ML17263A526: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:ttl'igRPjfpVEZEROCHESTER
{{#Wiki_filter:ttl'igRP jfpVEZE ROCHESTER GAS AND ELECTRIC CORPORATION
GASANDELECTRICCORPORATION
~89 EAST AVENUE, ROCHESTER N.Y..14649-0001
~89EASTAVENUE,ROCHESTER
ROBERT C MECREDY Vice President@irma Nuclear Production
N.Y..14649-0001
T Et.E PHONE AREA CODE 71B 546 2700 January 10, 1994 U.S.Nuclear Regulatory
ROBERTCMECREDYVicePresident
@irmaNuclearProduction
TEt.EPHONEAREACODE71B5462700January10,1994U.S.NuclearRegulatory
Commission
Commission
Attn:AllenR.JohnsonProjectDirectorate
Attn: Allen R.Johnson Project Directorate
I-3DocumentControlDeskWashington,
I-3 Document Control Desk Washington, DC 20555 Subject: Reply to a Notice of Violation NRC Inspection
DC20555Subject:ReplytoaNoticeofViolation
Report No.50-244/93-21, dated December 10, 1993 R.E.Ginna Nuclear Power Plant Docket No.50-244 Dear Mr.Johnson: During an NRC inspection
NRCInspection
conducted on October 4, 1993 to October 13, 1993, a violation of NRC requirements
ReportNo.50-244/93-21,
was identified.
datedDecember10,1993R.E.GinnaNuclearPowerPlantDocketNo.50-244DearMr.Johnson:DuringanNRCinspection
In accordance
conducted
with the"General Statement of Policy and Procedure for NRC Enforcement
onOctober4,1993toOctober13,1993,aviolation
Actions," 10 CFR Part 2, Appendix C, the violation is listed below: "Plant technical specification
ofNRCrequirements
wasidentified.
Inaccordance
withthe"GeneralStatement
ofPolicyandProcedure
forNRCEnforcement
Actions,"
10CFRPart2,AppendixC,theviolation
islistedbelow:"Planttechnical
specification
4.6.1.e.3.a
4.6.1.e.3.a
requiresthatatleastonceper18monthsduringshutdown,
requires that at least once per 18 months during shutdown, each emergency diesel generator shall be demonstrated
eachemergency
to be operable by simulating
dieselgenerator
a loss of offsite power in conjunction
shallbedemonstrated
with a safety injection test signal and verifying de-energization
tobeoperablebysimulating
of the emergency buses and load shedding from the emergency buses." Contrary to the above, on October 11, 1993, it was determined
alossofoffsitepowerinconjunction
that testing to verify load shedding from the emergency buses was not performed during the 18 month surveillance
withasafetyinjection
testing.(1)the reason for the violation, or, if contested, the basis for disputing the violation:
testsignalandverifying
Rochester Gas&Electric Corporation (RG&E)accepts the violation.
de-energization
We acknowledge
oftheemergency
that plant procedures
busesandloadsheddingfromtheemergency
did not adequately
buses."Contrarytotheabove,onOctober11,1993,itwasdetermined
test the bus undervoltage
thattestingtoverifyloadsheddingfromtheemergency
logic, as required by Technical Specification (TS)4.6.1.e.3.(a).  
buseswasnotperformed
Lettex: Page 2 Subject: Violation Response 93-21-01 Date: January 10, 1994 The reason for the violation, as stated in LER 93-005 (Docket Number 50-244, LER 93-005, dated November 10, 1993)was a mis-interpretation
duringthe18monthsurveillance
of TS surveillance
testing.(1)thereasonfortheviolation,
or,ifcontested,
thebasisfordisputing
theviolation:
Rochester
Gas&ElectricCorporation
(RG&E)acceptstheviolation.
Weacknowledge
thatplantprocedures
didnotadequately
testthebusundervoltage
logic,asrequiredbyTechnical
Specification
(TS)4.6.1.e.3.(a).  
Lettex:Page2Subject:Violation
Response93-21-01Date:January10,1994Thereasonfortheviolation,
asstatedinLER93-005(DocketNumber50-244,LER93-005,datedNovember10,1993)wasamis-interpretation
ofTSsurveillance
requirements.
requirements.
Theloadsheddingrequirement
The load shedding requirement
ofTS4.6.1.e.3.{a)
of TS 4.6.1.e.3.{a)
wasinterpreted
was interpreted
asthesheddingofnon-essential
as the shedding of non-essential
loadspoweredfromtheemergency
loads powered from the emergency buses.The shedding of non-essential
buses.Thesheddingofnon-essential
loads had been tested by simulating
loadshadbeentestedbysimulating
a safety injection (SI)signal during performance
asafetyinjection
of procedures
(SI)signalduringperformance
RSSP-2.1 (Safety Injection Functional
ofprocedures
Test)and RSSP-2.1A.(Safety Injection Functional
RSSP-2.1(SafetyInjection
Test Alignment/Realignment), which are performed each refueling outage.The need to verify load shedding capabilities
Functional
of safeguards
Test)andRSSP-2.1A.
loads, with undervoltage
(SafetyInjection
and SI present, had not been considexed.
Functional
(2)the corrective
TestAlignment
steps that have been taken and the results achieved: The immediate corrective
/Realignment),
action was to perform the surveillance
whichareperformed
tests necessary to verify load shedding capability
eachrefueling
from the emergency buses.A procedure change notice (PCN)was developed for each associated
outage.Theneedtoverifyloadsheddingcapabilities
PT-9.1 procedure (monthly surveillance
ofsafeguards
test procedures
loads,withundervoltage
for testing undervoltage
andSIpresent,hadnotbeenconsidexed.
(2)thecorrective
stepsthathavebeentakenandtheresultsachieved:
Theimmediate
corrective
actionwastoperformthesurveillance
testsnecessary
toverifyloadsheddingcapability
fromtheemergency
buses.Aprocedure
changenotice(PCN)wasdeveloped
foreachassociated
PT-9.1procedure
(monthlysurveillance
testprocedures
fortestingundervoltage
protection
protection
for480voltsafeguards
for 480 volt safeguards
busses14,16,17,and18).TestingwasstartedonOctober11,1993,andwascompleted
busses 14, 16, 17, and 18).Testing was started on October 11, 1993, and was completed on October 12, 1993, within twenty-four
onOctober12,1993,withintwenty-four
hours of discovery.
hoursofdiscovery.
Details of this testing and test methodology
Detailsofthistestingandtestmethodology
are discussed in Attachment
arediscussed
l.(To perfoim this testing, individual
inAttachment
l.(Toperfoimthistesting,individual
components
components
weredeclaredinoperable,
were declared inoperable, one at a time, fox brief periods.No more than one component was inoperable
oneatatime,foxbriefperiods.Nomorethanonecomponent
at a given time, and the diesel generators (DGs)were maintained
wasinoperable
operable during the entire testing pexiod.)The guidance of NRC Generic Letter{GL)87-09, entitled"Sections 3.0 and 4.0 of the Standard Technical Specifications (STS)on the Applicability
atagiventime,andthedieselgenerators
of Limiting Conditions
(DGs)weremaintained
for Operation and Surveillance
operableduringtheentiretestingpexiod.)TheguidanceofNRCGenericLetter{GL)87-09,entitled"Sections
Requirements", was followed.Both the"A" and"B" DGs were available to perform all intended functions throughout
3.0and4.0oftheStandardTechnical
the discovery and surveillance
Specifications
testing period.This testing demonstrated
(STS)ontheApplicability
ofLimitingConditions
forOperation
andSurveillance
Requirements",
wasfollowed.
