| {{#Wiki_filter:1NRR-PMDAPEm ResourceFrom:Green, KimberlySent:Friday, July 07, 2017 12:01 PMTo:Mathews, Mitchel A:(GenCo-Nuc) | | {{#Wiki_filter:1NRR-PMDAPEm Resource From:Green, Kimberly Sent:Friday, July 07, 2017 12:01 PM To:Mathews, Mitchel A:(GenCo-Nuc) |
|
| |
|
| ==Subject:== | | ==Subject:== |
| Draft RAI for QC LAR re Permanent Extension of Type A and Type C Leak Rate Testing FrequenciesAttachments:Quad Cities Draft RAI Set 2.docx | | Draft RAI for QC LAR re Permanent Extension of Type A and Type C Leak Rate Testing Frequencies Attachments: |
| | Quad Cities Draft RAI Set 2.docx |
|
| |
|
| ==Dear Mr. Mathews:== | | ==Dear Mr. Mathews:== |
Line 27: |
Line 28: |
| The U.S Nuclear Regulatory Commission (NRC) staff is reviewing your submittal and has identified areas where additional information is needed to complete its review. Attached, please find a draft request for additional information (RAI). | | The U.S Nuclear Regulatory Commission (NRC) staff is reviewing your submittal and has identified areas where additional information is needed to complete its review. Attached, please find a draft request for additional information (RAI). |
|
| |
|
| The draft RAI is being sent to ensure that the questions are understandable and the regulatory basis for the questions is clear. This email and the attachment do not convey or represent an NRC staff position regarding EGC's request. | | The draft RAI is being sent to ensure that the questions are understandable and the regulatory basis for the questions is clear. This email and the attachment do not convey or represent an NRC staff position regarding EGC's request. |
| Please note that the draft requests are numbered 7 and 8. An RAI with requests 1 through 6 were previously transmitted to you by letter dated June 29, 2017. | | |
| Please let me know if you need a call to clarify the NRC staff's requests. | | Please note that the draft requests are numbered 7 and 8. An RAI with requests 1 through 6 were previously transmitted to you by letter dated June 29, 2017. |
| Sincerely, Kimberly Green, Sr. Project Manager Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-1627 kimberly.green@nrc.gov Hearing Identifier: NRR_PMDA Email Number: 3612 Mail Envelope Properties (Kimberly.Green@nrc.gov20170707120000) | | |
| | Please let me know if you need a call to clarify the NRC staff's requests. |
| | |
| | Sincerely, Kimberly Green, Sr. Project Manager Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-1627 kimberly.green@nrc.gov |
| | |
| | Hearing Identifier: NRR_PMDA Email Number: 3612 Mail Envelope Properties (Kimberly.Green@nrc.gov20170707120000) |
|
| |
|
| ==Subject:== | | ==Subject:== |
| Draft RAI for QC LAR re Permanent Extension of Type A and Type C Leak Rate Testing Frequencies Sent Date: 7/7/2017 12:00:49 PM Received Date: 7/7/2017 12:00:00 PM From: Green, Kimberly Created By: Kimberly.Green@nrc.gov Recipients: "Mathews, Mitchel A:(GenCo-Nuc)" <Mitchel.Mathews@exeloncorp.com> Tracking Status: None | | Draft RAI for QC LAR re Permanent Extension of Type A and Type C Leak Rate Testing Frequencies Sent Date: 7/7/2017 12:00:49 PM Received Date: 7/7/2017 12:00:00 PM From: Green, Kimberly Created By: Kimberly.Green@nrc.gov Recipients: "Mathews, Mitchel A:(GenCo-Nuc)" <Mitchel.Mathews@exeloncorp.com> Tracking Status: None |
|
| |
|
| Post Office: Files Size Date & Time MESSAGE 1425 7/7/2017 12:00:00 PM Quad Cities Draft RAI Set 2.docx 34996 | | Post Office: Files Size Date & Time MESSAGE 1425 7/7/2017 12:00:00 PM Quad Cities Draft RAI Set 2.docx 34996 |
|
| |
|
| Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received: | | Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received: |
| DRAFT REQUEST FOR ADDITIONAL INFORMATION EXELON GENERATION COMPANY, LLC QUAD CITIES NUCLEAR POWER STATION (QCNPS), UNITS 1 AND 2 DOCKET NOS. 50-254 and 50-265 By letter dated April 27, 2017, Exelon Generation Company, LLC (EGC), submitted a license amendment request (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17121A449). The proposed amendment would modify Technical Specification 5.5.12, "Primary Containment Leakage Rate Testing Program," to allow for the permanent extension of the Type A Integrated Leak Rate Testing and Type C Leak Rate Testing frequencies. The additional information below is needed to support the Nuclear Regulatory (NRC) staff's continued technical review of the license amendment request (LAR). | | DRAFT REQUEST FOR ADDITIONAL INFORMATION EXELON GENERATION COMPANY, LLC QUAD CITIES NUCLEAR POWER STATION (QCNPS), UNITS 1 AND 2 DOCKET NOS. 50-254 and 50-265 |
