| CNL-14-129 August 28, 2014 10 CFR 2.202 10 CFR 50.4 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 | | CNL-14-129 August 28, 2014 |
|
| |
|
| Browns Ferry Nuclear Plant, Units 1, 2, and 3 Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296 | | 10 CFR 2.202 10 CFR 50.4 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 |
| | |
| | Browns Ferry Nuclear Plant, Units 1, 2, and 3 Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296 |
|
| |
|
| ==Subject:== | | ==Subject:== |
| Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant (TAC Nos. MF0881, MF0882, and MF0883) | | Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant (TAC Nos. MF0881, MF0882, and MF0883) |
|
| |
|
| ==References:== | | ==References:== |
| : 1. NRC Order Number EA-12-051, "Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," dated March 12, 2012 (ML12054A679) | | : 1. NRC Order Number EA-12-051, "Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," dated March 12, 2012 (ML12054A679) |
| : 2. NRC Interim Staff Guidance JLD-ISG-2012-03, "Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation," Revision 0, dated August 29, 2012 (ML12221A339) | | : 2. NRC Interim Staff Guidance JLD-ISG-2012-03, "Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation," Revision 0, dated August 29, 2012 (ML12221A339) |
| : 3. NEI 12-02, "Industry Guidance for Compliance with NRC Order EA-12-51, 'To Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation,'" Revision 1, dated August 2012 (ML12240A307) | | : 3. NEI 12-02, "Industry Guidance for Compliance with NRC Order EA-12-51, 'To Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation,'" Revision 1, dated August 2012 (ML12240A307) |
| : 4. Letter from TVA to NRC, "Tennessee Valley Authority (TVA) - Initial Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)," dated October 29, 2012 (ML12307A105) | | : 4. Letter from TVA to NRC, "Tennessee Valley Authority (TVA) - Initial Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)," dated October 29, 2012 (ML12307A105) |
| U.S. Nuclear Regulatory Commission Page 2 August 28, 2014 | | |
| : 5. Letter from TVA to NRC, "Tennessee Valley Authority (TVA) - Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant," dated February 28, 2013 (ML13063A437) | | U.S. Nuclear Regulatory Commission Page 2 August 28, 2014 |
| : 6. Letter from NRC to TVA, "Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Regarding Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) (TAC Nos. MF0881, MF0882, and MF0883)," dated June 18, 2013 (ML13157A164) 7. Letter from TVA to NRC, "Response to NRC Request for Additional Information Regarding Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | | : 5. Letter from TVA to NRC, "Tennessee Valley Authority (TVA) - Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant," dated February 28, 2013 (ML13063A437) |
| (TAC Nos. MF0881, MF0882, and MF0883)," dated July 18, 2013 (ML13206A005) 8. Letter from TVA to NRC, "First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant," dated August 28, 2013 (ML13247A290) 9. Letter from NRC to TVA, "Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation (TAC No. MF0881, MF0882, and MF0883)," dated November 14, 2013 (ML13274A657) 10. Letter from TVA to NRC, "Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant (TAC Nos. MF0881, MF0882, and MF0883), dated February 28, 2014 (ML14064A240) | | : 6. Letter from NRC to TVA, "Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Regarding Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) (TAC Nos. MF0881, MF0882, and MF0883)," dated June 18, 2013 (ML13157A164) |
| On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued an order (Reference 1) to Tennessee Valley Authority (TVA). Reference 1 was immediately effective and directs TVA to install reliable spent fuel pool level instrumentation (SFPLI). Specific requirements are outlined in Attachment 2 of Reference 1.
| | : 7. Letter from TVA to NRC, "Response to NRC Request for Additional Information Regarding Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for |
| | |
| | Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) |
| | (TAC Nos. MF0881, MF0882, and MF0883)," dated July 18, 2013 |
|
| |
|
| U.S. Nuclear Regulatory Commission Page 3 August 28, 2014 | | (ML13206A005) |
| | : 8. Letter from TVA to NRC, "First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant," dated August 28, 2013 (ML13247A290) |
| | : 9. Letter from NRC to TVA, "Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation (TAC No. MF0881, MF0882, and MF0883)," dated November 14, 2013 (ML13274A657) |
| | : 10. Letter from TVA to NRC, "Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant (TAC Nos. MF0881, MF0882, and MF0883), dated February 28, 2014 (ML14064A240) |
| | |
| | On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued an order (Reference 1) to Tennessee Valley Authority (TVA). |
| | Reference 1 was immediately effective and directs TVA to install reliable spent fuel pool level instrumentation (SFPLI). Specific requirements are outlined in Attachment 2 of Reference 1. |
| | |
| | U.S. Nuclear Regulatory Commission Page 3 August 28, 2014 |
|
| |
|
| Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (Reference 2) and an overall integrated plan pursuant to Section IV, Condition C. Reference 2 endorses industry guidance document Nuclear Energy Institute (NEI) 12-02, Revision 1 (Reference 3) with clarifications and exceptions identified in Reference 2. Reference 4 provided the TVA initial status report regarding SFPLI strategies. | | Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (Reference 2) and an overall integrated plan pursuant to Section IV, Condition C. Reference 2 endorses industry guidance document Nuclear Energy Institute (NEI) 12-02, Revision 1 (Reference 3) with clarifications and exceptions identified in Reference 2. Reference 4 provided the TVA initial status report regarding SFPLI strategies. |
| Reference 5 provided the TVA Browns Ferry Nuclear Plant, Units 1, 2, and 3 overall integrated plan. On June 18, 2013, the NRC issued a request for additional information (RAI) (Reference 6) and TVA provided its response on July 18, 2013 (Reference 7). Reference 1 requires submission of a status report at six-month intervals following submittal of the overall integrated plan. Reference 3 provides direction regarding the content of the status reports. TVA submitted the first six-month update on August 28, 2013 (Reference 8). | | Reference 5 provided the TVA Browns Ferry Nuclear Plant, Units 1, 2, and 3 overall |
| | |
| | integrated plan. On June 18, 2013, the NRC issued a request for additional information (RAI) (Reference 6) and TVA provided its response on July 18, 2013 (Reference 7). |
| | Reference 1 requires submission of a status report at six-month intervals following submittal of the overall integrated plan. Reference 3 provides direction regarding the content of the status reports. TVA submitted the first six-month update on August 28, 2013 (Reference 8). |
| The NRC issued its Interim Staff Evaluation and RAIs regarding TVA's overall integrated plan on November 14, 2013 (Reference 9). TVA submitted the second six-month update on February 28, 2014 (Reference 10). | | The NRC issued its Interim Staff Evaluation and RAIs regarding TVA's overall integrated plan on November 14, 2013 (Reference 9). TVA submitted the second six-month update on February 28, 2014 (Reference 10). |