Boththe"A"and"B"DGswereavailable
toperformallintendedfunctions
throughout
thediscovery
andsurveillance
testingperiod.Thistestingdemonstrated
end-to-end
end-to-end
operability
operability
oftheunder-voltageprotection
of the under-voltage protection
system.Itverifiedundervoltage
system.It verified undervoltage
signalstosafeguards
signals to safeguards
components,
components, and undervoltage
andundervoltage
in conjunction
inconjunction
with SI signal to the Component Cooling'ater (CCW)pumps.Initial testing of the"B" CCW pump undervoltage
withSIsignaltotheComponent
/SI trip logic was indeterminate.
Cooling'ater
At that time, the"B" CCW pump was declared inoperable, until further testing was conducted.
(CCW)pumps.Initialtestingofthe"B"CCWpumpundervoltage
The pump was subsequently
/SItriplogicwasindeterminate.
verified to be fully operable, and was returned to service approximately
Atthattime,the"B"CCWpumpwasdeclaredinoperable,
twelve hours later.The testing conducted on October 11-12, in combination
untilfurthertestingwasconducted.
with the surveillance
Thepumpwassubsequently
tests conducted during the 1993 outage, met the requixements
verifiedtobefullyoperable,
of TS 4.6.1.e.3.(a), and verified that the safeguards
andwasreturnedtoserviceapproximately
functions would have performed as required.  
twelvehourslater.Thetestingconducted
Letter: Page 3 Subject: Violation Response 93-21-01 Date: January 10, 1994 RG&E personnel subsequently
onOctober11-12,incombination
reviewed the requirements
withthesurveillance
of TS 4.6.1, and compared these requirements
testsconducted
with surveillance
duringthe1993outage,mettherequixements
proce-dures.No other noncompliances
ofTS4.6.1.e.3.(a),
were identified.
andverifiedthatthesafeguards
(3)the corrective
functions
steps that will be taken to avoid further violations:
wouldhaveperformed
0 A review of Section 4 of the Ginna TS will be performed to ensure that there are implementing
asrequired.  
Letter:Page3Subject:Violation
Response93-21-01Date:January10,1994RG&Epersonnel
subsequently
reviewedtherequirements
ofTS4.6.1,andcomparedtheserequirements
withsurveillance
proce-dures.Noothernoncompliances
wereidentified.
(3)thecorrective
stepsthatwillbetakentoavoidfurtherviolations:
0AreviewofSection4oftheGinnaTSwillbeperformed
toensurethatthereareimplementing
procedures
procedures
foreverysurveillance
for every surveillance
requiredbyTS.Thisreviewwillbecompleted
required by TS.This review will be completed prior to completion
priortocompletion
of the next scheduled refueling outage.Results of a preliminary
ofthenextscheduled
review of Section 4 have determined
refueling
that there are sufficient
outage.Resultsofapreliminary
reviewofSection4havedetermined
thattherearesufficient
procedural
procedural
controlsforimplementing
controls for implementing
Section4requirements.
Section 4 requirements.
00Areviewoftheidentified
0 0 A review of the identified
implementing
implementing
procedures
procedures
willbeperformed
will be performed to ensure that these procedures
toensurethattheseprocedures
do, in fact, implement the TS requirements.
do,infact,implement
This review will be completed prior to completion
theTSrequirements.
of the next scheduled refueling outage.Procedures
Thisreviewwillbecompleted
that verify load shedding capability
priortocompletion
will be upgraded to include safeguards
ofthenextscheduled
loads, for conditions
refueling
of undervoltage
outage.Procedures
and SI, prior to completion
thatverifyloadsheddingcapability
of the next scheduled refueling outage.(4)the date when full compliance
willbeupgradedtoincludesafeguards
will be achieved: Full compliance
loads,forconditions
with TS 4.6.1.e.3.(a)
ofundervoltage
was achieved on October 12, 1993, at the completion
andSI,priortocompletion
of surveillance
ofthenextscheduled
testing.Very truly yours, Robert C.Mecredy xc: Mr.Allen R.Johnson (Mail Stop 14D1)PWR Project Directorate
refueling
I-3 Washington, DC 20555 U.S.Nuclear Regulatory
outage.(4)thedatewhenfullcompliance
willbeachieved:
Fullcompliance
withTS4.6.1.e.3.(a)
wasachievedonOctober12,1993,atthecompletion
ofsurveillance
testing.Verytrulyyours,RobertC.Mecredyxc:Mr.AllenR.Johnson(MailStop14D1)PWRProjectDirectorate
I-3Washington,
DC20555U.S.NuclearRegulatory
Commission
Commission
RegionI475Allendale
Region I 475 Allendale Road King of Prussia, PA 19406 Ginna USNRC Senior Resident Inspector
RoadKingofPrussia,PA19406GinnaUSNRCSeniorResidentInspector
Attachment
Attachment
1PT-9.1SeriesTestDetailsThepurposeofthistestwastoverifyundervoltage
1 PT-9.1 Series Test Details The purpose of this test was to verify undervoltage
safeguards
safeguards
loadsheddingcapability.
load shedding capability.
MonthlyTSsurveillance
Monthly TS surveillance
testingcurrently
testing currently ensures each safeguards
ensureseachsafeguards
breaker can be stripped from the bus using the trip coil.To verify the undervoltage
breakercanbestrippedfromthebususingthetripcoil.Toverifytheundervoltage
stripping capability, all that was necessary was to verify the integrity of the undervoltage
stripping
logic contacts and associated
capability,
circuitry, to the trip coils.Jumpers were used to simulate SI for the CCW pumps because their breakers trip on undervoltage
allthatwasnecessary
wastoverifytheintegrity
oftheundervoltage
logiccontactsandassociated
circuitry,
tothetripcoils.JumperswereusedtosimulateSIfortheCCWpumpsbecausetheirbreakerstriponundervoltage
coincident
coincident
withSIsignal.TestingSequence:
with SI signal.Testing Sequence: 1~Manipulate
1~Manipulate
test switches and develop an undervoltage
testswitchesanddevelopanundervoltage
condition using test equipment.
condition
2~Verify auxiliary output relays energize to cause the trip function, initiated by appropriate
usingtestequipment.
operation of the intermediate
2~Verifyauxiliary
digital control logic circuitry.
outputrelaysenergizetocausethetripfunction,
3~4~5.6.Return test switches to normal and remove test equipment.
initiated
Verify component being tested is not, in service.Measure the continuity
byappropriate
of wiring between the undervoltage
operation
auxiliary relays and the breaker switchgear, using DC voltage measurements
oftheintermediate
to ground.)t Verify normally open output relay contacts using resistance
digitalcontrollogiccircuitry.