| RAI 7 Background Title 10 of the Code of Federal Regulations (10 CFR) 50, Appendix J, Option B, requires a general visual inspection of the containment prior to each Type A test and at a periodic interval between tests. Nuclear Energy Institute 94-01, Revision 3-A, recommends these inspections be performed in conjunction with the American Society of Mechanical Engineers (ASME) Code, Section XI, Subsection IWE required examinations. Section 3.5.2 of the LAR indicates that QCNPS will use the required ASME Code examinations to meet the Appendix J requirement regarding visual inspections. The regulation at 10 CFR 50.55a(b)(2)(ix)(A) imposes a condition on the use of ASME Code, Section XI, Subsection IWE, which requires licensees to evaluate the acceptability of inaccessible metal containment areas when conditions exist in accessible areas that could indicate the presence of, or result in degradation to, such inaccessible areas. | | |
| Issue Table 3.5-3 of the LAR summarizes the results of the ASME Section XI, Subsection IWE metal containment inspections performed over the last three outages. The table notes that both units have identified recordable indications on the moisture barrier; however, no discussion is provided regarding the containment behind the moisture barrier. A degraded moisture barrier could indicate the presence of degradation in the inaccessible areas behind the moisture barrier. | | By letter dated April 27, 2017, Exelon Generation Company, LLC (EGC), submitted a license amendment request (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17121A449). The proposed amendment would modify Technical Specification 5.5.12, "Primary Containment Leakage Rate Testing Program," to allow for the permanent extension of the Type A Integrated Leak Rate Testing and Type C Leak Rate Testing frequencies. The additional information below is needed to support the Nuclear Regulatory (NRC) staff's continued technical review of the license amendment request (LAR). |
| | |
| | RAI 7 Background |
| | |
| | Title 10 of the Code of Federal Regulations (10 CFR) 50, Appendix J, Option B, requires a general visual inspection of the containment prior to each Type A test and at a periodic interval between tests. Nuclear Energy Institute 94-01, Revision 3-A, recommends these inspections be performed in conjunction with the American Society of Mechanical Engineers (ASME) Code, Section XI, Subsection IWE required examinations. Section 3.5.2 of the LAR indicates that QCNPS will use the required ASME Code examinat ions to meet the Appendix J requirement regarding visual inspections. |
| | The regulation at 10 CFR 50.55a(b)(2)(ix)(A) imposes a condition on the use of ASME Code, Section XI, Subsection IWE, which requires licensees to evaluate the acceptability of inaccessible metal containment areas when conditions exist in accessible areas that could indicate the presence of, or result in degradation to, such inaccessible areas. |
| | |
| | Issue Table 3.5-3 of the LAR summarizes the results of the ASME Section XI, Subsection IWE metal containment inspections performed over the last three outages. The table notes that both units have identified recordable indications on the moisture barrier; however, no discussion is provided regarding the containment behind the moisture barrier. A degraded moisture barrier could indicate the presence of degradation in the inaccessible areas behind the moisture |
| | |
| | barrier. |
| | |
| | It is not clear to the staff how EGC determined that the degraded moisture barrier did not allow moisture to contact the containment and cause degradation in an inaccessible area. |
| | Request Summarize the results of any 10 CFR 50.55a(b)(2)(ix)(A) evaluations associated with noted moisture barrier indications, or explain how EGC determined that the inaccessible portions of the containment were not impacted and that an evaluation was not necessary. |
| | |
| | RAI 8 Background |
|
| |
|
| It is not clear to the staff how EGC determined that the degraded moisture barrier did not allow moisture to contact the containment and cause degradation in an inaccessible area. Request Summarize the results of any 10 CFR 50.55a(b)(2)(ix)(A) evaluations associated with noted moisture barrier indications, or explain how EGC determined that the inaccessible portions of the containment were not impacted and that an evaluation was not necessary.