|
| |
|
Line 48: |
Line 64: |
| The enclosure describes the plans that TVA will use to meet the regulatory requirements outlined in Attachment 2 of Reference 1, but does not identify any additional actions to be taken by TVA. Therefore, this letter contains no regulatory commitments. | | The enclosure describes the plans that TVA will use to meet the regulatory requirements outlined in Attachment 2 of Reference 1, but does not identify any additional actions to be taken by TVA. Therefore, this letter contains no regulatory commitments. |
|
| |
|
| If you have any question regarding this submittal, please contact Kevin Casey at (423) 751-8523. | | If you have any question regarding this submittal, please contact Kevin Casey at |
| | |
| | (423) 751-8523. |
| | |
| I declare under penalty of perjury that the foregoing is true and correct. Executed on the 28th day of August 2014. | | I declare under penalty of perjury that the foregoing is true and correct. Executed on the 28th day of August 2014. |
|
| |
|
Line 56: |
Line 75: |
|
| |
|
| ==Enclosure:== | | ==Enclosure:== |
| Tennessee Valley Authority Browns Ferry Nuclear Plant's Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) cc: See Page 4 J. W. SheaDigitally signed by J. W. Shea DN: cn=J. W. Shea, o=Tennessee Valley Authority, ou=Nuclear Licensing, email=jwshea@tva.gov, c=US Date: 2014.08.28 19:25:01 -04'00' U.S. Nuclear Regulatory Commission Page 4 August 28, 2014 | | |
| | Tennessee Valley Authority Browns Ferry Nuclear Plant's Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) cc: See Page 4 J. W. Shea Digitally signed by J. W. Shea DN: cn=J. W. Shea, o=Tennessee Valley |
| | |
| | Authority, ou=Nuclear Licensing, email=jwshea@tva.gov, c=US Date: 2014.08.28 19:25:01 -04'00' U.S. Nuclear Regulatory Commission Page 4 August 28, 2014 |
|
| |
|
| Enclosure | | Enclosure |
|
| |
|
| cc (Enclosure): NRR Director - NRC Headquarters NRO Director - NRC Headquarters NRR JLD Director - NRC Headquarters NRC Regional Administrator - Region II NRC Project Manager - Browns Ferry Nuclear Plant NRC Senior Resident Inspector - Browns Ferry Nuclear Plant Page 1 of 4 ENCLOSURE TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT THIRD SIX-MONTH STATUS REPORT IN RESPONSE TO THE MARCH 12, 2012, COMMISSION ORDER MODIFYING LICENSES WITH REGARD TO RELIABLE SPENT FUEL POOL INSTRUMENTATION (ORDER NUMBER EA-12-051) 1 Introduction Browns Ferry Nuclear Plant (BFN) developed an Overall Integrated Plan (Reference 1 in Section 8 of this Enclosure), documenting the requirements to install reliable spent fuel pool level instrumentation (SFPLI), in response to Reference 2. This enclosure provides an update of milestone accomplishments since submittal of the second six-month status report (Reference 7), including any changes to the compliance method or schedule. This enclosure also provides a response to the request for additional information (RAI) issued by the NRC in its Interim Staff Evaluation (Reference 6). | | cc (Enclosure): |
| 2 Milestone Accomplishments The following milestone(s) have been completed since the development of the Overall Integrated Plan (Reference 1), and are current as of July 31, 2014.
| | NRR Director - NRC Headquarters NRO Director - NRC Headquarters NRR JLD Director - NRC Headquarters NRC Regional Administrator - Region II NRC Project Manager - Browns Ferry Nuclear Plant NRC Senior Resident Inspector - Browns Ferry Nuclear Plant |
| 50% design impact review of Design Change Notices (DCNs) 71159, 71160, and 71161 (Units 1, 2, and 3), for design of SFPLI, was completed on March 25, 2014. 3 Milestone Schedule Status The following updates the milestone schedule to support the Overall Integrated Plan. This section provides the activity status of each item and the expected completion date, noting any change. The dates are planning dates subject to change as design and implementation details are developed.
| |
| The milestone target completion dates do not impact the order implementation date.
| |
|
| |
|
| Page 2 of 4 Milestone Target Completion Date as Stated in the Second Six-Month Update (Reference 7) Activity Status Revised Target Completion Date Submit 60 Day Status Report 10/29/2012 Complete Submit Overall Integrated Plan 02/28/2013 Complete Submit 6 Month Updates: Update 1 08/28/2013 Complete Update 2 02/28/2014 Complete Update 3 08/28/2014 Complete Update 4 02/28/2015 Not Started Update 5 08/28/2015 Not Started Update 6 02/282016 Not Started Update 7 08/28/2016 Not Started June 18, 2013 RAI Response 07/18/2013 Complete NRC ISE RAI Response 10/31/2014 Started Modifications: Unit 1 Design Engineering 06/24/2014 Design started 09/02/2014 Unit 1 Implementation 07/20/2015Not Started 07/15/2015 Unit 2 Design Engineering 06/24/2014 Design started 09/02/2014 Unit 2 Implementation 04/22/2015Not Started 03/25/2015 Unit 3 Design Engineering 06/24/2014 Design started 09/02/2014 Unit 3 Implementation 08/14/2015Not Started 07/10/2015 Procedures: Create Procedures 10/31/2014 Not Started Training: Develop Training Plan 09/30/2014 Not Started Training Complete 03/31/2015 Not Started 03/25/2015 Full Site SFPLI Implementation 11/15/2016 Not Started 07/15/2015 Submit Completion Report 12/15/2016 Not Started 08/15/2015 4 Changes to Compliance Method There are no other changes to the compliance method as documented in the Overall Integrated Plan (Reference 1) and the first and second six-month update (References 5 and 7). | | Page 1 of 4 ENCLOSURE TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT THIRD SIX-MONTH STATUS REPORT IN RESPONSE TO THE MARCH 12, 2012, COMMISSION ORDER MODIFYING LICENSES WITH REGARD TO RELIABLE SPENT FUEL POOL INSTRUMENTATION (ORDER NUMBER EA-12-051) 1 Introduction |
| 5 Need for Relief/Relaxation and Basis for the Relief/Relaxation Browns Ferry Nuclear Plant (BFN) expects to comply with the order implementation date and no relief/relaxation is required at this time.
| |
|
| |
|
| Page 3 of 4 6 Open Items from Overall Integrated Plan and NRC Evaluation The following tables provide a summary of the open items documented in the Overall Integrated Plan or the NRC Evaluation and the status of each item. Overall Integrated Plan Open Item Status OI-1) TVA will complete an instrument channel uncertainty calculation and document instrument channel accuracy and calibration requirements. Engineering and vendor documentation are in progress. This will complete on the Design Engineering milestone shown in the table in Section 3. OI-2) TVA plans to utilize Guided Wave Radar technology. Confirm final technology selection after contracts are complete. Closed - Guided Wave Radar technology was utilized. OI-3) Confirm that the sensor cable and light weight at the bottom of sensor cable will not damage the SFP liner from impact during seismic event. Engineering and vendor documentation are in progress. This will complete on the Design Engineering milestone shown in the table in Section 3. OI-4) After detailed engineering design is complete, confirm that SFP level channel components and cable routing will be contained within seismic structures such that the installation will comply with the reasonable protection guidance of NEI-12-06. Engineering and vendor documentation are in progress.