3~4~5.6.Returntestswitchestonormalandremovetestequipment.
Verifycomponent
beingtestedisnot,inservice.Measurethecontinuity
ofwiringbetweentheundervoltage
auxiliary
relaysandthebreakerswitchgear,
usingDCvoltagemeasurements
toground.)tVerifynormallyopenoutputrelaycontactsusingresistance
measurements.
measurements.
7~8.Locallytriptheassociated
7~8.Locally trip the associated
auxiliary
auxiliary relay and verify proper indicator lamp response and relay contacts indicate closed by resistance
relayandverifyproperindicator
lampresponseandrelaycontactsindicateclosedbyresistance
measurement.
measurement.
Resettheauxiliary
Reset the auxiliary relay and verify relay contacts indicate open by resistance
relayandverifyrelaycontactsindicateopenbyresistance
measurement.
measurement.
9.Repeatsteps1-8forallfourchannels(27/X,27/BX,27D/X,and27D/BX).Onetestanomolywasidentified,
9.Repeat steps 1-8 for all four channels (27/X, 27/BX, 27D/X, and 27D/BX).One test anomoly was identified, as noted in the violation response.Relay 86-16B, associated
asnotedintheviolation
with the"B" CCW pump breaker, failed to meet the specified resistance
response.
Relay86-16B,associated
withthe"B"CCWpumpbreaker,failedtomeetthespecified
resistance
acceptance
acceptance
criteria.
criteria.Emergency Maintenance
Emergency
procedure EM-778 was performed to verify the contact did in fact trip the breaker.After being verified, the contact was reworked by simple burnishing
Maintenance
of exposed contact surfaces.~~~v  
procedure
~'i 0
EM-778wasperformed
toverifythecontactdidinfacttripthebreaker.Afterbeingverified,
thecontactwasreworkedbysimpleburnishing
ofexposedcontactsurfaces.
~~~v  
~'i0
ACCELERATED
ACCELERATED
DISTRIBUTION
DISTRIBUTION
DEMONSTRATION
DEMONSTRATION
SYSTEMREGULATORY
SYSTEM REGULATORY
INFORMATION
INFORMATION
DISTRIBUTION
DISTRIBUTION
SYSTEM(RIDS)CCESSIONNBR:9402010169
SYSTEM (RIDS)CCESSION NBR:9402010169
DOC.DATE'4/01/10
DOC.DATE'4/01/10
NOTARIZED:
NOTARIZED:
NOFACIL:50-244
NO FACIL:50-244
RobertEmmetGinnaNuclearPlant,Unit1,Rochester
Robert Emmet Ginna Nuclear Plant, Unit 1, Rochester G AUTH.NAME AUTHOR AFFILIATION
GAUTH.NAMEAUTHORAFFILIATION
MECREDY,R.C.
MECREDY,R.C.
Rochester
Rochester Gas&Electric Corp.RECIP.NAME
Gas&ElectricCorp.RECIP.NAME
RECIPIENT AFFILIATION
RECIPIENT
AFFILIATION
JOHNSON,A.R.
JOHNSON,A.R.
ProjectDirectorate
Project Directorate
I-3ISUBJECT:Respondstoviolations
I-3 I SUBJECT: Responds to violations
notedininsprept50-244/93-21.
noted in insp rept 50-244/93-21.
Corrective
Corrective
actions:surveillance
actions:surveillance
testsnecessary
tests necessary to verify load shedding capability
toverifyloadsheddingcapability
from emergency buses performed&procedure revised.DISTRIBUTION
fromemergency
CODE: IE01D COPIES RECEIVED:LTR
busesperformed
2 ENCL SIZE: TITLE: General (50 Dkt)-Insp Rept/Notice
&procedure
of Vi&o ation Response NOTES:License
revised.DISTRIBUTION
Exp date in'ccordance
CODE:IE01DCOPIESRECEIVED:LTR
with 10CFR2,2.109(9/19/72).
2ENCLSIZE:TITLE:General(50Dkt)-Insp
DOCKET 05000244 D$/05000244 RECIPIENT ID CODE/NAME PD1-3 PD INTERNAL: AEOD/DEIB AEOD/DS P/TPAB DEDRO NRR/DRCH/HHFB
Rept/Notice
ofVi&oationResponseNOTES:License
Expdatein'ccordance
with10CFR2,2.109(9/19/72).
DOCKET05000244D$/05000244RECIPIENT
IDCODE/NAME
PD1-3PDINTERNAL:
AEOD/DEIB
AEOD/DSP/TPABDEDRONRR/DRCH/HHFB
NRR/DRSS/PEPB
NRR/DRSS/PEPB
NRR/PMAS/ILPB2
NRR/PMAS/ILPB2
~BI~REGFILM02RGNTFILEOlEXTERNALEG&G/BRYCE
~BI~REG FILM 02 RGNT FILE Ol EXTERNAL EG&G/BRYCE
iJH~NSICCOPIESLTTRENCL111111111111111111111111RECIPIENT
i J H~NSIC COPIES LTTR ENCL 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 RECIPIENT ID CODE/NAME JOHNSON,A AEOD/DSP/ROAB
IDCODE/NAME
AEOD/TTC NRR/DORS/OEAB
JOHNSON,A
AEOD/DSP/ROAB
AEOD/TTCNRR/DORS/OEAB
NRR/DRIL/RPEB-
NRR/DRIL/RPEB-
NRR/PMAS/ILPB1
NRR/PMAS/ILPB1
NUDOCS-ABSTRACT
NUDOCS-ABSTRACT
OGC/HDS1RES/HFBNRCPDRCOPIESLTTRENCL11111111'11111111111DDRDSNOTETOALL"RIDS"RECIPIENTS:
OGC/HDS1 RES/HFB NRC PDR COPIES LTTR ENCL 1 1 1 1 1 1 1 1'1 1 1 1 1 1 1 1 1 1 1 D D R D S NOTE TO ALL"RIDS" RECIPIENTS:
DDPLEASEHELPUSTOREDUCEWASTE!CONTACTTHEDOCUMENTCONTROLDESK,ROOMP1-37(EXT.20079)TOELIMINATE
D D PLEASE HELP US TO REDUCE WASTE!CONTACT THE DOCUMENT CONTROL DESK, ROOM P 1-37 (EXT.20079)TO ELIMINATE YOUR NAME FROM DISTRIBUTION
YOURNAMEFROMDISTRIBUTION
LISTS FOR DOCUMENTS YOU DON'T NEEDI OTAL NUMBER OF COPIES REQUIRED: LTTR 22 ENCL 22
LISTSFORDOCUMENTS
YOUDON'TNEEDIOTALNUMBEROFCOPIESREQUIRED:
LTTR22ENCL22
''t"'l'i"~lliPjt'I
''t"'l'i"~lliPjt'I
/'l'gjll,"i,",iiel't
/'l'gjll,"i,",iiel't
It,/f//IP'(/
I t,/f//IP'(/
ROCHESTER
ROCHESTER GAS AND ELECTRIC CORPORATION
GASANDELECTRICCORPORATION
ROBERT C.MECREDY Vice Ptesident Ctnna Nuetear Ptoduetion
ROBERTC.MECREDYVicePtesident
,/net~~~VA~~G ToAtt II F I$Tate~89 EAST AVENUE, ROCHESTER N.Y.14649.OO0'I
CtnnaNuetearPtoduetion
TELEPHONE AREA CODE 716 546'2700 January 10, 1994 U.S.Nuclear Regulatory
,/net~~~VA~~GToAttIIFI$Tate~89EASTAVENUE,ROCHESTER
N.Y.14649.OO0'I
TELEPHONE
AREACODE716546'2700January10,1994U.S.NuclearRegulatory
Commission
Commission
Attn:AllenR.JohnsonProjectDirectorate
Attn: Allen R.Johnson Project Directorate
I-3DocumentControlDeskWashington,
I-3 Document Control Desk Washington, DC 20555 Subject: Reply to a Notice of Violation NRC Inspection
DC20555Subject:ReplytoaNoticeofViolation
Report No.50-244/93-21, dated December 10, 1993 R.E.Ginna Nuclear Power Plant Docket No.50-244 Dear Mr.Johnson: During an NRC inspection
NRCInspection
conducted on October 4, 1993 to October 13, 1993, a violation of NRC requirements
ReportNo.50-244/93-21,
was identified.