| | Appendix J to 10 CFR 50, Option B, requires a general visual inspection of the containment prior to each Type A test and at a periodic interval between tests for indications of structural deterioration that may impact leak-tightness. Section 3.6.5 of the LAR notes that inspections of the sand pocket region and drywell liner area are conducted at QCNPS during each refueling outage. Table 3.6.5-1 of the LAR summarizes the results of the last two inspections. |
|
| |
|
| RAI 8 Background Appendix J to 10 CFR 50, Option B, requires a general visual inspection of the containment prior to each Type A test and at a periodic interval between tests for indications of structural deterioration that may impact leak-tightness. Section 3.6.5 of the LAR notes that inspections of the sand pocket region and drywell liner area are conducted at QCNPS during each refueling outage. Table 3.6.5-1 of the LAR summarizes the results of the last two inspections.
| | Issue Table 3.6.5-1 Note (2) of the LAR, related to Unit 1, states that there is leakage but that the leakage is not from the drains and appears to be groundwater leakage with no structural impact. Note (4), related to Unit 2, also indicates issues with groundwater leakage. From the notes, it appears the leakage is an ongoing issue. |
|
| |
|
| Issue Table 3.6.5-1 Note (2) of the LAR, related to Unit 1, states that there is leakage but that the leakage is not from the drains and appears to be groundwater leakage with no structural impact. Note (4), related to Unit 2, also indicates issues with groundwater leakage. From the notes, it appears the leakage is an ongoing issue.
| |
| It is not clear to the staff how EGC determined that the leakage is groundwater and that the leakage is not impacting the structural integrity or leak-tightness of the containment. | | It is not clear to the staff how EGC determined that the leakage is groundwater and that the leakage is not impacting the structural integrity or leak-tightness of the containment. |
|
| |
|
| Request For both units, explain how EGC determined that the identified leakage is groundwater and that the leakage is not impacting the structural integrity or leak-tightness of the containment.}} | | Request For both units, explain how EGC determined that the identified leakage is groundwater and that the leakage is not impacting the structural integrity or leak-tightness of the containment.}} |
|
---|
Category:E-Mail
MONTHYEARML24254A2082024-09-10010 September 2024 NRR E-mail Capture - Quad Cities, Unit Nos. 1 and 2 - Alternative to RV-08, Rev 1, SRV Testing Interval - Acceptance of Requested Licensing Action Re Relief Request Associated with Safety Relief Valve Testing Interval ML24250A1062024-09-0606 September 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 ML24197A0482024-07-12012 July 2024 Information Request for the Quad Cities Nuclear Station Biennial Problem Identification and Resolution Inspection ML24135A0182024-05-13013 May 2024 NRR E-mail Capture - Draft Request for Additional Information Quad Cities TSTF-505 Amendment ML24131A0612024-05-10010 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24086A5182024-04-30030 April 2024 E-mail to Christian Williams Decision on the Exemption Request for Quad Cities ML24086A4782024-04-24024 April 2024 Email to Christian Williams Availability of Environmental Assessment for the Quad Cities Exemption ML24114A1702024-04-15015 April 2024 Request for State Review of the Quad Cities HI-STORM Exemption Request Environmental Assessment ML24102A2422024-04-10010 April 2024 NRR E-mail Capture - Draft Request for Additional Information Quad Cities TSTF-505 and 50.69 Amendments ML24089A0102024-03-29029 March 2024 NRR E-mail Capture - Quad Cities Unit Nos. 1 and 2 - Alternative to Core Spray Pump Testing - Acceptance of Requested Licensing Action Relief Request Associated with the Sixth Inservice Testing Interval ML24066A1532024-03-0606 March 2024 NRR E-mail Capture - Request for Additional Information TSTF-505, R2, Provide Risk-Informed Extended Completion Times, RITSTF (Risk-Informed Technical Specification Task Force) Initiative 4b and 10 CFR 50.69 License Amendments ML23349A0362023-12-14014 December 2023 NRR E-mail Capture - Draft Request for Additional Information Re Quad Cities Emergency Amendment Related to Unit 1 Diesel Generator Inoperability ML23338A1192023-11-21021 November 2023 NRR E-mail