MONTHYEARIR 05000254/20240112024-11-13013 November 2024 Biennial Problem Identification and Resolution Inspection Report 05000254/2024011 and 05000265/2024011 IR 05000254/20240032024-11-12012 November 2024 Integrated Inspection Report 05000254/2024003, 05000265/2024003 and 07200053/2024001 ML24317A1432024-11-0404 November 2024 Constellation Energy Generation, LLC, 2024 Annual Report - Guarantees of Payment of Deferred Premiums RS-24-101, License Amendment Request for One-Time Extension of Standby Gas Treatment System Technical Specifications Completion Time to Support Piping Repair2024-11-0404 November 2024 License Amendment Request for One-Time Extension of Standby Gas Treatment System Technical Specifications Completion Time to Support Piping Repair RS-24-126, Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in Accordance with 10 CFR 2.390(b)(4)2024-10-31031 October 2024 Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in Accordance with 10 CFR 2.390(b)(4) 05000265/LER-2024-002-01, Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure2024-10-30030 October 2024 Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure SVP-24-065, Offsite Dose Calculation Manual (ODCM) Section 12.2.2 Radioactive Gaseous Effluent Monitoring Instrumentation Report Main Chimney High Range Noble Gas Monitor2024-10-29029 October 2024 Offsite Dose Calculation Manual (ODCM) Section 12.2.2 Radioactive Gaseous Effluent Monitoring Instrumentation Report Main Chimney High Range Noble Gas Monitor IR 05000254/20240102024-10-28028 October 2024 Age Related Degradation Inspection Report 05000254/2024010 and 05000265/2024010 and Notice of Violation RS-24-080, Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in .2024-10-16016 October 2024 Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in . RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests SVP-24-059, Correction to Registration of Use of Casks to Store Spent Fuel2024-10-0404 October 2024 Correction to Registration of Use of Casks to Store Spent Fuel ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24247A1642024-09-30030 September 2024 Alternative Request RP-01 IR 05000254/20244022024-09-12012 September 2024 Material Control and Accounting Program Inspection Report 05000254/2024402 and 05000265/2024402 (Public) SVP-24-054, Deviation from BWR Vessel and Internals Project (BWRVIP) Guidelines - Inspection of Top Guide Rim Welds2024-09-11011 September 2024 Deviation from BWR Vessel and Internals Project (BWRVIP) Guidelines - Inspection of Top Guide Rim Welds ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000254/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Quad Cities Nuclear Power Station (Report 05000254/2024005; 05000265/2024005) RS-24-078, Alternative Request RV-08, Revision 1, Associated with Safety Relief Valve Testing Interval2024-08-20020 August 2024 Alternative Request RV-08, Revision 1, Associated with Safety Relief Valve Testing Interval ML24183A1082024-08-0808 August 2024 – Issuance of Amendment Nos. 302 and 298 Adoption of Tstf-505, Provide Risk Informed Extended Completion Times – RITSTF Initiative 4b SVP-24-049, Owners Activity Report Submittal Sixth 10-Year Interval 2024 Refueling Outage Activities2024-08-0707 August 2024 Owners Activity Report Submittal Sixth 10-Year Interval 2024 Refueling Outage Activities IR 05000254/20243012024-08-0101 August 2024 NRC Initial License Examination Report 05000254/2024301; 05000265/2024301 SVP-24-048, Registration of Use of Casks to Store Spent Fuel2024-07-31031 July 2024 Registration of Use of Casks to Store Spent Fuel 05000265/LER-2024-002, Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure2024-07-22022 July 2024 Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions SVP-24-041, Regulatory Commitment Change Summary Report2024-07-0505 July 2024 Regulatory Commitment Change Summary Report SVP-24-043, Registration of Use of Casks to Store Spent Fuel2024-07-0505 July 2024 Registration of Use of Casks to Store Spent Fuel ML24162A0982024-07-0303 July 2024 – Issuance of Amendment Nos. 301 and 297 Adoption of 10 CFR 50.69 Risk Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors SVP-24-040, Registration of Use of Casks to Store Spent Fuel2024-06-25025 June 2024 Registration of Use of Casks to Store Spent Fuel RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations SVP-24-039, Ile Post Exam Package Letter2024-06-12012 June 2024 Ile Post Exam Package Letter RS-24-053, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed2024-06-0606 June 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed ML24110A0492024-05-28028 May 2024 Audit Report Related to the TSTF-505 and 10 CFR 50.59 Amendments ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes ML24141A2102024-05-20020 May 2024 Operator Licensing Examination Approval - Quad Cities Nuclear Power Station, May 2024 RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report IR 05000254/20240012024-05-14014 May 2024 Integrated Inspection Report Nos. 05000254/2024001 and 05000265/2024001 