Other: CNL-14-030, Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), CNL-14-131, Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Watts Bar Nuclear Plant, CNL-14-191, Compliance Status Letter and Final Integrated Plan in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049, CNL-14-192, Compliance Letter in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Watts Bar Nuclear Plant, CNL-14-232, Closure of Open Item Discussed in Tennessee Valley Authoritys Compliance Letter in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051), ML12307A105, ML13063A440, ML13247A288, ML13254A297, ML13261A038, ML14128A129
|
MONTHYEARML12307A1052012-10-29029 October 2012 Tennessee Valley Authority - Initial Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML13063A4402013-02-28028 February 2013 Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML13204A2312013-08-0202 August 2013 RAI Related Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: RAI ML13161A2862013-08-0202 August 2013 Acknowledgement Letter for 60 Day Response to Issuance of Seismic Guidance Related to the NTTF Recommendation 2.1, Seismic Reevaluations Project stage: Request ML13254A2972013-08-28028 August 2013 First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML13247A2882013-08-28028 August 2013 First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) for Watts Bar Nuclea Project stage: Other ML13261A0382013-08-28028 August 2013 Tennessee Valley Authority, Watts Bar, First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML13254A0652013-09-0606 September 2013 Response to NRC Request for Additional Information Related to Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation Project stage: Response to RAI ML13275A3732013-10-24024 October 2013 Interim Staff Evaluation and Request for RAI Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation Project stage: RAI CNL-13-125, Response to NRC Request for Additional Information Related to Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2013-11-22022 November 2013 Response to NRC Request for Additional Information Related to Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Response to RAI CNL-14-007, Follow-up Response to NRC Request for Additional Information Related to Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number2014-01-10010 January 2014 Follow-up Response to NRC Request for Additional Information Related to Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA Project stage: Response to RAI CNL-14-030, Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2014-02-28028 February 2014 Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML14128A1292014-05-15015 May 2014 Report for the Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other CNL-14-072, Follow-up Response to NRC Request for Additional Information Related to Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order EA-12-02014-06-25025 June 2014 Follow-up Response to NRC Request for Additional Information Related to Overall Integrated Plan in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order EA-12-051 Project stage: Response to RAI ML14211A3462014-08-18018 August 2014 Report for the Westinghouse Audit in Support of Reliable Spent Fuel Instrumentation Related to Order EA-12-051 Project stage: Acceptance Review CNL-14-131, Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Watts Bar Nuclear Plant2014-08-28028 August 2014 Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Watts Bar Nuclear Plant Project stage: Other CNL-14-192, Compliance Letter in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Watts Bar Nuclear Plant2014-10-29029 October 2014 Compliance Letter in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Watts Bar Nuclear Plant Project stage: Other CNL-14-191, Compliance Status Letter and Final Integrated Plan in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-0492014-10-30030 October 2014 Compliance Status Letter and Final Integrated Plan in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other CNL-14-232, Closure of Open Item Discussed in Tennessee Valley Authoritys Compliance Letter in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)2014-12-19019 December 2014 Closure of Open Item Discussed in Tennessee Valley Authoritys Compliance Letter in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) Project stage: Other ML15078A1932015-03-27027 March 2015 Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Approval 2014-10-29
[Table View] |
Text
Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 EA-12-051 October 29, 2012 10 CFR 2.202 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Bellefonte Nuclear Plant, Units 1 and 2 Construction Permit Nos. CPPR-122 and CPPR-123 NRC Docket Nos. 50-438 and 50-439 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296 Sequoyah Nuclear Plant, Units 1 and 2 Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328 Watts Bar Nuclear Plant, Unit 1 Facility Operating License No. NPF-90 NRC Docket No. 50-390 Watts Bar Nuclear Plant, Unit 2 Construction Permit No. CPPR-92 NRC Docket No. 50-391
Subject:
Tennessee Valley Authority (TVA) - Initial Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Fuel Pool Instrumentation (Order Number EA-1 2-051)
References:
- 1. NRC Order Number EA-12-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation
- 2. NRC Interim Staff Guidance JLD-ISG-2012-03, Compliance with Order EA-1 2-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, Revision 0, dated August 29, 2012 eoo Printed on recycled paper
U.S. Nuclear Regulatory Commission Page 2 October 29, 2012 On March 12, 2012, the Nuclear Regulatory Commission ("NRC" or "Commission") issued an order (Reference 1) to the Tennessee Valley Authority (TVA). Reference 1 was immediately effective and directs TVA to have a reliable indication of the water level in associated spent fuel storage pools. Specific requirements are outlined in Attachment 2 of Reference 1.