| | Browns Ferry Nuclear Plant (BFN) developed an Overall Integrated Plan (Reference 1 in Section 8 of this Enclosure), documenting the requirements to install reliable spent fuel pool level instrumentation (SFPLI), in response to Reference 2. This enclosure provides an update of milestone accomplishments since submittal of the second six-month status report (Reference 7), including any changes to the compliance method or schedule. This enclosure also provides a response to the request for additional information (RAI) issued by the NRC in its Interim Staff Evaluation (Reference 6). |
| This will complete on the Design Engineering milestone shown in the table in Section 3. Draft Safety Evaluation Open Item Status None N/A 7 Potential NRC Evaluation Impacts There are no potential impacts to the NRC Evaluation identified at this time. | |
|
| |
|
| Page 4 of 4 8 References The following references support the updates to the Overall Integrated Plan described in this enclosure. 1. Letter from TVA to NRC, "Tennessee Valley Authority (TVA) - Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant," dated February 28, 2013. (ML13063A437) 2. NRC Order Number EA-12-051, "Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," dated March 12, 2012. (ML12054A679) | | 2 Milestone Accomplishments |
| | |
| | The following milestone(s) have been completed since the development of the Overall Integrated Plan (Reference 1), and are current as of July 31, 2014. |
| | |
| | 50% design impact review of Design Change Notices (DCNs) 71159, 71160, and 71161 (Units 1, 2, and 3), for design of SFPLI, was completed on March 25, 2014. |
| | 3 Milestone Schedule Status |
| | |
| | The following updates the milestone schedule to support the Overall Integrated Plan. This section provides the activity status of each item and the expected completion date, noting any change. The dates are planning dates subject to change as design and implementation details |
| | |
| | are developed. |
| | |
| | The milestone target completion dates do not impact the order implementation date. |
| | |
| | Page 2 of 4 Milestone Target Completion Date as Stated in the Second Six-Month Update (Reference 7) Activity Status Revised Target Completion Date Submit 60 Day Status Report 10/29/2012 Complete Submit Overall Integrated Plan 02/28/2013 Complete Submit 6 Month Updates: |
| | Update 1 08/28/2013 Complete Update 2 02/28/2014 Complete Update 3 08/28/2014 Complete Update 4 02/28/2015 Not Started Update 5 08/28/2015 Not Started Update 6 02/282016 Not Started Update 7 08/28/2016 Not Started June 18, 2013 RAI Response 07/18/2013 Complete NRC ISE RAI Response 10/31/2014 Started Modifications: |
| | Unit 1 Design Engineering 06/24/2014 Design started 09/02/2014 Unit 1 Implementation 07/20/2015Not Started 07/15/2015 Unit 2 Design Engineering 06/24/2014 Design started 09/02/2014 Unit 2 Implementation 04/22/2015Not Started 03/25/2015 Unit 3 Design Engineering 06/24/2014 Design started 09/02/2014 Unit 3 Implementation 08/14/2015Not Started 07/10/2015 Procedures: |
| | Create Procedures 10/31/2014 Not Started Training: |
| | Develop Training Plan 09/30/2014 Not Started Training Complete 03/31/2015 Not Started 03/25/2015 Full Site SFPLI Implementation 11/15/2016 Not Started 07/15/2015 Submit Completion Report 12/15/2016 Not Started 08/15/2015 4 Changes to Compliance Method |
| | |
| | There are no other changes to the compliance method as documented in the Overall Integrated Plan (Reference 1) and the first and second six-month update (References 5 and 7). |
| | |
| | 5 Need for Relief/Relaxation and Basis for the Relief/Relaxation |
| | |
| | Browns Ferry Nuclear Plant (BFN) expects to comply with the order implementation date and no relief/relaxation is required at this time. |
| | |
| | Page 3 of 4 6 Open Items from Overall Integrated Plan and NRC Evaluation The following tables provide a summary of the open items documented in the Overall Integrated Plan or the NRC Evaluation and the status of each item. |
| | Overall Integrated Plan Open Item Status OI-1) TVA will complete an instrument channel uncertainty calculation and document instrument channel accuracy and calibration requirements. |
| | Engineering and vendor documentation are in progress. This will complete on the Design Engineering milestone shown in the table in Section 3. OI-2) TVA plans to utilize Guided Wave Radar technology. Confirm final technology selection |
| | |
| | after contracts are complete. |
| | Closed - Guided Wave Radar technology was utilized. OI-3) Confirm that the sensor cable and light weight at the bottom of sensor cable will not damage the SFP liner from impact during seismic event. Engineering and vendor documentation are in progress. This will complete on the Design Engineering milestone shown in the table in Section 3. OI-4) After detailed engineering design is complete, confirm that SFP level channel components and cable routing will be contained within seismic structures such that the installation will comply with the reasonable protection guidance of NEI-12-06. Engineering and vendor documentation are in progress. |
| | This will complete on the Design Engineering milestone shown in the table in Section 3. |
| | Draft Safety Evaluation Open Item Status None N/A 7 Potential NRC Evaluation Impacts There are no potential impacts to the NRC Evaluation identified at this time. |
| | |
| | Page 4 of 4 8 References The following references support the updates to the Overall Integrated Plan described in this enclosure. |
| | : 1. Letter from TVA to NRC, "Tennessee Valley Authority (TVA) - Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant," dated February 28, 2013. (ML13063A437) |
| | : 2. NRC Order Number EA-12-051, "Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," dated March 12, 2012. (ML12054A679) |
| : 3. Letter from NRC to TVA, "Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Regarding Overall integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) (TAC Nos. MF0881, MF0882, and MF0883)," | | : 3. Letter from NRC to TVA, "Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Regarding Overall integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) (TAC Nos. MF0881, MF0882, and MF0883)," |
| dated June 18, 2013. (ML13157A164) | | dated June 18, 2013. (ML13157A164) |
| : 4. Letter from TVA to NRC, "Response to NRC Request for Additional Information Regarding Overall integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) (TAC Nos. MF0881, MF0882, and MF0883)," dated July 18, 2013. | | : 4. Letter from TVA to NRC, "Response to NRC Request for Additional Information Regarding Overall integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) (TAC Nos. MF0881, MF0882, and MF0883)," dated July 18, 2013. |
| | |
| (ML13206A005) | | (ML13206A005) |
| : 5. Letter from TVA to NRC, "First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant," dated August 28, 2013. (ML13247A290) | | : 5. Letter from TVA to NRC, "First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant," dated August 28, 2013. (ML13247A290) |
| : 6. Letter from NRC to TVA, "Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation (TAC No. MF0881, MF0882, and MF0883)," dated November 14, 2013. (ML13274A657) | | : 6. Letter from NRC to TVA, "Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation (TAC No. MF0881, MF0882, and MF0883)," dated November 14, 2013. (ML13274A657) |