datedDecember10,1993R.E.GinnaNuclearPowerPlantDocketNo.50-244DearMr.Johnson:DuringanNRCinspection
In acccrdance
conducted
with the"General Statement of Policy and Procedure for NRC Enforcement
onOctober4,1993toOctober13,1993,aviolation
Actions," 10 CFR Part 2, Appendix C, the violation is listed below: "Plant technical specification
ofNRCrequirements
wasidentified.
Inacccrdance
withthe"GeneralStatement
ofPolicyandProcedure
forNRCEnforcement
Actions,"
10CFRPart2,AppendixC,theviolation
islistedbelow:"Planttechnical
specification
4.6.l.e.3.a
4.6.l.e.3.a
requiresthatatleastonceper18monthsduringshutdown,
requires that at least once per 18 months during shutdown, each emergency diesel generator shall be demonstrated
eachemergency
to be operable by simulating
dieselgenerator
a loss of offsite power in conjunction
shallbedemonstrated
with a safety injection test signal and verifying de-energization
tobeoperablebysimulating
of the emergency buses and load shedding from the emergency buses." Contrary to the above, on October 11, 1993, it was determined
alossofoffsitepowerinconjunction
that testing to verify load shedding from the emergency buses was not performed during the 18 month surveillance
withasafetyinjection
testing.(1)the reason for the violation, or, if contested, the basis for disputing the violation:
testsignalandverifying
Rochester Gas&Electric Corporation (RG&E)accepts the violation.
de-energization
We acknowledge
oftheemergency
that plant procedures
busesandloadsheddingfromtheemergency
did not adequately
buses."Contrarytotheabove,onOctober11,1993,itwasdetermined
test the bus undervoltage
thattestingtoverifyloadsheddingfromtheemergency
logic, as required by Technical Specification (TS)4.6.1.e.3.(a).gw~I To iQ'.9402010169
buseswasnotperformed
940110 PDR ADOCK 05000244 9 PDR
duringthe18monthsurveillance
testing.(1)thereasonfortheviolation,
or,ifcontested,
thebasisfordisputing
theviolation:
Rochester
Gas&ElectricCorporation
(RG&E)acceptstheviolation.
Weacknowledge
thatplantprocedures
didnotadequately
testthebusundervoltage
logic,asrequiredbyTechnical
Specification
(TS)4.6.1.e.3.(a).gw~IToiQ'.9402010169
940110PDRADOCK050002449PDR
0'  
0'  
Letter:Page2Subject:"Violation
Letter: Page 2 Subject: "Violation
Response93-21-01Date:January10,1994Thereasonfortheviolation,
Response 93-21-01 Date: January 10, 1994 The reason for the violation, as stated in LER 93-005 (Docket Number 50-244, LER 93-005, dated November 10, 1993)was a mis-interpretation'of
asstatedinLER93-005(DocketNumber50-244,LER93-005,datedNovember10,1993)wasamis-interpretation'of
TS surveill'ance
TSsurveill'ance
requirements.
requirements.
Theloadsheddingrequirement
The load shedding requirement
ofTS4.6.1.e.3.(a)
of TS 4.6.1.e.3.(a)
wasinterpreted
was interpreted
asthesheddingofnon-essential
as the shedding of non-essential
loadspoweredfrom,theemergency
loads powered from ,the emergency buses.The shedding of non-essential
buses.Thesheddingofnon-essential
loads had been tested by.simulating
loadshadbeentestedby.simulating
a safety injection (SI)signal.during performance
asafetyinjection
of procedures
(SI)signal.duringperformance
RSSP-2.1 (Safety Injection Functional
ofprocedures
Test)and RSSP-2.1A (Safety Injection Functional
RSSP-2.1(SafetyInjection
Test Alignment/Realignment), which are performed each refueling outage.The need to verify load shedding capabilities
Functional
of safeguards
Test)andRSSP-2.1A
loads, with undervoltage
(SafetyInjection
and SI present, had not been considered., l (2)the corrective
Functional
steps that have been taken and the results achieved: The immediate corrective
TestAlignment
action was to perform the surveillance
/Realignment),
tests necessary to verify load shedding capability
whichareperformed
from the emergency buses.A procedure change notice (PCN)was developed for each associated
eachrefueling
PT-9.1 procedure (monthly surveillance
outage.Theneedtoverifyloadsheddingcapabilities
test procedures
ofsafeguards
for testing'undervoltage
loads,withundervoltage
andSIpresent,hadnotbeenconsidered.,
l(2)thecorrective
stepsthathavebeentakenandtheresultsachieved:
Theimmediate
corrective
actionwastoperformthesurveillance
testsnecessary
toverifyloadsheddingcapability
fromtheemergency
buses.Aprocedure
changenotice(PCN)wasdeveloped
foreachassociated
PT-9.1procedure
(monthlysurveillance
testprocedures
fortesting'undervoltage
protection
protection
for480voltsafeguards
for 480 volt safeguards
busses14,16,17,and18).TestingwasstartedonOctober11,1993,andwascompleted
busses 14, 16, 17, and 18).Testing was started on October 11, 1993, and was completed on October 12, 1993, within twenty-four
onOctober12,1993,withintwenty-four
hours of discovery.
hoursofdiscovery.