Reference 1 requires submission of an initial status report 60 days following issuance of the final interim staff guidance. The final interim staff guidance (Reference 2) was issued August 29, 2012. The purpose of this letter is to provide the initial status report pursuant to Section IV, Condition C.2, of Reference 1 within 60 days following issuance of Reference 2.
This report confirms TVA has received Reference 2 and is in the process of evaluating the guidance for the purpose of providing a reliable indication of the water level in associated spent fuel storage pools as described in Attachment 2 of Reference 1.
Major activities completed during this reporting period:
Resources are being identified and project plans initiated, including development of milestones, to assure compliance with Reference 1.
Planned activities for Browns Ferry Nuclear Plant, Units 1, 2, and 3, Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 for the next six months:
Development and submittal of the overall integrated plan.
Planned activities for Bellefonte Nuclear Plant Units 1 and 2 for the next six months:
Development of the overall integrated plan.
Technical difficulties encountered that could affect the ability to provide the licensee's February 28, 2013, submittal:
None at this time.
U.S. Nuclear Regulatory Commission Page 3 October 29, 2012 Project milestones schedule through completion of installation and testing:
S S
A project milestones schedule will be provided with the overall integrated plan.
Implementation of the order will be completed for each Site and Unit number prior to startup from the Refueling Outage (RFO) or prior to issuance of an operating license as indicated below:
0 0
0 0
0 0
0 0
0 Bellefonte Nuclear Plant, Unit 1 Bellefonte Nuclear Plant, Unit 2 Browns Ferry Nuclear Plant, Unit 1 Browns Ferry Nuclear Plant, Unit 2 Browns Ferry Nuclear Plant, Unit 3 Sequoyah Nuclear Plant, Unit 1 Sequoyah Nuclear Plant, Unit 2 Watts Bar Nuclear Plant, Unit 1 Watts Bar Nuclear Plant, Unit 2 prior to issuance of an operating license prior to issuance of an operating license prior to startup from RFO 11, Fall/2016 prior to startup from RFO 18, Spring/2015 prior to startup from RFO 17, Spring/2016 prior to startup from RFO 20, Spring/2015 prior to startup from RFO 20, Fall/2015 prior to startup from RFO 13, Fall/2015 prior to issuance of an operating license This letter contains no new regulatory commitments. If you have questions regarding our comments, please contact Kevin Casey at (423)751-8523.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 29th day of October 2012.
Licensing
U.S. Nuclear Regulatory Commission Page 4 October 29, 2012 cc:
NRR Director - NRC Headquarters NRO Director - NRC Headquarters NRC Regional Administrator - Region II NRR Project Manager - Bellefonte Nuclear Plant NRR Project Manager - Browns Ferry Nuclear Plant NRR Project Manager - Sequoyah Nuclear Plant NRR Project Manager - Watts Bar Nuclear Plant NRC Senior Resident Inspector - Browns Ferry Nuclear Plant NRC Senior Resident Inspector - Sequoyah Nuclear Plant NRC Senior Resident Inspector - Watts Bar Nuclear Plant Ms. Lisa M. Regner, NRR/JLD/PMB, NRC Mr. Blake A. Purnell, NRR/JLD/PMB, NRC Mr. Steven R. Jones, NRR/DSS/SBPB, NRC