| : 7. Letter from TVA to NRC, ""Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant (TAC Nos. MF0881, MF0882, and MF0883), dated February 28, 2014 (ML14064A240) | | : 7. Letter from TVA to NRC, ""Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant (TAC Nos. MF0881, MF0882, and MF0883), dated February 28, 2014 (ML14064A240) |
| : 9. RAI Response On November 14, 2014, the NRC issued RAIs with its Interim Staff Evaluation (Reference 6). The NRC requested all RAI information be provided by October 31, 2014.}} | | : 9. RAI Response |
| | |
| | On November 14, 2014, the NRC issued RAIs with its Interim Staff Evaluation (Reference 6). The NRC requested all RAI information be provided by October 31, 2014.}} |
Letter Sequence Other |
---|
|
Results
Other: CNL-14-129, Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant, CNL-15-036, Fourth Six-Month Status Report in Response to the March 1, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), CNL-15-068, Completion of Required Action by NRC Order EA-12-051, Reliable Spent Fuel Pool Instrumentation, CNL-15-160, Fifth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), ML13063A437, ML13247A290, ML14323A295, ML15069A358
|
MONTHYEARML13063A4372013-02-28028 February 2013 Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order # EA-12-051) Project stage: Other ML13157A1642013-06-18018 June 2013 RAI Re. Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order EA-12-051)(TAC MF0881 - MF0883) Project stage: RAI ML13206A0052013-07-18018 July 2013 Response to NRC Request for Additional Information Regarding Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation Project stage: Response to RAI ML13247A2902013-08-28028 August 2013 First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant Project stage: Other ML13274A6572013-11-14014 November 2013 Interim Staff Evaluations and Request for RAI Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation Project stage: RAI CNL-14-129, Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant2014-08-28028 August 2014 Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant Project stage: Other ML14323A2952014-11-26026 November 2014 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other CNL-15-036, Fourth Six-Month Status Report in Response to the March 1, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-02-27027 February 2015 Fourth Six-Month Status Report in Response to the March 1, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML15069A3582015-04-0606 April 2015 Report for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other CNL-15-068, Completion of Required Action by NRC Order EA-12-051, Reliable Spent Fuel Pool Instrumentation2015-06-0909 June 2015 Completion of Required Action by NRC Order EA-12-051, Reliable Spent Fuel Pool Instrumentation Project stage: Other CNL-15-160, Fifth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-08-28028 August 2015 Fifth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other 2014-11-26
[Table View] |
|
---|
Category:Letter
MONTHYEARML24289A1232024-10-24024 October 2024 Letter to James Barstow Re Environmental Scoping Summary Report for Browns Ferry CNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-24-077, Application for Subsequent Renewed Operating Licenses, Response to Request for Additional Information, Set 12024-10-0909 October 2024 Application for Subsequent Renewed Operating Licenses, Response to Request for Additional Information, Set 1 ML24270A2162024-09-27027 September 2024 Notice of Intentions Regarding Preliminary Finding from NRC Inspection Report 05000260/2024090, EA-24-075 ML24262A1502024-09-24024 September 2024 Requalification Program Inspection - Browns Ferry Nuclear Plant CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24263A2952024-09-19019 September 2024 Site Emergency Plan Implementing Procedure Revision CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000260/20240902024-09-17017 September 2024 NRC Inspection Report 05000260/2024090 and Preliminary White Finding and Apparent Violation - 1 CNL-24-062, Cycle 16 Reload Analysis Report2024-09-16016 September 2024 Cycle 16 Reload Analysis Report ML24255A8862024-09-10010 September 2024 Core Operating Limits Report for Cycle 16 Operation, Revision 0 ML24239A3332024-09-0303 September 2024 Full Audit Plan IR 05000259/20244042024-09-0303 September 2024 Cyber Security Inspection Report 05000259/2024404 and 05000260-2024404 and 05000296/2024404-Cover Letter IR 05000259/20240052024-08-26026 August 2024 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2024005, 05000260/2024005 and 05000296/2024005 ML24225A1682024-08-16016 August 2024 – Notification of Inspection and Request ML24219A0272024-08-0606 August 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000259/20244022024-08-0606 August 2024 Security Baseline Inspection Report 05000259/2024402 and 05000260/2024402 and 05000296/2024402 IR 05000259/20240022024-08-0202 August 2024 Brown Ferry Nuclear Plant – Integrated Inspection Report05000259/2024002 and 05000260/2024002 and 05000296/2024002 ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter ML24183A4142024-07-10010 July 2024 – License Renewal Regulatory Limited Scope Audit Regarding the Environmental Review of the License Renewal Application (EPID Number: L-2024-SLE-0000) (Docket Numbers: 50-259, 50-260, and 50-296) ML24190A1292024-07-0808 July 2024 Main Steam Relief Valves Lift Settings Outside of Technical Specifications Required Setpoints ML24185A1512024-07-0303 July 2024 Inoperability of Unit 3 Diesel Generator Due to Relay Failure ML24184A1142024-07-0202 July 2024 Site Emergency Plan Implementing Procedure Revision ML24183A3842024-07-0101 July 2024 Registration of Use of Cask to Store Spent Fuel (MPC-364, -365) ML24179A0282024-06-26026 June 2024 Evaluation of Effects of Out-of-Limits Condition as Described in IWB-3720(a) ML24176A1022024-06-24024 June 2024 Reactor Scram Due to Generator Step-Up Transformer Failure ML24175A0042024-06-23023 June 2024 Interim Report of a Deviation or Failure to Comply Associated with a Valve in the Unit 3 High Pressure Coolant Injection System ML24176A1132024-06-23023 June 2024 American Society of Mechanical Engineers, Section XI, Fourth 10 Year Inspection Interval, Inservice Inspection, System Pressure Test, Containment Inspection, and Repair and Replacement Programs, Owner’S Activity Report Cycle 21 Oper ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24155A0042024-06-18018 June 2024 Proposed Alternative to the Requirements of the ASME Code (Revised Alternative Request 0-ISI-47) ML24158A5312024-06-0606 June 2024 Registration of Use of Cask to Store Spent Fuel (MPC-361, -362, -363) ML24071A0292024-06-0505 June 2024 Subsequent License Renewal Application Enclosure 3 - Proprietary Determination Letter ML24068A2612024-06-0505 June 2024 SLRA Fluence Methodology Report - Proprietary Determination Letter IR 05000259/20244032024-05-22022 May 2024 – Security Baseline Report 05000259/2024403 and 05000260/2024403 and 05000296/2024403 ML24141A2462024-05-20020 May 2024 High Pressure Coolant Injection Inoperable Due to Rupture Disc Failure and Resulting System Isolation ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24136A0702024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report IR 05000259/20240012024-05-14014 May 2024 Integrated Inspection Report 05000259/2024001, 05000260/2024001, and 05000296/2024001 CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24123A2012024-05-0202 May 2024 NRC Cybersecurity Baseline Inspection (NRC Inspection Report 05000259/2024404, 05000260-2024404, 05000296/2024404) and Request for Information ML24122A6852024-05-0101 May 2024 2023 Annual Radioactive Effluent Release Report and Offsite Dose Calculation Manual CNL-24-036, – 10 CFR 50.46 Annual Report2024-04-25025 April 2024 – 10 CFR 50.46 Annual Report ML24116A2522024-04-25025 April 2024 Site Emergency Plan Implementing Procedure Revision ML24115A1652024-04-24024 April 2024 Breaker Trip Automatically Started an Emergency Diesel Generator 05000296/LER-2024-001, Primary Containment Isolation Valve Inoperable Due to Incorrect Motor Operated Valve Setup2024-04-22022 April 2024 Primary Containment Isolation Valve Inoperable Due to Incorrect Motor Operated Valve Setup CNL-24-037, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 422024-04-22022 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 42 ML24087A2302024-04-18018 April 2024 Exemption from Select Requirements of 10 CFR Part 73, Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 2024-09-03