Details of this testing and test methodology
Detailsofthistestingandtestmethodology
are discussed in Attachment
arediscussed
1..(To perform this testing, indiyidua2.
inAttachment
1..(Toperformthistesting,indiyidua2.
components
components
weredeclaredinoperable,
were declared inoperable, one at a time, for brief periods.No more than one component was inoperable
oneatatime,forbriefperiods.Nomorethanonecomponent
at a given time, and the diesel generators (DGs)were maintained
wasinoperable
operable during the entire testing period.)The guidance of.NRC Generic Letter (GL)87-09, entitled"Sections 3.0 and 4.0 of the Standard Technical Specifications (STS)on the Applicability
atagiventime,andthedieselgenerators
of Limiting Conditions
(DGs)weremaintained
for Operation and Surveillance
operableduringtheentiretestingperiod.)Theguidanceof.NRCGenericLetter(GL)87-09,entitled"Sections
Requirements", was followed.,Both the"A" and"B" DGs were available to perform all intended functions throughout
3.0and4.0oftheStandardTechnical
the discovery.
Specifications
and surveillance
(STS)ontheApplicability
testing period.This testing demonstrated
ofLimitingConditions
forOperation
andSurveillance
Requirements",
wasfollowed.
,Boththe"A"and"B"DGswereavailable
toperformallintendedfunctions
throughout
thediscovery.
andsurveillance
testingperiod.Thistestingdemonstrated
end-to-end
end-to-end
operability
operability
oftheunder-voltageprotection
of the under-voltage protection
system.Itverifiedundervoltage
system.It verified undervoltage
signalstosafeguards
signals to safeguards
components,
components, and undervoltage
andundervoltage
in conjunction
inconjunction
with SI signal to the Component Cooling Water (CCW)pumps.Initial testing of the"B" CCW pump undervoltage
withSIsignaltotheComponent
/SI trip logic was indeterminate.
CoolingWater(CCW)pumps.Initialtestingofthe"B"CCWpumpundervoltage
At that time, the"B" CCW pump was declared inoperable, until further testing was conducted.
/SItriplogicwasindeterminate.
The pump was subsequently
Atthattime,the"B"CCWpumpwasdeclaredinoperable,
untilfurthertestingwasconducted.
Thepumpwassubsequently
verified,to
verified,to
befullyoperable,
be fully operable, and was returned to service approximately
andwasreturnedtoserviceapproximately
twelve hours later.The testing conducted on October 11-12, in combination
twelvehourslater.Thetestingconducted
with the surveillance
onOctober11-12,incombination
tests conducted during the 1993 outage, met the requirements
withthesurveillance
of TS 4.6.1.e.3.(a), and verified that the safeguards
testsconducted
functions would have performed as required.  
duringthe1993outage,mettherequirements
Letter: Page 3 Subja't: Violation Response 93-21-01 Date: January 10, 1994 RG&E personnel subsequently
ofTS4.6.1.e.3.(a),
reviewed the requirements
andverifiedthatthesafeguards
of TS 4.6.1, and compared these requirements
functions
with surveillance
wouldhaveperformed
proce-dures.No other noncompliances
asrequired.  
were identified.
Letter:Page3Subja't:Violation
(3')the corrective
Response93-21-01Date:January10,1994RG&Epersonnel
steps that will be taken to avoid further violations:
subsequently
0 0 0 A review of Section 4 of the Ginna TS will be performed to ensure that there are implementing
reviewedtherequirements
ofTS4.6.1,andcomparedtheserequirements
withsurveillance
proce-dures.Noothernoncompliances
wereidentified.
(3')thecorrective
stepsthatwillbetakentoavoidfurtherviolations:
000AreviewofSection4oftheGinnaTSwillbeperformed
toensurethatthereareimplementing
procedures
procedures
foreverysurveillance
for every surveillance
requiredbyTS.Thisreviewwillbecompleted
required by TS.This review will be completed prior to completion
priortocompletion
of the next scheduled refueling outage.Results of a preliminary
ofthenextscheduled
review of Section 4 have determined
refueling
that there are sufficient
outage.Resultsofapreliminary
reviewofSection4havedetermined
thattherearesufficient
procedural
procedural
controlsforimplementing
controls for implementing
Section4requirements.
Section 4 requirements.
Areviewoftheidentified
A review of the identified
implementing
implementing
procedures
procedures
willbeperformed
will be performed to ensure that these procedures
toensurethattheseprocedures
do, in fact, implement the TS requirements.
do,infact,implement
This review will be completed prior to completion
theTSrequirements.
of the next scheduled refueling outage.Procedures
Thisreviewwillbecompleted
that verify load shedding capability
priortocompletion
will be upgraded to include safeguards
ofthenextscheduled
loads, for conditions
refueling
of undervoltage
outage.Procedures
and SI, prior to completion
thatverifyloadsheddingcapability
of the next scheduled refueling outage.(4)the date when full compliance
willbeupgradedtoincludesafeguards
will be achieved: Full compliance
loads,forconditions
with TS 4.6.1.e.3.(a)
ofundervoltage
was achieved on.October 12, 1993, at the completion
andSI,priortocompletion
of surveillance
ofthenextscheduled
testing.Very truly yours, Robert C.Mecredy xc: Mr.Allen R.Johnson (Mail Stop 14D1)PWR Project Directorate
refueling
I-3 Washington, DC 20555 U.S.Nuclear Regulatory
outage.(4)thedatewhenfullcompliance
willbeachieved:
Fullcompliance
withTS4.6.1.e.3.(a)
wasachievedon.October12,1993,atthecompletion
ofsurveillance
testing.Verytrulyyours,RobertC.Mecredyxc:Mr.AllenR.Johnson(MailStop14D1)PWRProjectDirectorate
I-3Washington,
DC20555U.S.NuclearRegulatory
Commission
Commission
RegionI475Allendale
Region I 475 Allendale Road King of Prussia, PA 19406 Ginna USNRC Senior Resident Inspector
RoadKingofPrussia,PA19406GinnaUSNRCSeniorResidentInspector
Attachment
Attachment
1PT-9.1SeriesTestDetailsThepurposeofthistestwastoverifyundervoltage
1 PT-9.1 Series Test Details The purpose of this test was to verify undervoltage
safeguards
safeguards
loadsheddingcapability.
load shedding capability.
MonthlyTSsurveillance
Monthly TS surveillance
test'ingcurrently
test'ing currently ensures each safeguards
ensureseachsafeguards
breaker can be stripped from the bus using the trip coil.To verify the undervoltage
breakercanbestrippedfromthebususingthetripcoil.Toverifytheundervoltage
stripping capability, all that was necessary was to verify the integrity of the undervoltage
stripping
logic contacts and associated
capability,
circuitry, to the trip coils.Zumpers were used to simulate SI for the CCW pumps because their breakers trip on undervoltage
allthatwasnecessary
wastoverifytheintegrity
oftheundervoltage
logiccontactsandassociated
circuitry,
tothetripcoils.ZumperswereusedtosimulateSIfortheCCWpumpsbecausetheirbreakerstriponundervoltage
coincident
coincident
withSIsignal.TestingSequence:
with SI signal.Testing Sequence: 1~Manipulate
1~Manipulate
test switches and develop an undervoltage
testswitchesanddevelopanundervoltage
condition using test equipment.
condition
2~Verify auxiliary output relays energize to cause the trip function, initiated by appropriate
usingtestequipment.
operation of the intermediate
2~Verifyauxiliary
digital control logic circuitry.
outputrelaysenergizetocausethetripfunction,
3~4~5.Return test switches to normal and remove test equipment.
initiated
Verify component being tested is not in service.Measure the continuity
byappropriate
of wiring between the undervoltage
operation
auxiliary relays and the breaker switchgear, using DC voltage measurements
oftheintermediate
to ground.6.Verify normally open output relay contacts using resistance
digitalcontrollogiccircuitry.