Capture - Draft Request for Additional Information Quad Cities Relief Request I5R-26 ML23268A0022023-09-22022 September 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-264-A, Revision 0 ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC – Fleet Request – License Amendment Request to Adopt TSTF-580, Revision 1 ML23262A7432023-09-19019 September 2023 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 – Acceptance of Relief Request I5R-26 ML23186A1412023-07-0505 July 2023 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Requested Licensing Action Amendment to Adopt TSTF-505 ML23186A1482023-07-0505 July 2023 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Requested Licensing Action Amendment to Adopt 10 CFR 50.69 ML23163A2292023-06-12012 June 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-580, Revision 1 ML23118A1652023-04-28028 April 2023 NRR E-mail Capture - Request for Additional Information Quad Cities, Unit 2, Alternative Request I6R-11 ML23083B9572023-03-24024 March 2023 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Requested Licensing Action Amendment to Adopt TSTF-564 ML23055A0392023-02-24024 February 2023 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Amendment to Adopt TSTF-416 ML23052A0772023-02-21021 February 2023 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance Timely Renewal Exemption Request ML22357A0392022-12-23023 December 2022 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of I6R-10 Related to Repair of Penetration N-11B ML22354A2622022-12-20020 December 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Request to Use Certain Provisions of the 2019 Edition of the ASME BPV Code, Section XI ML23004A0262022-12-16016 December 2022 NRR E-mail Capture - Draft Request for Additional Information - Quad Cities Alternative RV-04, Inservice Testing of High Pressure Coolant Injection Drain Pot Solenoid Valves (EPD L-2022-LLR-0070) ML22348A0452022-12-14014 December 2022 NRR E-mail Capture - Draft Request for Additional Information Regarding Quad Cities Alternative I6R-09 ML22301A0902022-10-28028 October 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-301, Revision 2 ML22290A0662022-10-17017 October 2022 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Alternative RV-04 Related to HPCI Drain Pot Solenoid Valve Testing ML23079A0272022-10-0505 October 2022 Licensee Outline Submittal Email (Quad Cities, 2023) ML22256A0112022-09-12012 September 2022 NRR E-mail Capture - Request for Additional Information LaSalle County Station, Units 1 and 2 and Quad Cities Nuclear Power Station, Units 1 and 2 License Amendments Related to Fuel Storage ML22224A0222022-08-12012 August 2022 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Alternative I6R-09 Related to Use of Certain 2013 Edition ASME Code Requirements ML22200A0782022-07-19019 July 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request to Use Honeywell Mururoa V4F1 R Supplied Air Suits ML22206A0352022-07-13013 July 2022 NRR E-mail Capture - Draft RAI Quad Cities Alternative Related to Sblc Nozzle Inspection ML22193A0412022-07-11011 July 2022 NRR E-mail Capture - RAI Quad Cities License Amendment to Expand the Use of Prime Methods ML22187A1832022-07-0606 July 2022 NRR E-mail Capture - Completion of Activities Related to EPID L-2022-LLD-003, Quad Cities Potential NOED ML22182A1992022-07-0101 July 2022 NRR E-mail Capture - RAI Alternative RV-11, Code Case OMN-28 ML22164A8582022-06-13013 June 2022 NRR E-mail Capture - RAI Alternative RV-09, MSSVs ML22164A8562022-06-13013 June 2022 NRR E-mail Capture - RAI Quad Cities Alternative RV-08, Safety Relief Valves ML22164A7852022-06-13013 June 2022 NRR E-mail Capture - RAI Quad Cities Amendment for Spent Fuel Pool Storage Analysis ML22101A0932022-04-11011 April 2022 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Relief I6R-01 Related to SLC Nozzle Inner Radius Inspection ML22077A4122022-03-18018 March 2022 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Alternative RV-06 Related to MSSV Setpoint Testing ML22076A0322022-03-17017 March 2022 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Alternative RV-03 Related to PIV Leak Test Frequency ML22075A0752022-03-16016 March 2022 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Alternative RV-07 Related to MSIV Stroke Testing ML22068A1512022-03-0909 March 2022 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Alternative RV-10 Related to Code Case OMN-28, MOV Testing ML22068A0552022-03-0909 March 2022 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Alternative RV-09 Related to MSSV Testing ML22068A0062022-03-0909 March 2022 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Alternative RV-11 Related to OMN-28, Valve Position Verification ML22067A2172022-03-0808 March 2022 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Alternative Related to MSRV Testing ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 2024-09-06