RS-24-042, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion2024-05-10010 May 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion 05000265/LER-2024-001, Automatic Actuation of Reactor Protection System During Scram Discharge Volume Leak Rate Testing2024-05-10010 May 2024 Automatic Actuation of Reactor Protection System During Scram Discharge Volume Leak Rate Testing SVP-24-034, Annual Radiological Environmental Operating Report2024-05-10010 May 2024 Annual Radiological Environmental Operating Report RS-24-046, 10 CFR 50.46 Annual Report2024-05-0606 May 2024 10 CFR 50.46 Annual Report ML24109A0662024-05-0202 May 2024 – Relief Request I5R-26, Revision 0 RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests SVP-24-028, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2024-04-26026 April 2024 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report SVP-24-029, Radioactive Effluent Release Report for 20232024-04-26026 April 2024 Radioactive Effluent Release Report for 2023 ML24114A1712024-04-23023 April 2024 State of Illinois (IEMA-OHS) Comment Quad Cities HI-STORM Exemption Environmental Assessment SVP-24-024, Corrected Radioactive Effluent Release Report for 20222024-04-0505 April 2024 Corrected Radioactive Effluent Release Report for 2022 IR 05000254/20245012024-04-0505 April 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000254/2024501 and 05000265/2024501 RS-24-032, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion2024-04-0505 April 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report 2024-09-04
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24197A0482024-07-12012 July 2024 Information Request for the Quad Cities Nuclear Station Biennial Problem Identification and Resolution Inspection ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes ML24135A0182024-05-13013 May 2024 NRR E-mail Capture - Draft Request for Additional Information Quad Cities TSTF-505 Amendment ML24102A2422024-04-10010 April 2024 NRR E-mail Capture - Draft Request for Additional Information Quad Cities TSTF-505 and 50.69 Amendments ML24066A1532024-03-0606 March 2024 NRR E-mail Capture - Request for Additional Information TSTF-505, R2, Provide Risk-Informed Extended Completion Times, RITSTF (Risk-Informed Technical Specification Task Force) Initiative 4b and 10 CFR 50.69 License Amendments ML24053A1192024-02-22022 February 2024 Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000265/2024010 and 05000254/2024010 ML23349A0362023-12-14014 December 2023 NRR E-mail Capture - Draft Request for Additional Information Re Quad Cities Emergency Amendment Related to Unit 1 Diesel Generator Inoperability ML23338A1192023-11-21021 November 2023 NRR E-mail Capture - Draft Request for Additional Information Quad Cities Relief Request I5R-26 ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC – Fleet Request – License Amendment Request to Adopt TSTF-580, Revision 1 ML23118A1652023-04-28028 April 2023 NRR E-mail Capture - Request for Additional Information Quad Cities, Unit 2, Alternative Request I6R-11 ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML23065A2832023-03-0707 March 2023 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000254/2023010 and 05000265/2023010 ML23013A1502023-01-17017 January 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000254/2023002 ML23004A0262022-12-16016 December 2022 NRR E-mail Capture - Draft Request for Additional Information - Quad Cities Alternative RV-04, Inservice Testing of High Pressure Coolant Injection Drain Pot Solenoid Valves (EPD L-2022-LLR-0070) ML22348A0452022-12-14014 December 2022 NRR E-mail Capture - Draft Request for Additional Information Regarding Quad Cities Alternative I6R-09 ML22227A1152022-09-27027 September 2022 Request for Withholding Information from Public Disclosure ML22256A0112022-09-12012 September 2022 NRR E-mail Capture - Request for Additional Information LaSalle County Station, Units 1 and 2 and Quad Cities Nuclear Power Station, Units 1 and 2 License Amendments Related to Fuel Storage ML22249A2332022-09-0606 September 2022 Notification of NRC Fire Protection Team Inspection Request for Information Inspection Report 05000254/2022011 05000265/2022011 ML22206A0352022-07-13013 July 2022 NRR E-mail Capture - Draft RAI Quad Cities Alternative Related to Sblc Nozzle Inspection ML22193A0412022-07-11011 July 2022 NRR E-mail Capture - RAI Quad Cities License Amendment to Expand the Use of Prime Methods ML22182A1992022-07-0101 July 2022 NRR E-mail Capture - RAI Alternative RV-11, Code Case OMN-28 ML22178A1362022-06-28028 June 2022 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Quad Cities Station ML22164A8582022-06-13013 June 2022 NRR E-mail Capture - RAI Alternative RV-09, MSSVs ML22164A8562022-06-13013 June 2022 NRR E-mail Capture - RAI Quad Cities Alternative RV-08, Safety Relief Valves ML22164A7852022-06-13013 June 2022 NRR E-mail Capture - RAI Quad Cities Amendment for Spent Fuel Pool Storage Analysis ML22076A1122022-03-15015 March 2022 Request for Additional Information Related to the Amendment Request to Transition