[Table view] Category:Report
MONTHYEARML24179A0282024-06-26026 June 2024 Evaluation of Effects of Out-of-Limits Condition as Described in IWB-3720(a) ML24047A2092024-02-22022 February 2024 Calendar Year 2023 Baseline Inspection Completion ML23192A4472023-07-31031 July 2023 Staff Assessment of Updated Seismic Hazards at TVA Sites Following the NRC Process for the Ongoing Assessment of Natural Hazards Information ML23025A0752023-01-25025 January 2023 American Society of Mechanical Engineers, Section XI, Third 10 Year Inspection Interval, Inservice Inspection, System Pressure Test, Containment Inspection, and Repair and Replacement Programs, Owners Activity Report Cycle . ML22363A3922022-12-28028 December 2022 Cycle 14 Mellla+ Eigenvalue Tracking Data CNL-22-090, Request to Use a Later Edition of the American Society of Mechanical Engineers Operation and Maintenance Code and Alternative Requests for the Fifth Inservice Testing Interval2022-12-12012 December 2022 Request to Use a Later Edition of the American Society of Mechanical Engineers Operation and Maintenance Code and Alternative Requests for the Fifth Inservice Testing Interval CNL-22-100, to Request for License Amendment Regarding Application of Advanced Framatome Methodologies, and Adoption of TSTF-564 Revision 2 for Browns Ferry Nuclear Plant Units 1, 2, and 3,in Support of Atrium 11 Fuel Use at Browns Ferry (TS-535)2022-12-0909 December 2022 to Request for License Amendment Regarding Application of Advanced Framatome Methodologies, and Adoption of TSTF-564 Revision 2 for Browns Ferry Nuclear Plant Units 1, 2, and 3,in Support of Atrium 11 Fuel Use at Browns Ferry (TS-535) CNL-22-066, Request for License Amendment Regarding Application of Advanced Framatome Methodologies, and Adoption of TSTF-564 Revision 2 for in Support of Atrium 11 Fuel Use Supplement 3, Response to Request for Additional Information2022-07-18018 July 2022 Request for License Amendment Regarding Application of Advanced Framatome Methodologies, and Adoption of TSTF-564 Revision 2 for in Support of Atrium 11 Fuel Use Supplement 3, Response to Request for Additional Information ML22154A4042022-06-0303 June 2022 Unit 3 Cycle 20 Mellla+ Eigenvalue Tracking Data CNL-22-057, to Request for License Amendment Regarding Application of Advanced Framatome Methodologies, and Adoption of TSTF-564 Revision 2 in Support of Atrium 11 Fuel Use2022-05-27027 May 2022 to Request for License Amendment Regarding Application of Advanced Framatome Methodologies, and Adoption of TSTF-564 Revision 2 in Support of Atrium 11 Fuel Use ML21277A1232021-10-0404 October 2021 Submittal of Browns Ferry Unit 2 Reactor Pressure Vessel Vertical Weld Flaw Evaluation ML21246A2952021-09-29029 September 2021 Memo to File ML21246A2942021-09-29029 September 2021 Enclosufinal Ea/Fonsi for Tva'S Initial and Updated Triennial Decommissioning Funding Plans for Browns Ferry Nuclear Plant ISFSIs CNL-20-102, 10 CFR 71.95 Report for 3-60B Casks User2020-12-16016 December 2020 10 CFR 71.95 Report for 3-60B Casks User ML20255A0002020-09-24024 September 2020 Staff Review of Seismic Probabilistic Risk Assessment Associated with Reevaluated Seismic Hazard Implementation of the Near Term Task Force Recommendation 2.1: Seismic ML20112F4852020-05-0606 May 2020 Staff Assessment of Flooding Focused Evaluation CNL-19-074, Extended Power Uprate - Flow Induced Vibration Summary Report2019-09-0404 September 2019 Extended Power Uprate - Flow Induced Vibration Summary Report CNL-19-004, Tennessee Valley Authority, Browns Ferry Nuclear Plant, Unit 2, Completion of Required Action for NRC Order EA-13-109, Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions2019-06-0707 June 2019 Tennessee Valley Authority, Browns Ferry Nuclear Plant, Unit 2, Completion of Required Action for NRC Order EA-13-109, Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions CNL-19-041, Extended Power Uprate - Unit 1 Flow Induced Vibration Summary Report2019-04-16016 April 2019 Extended Power Uprate - Unit 1 Flow Induced Vibration Summary Report CNL-19-032, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 8, Additional Operator Training Information2019-03-13013 March 2019 Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 8, Additional Operator Training Information CNL-18-134, Extended Power Uprate - Replacement Steam Dryer Revised Analysis and Limit Curves Report2018-11-29029 November 2018 Extended Power Uprate - Replacement Steam Dryer Revised Analysis and Limit Curves Report ML18283B5472018-10-10010 October 2018 Responding to Letter of 11/18/1977 from E. G. Case to G. Williams, Providing Environmental Qualification Information for Electrical Connectors in Reference of IE Bulletins 77-05 & 77-05A CNL-18-112, Extended Power Uprate - Flow Induced Vibration Summary Report2018-09-13013 September 2018 Extended Power Uprate - Flow Induced Vibration Summary Report CNL-18-060, Completion of Required Action for NRC Order EA-13-109, Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions2018-05-31031 May 2018 Completion of Required Action for NRC Order EA-13-109, Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions ML18079B1402018-02-23023 February 2018 Browns Ferry Nuclear Plant, Units 1, 2, and 3: Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus ML17222A3282017-09-0505 September 2017 Flood Hazard Mitigation Strategies Assessment ML17170A0732017-06-15015 June 2017 Report Pursuant to 10 CFR 71.95 (a)(3) and (B) - Failure to Follow Conditions of TN-RAM Packaging Certificate of Compliance No. 9233 ML17114A3712017-04-20020 April 2017 Errata for BWRVIP-271NP: BWR Vessel and Internals Project, Testing and Evaluation of the Browns Ferry, Unit 2, 120 Degree Capsule ML17033B1642017-02-0202 February 2017 American Society of Mechanical Engineers Section XI, Inservice Inspection, System Pressure Test, Containment Inservice Inspection, and Repair and Replacement - Cycle 11 Operation Programs ML17024A0362016-12-31031 December 2016 Operating Data Report for 2016 CNL-16-169, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 35, Consolidated Power Uprate Safety Analysis Report Revision2016-10-28028 October 2016 Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 35, Consolidated Power Uprate Safety Analysis Report Revision ML16196A0882016-08-0505 August 2016 Staff Assessment of Response to 10 