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24197A0482024-07-12012 July 2024 Information Request for the Quad Cities Nuclear Station Biennial Problem Identification and Resolution Inspection ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes ML24135A0182024-05-13013 May 2024 NRR E-mail Capture - Draft Request for Additional Information Quad Cities TSTF-505 Amendment ML24102A2422024-04-10010 April 2024 NRR E-mail Capture - Draft Request for Additional Information Quad Cities TSTF-505 and 50.69 Amendments ML24066A1532024-03-0606 March 2024 NRR E-mail Capture - Request for Additional Information TSTF-505, R2, Provide Risk-Informed Extended Completion Times, RITSTF (Risk-Informed Technical Specification Task Force) Initiative 4b and 10 CFR 50.69 License Amendments ML24053A1192024-02-22022 February 2024 Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000265/2024010 and 05000254/2024010 ML23349A0362023-12-14014 December 2023 NRR E-mail Capture - Draft Request for Additional Information Re Quad Cities Emergency Amendment Related to Unit 1 Diesel Generator Inoperability ML23338A1192023-11-21021 November 2023 NRR E-mail Capture - Draft Request for Additional Information Quad Cities Relief Request I5R-26 ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC – Fleet Request – License Amendment Request to Adopt TSTF-580, Revision 1 ML23118A1652023-04-28028 April 2023 NRR E-mail Capture - Request for Additional Information Quad Cities, Unit 2, Alternative Request I6R-11 ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML23065A2832023-03-0707 March 2023 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000254/2023010 and 05000265/2023010 ML23013A1502023-01-17017 January 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000254/2023002 ML23004A0262022-12-16016 December 2022 NRR E-mail Capture - Draft Request for Additional Information - Quad Cities Alternative RV-04, Inservice Testing of High Pressure Coolant Injection Drain Pot Solenoid Valves (EPD L-2022-LLR-0070) ML22348A0452022-12-14014 December 2022 NRR E-mail Capture - Draft Request for Additional Information Regarding Quad Cities Alternative I6R-09 ML22227A1152022-09-27027 September 2022 Request for Withholding Information from Public Disclosure ML22256A0112022-09-12012 September 2022 NRR E-mail Capture - Request for Additional Information LaSalle County Station, Units 1 and 2 and Quad Cities Nuclear Power Station, Units 1 and 2 License Amendments Related to Fuel Storage ML22249A2332022-09-0606 September 2022 Notification of NRC Fire Protection Team Inspection Request for Information Inspection Report 05000254/2022011 05000265/2022011 ML22206A0352022-07-13013 July 2022 NRR E-mail Capture - Draft RAI Quad Cities Alternative Related to Sblc Nozzle Inspection ML22193A0412022-07-11011 July 2022 NRR E-mail Capture - RAI Quad Cities License Amendment to Expand the Use of Prime Methods ML22182A1992022-07-0101 July 2022 NRR E-mail Capture - RAI Alternative RV-11, Code Case OMN-28 ML22178A1362022-06-28028 June 2022 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Quad Cities Station ML22164A8582022-06-13013 June 2022 NRR E-mail Capture - RAI Alternative RV-09, MSSVs ML22164A8562022-06-13013 June 2022 NRR E-mail Capture - RAI Quad Cities Alternative RV-08, Safety Relief Valves ML22164A7852022-06-13013 June 2022 NRR E-mail Capture - RAI Quad Cities Amendment for Spent Fuel Pool Storage Analysis ML22076A1122022-03-15015 March 2022 Request for Additional Information Related to the Amendment Request to Transition to GNF3 Fuels (EPID L-2021-LLA-0159) (Redacted) ML22059A9902022-03-0101 March 2022 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment to Implement Prime Methodologies for Evaluating Thermal Overpower and Mechanical Overpower Limits for Non-Global Nuclear Fuels Fuel ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML22039A1912022-02-0808 