3~4~5.Returntestswitchestonormalandremovetestequipment.
Verifycomponent
beingtestedisnotinservice.Measurethecontinuity
ofwiringbetweentheundervoltage
auxiliary
relaysandthebreakerswitchgear,
usingDCvoltagemeasurements
toground.6.Verifynormallyopenoutputrelaycontactsusingresistance
measurements.
measurements.
7~8.Locallytriptheassociated
7~8.Locally trip the associated
auxiliary
auxiliary relay and verify proper indicator lamp response and relay contacts indicate closed by resistance
relayandverifyproperindicator
lampresponseandrelaycontactsindicateclosedbyresistance
measurement.
measurement.
Resettheauxiliary
Reset the auxiliary relay and verify relay contacts indicate open by resistance
relayandverifyrelaycontactsindicateopenbyresistance
measurement.
measurement.
9.Repeatsteps1-8forallfourchannels(27/X,27/BX,27D/X,and27D/BX).Onetestanomolywasidentified,
9.Repeat steps 1-8 for all four channels (27/X, 27/BX, 27D/X, and 27D/BX).One test anomoly was identified, as noted in the violation response.Relay 86-16B, associated
asnotedintheviolation
with the"B" CCW pump breaker, failed to meet the specified resistance
response.
Relay86-16B,associated
withthe"B"CCWpumpbreaker,failedtomeetthespecified
resistance
acceptance
acceptance
criteria.
criteria.Emergency Maintenance'rocedure
Emergency
EM-778 was performed to verify the contact did in fact trip.the breaker.After being verified, the contact was reworked by simple burnishing
Maintenance'rocedure
of exposed contact surfaces.  
EM-778wasperformed
toverifythecontactdidinfacttrip.thebreaker.Afterbeingverified,
thecontactwasreworkedbysimpleburnishing
ofexposedcontactsurfaces.  
~l
~l
}}
}}

Revision as of 14:05, 7 July 2018

Responds to Violations Noted in Insp Rept 50-244/93-21. Corrective Actions:Surveillance Tests Necessary to Verify Load Shedding Capability from Emergency Buses Performed & Procedure Revised
ML17263A526
Person / Time
Site: Ginna Constellation icon.png
Issue date: 01/10/1994
From: MECREDY R C
ROCHESTER GAS & ELECTRIC CORP.
To: JOHNSON A R
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM), Office of Nuclear Reactor Regulation
References
NUDOCS 9402010169
Download: ML17263A526 (12)


See also: IR 05000244/1993021

Text

ttl'igRP jfpVEZE ROCHESTER GAS AND ELECTRIC CORPORATION

~89 EAST AVENUE, ROCHESTER N.Y..14649-0001

ROBERT C MECREDY Vice President@irma Nuclear Production

T Et.E PHONE AREA CODE 71B 546 2700 January 10, 1994 U.S.Nuclear Regulatory

Commission

Attn: Allen R.Johnson Project Directorate

I-3 Document Control Desk Washington, DC 20555 Subject: Reply to a Notice of Violation NRC Inspection

Report No.50-244/93-21, dated December 10, 1993 R.E.Ginna Nuclear Power Plant Docket No.50-244 Dear Mr.Johnson: During an NRC inspection

conducted on October 4, 1993 to October 13, 1993, a violation of NRC requirements

was identified.

In accordance

with the"General Statement of Policy and Procedure for NRC Enforcement

Actions," 10 CFR Part 2, Appendix C, the violation is listed below: "Plant technical specification 4.6.1.e.3.a

requires that at least once per 18 months during shutdown, each emergency diesel generator shall be demonstrated

to be operable by simulating

a loss of offsite power in conjunction

with a safety injection test signal and verifying de-energization

of the emergency buses and load shedding from the emergency buses." Contrary to the above, on October 11, 1993, it was determined

that testing to verify load shedding from the emergency buses was not performed during the 18 month surveillance

testing.(1)the reason for the violation, or, if contested, the basis for disputing the violation:

Rochester Gas&Electric Corporation (RG&E)accepts the violation.

We acknowledge

that plant procedures

did not adequately

test the bus undervoltage

logic, as required by Technical Specification (TS)4.6.1.e.3.(a).

Lettex: Page 2 Subject: Violation Response 93-21-01 Date: January 10, 1994 The reason for the violation, as stated in LER 93-005 (Docket Number 50-244, LER 93-005, dated November 10, 1993)was a mis-interpretation

of TS surveillance

requirements.

The load shedding requirement

of TS 4.6.1.e.3.{a)

was interpreted

as the shedding of non-essential

loads powered from the emergency buses.The shedding of non-essential

loads had been tested by simulating

a safety injection (SI)signal during performance

of procedures

RSSP-2.1 (Safety Injection Functional

Test)and RSSP-2.1A.(Safety Injection Functional

Test Alignment/Realignment), which are performed each refueling outage.The need to verify load shedding capabilities

of safeguards

loads, with undervoltage

and SI present, had not been considexed.

(2)the corrective

steps that have been taken and the results achieved: The immediate corrective

action was to perform the surveillance

tests necessary to verify load shedding capability

from the emergency buses.A procedure change notice (PCN)was developed for each associated

PT-9.1 procedure (monthly surveillance

test procedures

for testing undervoltage

protection

for 480 volt safeguards

busses 14, 16, 17, and 18).Testing was started on October 11, 1993, and was completed on October 12, 1993, within twenty-four

hours of discovery.

Details of this testing and test methodology

are discussed in Attachment

l.(To perfoim this testing, individual

components

were declared inoperable, one at a time, fox brief periods.No more than one component was inoperable

at a given time, and the diesel generators (DGs)were maintained

operable during the entire testing pexiod.)The guidance of NRC Generic Letter{GL)87-09, entitled"Sections 3.0 and 4.0 of the Standard Technical Specifications (STS)on the Applicability

of Limiting Conditions

for Operation and Surveillance

Requirements", was followed.Both the"A" and"B" DGs were available to perform all intended functions throughout

the discovery and surveillance

testing period.This testing demonstrated

end-to-end

operability

of the under-voltage protection

system.It verified undervoltage

signals to safeguards

components, and undervoltage

in conjunction

with SI signal to the Component Cooling'ater (CCW)pumps.Initial testing of the"B" CCW pump undervoltage

/SI trip logic was indeterminate.

At that time, the"B" CCW pump was declared inoperable, until further testing was conducted.

