{{#Wiki_filter:& Progress Energy 10 CFR 50.4 10 CFR 50.47 (b)(10)10 CFR50, Appendix E Serial: RNP-RA/12-0136 DEC 1 7 2012'ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET NO. 50-261/RENEWED LICENSE NO. DPR-23 EVACUATION TIME ESTIMATE ANALYSIS
==Dear Sir or Madam:==
Carolina Power and Light Company (CP&L), now doing business as Progress Energy, herein submits an updated Evacuation Time Estimate (ETE) analysis for the H. B. Robinson Steam Electric Plant Unit No. 2 (HBRSEP).
The revised ETE analysis is being submitted in accordance with 10 CFR 50.47(b)(10) and 10 CFR 50, Appendix E, Section IV, paragraph 4.This letter contains no regulatory commitments.
If you should have any questions regarding this submittal, please contact Mr. Richard Hightower, Supervisor-Regulatory Affairs at (843) 857-1329.I declare under penalty of perjury that the foregoing is true and correct. Executed On: 6ee Ad-~i 1-7 ~~Sincerely, Sharon A. Wheeler Manager -Support Services -Nuclear SAW/am Enclosure Robinson Nuclear Plant Development of Evacuation Time Estimates, October 2012.cc: Mr. V. M. McCree, NRC Region II Ms. A. T. Billoch-Colon, NRC Project Manager, NRR NRC Resident Inspectors, HBRSEP Progress Energy Carolinas, Inc.Robinson Nuclear Plant 3581 West Entrance Road Hartsville, SC 29550}}

Latest revision as of 17:13, 1 August 2018

H. B. Robinson, Unit 2, Evacuation Time Estimate Analysis
ML12363A055
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 12/17/2012
From: Wheeler S A
Carolina Power & Light Co, Progress Energy Carolinas
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
RNP-RA/12-0136
Download: ML12363A055 (1)


Text

& Progress Energy 10 CFR 50.4 10 CFR 50.47 (b)(10)10 CFR50, Appendix E Serial: RNP-RA/12-0136 DEC 1 7 2012'ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET NO. 50-261/RENEWED LICENSE NO. DPR-23 EVACUATION TIME ESTIMATE ANALYSIS

Dear Sir or Madam:

Carolina Power and Light Company (CP&L), now doing business as Progress Energy, herein submits an updated Evacuation Time Estimate (ETE) analysis for the H. B. Robinson Steam Electric Plant Unit No. 2 (HBRSEP).

The revised ETE analysis is being submitted in accordance with 10 CFR 50.47(b)(10) and 10 CFR 50, Appendix E, Section IV, paragraph 4.This letter contains no regulatory commitments.

If you should have any questions regarding this submittal, please contact Mr. Richard Hightower, Supervisor-Regulatory Affairs at (843) 857-1329.I declare under penalty of perjury that the foregoing is true and correct. Executed On: 6ee Ad-~i 1-7 ~~Sincerely, Sharon A. Wheeler Manager -Support Services -Nuclear SAW/am Enclosure Robinson Nuclear Plant Development of Evacuation Time Estimates, October 2012.cc: Mr. V. M. McCree, NRC Region II Ms. A. T. Billoch-Colon, NRC Project Manager, NRR NRC Resident Inspectors, HBRSEP Progress Energy Carolinas, Inc.Robinson Nuclear Plant 3581 West Entrance Road Hartsville, SC 29550