February 2022 Information Request for an NRC Triennial 10 CFR 50.59 (Evaluation of Changes, Tests, and Experiments) Baseline Inspection ML22020A0642022-01-13013 January 2022 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles ML21342A3842021-12-0808 December 2021 NRR E-mail Capture - Request for Additional Information: Quad Cities 1 & 2 License Amendment Request Transition to GNF3 Fuel ML21294A0032021-10-26026 October 2021 Supplemental Information Needed for Acceptance of Requested Licensing Action License Amendment Request Regarding Transition to GNF3 Fuel ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21238A3142021-08-26026 August 2021 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000254/2021004; 05000265/2021004 ML21190A0192021-07-0808 July 2021 NRR E-mail Capture - Exelon Fleet - Request for Additional Information Regarding Adoption of TSTF-582 and TSTF-583-T ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML20239A7982020-08-25025 August 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet License Amendment Request to Adopt TSTF-568, Revision 2 ML20183A2852020-07-0101 July 2020 Request for Information for an NRC Triennial Baseline Bases Assurance Inspection (Team): Inspection Report 05000254/2020011 and 05000265/2020011 ML20135H1972020-05-14014 May 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Request to Extend Safety Relief Valve Test Interval ML20031C8332020-01-31031 January 2020 NRR E-mail Capture - Request for Additional Information for Quad Cities Request to Revise Technical Specifications to Increase the MSIV Leakage Rate (L-2019-LLA-0045) ML20021A0342020-01-17017 January 2020 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000254/2020002; 05000265/2020002 ML19134A2792019-05-15015 May 2019 Supplemental Information Needed for Acceptance of License Amendment Request to Increase Main Steam Isolation Valve Allowable Leakage Rates ML18346A4032018-12-0707 December 2018 10 CFR 50.59 (Evaluation of Changes, Tests and Experiments) Inspection Supplemental Request for Information (DRS-A.Shaikh) ML18067A1482018-03-0808 March 2018 Enclosurequest for Additional Information (Letter to P. R. Simpson Request for Additional Information Regarding Exelon Generating Company, Llc'S Decommissioning Funding Plan Update for Independent Spent Fuel Storage Installation) ML17353A9492018-01-0909 January 2018 Supplemental Information Needed for Acceptance of License Amendment Request to Revise Technical Specification Requirements for Secondary Containment ML17355A0112017-12-20020 December 2017 NRR E-mail Capture - Request for Additional Information Regarding Relief Request I5R-11, Revision 2 ML17333A0822017-11-28028 November 2017 17 Quad Cities Nuclear Plant, Unit 2 - Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000265/2018001 (DRS-M.Domke) ML17262A0892017-09-19019 September 2017 Request for Additional Information Concerning Permanent Extension of Type a and Type C Leak Rate Test Frequencies (RS-17-051) 2024-07-12
[Table view] |
Text
1NRR-PMDAPEm Resource From:Green, Kimberly Sent:Friday, July 07, 2017 12:01 PM To:Mathews, Mitchel A:(GenCo-Nuc)
Subject:
Draft RAI for QC LAR re Permanent Extension of Type A and Type C Leak Rate Testing Frequencies Attachments:
Quad Cities Draft RAI Set 2.docx
Dear Mr. Mathews:
By letter dated April 27, 2017, Exelon Generation Company, LLC (EGC), submitted an amendment request for Quad Cities Nuclear Power Station, Units 1 and 2 (Agencywide Documents Access and Management System Accession No. ML17121A449). The proposed amendment would modify Technical Specification 5.5.12, "Primary Containment Leakage Rate Testing Program," to allow for the permanent extension of the Type A Integrated Leak Rate Testing and Type C Leak Rate Testing frequencies.
The U.S Nuclear Regulatory Commission (NRC) staff is reviewing your submittal and has identified areas where additional information is needed to complete its review. Attached, please find a draft request for additional information (RAI).
The draft RAI is being sent to ensure that the questions are understandable and the regulatory basis for the questions is clear. This email and the attachment do not convey or represent an NRC staff position regarding EGC's request.
Please note that the draft requests are numbered 7 and 8. An RAI with requests 1 through 6 were previously transmitted to you by letter dated June 29, 2017.
