MONTHYEARML24257A0212024-09-11011 September 2024 Document Request for Oconee Nuclear Station - Radiation Protection Inspection - Inspection Report 2024-04 ML24234A2972024-08-21021 August 2024 August 21, 2024 - Oconee Nuclear Station, Units 1, 2, and 3 - Acceptance of Requested Licensing Action License Amendment Request to Revise Technical Specification 3.7.7 ML24211A0872024-07-27027 July 2024 EN 57079 Paragon Energy Solutions Final - No Active Links ML24197A2292024-07-15015 July 2024 Email from Mark Yoo (NRC) to Steve Snider (Duke) - Oconee SLRA - RAI - 2024 Annual Update ML24190A0462024-07-0505 July 2024 Notification of Inspection and Request for Information ML24179A1292024-06-24024 June 2024 Acceptance Review for LAR to Revise TS to Adopt TSTF-234-A, Revision 1 ML24143A1322024-05-22022 May 2024 May 22, 2024, Verbal Authorization for Duke Energy Request to Use a Provision of a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XI (RA-24-0152) (EPID L- 2024-LLR-0034) ML24127A0892024-05-0202 May 2024 57079-EN57079-1 - Redline Strikethrough e-mail Re Part 21 Interim Notification of Potential Defect with Schneider Electric Medium Voltage Vr Type Circuit Breaker ML24108A0792024-04-16016 April 2024 EN 57079 Paragon Energy Solutions Email Forwarding Part 21 Interim Report Re Potential Defect with Schneider Electric Medium Voltage Vr Type Circuit Breaker Part Number V5D4133Y000 ML24086A3772024-03-26026 March 2024 Request for Additional Information License Amendment Request to Revise Technical Specification 5.5.2 ML24036A1442024-02-27027 February 2024 NRC to Fws, NRC Request for Concurrence with Endangered Species Act Determinations for Oconee Nuclear Station, Units 1, 2, and 3, Proposed Subsequent License Renewal in Oconee County, South Carolina (Consultation Code: 2023-0054989) ML24054A0492024-02-21021 February 2024 Notification of Oconee Nuclear Station FEI Inspection and Information Request-Email ML23349A0272023-12-15015 December 2023 – Acceptance of Requested Licensing Action License Amendment Request to Revise Technical Specification 5.5.2 ML23284A3322023-10-11011 October 2023 Request for Additional Information Alternative Request (RA-22-0174) (L-2022-LLR-0060) ML23270B8362023-09-26026 September 2023 Code Case N-752 Audit September 26, 2023, E-mail Providing Additional Information Regarding the Use of Owner'S Requirements and Engineering Judgment in Lieu of Code and Standards ML23267A0032023-09-21021 September 2023 RP Inspection Document Request ML23269A0412023-08-22022 August 2023 Code Case N-752 Audit; August 22, 2023, E-mail Providing Additional Information Regarding Design and Quality Program Requirements ML23172A0132023-06-20020 June 2023 Duke Fleet - Correction to June 2, 2023, Request for Additional Information Proposed License Amendment Request to Revise Restrictive Surveillance Requirement Frequencies ML23153A1892023-06-0202 June 2023 Duke Fleet - Request for Additional Information Proposed License Amendment Request to Revise Restrictive Surveillance Requirement Frequencies ML23151A3482023-05-30030 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML23144A0862023-05-24024 May 2023 Acceptance of Requested Licensing Action Proposed Relief Request (RA-23-0018) to Use ASME Code Case 853 ML23142A2732023-05-22022 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) ML23125A1452023-05-0505 May 2023 Change in Estimated Review Schedule and Level of Effort for Proposed Alternative to Use Code Case N-752 ML23124A1212023-05-0404 May 2023 Acceptance of Requested Licensing Action Duke Fleet Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML23095A0052023-04-0404 April 2023 002 Radiation Safety Baseline Inspection Information Request ML23086C0362023-03-27027 March 2023 Request for Additional Information Steam Generator Tube Inspection Report (03R31) ML23073A2282023-03-13013 March 2023 Duke Fleet- Adoption of TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements - Acceptance Review ML23058A0562023-02-27027 February 2023 Acceptance of Amendment to Revise Surveillance Frequencies for RCS Pressure Isolation Valve Operational Leakage Testing and Reactor Trip System Instrumentation ML23048A1512023-02-16016 February 2023 Acceptance Review - Proposed Alternative for Steam Generator Welds (L-2023-LLR-0003) ML23038A1832023-02-0707 February 2023 Request for Additional Information Alternative Request (RA-22-0174) to Use ASME Code Case N-752 ML23031A1552023-01-17017 January 2023 1/17/2023 Email from John Moses, Deputy Director, Division of Rulemaking, Environmental, and Financial Support, to Diane Curran, Counsel to Beyond Nuclear and the Sierra Club, Request for Extension of Scoping Comment Period for Oconee EIS ML22294A0812022-10-21021 October 2022 Nrc/Duke Steam Generator Inspection Call for November 8, 2022 NRC-2100-2022, EN 55999 Valcor Coil Shell Assemblies Final Notification (004)2022-09-12012 September 2022 EN 55999 Valcor Coil Shell Assemblies Final Notification (004) ML22251A2902022-09-0808 September 2022 Request for Additional Information Additional Mode Change Limitations Applicable to the Adoption of Technical Specifications Tasks Force Traveler (TSTF) No. 359, Revision 9 ML22235A6552022-08-23023 August 2022 Acceptance of Requested Licensing Action Proposed Alternative to Use ASME Code Case N-752 NRC 2110-2022, EN 55999 - Valcor Engineering Corporation (009)2022-07-18018 July 2022 EN 55999 - Valcor Engineering Corporation (009) ML22234A1262022-07-0808 July 2022 Email from NRC to Duke - Feedback on Trp 76 RAI Responses - July 8, 2022 ML22234A1272022-06-14014 June 2022 Email from NRC to Duke - Feedback on Trp 76 RAI Responses - June 14, 2022 ML22154A2142022-06-0101 June 2022 Email from NRC (Angela Wu) to Duke (Paul Guill) - Oconee SLRA - 2nd Round RAI B2.1.7-4b ML22157A0012022-06-0101 June 2022 Email from NRC (Angela Wu) to Duke (Paul Guill) - Oconee SLRA - Additional NRC Comments on RAI 4.6.1-1a ML22124A2052022-05-0404 May 2022 Summary of May 4, 2022, Clarification Call with Duke Energy Carolinas, LLC, Application to Revise TS 3.7.7, Low Pressure Service Water (LPSW) System ML22124A1612022-05-0303 May 2022 Email from Angela Wu (NRC) to Steve Snider (Duke) - Oconee SLRA - 2nd Round RAI B2.1.7-4a ML22122A0192022-04-28028 April 2022 Email from Angela Wu (NRC) to Steve Snider (Duke) - Oconee SLRA - 2nd Round RAI B2.1.9-2a ML22122A1322022-04-27027 April 2022 Email from Angela Wu (NRC) to Steve Snider (Duke) - Oconee SLRA - 2nd Round Requests for Additional Information (FE 3.5.2.2.2.6 - Irradiation Structural) ML22115A1412022-04-25025 April 2022 NRR E-mail Capture - Duke Common EOF Relocation - Request for Addition Information ML22130A0112022-04-25025 April 2022 Email: Oconee SLRA - RAI 4.6.1-1a - NRC Staff Comments ML22112A1892022-04-22022 April 2022 Acceptance Review for Additional Mode Change Limitations Applicable to the Adoption of TSTF- 359, Revision 9 ML22113A0082022-04-20020 April 2022 Email from Marieliz Johnson (NRC) to Steve Snider (Duke) - Oconee SLRA - Request for Additional Information 3.1.2-1 ML22112A0072022-04-20020 April 2022 Email from Marieliz Johnson (NRC) to Steve Snider (Duke) - Oconee SLRA - Request for Confirmation of Information 3.5.2.2.2.6-L ML22088A0452022-03-28028 March 2022 Radiation Safety Baseline Inspection Initial Information Request Inspection Report 2022002 2024-09-11
[Table view] |
Text
of Circle, Jeff Mike Franovich ' ' L --
From:
Sent: Friday, August 08, 2008 9:02 AM To: James Vail; Jeff Circle
Subject:
FW: Request for COM TA brief Showtime ..... mark your calendars.
From: John Adams t '*Q Sent: Friday, August 08, 2008 8:00 AM To: Jon Thompson Cc: Mike Franovich; Melanie Wong; Melanie Galloway
Subject:
RE: Request for COM TA brief This is to confirm that the staff will brief the TAs on the subject topic on Tuesday (8/12) at 4:00 p.m. in the 18th floor conference room.
Note that some of the TAs may be tied up in the Commission meeting which is scheduled to run until 4:30.
That may delay the start of this briefing.
From: Jon Thompson I n v Sent: Thursday, August 07, 2008 11:15 AM To: John Adams Cc: Mike Franovich; Melanie Wong; Melanie Galloway
Subject:
Request for COM TA brief REQUEST FOR COMMISSIONERS ASSISTANT'S BRIEFING:
To: J. Adams, OEDO From: J. Thompson, NRR/DORL/LPL 2-1
Subject:
Staff requests a briefing of the Commission Technical Assistants on Issuance of Request for Information per 10 CFR 50.54(f) regarding the Oconee Flood Issue.
Summary:
The purpose of the briefing is to inform the Technical Assistants of the NRC staff's intent to issue a request for information per 10 CFR 50.54(f) related to predicted failure frequencies and event consequences for the Jocassee Pumped Storage Dam which is located in proximity to the Oconee Nuclear Station (ONS). There is the potential for this request to be followed by a safety order following NRC staff review of the licensee's response. NRC staff evaluated licensee responses to an ROP White Finding have discovered that there may be a significant underestimate of both the consequences and likelihood of an external flooding event at the site. The licensee's response would provide the information necessary to assess what regulatory action the NRC may deem necessary to take in order to protect public health and safety.
Key Messages:
1
- The NRC is taking this action to ensure protection of public health and safety.
- This information request pursuant to 10 CFR 50.54(f) requires the licensee to provide the NRC with information regarding external flooding of the Oconee site, including the consequences of a Jocassee Dam failure. The NRC will use this information to determine whether further regulatory action is needed with respect to the affected licensees and whether further additional assessment is needed.
- The NRC staff have performed a preliminary cost-benefit analysis which indicates modifications up to $13 million could be justified with an estimated preliminary cost for modifications (higher walls, water-proof doors, etc.) of approximately $3 million.
- The NRC recognizes that the use of an erroneous rupture frequency, significantly lower than what should have been based on actual data, could be a cause of concern at certain nuclear power plants. This information request is part of NRC's plan to address this issue.
- The NRC staff will issue an IN to apprise other licensees of the potential discrepancies in the flood analyses used to assess protection and begin to review potential impacts on other plants.
Proposed times:
Possible briefing times are Monday, 8/11 at 10:00 am (preferred) or 3:00 pm; or Tuesday 8/12 at 11:00 am or 4:00 p.m. Staff are also available Friday afternoon if desired. Approximately 45 minutes is needed for this briefing.