to GNF3 Fuels (EPID L-2021-LLA-0159) (Redacted) ML22059A9902022-03-0101 March 2022 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment to Implement Prime Methodologies for Evaluating Thermal Overpower and Mechanical Overpower Limits for Non-Global Nuclear Fuels Fuel ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML22039A1912022-02-0808 February 2022 Information Request for an NRC Triennial 10 CFR 50.59 (Evaluation of Changes, Tests, and Experiments) Baseline Inspection ML22020A0642022-01-13013 January 2022 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles ML21342A3842021-12-0808 December 2021 NRR E-mail Capture - Request for Additional Information: Quad Cities 1 & 2 License Amendment Request Transition to GNF3 Fuel ML21294A0032021-10-26026 October 2021 Supplemental Information Needed for Acceptance of Requested Licensing Action License Amendment Request Regarding Transition to GNF3 Fuel ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21238A3142021-08-26026 August 2021 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000254/2021004; 05000265/2021004 ML21190A0192021-07-0808 July 2021 NRR E-mail Capture - Exelon Fleet - Request for Additional Information Regarding Adoption of TSTF-582 and TSTF-583-T ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML20239A7982020-08-25025 August 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet License Amendment Request to Adopt TSTF-568, Revision 2 ML20183A2852020-07-0101 July 2020 Request for Information for an NRC Triennial Baseline Bases Assurance Inspection (Team): Inspection Report 05000254/2020011 and 05000265/2020011 ML20135H1972020-05-14014 May 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Request to Extend Safety Relief Valve Test Interval ML20031C8332020-01-31031 January 2020 NRR E-mail Capture - Request for Additional Information for Quad Cities Request to Revise Technical Specifications to Increase the MSIV Leakage Rate (L-2019-LLA-0045) ML20021A0342020-01-17017 January 2020 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000254/2020002; 05000265/2020002 ML19134A2792019-05-15015 May 2019 Supplemental Information Needed for Acceptance of License Amendment Request to Increase Main Steam Isolation Valve Allowable Leakage Rates ML18346A4032018-12-0707 December 2018 10 CFR 50.59 (Evaluation of Changes, Tests and Experiments) Inspection Supplemental Request for Information (DRS-A.Shaikh) ML18067A1482018-03-0808 March 2018 Enclosurequest for Additional Information (Letter to P. R. Simpson Request for Additional Information Regarding Exelon Generating Company, Llc'S Decommissioning Funding Plan Update for Independent Spent Fuel Storage Installation) ML17353A9492018-01-0909 January 2018 Supplemental Information Needed for Acceptance of License Amendment Request to Revise Technical Specification Requirements for Secondary Containment ML17355A0112017-12-20020 December 2017 NRR E-mail Capture - Request for Additional Information Regarding Relief Request I5R-11, Revision 2 ML17333A0822017-11-28028 November 2017 17 Quad Cities Nuclear Plant, Unit 2 - Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000265/2018001 (DRS-M.Domke) ML17262A0892017-09-19019 September 2017 Request for Additional Information Concerning Permanent Extension of Type a and Type C Leak Rate Test Frequencies (RS-17-051) 2024-07-12
[Table view] |
See also: IR 05000254/2020002
Text
January 17, 2020
Mr. Bryan C. Hanson
Senior VP, Exelon Generation Company, LLC
President and CNO, Exelon Nuclear
4300 Winfield Road
Warrenville, IL 60555
SUBJECT: QUAD CITIES NUCLEAR POWER STATION, UNIT 2NOTIFICATION OF NRC
BASELINE INSPECTION AND REQUEST FOR INFORMATION; INSPECTION
REPORT 05000254/2020002; 05000265/2020002
Dear Mr. Hanson:
On March 30, 2020, the U.S. Nuclear Regulatory Commission (NRC) will begin the Baseline
Inservice Inspection Procedure 71111.08. This onsite inspection is scheduled to be performed
March 30, 2020, through April 10, 2020.
Experience has shown that this inspection is resource intensive both for the NRC inspector and
your staff. In order to minimize the impact to your onsite resources, and to ensure a productive
inspection for both sides, we have enclosed a request for documents needed for this inspection.
These documents have been divided into two groups.
The first group identifies information necessary to ensure that the inspector is adequately
prepared. The second group identifies the information the inspector will need upon arrival at
the site. It is important that all of these documents are up-to-date, and complete, in order to
minimize the number of additional documents requested during the preparation and/or the
onsite portions of the inspection.
We have discussed the schedule for inspection activities with your staff and understand that our
regulatory contact for this inspection will be Mr. Thomas Petersen, of your organization. If there
are any questions about this inspection or the material requested, please contact the lead
inspector Mr. Joon Park at 630-829-9715, or via e-mail at joon.park@nrc.gov.