CFR 50.54(f) Information Request - Flood Causing Mechanism Reevaluation ML16146A0182016-05-25025 May 2016 Special Report 296/2016-001 for Inoperable Post Accident Monitoring (PAM) Instrumentation ML16028A2952016-01-29029 January 2016 10 CFR 71.95 Notification Associated with the Failure to Observe Certificate of Compliance Condition of the 8-120B Secondary Lid Test Port Configuration ML16027A0592016-01-27027 January 2016 Snubbers Added to Lnservice Testing Program ML15356A6542015-12-22022 December 2015 Submittal of 10 CFR 50.46 30-Day Report CNL-15-056, Application to Modify Technical Specification 2.1.1.2, Reactor Core Minimum Critical Power Ratio Safety Limits (TS-506)2015-09-25025 September 2015 Application to Modify Technical Specification 2.1.1.2, Reactor Core Minimum Critical Power Ratio Safety Limits (TS-506) NL-15-169, Browns Ferry, Units 1, 2, and 3, Startup Test Plan2015-09-21021 September 2015 Browns Ferry, Units 1, 2, and 3, Startup Test Plan NL-15-169, Non-Proprietary - Safety Analysis Report for Browns Ferry, Units 1, 2 and 3, Extended Power Uprate, Attachment 72015-09-21021 September 2015 Non-Proprietary - Safety Analysis Report for Browns Ferry, Units 1, 2 and 3, Extended Power Uprate, Attachment 7 NL-15-169, Browns Ferry Units 1, 2 and 3, Flow Induced Vibration Analysis and Monitoring Program2015-09-21021 September 2015 Browns Ferry Units 1, 2 and 3, Flow Induced Vibration Analysis and Monitoring Program ML15282A1812015-09-21021 September 2015 Non-Proprietary - Safety Analysis Report for Browns Ferry, Units 1, 2 and 3, Extended Power Uprate, Attachment 7 ML15282A2402015-09-21021 September 2015 Startup Test Plan ML15282A2392015-09-21021 September 2015 Flow Induced Vibration Analysis and Monitoring Program ML15254A5432015-09-11011 September 2015 Submittal of 10 CFR 72.48 Changes, Tests, and Experiments, Biennial Summary Report Associated with the Independent Spent Fuel Storage Installation NL-15-169, ANP-3378NP, Browns Ferry Units 1, 2 and 3, LOCA-ECCS Analysis MAPLHGR Limits for Atrium 10XM Fuel (Epu).2015-08-31031 August 2015 ANP-3378NP, Browns Ferry Units 1, 2 and 3, LOCA-ECCS Analysis MAPLHGR Limits for Atrium 10XM Fuel (Epu). ML15282A2362015-08-31031 August 2015 NEDO-33824, Revision 0, Engineering Report, Browns Ferry Replacement Steam Dryer Stress Analysis. ML15282A1822015-08-31031 August 2015 ANP-3403NP, Revision 2, Fuel Uprate Safety Analysis Report for Browns Ferry Units 1, 2, and 3, Attachment 9 NL-15-169, ANP-3377NP, Browns Ferry Units 1, 2 and 3 LOCA Break Spectrum Analysis Atrium 10XM Fuel (Epu).2015-08-31031 August 2015 ANP-3377NP, Browns Ferry Units 1, 2 and 3 LOCA Break Spectrum Analysis Atrium 10XM Fuel (Epu). NL-15-169, NEDO-33824, Revision 0, Engineering Report, Browns Ferry Replacement Steam Dryer Stress Analysis.2015-08-31031 August 2015 NEDO-33824, Revision 0, Engineering Report, Browns Ferry Replacement Steam Dryer Stress Analysis. ML15282A1842015-08-31031 August 2015 ANP-3377NP, Browns Ferry Units 1, 2 and 3 LOCA Break Spectrum Analysis Atrium 10XM Fuel (Epu). 2024-06-26
[Table view] Category:Miscellaneous
MONTHYEARML24047A2092024-02-22022 February 2024 Calendar Year 2023 Baseline Inspection Completion ML23025A0752023-01-25025 January 2023 American Society of Mechanical Engineers, Section XI, Third 10 Year Inspection Interval, Inservice Inspection, System Pressure Test, Containment Inspection, and Repair and Replacement Programs, Owners Activity Report Cycle . CNL-22-090, Request to Use a Later Edition of the American Society of Mechanical Engineers Operation and Maintenance Code and Alternative Requests for the Fifth Inservice Testing Interval2022-12-12012 December 2022 Request to Use a Later Edition of the American Society of Mechanical Engineers Operation and Maintenance Code and Alternative Requests for the Fifth Inservice Testing Interval CNL-18-060, Completion of Required Action for NRC Order EA-13-109, Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions2018-05-31031 May 2018 Completion of Required Action for NRC Order EA-13-109, Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions ML17170A0732017-06-15015 June 2017 Report Pursuant to 10 CFR 71.95 (a)(3) and (B) - Failure to Follow Conditions of TN-RAM Packaging Certificate of Compliance No. 9233 ML17033B1642017-02-0202 February 2017 American Society of Mechanical Engineers Section XI, Inservice Inspection, System Pressure Test, Containment Inservice Inspection, and Repair and Replacement - Cycle 11 Operation Programs ML17024A0362016-12-31031 December 2016 Operating Data Report for 2016 ML16146A0182016-05-25025 May 2016 Special Report 296/2016-001 for Inoperable Post Accident Monitoring (PAM) Instrumentation ML16028A2952016-01-29029 January 2016 10 CFR 71.95 Notification Associated with the Failure to Observe Certificate of Compliance Condition of the 8-120B Secondary Lid Test Port Configuration ML15356A6542015-12-22022 December 2015 Submittal of 10 CFR 50.46 30-Day Report ML15254A5432015-09-11011 September 2015 Submittal of 10 CFR 72.48 Changes, Tests, and Experiments, Biennial Summary Report Associated with the Independent Spent Fuel Storage Installation CNL-15-106, 3, Sequoyah and Watts Bar, Units 1 & 2 - Provides Service List Update for Routine Information2015-07-0808 July 2015 3, Sequoyah and Watts Bar, Units 1 & 2 - Provides Service List Update for Routine Information ML14356A3622015-02-11011 February 2015 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-13-109 (Severe Accident Capable Hardened Vents) CNL-14-210, Expedited Seismic Evaluation Process Report (CEUS Sites) Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima.2014-12-22022 December 2014 Expedited Seismic Evaluation Process Report (CEUS Sites) Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima. CNL-14-129, Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant2014-08-28028 August 2014 Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant ML13177A3522013-07-16016 July 2013 Review of Commitment Submittal for License Renewal Regarding the One-Time Inspection Procedure (TAC ME7797, ME7798, and ME7799) ML13144A5762013-05-22022 May 2013 Watt Bar, Units 1 & 2, Report of Drug Testing Error in Accordance with 10 CFR 26.719(c)(1) ML13115A9552013-05-16016 May 2013 Final ASP Analysis-Browns Ferry Nuclear Plant, Unit 3, Reactor Trip and Subsequent Loss of Offsite Power Due Failure of Unit Station System Transformer Differential Relay (LER 296/12-004) ML13092A3922013-03-27027 March 2013 Transition to 10 CFR 50.48(c) - NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition - Transition Report ML12356A1762012-11-30030 November 2012 Kld TR-505, Rev. 1, Development of Evacuation Time Estimates, Part 6 of 8 ML12335A3402012-11-27027 November 2012 Tennessee Valley Authority - Fleet Response to NRC Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding the Flooding Walkdown Results of Recommendation 2.3 of the Near-Term Task Force Review of ML1127000692011-09-26026 September 2011 Enclosure 2, Mfn 10-245 R4, Description of the Evaluation and Surveillance Recommendations for BWR/2-5 Plants ML1108712502011-03-24024 March 2011 BWR Vessel and Internals Inspection Summaries for Spring 2010 Outages ML1100502872010-06-22022 June 2010 Investigation of Tritium Releases to Groundwater ML1019304172010-05-0606 May 2010 Tritium Database Report ML12171A1892010-03-31031 March 2010 Integrated Resource Plan, Tva'S Environmental & Energy Future ML1008800282010-03-24024 