Please let me know if you need a call to clarify the NRC staff's requests.
Sincerely, Kimberly Green, Sr. Project Manager Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-1627 kimberly.green@nrc.gov
Hearing Identifier: NRR_PMDA Email Number: 3612 Mail Envelope Properties (Kimberly.Green@nrc.gov20170707120000)
Subject:
Draft RAI for QC LAR re Permanent Extension of Type A and Type C Leak Rate Testing Frequencies Sent Date: 7/7/2017 12:00:49 PM Received Date: 7/7/2017 12:00:00 PM From: Green, Kimberly Created By: Kimberly.Green@nrc.gov Recipients: "Mathews, Mitchel A:(GenCo-Nuc)" <Mitchel.Mathews@exeloncorp.com> Tracking Status: None
Post Office: Files Size Date & Time MESSAGE 1425 7/7/2017 12:00:00 PM Quad Cities Draft RAI Set 2.docx 34996
Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received:
DRAFT REQUEST FOR ADDITIONAL INFORMATION EXELON GENERATION COMPANY, LLC QUAD CITIES NUCLEAR POWER STATION (QCNPS), UNITS 1 AND 2 DOCKET NOS. 50-254 and 50-265
By letter dated April 27, 2017, Exelon Generation Company, LLC (EGC), submitted a license amendment request (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17121A449). The proposed amendment would modify Technical Specification 5.5.12, "Primary Containment Leakage Rate Testing Program," to allow for the permanent extension of the Type A Integrated Leak Rate Testing and Type C Leak Rate Testing frequencies. The additional information below is needed to support the Nuclear Regulatory (NRC) staff's continued technical review of the license amendment request (LAR).
RAI 7 Background
Title 10 of the Code of Federal Regulations (10 CFR) 50, Appendix J, Option B, requires a general visual inspection of the containment prior to each Type A test and at a periodic interval between tests. Nuclear Energy Institute 94-01, Revision 3-A, recommends these inspections be performed in conjunction with the American Society of Mechanical Engineers (ASME) Code,Section XI, Subsection IWE required examinations. Section 3.5.2 of the LAR indicates that QCNPS will use the required ASME Code examinat ions to meet the Appendix J requirement regarding visual inspections.
The regulation at 10 CFR 50.55a(b)(2)(ix)(A) imposes a condition on the use of ASME Code,Section XI, Subsection IWE, which requires licensees to evaluate the acceptability of inaccessible metal containment areas when conditions exist in accessible areas that could indicate the presence of, or result in degradation to, such inaccessible areas.
Issue Table 3.5-3 of the LAR summarizes the results of the ASME Section XI, Subsection IWE metal containment inspections performed over the last three outages. The table notes that both units have identified recordable indications on the moisture barrier; however, no discussion is provided regarding the containment behind the moisture barrier. A degraded moisture barrier could indicate the presence of degradation in the inaccessible areas behind the moisture
barrier.
It is not clear to the staff how EGC determined that the degraded moisture barrier did not allow moisture to contact the containment and cause degradation in an inaccessible area.
Request Summarize the results of any 10 CFR 50.55a(b)(2)(ix)(A) evaluations associated with noted moisture barrier indications, or explain how EGC determined that the inaccessible portions of the containment were not impacted and that an evaluation was not necessary.
RAI 8 Background
Appendix J to 10 CFR 50, Option B, requires a general visual inspection of the containment prior to each Type A test and at a periodic interval between tests for indications of structural deterioration that may impact leak-tightness. Section 3.6.5 of the LAR notes that inspections of the sand pocket region and drywell liner area are conducted at QCNPS during each refueling outage. Table 3.6.5-1 of the LAR summarizes the results of the last two inspections.
Issue Table 3.6.5-1 Note (2) of the LAR, related to Unit 1, states that there is leakage but that the leakage is not from the drains and appears to be groundwater leakage with no structural impact. Note (4), related to Unit 2, also indicates issues with groundwater leakage. From the notes, it appears the leakage is an ongoing issue.
It is not clear to the staff how EGC determined that the leakage is groundwater and that the leakage is not impacting the structural integrity or leak-tightness of the containment.
Request For both units, explain how EGC determined that the identified leakage is groundwater and that the leakage is not impacting the structural integrity or leak-tightness of the containment.