The pump was subsequently

verified to be fully operable, and was returned to service approximately

twelve hours later.The testing conducted on October 11-12, in combination

with the surveillance

tests conducted during the 1993 outage, met the requixements

of TS 4.6.1.e.3.(a), and verified that the safeguards

functions would have performed as required.

Letter: Page 3 Subject: Violation Response 93-21-01 Date: January 10, 1994 RG&E personnel subsequently

reviewed the requirements

of TS 4.6.1, and compared these requirements

with surveillance

proce-dures.No other noncompliances

were identified.

(3)the corrective

steps that will be taken to avoid further violations:

0 A review of Section 4 of the Ginna TS will be performed to ensure that there are implementing

procedures

for every surveillance

required by TS.This review will be completed prior to completion

of the next scheduled refueling outage.Results of a preliminary

review of Section 4 have determined

that there are sufficient

procedural

controls for implementing

Section 4 requirements.

0 0 A review of the identified

implementing

procedures

will be performed to ensure that these procedures

do, in fact, implement the TS requirements.

This review will be completed prior to completion

of the next scheduled refueling outage.Procedures

that verify load shedding capability

will be upgraded to include safeguards

loads, for conditions

of undervoltage

and SI, prior to completion

of the next scheduled refueling outage.(4)the date when full compliance

will be achieved: Full compliance

with TS 4.6.1.e.3.(a)

was achieved on October 12, 1993, at the completion

of surveillance

testing.Very truly yours, Robert C.Mecredy xc: Mr.Allen R.Johnson (Mail Stop 14D1)PWR Project Directorate

I-3 Washington, DC 20555 U.S.Nuclear Regulatory

Commission

Region I 475 Allendale Road King of Prussia, PA 19406 Ginna USNRC Senior Resident Inspector

Attachment

1 PT-9.1 Series Test Details The purpose of this test was to verify undervoltage

safeguards

load shedding capability.

Monthly TS surveillance

testing currently ensures each safeguards

breaker can be stripped from the bus using the trip coil.To verify the undervoltage

stripping capability, all that was necessary was to verify the integrity of the undervoltage

logic contacts and associated

circuitry, to the trip coils.Jumpers were used to simulate SI for the CCW pumps because their breakers trip on undervoltage

coincident

with SI signal.Testing Sequence: 1~Manipulate

test switches and develop an undervoltage

condition using test equipment.

2~Verify auxiliary output relays energize to cause the trip function, initiated by appropriate

operation of the intermediate

digital control logic circuitry.

3~4~5.6.Return test switches to normal and remove test equipment.

Verify component being tested is not, in service.Measure the continuity

of wiring between the undervoltage

auxiliary relays and the breaker switchgear, using DC voltage measurements

to ground.)t Verify normally open output relay contacts using resistance

measurements.

7~8.Locally trip the associated

auxiliary relay and verify proper indicator lamp response and relay contacts indicate closed by resistance

measurement.

Reset the auxiliary relay and verify relay contacts indicate open by resistance

measurement.

9.Repeat steps 1-8 for all four channels (27/X, 27/BX, 27D/X, and 27D/BX).One test anomoly was identified, as noted in the violation response.Relay 86-16B, associated

with the"B" CCW pump breaker, failed to meet the specified resistance

acceptance

criteria.Emergency Maintenance

procedure EM-778 was performed to verify the contact did in fact trip the breaker.After being verified, the contact was reworked by simple burnishing

of exposed contact surfaces.~~~v

~'i 0

ACCELERATED

DISTRIBUTION

DEMONSTRATION

SYSTEM REGULATORY

INFORMATION

DISTRIBUTION

SYSTEM (RIDS)CCESSION NBR:9402010169

DOC.DATE'4/01/10

NOTARIZED:

NO FACIL:50-244

Robert Emmet Ginna Nuclear Plant, Unit 1, Rochester G AUTH.NAME AUTHOR AFFILIATION

MECREDY,R.C.

Rochester Gas&Electric Corp.RECIP.NAME

RECIPIENT AFFILIATION

JOHNSON,A.R.

Project Directorate

I-3 I SUBJECT: Responds to violations

noted in insp rept 50-244/93-21.

Corrective

actions:surveillance

tests necessary to verify load shedding capability

from emergency buses performed&procedure revised.DISTRIBUTION

CODE: IE01D COPIES RECEIVED:LTR

2 ENCL SIZE: TITLE: General (50 Dkt)-Insp Rept/Notice

of Vi&o ation Response NOTES:License

Exp date in'ccordance

with 10CFR2,2.109(9/19/72).

DOCKET 05000244 D$/05000244 RECIPIENT ID CODE/NAME PD1-3 PD INTERNAL: AEOD/DEIB AEOD/DS P/TPAB DEDRO NRR/DRCH/HHFB

NRR/DRSS/PEPB

NRR/PMAS/ILPB2

~BI~REG FILM 02 RGNT FILE Ol EXTERNAL EG&G/BRYCE

i J H~NSIC COPIES LTTR ENCL 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 RECIPIENT ID CODE/NAME JOHNSON,A AEOD/DSP/ROAB

AEOD/TTC NRR/DORS/OEAB

NRR/DRIL/RPEB-

NRR/PMAS/ILPB1

NUDOCS-ABSTRACT

OGC/HDS1 RES/HFB NRC PDR COPIES LTTR ENCL 1 1 1 1 1 1 1 1'1 1 1 1 1 1 1 1 1 1 1 D D R D S NOTE TO ALL"RIDS" RECIPIENTS:

D D PLEASE HELP US TO REDUCE WASTE!CONTACT THE DOCUMENT CONTROL DESK, ROOM P 1-37 (EXT.20079)TO ELIMINATE YOUR NAME FROM DISTRIBUTION

LISTS FOR DOCUMENTS YOU DON'T NEEDI OTAL NUMBER OF COPIES REQUIRED: LTTR 22 ENCL 22

t"'l'i"~lliPjt'I

/'l'gjll,"i,",iiel't

I t,/f//IP'(/

ROCHESTER GAS AND ELECTRIC CORPORATION

ROBERT C.MECREDY Vice Ptesident Ctnna Nuetear Ptoduetion

,/net~~~VA~~G ToAtt II F I$Tate~89 EAST AVENUE, ROCHESTER N.Y.14649.OO0'I

TELEPHONE AREA CODE 716 546'2700 January 10, 1994 U.S.Nuclear Regulatory

Commission

Attn: Allen R.Johnson Project Directorate

I-3 Document Control Desk Washington, DC 20555 Subject: Reply to a Notice of Violation NRC Inspection

Report No.50-244/93-21, dated December 10, 1993 R.E.Ginna Nuclear Power Plant Docket No.50-244 Dear Mr.Johnson: During an NRC inspection

conducted on October 4, 1993 to October 13, 1993, a violation of NRC requirements

was identified.