March 2010 Day Report of Emergency Core Cooling System Evaluation Model Changes ML1002010142010-01-15015 January 2010 Attachment 2, Browns Ferry, Unit 1 Response to NRC Request for Supplemental Information Regarding Technical Specification Change TS-467 - Utilization of Areva Fuel and Associated Analysis Methodologies ML1002010162010-01-15015 January 2010 Gnf 0000-0111-8036-R0-NP, GE14 Fuel Thermal-Mechanical Information ML1002010152010-01-15015 January 2010 NEDO-32484, Rev. 7, Browns Ferry Nuclear Plant Units 1, 2, and 3 SAFER/GESTR-LOCA Loss-of-Coolant Accident Analysis. ML1011602102009-10-0606 October 2009 51-9121503-002, Engineering Information Record, Responses to NRC Comments Regarding Browns Ferry Unit 1 Proposed Fuel Transition Amendment ML0924605002009-08-31031 August 2009 CDI Report No. 09-25NP, Rev. 0, Stress Assessment of Browns Ferry Nuclear, Unit 1 Steam Dryer to 120% OLTP Power Level, Enclosure 5 ML0834600222008-11-30030 November 2008 Enclosure 2 - Browns Ferry, Units 1, 2, & 3 - Technical Specifications Changes TS-418 and TS-431 - Extended Power Uprate - CDI Report 07-11NP, Revision 1, Dynamics of BWR Steam Dryer Components, Non-Proprietary Version ML0711503692007-04-23023 April 2007 Units 1, 2, & 3 - Submittal of Unit 1 Periodic Inspection Program for License Renewal Procedure in Fulfillment of License Renewal Commitment ML0710303972007-04-13013 April 2007 Status of Unit 1 Restart Issues, Revision 12 ML0635300372006-12-14014 December 2006 Core Operating Limits Report for Cycle 7 Operation ML0631004422006-11-0101 November 2006 Supplemental Information - Changes to Instrumentation Surveillance Test Intervals and Allowed Out-of-Service Times ML0622002772006-07-26026 July 2006 Technical Specifications (TS) Changes TS-431 & TS-418 - Extended Power Uprate (EPU) - Response to Round 7 Requests for Additional Information ML0616701512006-06-12012 June 2006 Extended Power Uprate (EPU) - Reload Analysis Report ML0625103852006-05-31031 May 2006 Enclosure 3, Browns Ferry, Units 1, 2 & 3 - CDI Report No. 05-28P, Rev 1, Bounding Methodology to Predict Full Scale Steam Dryer Loads from In-Plant Measurements. ML0614503972006-05-15015 May 2006 0043-8325-SRLR, Revision 1, Supplemental Reload Licensing Report for Brown Ferry 1, Reload 6 Cycle 7, Pages 123 Through End ML0614503952006-05-15015 May 2006 0043-8325-SRLR, Revision 1, Supplemental Reload Licensing Report for Brown Ferry 1, Reload 6 Cycle 7, Cover Through Page 122 ML0608804132006-03-21021 March 2006 EPU Containment Overpressure Credit Risk Assessment, Rev. 1 ML0607204302006-03-0101 March 2006 March 1, 2006 Public Meeting Slides for Proposed Generic Letter Post-Fire Safe-Shutdown Circuit Analysis Spurious Actuations. ML0513004622005-04-27027 April 2005 Technical Specifications Change 438- Response to Request for Additional Information Regarding Excess Flow Check Valve Surveillance Test Frequency ML0511702422005-04-25025 April 2005 (BFN) - Units 2, and 3 - Response to Nrc'S Request for Additional Information Related to Technical Specifications (TS) Change No. TS-418 - Request for Extended Power Uprate Operation ML0511702442005-04-25025 April 2005 (BFN) - Unit 1 - Response to Nrc'S Request for Additional Information Related to Technical Specifications (TS) Change No. TS-431 - Request for Extended Power Uprate Operation ML0606805962005-02-28028 February 2005 Hydrothermal Modeling of Browns Ferry with Units 1, 2, and 3 at Extended Power Uprate ML0603806742004-03-26026 March 2004 Seismic - Induced Ii/I Spray Evaluations at Browns Ferry Nuclear Plant Unit 1 ML0423305632004-03-18018 March 2004 TVA Systems and Analysis Browns Ferry Nuclear Plant, Probabilistic Safety Assessment Unit 3.Summary Report Rev. 1, January 2003 2024-02-22
[Table view] |
Text
Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402
CNL-14-129 August 28, 2014
10 CFR 2.202 10 CFR 50.4 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Browns Ferry Nuclear Plant, Units 1, 2, and 3 Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296
Subject:
Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant (TAC Nos. MF0881, MF0882, and MF0883)
References:
- 1. NRC Order Number EA-12-051, "Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," dated March 12, 2012 (ML12054A679)
- 2. NRC Interim Staff Guidance JLD-ISG-2012-03, "Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation," Revision 0, dated August 29, 2012 (ML12221A339)
- 3. NEI 12-02, "Industry Guidance for Compliance with NRC Order EA-12-51, 'To Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation,'" Revision 1, dated August 2012 (ML12240A307)
- 4. Letter from TVA to NRC, "Tennessee Valley Authority (TVA) - Initial Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)," dated October 29, 2012 (ML12307A105)
U.S. Nuclear Regulatory Commission Page 2 August 28, 2014
- 5. Letter from TVA to NRC, "Tennessee Valley Authority (TVA) - Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant," dated February 28, 2013 (ML13063A437)
- 6. Letter from NRC to TVA, "Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Regarding Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) (TAC Nos. MF0881, MF0882, and MF0883)," dated June 18, 2013 (ML13157A164)
- 7. Letter from TVA to NRC, "Response to NRC Request for Additional Information Regarding Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for
Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)
(TAC Nos. MF0881, MF0882, and MF0883)," dated July 18, 2013
(ML13206A005)
- 8. Letter from TVA to NRC, "First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant," dated August 28, 2013 (ML13247A290)
- 9. Letter from NRC to TVA, "Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation (TAC No. MF0881, MF0882, and MF0883)," dated November 14, 2013 (ML13274A657)
- 10. Letter from TVA to NRC, "Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant (TAC Nos. MF0881, MF0882, and MF0883), dated February 28, 2014 (ML14064A240)
On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued an order (Reference 1) to Tennessee Valley Authority (TVA).
Reference 1 was immediately effective and directs TVA to install reliable spent fuel pool level instrumentation (SFPLI). Specific requirements are outlined in Attachment 2 of Reference 1.
U.S. Nuclear Regulatory Commission Page 3 August 28, 2014
Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (Reference 2) and an overall integrated plan pursuant to Section IV, Condition C. Reference 2 endorses industry guidance document Nuclear Energy Institute (NEI) 12-02, Revision 1 (Reference 3) with clarifications and exceptions identified in Reference 2. Reference 4 provided the TVA initial status report regarding SFPLI strategies.
Reference 5 provided the TVA Browns Ferry Nuclear Plant, Units 1, 2, and 3 overall
integrated plan. On June 18, 2013, the NRC issued a request for additional information (RAI) (Reference 6) and TVA provided its response on July 18, 2013 (Reference 7).
Reference 1 requires submission of a status report at six-month intervals following submittal of the overall integrated plan. Reference 3 provides direction regarding the content of the status reports. TVA submitted the first six-month update on August 28, 2013 (Reference 8).
The NRC issued its Interim Staff Evaluation and RAIs regarding TVA's overall integrated plan on November 14, 2013 (Reference 9). TVA submitted the second six-month update on February 28, 2014 (Reference 10).
