its letter dated July 15, 2015, that the impact of the requested additional implementation time on the effectiveness of the overall cyber security program is considered to be very low, because the milestones already completed have resulted in a high degree of protection of safety-related, important-to-safety, and security CDAs against common threat vectors. Additionally, extensive physical and administrative measures are already in place for CDAs [because they are plant components], pursuant to the Pilgrim Security Plan and Technical Specification Requirements. Question 2: Have other plants asked for an extension? Yes, other plants have also asked for an extension. Question 3: Any safety issues by extending the deadline 1.5 years out? The licensee indicated that completion of the activities associated with the CSP, as described in Milestones 1 through 7 were completed prior to December 31, 2012, and provide a high degree of protection to ensure that the most significant digital computer and communication systems and networks associated with safety, security and emergency preparedness functions are protected against cyber-attacks. The NRC staff finds that the licensee's site is more secure after the implementation of Milestones 1 through 7 because the activities the licensee has completed mitigate the most significant cyber- attack vectors for the most significant CDAs.
Thanks, Booma US. NRC/NRR/DORL 301.415.2934 From: Giarrusso, John (CDA) [2] Sent: Wednesday, April 13, 2016 7:29 AMTo: Venkataraman, Booma <Booma.Venkataraman@nrc.gov>
Cc: McNamara, Nancy <Nancy.McNamara@nrc.gov>; Tifft, Doug <Doug.Tifft@nrc.gov>
Subject:
[External_Sender] RE: Planned issuance of NRC License Amendment for Pilgrim- Revision of the Cyber Security Plan implementation schedule Milestone 8 (CAC NO. MF6517) BoomaHas Pilgrim given a reason for the extension? Also have other plants asked for this extension? Any safety issues by extended the deadline 1.5 years out John
John Giarrusso, Jr Planning, Nuclear & Preparedness Section Chief Massachusetts Emergency Management Agency Work - 508-820-2040 Cell - 603-817-0560 From: Venkataraman, Booma [3] Sent: Monday, April 11, 2016 12:40 PMTo: Giarrusso, John (CDA); Giarrusso, John (CDA)Cc: McNamara, Nancy; Tifft, Doug
Subject:
Planned issuance of NRC License Amendment for Pilgrim- Revision of the Cyber Security Plan implementation schedule Milestone 8 (CAC NO. MF6517) John, The NRC staff is preparing to issue the following license amendment regarding Pilgrim Nuclear Power Station (PNPS). A brief description of the license amendment request (LAR) is provided below. Additional information can be found in the licensee's submittal which is also referenced below by ADAMS Accession No.
Please let me know if you have any comments or questions regarding this licensing action by April 18, 2016, if possible. My current projection for issuance of the amendment is April 29, 2016. PILGRIM NUCLEAR POWER STATION - ISSUANCE OF AMENDMENT RE: CYBER SECURITY PLAN (CSP) IMPLEMENTATION SCHEDULE Application date: July 15, 2015 (ML15205A287) Brief
Description:
The amendment would revise the completion date of the PNPS CSP by extending the date for full implementation from June 30, 2016, to December 31, 2017. The proposed change would revise the Paragraph 3.G in the renewed facility operating license. The NRC issued a proposed finding that the amendment involves no significant hazards consideration in the Federal Register on October 27, 2015 (80 FR 65812) (Link). The NRC has not received any public comment or requests for hearing on this LAR.
Thanks, Booma Booma Venkataraman, P.E.Project Manager, NRR/DORL/LPL1-1 Office of Nuclear Reactor RegulationBooma.Venkataraman@nrc.gov301.415.2934