In acccrdance

with the"General Statement of Policy and Procedure for NRC Enforcement

Actions," 10 CFR Part 2, Appendix C, the violation is listed below: "Plant technical specification 4.6.l.e.3.a

requires that at least once per 18 months during shutdown, each emergency diesel generator shall be demonstrated

to be operable by simulating

a loss of offsite power in conjunction

with a safety injection test signal and verifying de-energization

of the emergency buses and load shedding from the emergency buses." Contrary to the above, on October 11, 1993, it was determined

that testing to verify load shedding from the emergency buses was not performed during the 18 month surveillance

testing.(1)the reason for the violation, or, if contested, the basis for disputing the violation:

Rochester Gas&Electric Corporation (RG&E)accepts the violation.

We acknowledge

that plant procedures

did not adequately

test the bus undervoltage

logic, as required by Technical Specification (TS)4.6.1.e.3.(a).gw~I To iQ'.9402010169

940110 PDR ADOCK 05000244 9 PDR

0'

Letter: Page 2 Subject: "Violation

Response 93-21-01 Date: January 10, 1994 The reason for the violation, as stated in LER 93-005 (Docket Number 50-244, LER 93-005, dated November 10, 1993)was a mis-interpretation'of

TS surveill'ance

requirements.

The load shedding requirement

of TS 4.6.1.e.3.(a)

was interpreted

as the shedding of non-essential

loads powered from ,the emergency buses.The shedding of non-essential

loads had been tested by.simulating

a safety injection (SI)signal.during performance

of procedures

RSSP-2.1 (Safety Injection Functional

Test)and RSSP-2.1A (Safety Injection Functional

Test Alignment/Realignment), which are performed each refueling outage.The need to verify load shedding capabilities

of safeguards

loads, with undervoltage

and SI present, had not been considered., l (2)the corrective

steps that have been taken and the results achieved: The immediate corrective

action was to perform the surveillance

tests necessary to verify load shedding capability

from the emergency buses.A procedure change notice (PCN)was developed for each associated

PT-9.1 procedure (monthly surveillance

test procedures

for testing'undervoltage

protection

for 480 volt safeguards

busses 14, 16, 17, and 18).Testing was started on October 11, 1993, and was completed on October 12, 1993, within twenty-four

hours of discovery.

Details of this testing and test methodology

are discussed in Attachment

1..(To perform this testing, indiyidua2.

components

were declared inoperable, one at a time, for brief periods.No more than one component was inoperable

at a given time, and the diesel generators (DGs)were maintained

operable during the entire testing period.)The guidance of.NRC Generic Letter (GL)87-09, entitled"Sections 3.0 and 4.0 of the Standard Technical Specifications (STS)on the Applicability

of Limiting Conditions

for Operation and Surveillance

Requirements", was followed.,Both the"A" and"B" DGs were available to perform all intended functions throughout

the discovery.

and surveillance

testing period.This testing demonstrated

end-to-end

operability

of the under-voltage protection

system.It verified undervoltage

signals to safeguards

components, and undervoltage

in conjunction

with SI signal to the Component Cooling Water (CCW)pumps.Initial testing of the"B" CCW pump undervoltage

/SI trip logic was indeterminate.

At that time, the"B" CCW pump was declared inoperable, until further testing was conducted.

The pump was subsequently

verified,to

be fully operable, and was returned to service approximately

twelve hours later.The testing conducted on October 11-12, in combination

with the surveillance

tests conducted during the 1993 outage, met the requirements

of TS 4.6.1.e.3.(a), and verified that the safeguards

functions would have performed as required.

Letter: Page 3 Subja't: Violation Response 93-21-01 Date: January 10, 1994 RG&E personnel subsequently

reviewed the requirements

of TS 4.6.1, and compared these requirements

with surveillance

proce-dures.No other noncompliances

were identified.

(3')the corrective

steps that will be taken to avoid further violations:

0 0 0 A review of Section 4 of the Ginna TS will be performed to ensure that there are implementing

procedures

for every surveillance

required by TS.This review will be completed prior to completion

of the next scheduled refueling outage.Results of a preliminary

review of Section 4 have determined

that there are sufficient

procedural

controls for implementing

Section 4 requirements.

A review of the identified

implementing

procedures

will be performed to ensure that these procedures

do, in fact, implement the TS requirements.

This review will be completed prior to completion

of the next scheduled refueling outage.Procedures

that verify load shedding capability

will be upgraded to include safeguards

loads, for conditions

of undervoltage

and SI, prior to completion

of the next scheduled refueling outage.(4)the date when full compliance

will be achieved: Full compliance

with TS 4.6.1.e.3.(a)

was achieved on.October 12, 1993, at the completion

of surveillance

testing.Very truly yours, Robert C.Mecredy xc: Mr.Allen R.Johnson (Mail Stop 14D1)PWR Project Directorate

I-3 Washington, DC 20555 U.S.Nuclear Regulatory

Commission

Region I 475 Allendale Road King of Prussia, PA 19406 Ginna USNRC Senior Resident Inspector

Attachment

1 PT-9.1 Series Test Details The purpose of this test was to verify undervoltage

safeguards

load shedding capability.

Monthly TS surveillance

test'ing currently ensures each safeguards

breaker can be stripped from the bus using the trip coil.To verify the undervoltage

stripping capability, all that was necessary was to verify the integrity of the undervoltage

logic contacts and associated

circuitry, to the trip coils.Zumpers were used to simulate SI for the CCW pumps because their breakers trip on undervoltage

coincident

with SI signal.Testing Sequence: 1~Manipulate

test switches and develop an undervoltage

condition using test equipment.

2~Verify auxiliary output relays energize to cause the trip function, initiated by appropriate

operation of the intermediate

digital control logic circuitry.

3~4~5.Return test switches to normal and remove test equipment.

Verify component being tested is not in service.Measure the continuity

of wiring between the undervoltage

auxiliary relays and the breaker switchgear, using DC voltage measurements

to ground.6.Verify normally open output relay contacts using resistance

measurements.

7~8.Locally trip the associated

auxiliary relay and verify proper indicator lamp response and relay contacts indicate closed by resistance

measurement.

Reset the auxiliary relay and verify relay contacts indicate open by resistance

measurement.

9.Repeat steps 1-8 for all four channels (27/X, 27/BX, 27D/X, and 27D/BX).One test anomoly was identified, as noted in the violation response.Relay 86-16B, associated

with the"B" CCW pump breaker, failed to meet the specified resistance

acceptance

criteria.Emergency Maintenance'rocedure

EM-778 was performed to verify the contact did in fact trip.the breaker.After being verified, the contact was reworked by simple burnishing

of exposed contact surfaces.

~l