The purpose of this letter is to provide the third six-month status report pursuant to Section IV, Condition C.2, of Reference 1 that delineates progress made in implementing the requirements of Reference 1. The enclosed report provides an update of milestone accomplishments since submittal of the second six-month status report, including any changes to the compliance method or schedule. The enclosed report also provides a status of the response to the RAIs issued by NRC in Reference 9.
The enclosure describes the plans that TVA will use to meet the regulatory requirements outlined in Attachment 2 of Reference 1, but does not identify any additional actions to be taken by TVA. Therefore, this letter contains no regulatory commitments.
If you have any question regarding this submittal, please contact Kevin Casey at
(423) 751-8523.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 28th day of August 2014.
Respectfully,
J. W. Shea Vice President, Nuclear Licensing
Enclosure:
Tennessee Valley Authority Browns Ferry Nuclear Plant's Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) cc: See Page 4 J. W. Shea Digitally signed by J. W. Shea DN: cn=J. W. Shea, o=Tennessee Valley
Authority, ou=Nuclear Licensing, email=jwshea@tva.gov, c=US Date: 2014.08.28 19:25:01 -04'00' U.S. Nuclear Regulatory Commission Page 4 August 28, 2014
Enclosure
cc (Enclosure):
NRR Director - NRC Headquarters NRO Director - NRC Headquarters NRR JLD Director - NRC Headquarters NRC Regional Administrator - Region II NRC Project Manager - Browns Ferry Nuclear Plant NRC Senior Resident Inspector - Browns Ferry Nuclear Plant
Page 1 of 4 ENCLOSURE TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT THIRD SIX-MONTH STATUS REPORT IN RESPONSE TO THE MARCH 12, 2012, COMMISSION ORDER MODIFYING LICENSES WITH REGARD TO RELIABLE SPENT FUEL POOL INSTRUMENTATION (ORDER NUMBER EA-12-051) 1 Introduction
Browns Ferry Nuclear Plant (BFN) developed an Overall Integrated Plan (Reference 1 in Section 8 of this Enclosure), documenting the requirements to install reliable spent fuel pool level instrumentation (SFPLI), in response to Reference 2. This enclosure provides an update of milestone accomplishments since submittal of the second six-month status report (Reference 7), including any changes to the compliance method or schedule. This enclosure also provides a response to the request for additional information (RAI) issued by the NRC in its Interim Staff Evaluation (Reference 6).
2 Milestone Accomplishments
The following milestone(s) have been completed since the development of the Overall Integrated Plan (Reference 1), and are current as of July 31, 2014.
50% design impact review of Design Change Notices (DCNs) 71159, 71160, and 71161 (Units 1, 2, and 3), for design of SFPLI, was completed on March 25, 2014.
3 Milestone Schedule Status
The following updates the milestone schedule to support the Overall Integrated Plan. This section provides the activity status of each item and the expected completion date, noting any change. The dates are planning dates subject to change as design and implementation details
are developed.
The milestone target completion dates do not impact the order implementation date.
Page 2 of 4 Milestone Target Completion Date as Stated in the Second Six-Month Update (Reference 7) Activity Status Revised Target Completion Date Submit 60 Day Status Report 10/29/2012 Complete Submit Overall Integrated Plan 02/28/2013 Complete Submit 6 Month Updates:
Update 1 08/28/2013 Complete Update 2 02/28/2014 Complete Update 3 08/28/2014 Complete Update 4 02/28/2015 Not Started Update 5 08/28/2015 Not Started Update 6 02/282016 Not Started Update 7 08/28/2016 Not Started June 18, 2013 RAI Response 07/18/2013 Complete NRC ISE RAI Response 10/31/2014 Started Modifications:
Unit 1 Design Engineering 06/24/2014 Design started 09/02/2014 Unit 1 Implementation 07/20/2015Not Started 07/15/2015 Unit 2 Design Engineering 06/24/2014 Design started 09/02/2014 Unit 2 Implementation 04/22/2015Not Started 03/25/2015 Unit 3 Design Engineering 06/24/2014 Design started 09/02/2014 Unit 3 Implementation 08/14/2015Not Started 07/10/2015 Procedures:
Create Procedures 10/31/2014 Not Started Training:
Develop Training Plan 09/30/2014 Not Started Training Complete 03/31/2015 Not Started 03/25/2015 Full Site SFPLI Implementation 11/15/2016 Not Started 07/15/2015 Submit Completion Report 12/15/2016 Not Started 08/15/2015 4 Changes to Compliance Method
There are no other changes to the compliance method as documented in the Overall Integrated Plan (Reference 1) and the first and second six-month update (References 5 and 7).
5 Need for Relief/Relaxation and Basis for the Relief/Relaxation
Browns Ferry Nuclear Plant (BFN) expects to comply with the order implementation date and no relief/relaxation is required at this time.
Page 3 of 4 6 Open Items from Overall Integrated Plan and NRC Evaluation The following tables provide a summary of the open items documented in the Overall Integrated Plan or the NRC Evaluation and the status of each item.
Overall Integrated Plan Open Item Status OI-1) TVA will complete an instrument channel uncertainty calculation and document instrument channel accuracy and calibration requirements.
Engineering and vendor documentation are in progress. This will complete on the Design Engineering milestone shown in the table in Section 3. OI-2) TVA plans to utilize Guided Wave Radar technology. Confirm final technology selection
after contracts are complete.
Closed - Guided Wave Radar technology was utilized. OI-3) Confirm that the sensor cable and light weight at the bottom of sensor cable will not damage the SFP liner from impact during seismic event. Engineering and vendor documentation are in progress. This will complete on the Design Engineering milestone shown in the table in Section 3. OI-4) After detailed engineering design is complete, confirm that SFP level channel components and cable routing will be contained within seismic structures such that the installation will comply with the reasonable protection guidance of NEI-12-06. Engineering and vendor documentation are in progress.
This will complete on the Design Engineering milestone shown in the table in Section 3.
Draft Safety Evaluation Open Item Status None N/A 7 Potential NRC Evaluation Impacts There are no potential impacts to the NRC Evaluation identified at this time.
Page 4 of 4 8 References The following references support the updates to the Overall Integrated Plan described in this enclosure.
- 1. Letter from TVA to NRC, "Tennessee Valley Authority (TVA) - Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant," dated February 28, 2013. (ML13063A437)
- 2. NRC Order Number EA-12-051, "Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," dated March 12, 2012. (ML12054A679)
- 3. Letter from NRC to TVA, "Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request for Additional Information Regarding Overall integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) (TAC Nos. MF0881, MF0882, and MF0883),"
dated June 18, 2013. (ML13157A164)
- 4. Letter from TVA to NRC, "Response to NRC Request for Additional Information Regarding Overall integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) (TAC Nos. MF0881, MF0882, and MF0883)," dated July 18, 2013.
(ML13206A005)
- 5. Letter from TVA to NRC, "First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant," dated August 28, 2013. (ML13247A290)
- 6. Letter from NRC to TVA, "Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation (TAC No. MF0881, MF0882, and MF0883)," dated November 14, 2013. (ML13274A657)
- 7. Letter from TVA to NRC, ""Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant (TAC Nos. MF0881, MF0882, and MF0883), dated February 28, 2014 (ML14064A240)
- 9. RAI Response
On November 14, 2014, the NRC issued RAIs with its Interim Staff Evaluation (Reference 6). The NRC requested all RAI information be provided by October 31, 2014.