This letter does not contain new or amended information collection requirements subject
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
collection requirements were approved by the Office of Management and Budget, Control
Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget Control
Number.
B. Hanson
-2-
This letter and its enclosure will be made available for public inspection and copying at
http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in
accordance with Title 10 of the Code of Federal Regulations, Part 2.390, Public Inspections,
Exemptions, Requests for Withholding.
Sincerely,
/RA/
Joon S. Park, Reactor Inspector
Engineering Branch 1
Division of Reactor Safety
Docket Nos. 50-254, 50-265
License Nos. DPR-29; DPR-30
Enclosure:
Document Request for Baseline Inservice
Inspection
cc: Distribution via LISTSERV
B. Hanson
-3-
Letter to Bryan C. Hanson from Joon S. Park dated January 17, 2020.
SUBJECT: QUAD CITIES NUCLEAR POWER STATION, UNIT 2NOTIFICATION OF NRC
BASELINE INSPECTION AND REQUEST FOR INFORMATION; INSPECTION
REPORT 05000254/2020002; 05000265/2020002
DISTRIBUTION:
Jessie Quichocho
Omar Lopez-Santiago
RidsNrrDorlLpl3
RidsNrrPMQuadCities Resource
RidsNrrDroIrib Resource
Darrell Roberts
John Giessner
Jamnes Cameron
Allan Barker
DRPIII
DRSIII
ADAMS Accession Number: ML20021A034
OFFICE
RIII
NAME
JPark:jw
DATE
01/17/20
OFFICIAL RECORD COPY
BASELINE INSERVICE INSPECTION DOCUMENT REQUEST
Enclosure
Inspection Report:
05000254/2020002; 05000265/2020002
Inspection Dates:
March 30, 2020 - April 10, 2020
Inspection Procedures:
Inspection Procedure 71111-08, Inservice Inspection
Lead Inspector:
Joon S. Park, DRS
630-829-9715
joon.park@nrc.gov
A.
Information for the In-Office Preparation Week
The following information (electronic copy CD ROM if possible) is requested by
February 24, 2020, to facilitate the selection of specific items that will be reviewed during
the onsite inspection week. The inspector will select specific items from the information
requested below and request a list of additional documents needed onsite to your staff.
We request that the specific items selected from the lists be available and ready for
review on the first day of inspection. If you have any questions regarding this
information, please call the inspector as soon as possible.
1. For the upcoming outage, a detailed schedule and description of:
a. Non-Destructive Examinations (NDEs) planned for Class 1 and 2 Systems
and containment, performed as part of your American Society of Mechanical
Engineers (ASME) Code Inservice Inspection (ISI) Program (include edition
and addenda of Code committed to), and NDEs planned for other systems
performed as part of a Risk-Informed ISI Program, or other augmented
inspection programs commitments, as part of an industry initiative; and
b. Welding on Code Class 1, 2, or 3 components. For each weld examination,
include the weld identification number, description of weld (component name),
category, class, type of exam and procedure number, and date of examination.
2. A copy of the NDE procedures and welding procedures used to perform the activities
identified in A.1 (including NDE calibration and flaw characterization/sizing
procedures and Welding Procedure Qualification Records). For ultrasonic
examination procedures qualified in accordance with Appendix VIII, of Section XI
of the ASME Code, provide documentation supporting the procedure qualification
(e.g., the Electric Power Research Institute performance demonstration qualification
summary sheets).
3. A copy of ASME Section XI, Code Relief Requests applicable to the examinations
identified in A.1.
4. A copy of the 10-year ISI Program showing those required exams scheduled to be
performed this outage, and those which have been completed.
BASELINE INSERVICE INSPECTION DOCUMENT REQUEST
2
5. A list identifying NDE reports (ultrasonic, radiography, magnetic particle, or dye
penetrant), which have identified relevant indications on Code Class 1 and 2 systems
since the beginning of the last refueling outage.
6. List with short description of the welds in Code Class 1, 2 and 3 systems, which have
been fabricated due to component repair/replacement activities since the beginning
of the last refueling outage and identify the system, weld number, and reference
applicable documentation (e.g., NIS-2 forms with definitions of system and
component acronyms).
7. If reactor vessel weld examinations required by the ASME Code are scheduled to
occur during the inspection period, provide a detailed description of the welds to be
examined, and the extent of the planned examination.
8. List with description of ISI-related issues such as piping degradation or damage
(e.g., cracks, wall thinning, wear, microbiologically induced corrosion) or errors
identified in piping examinations that have been entered into your corrective action
system since the beginning of the last refueling outage. Also, include a list of
corrective action records associated with foreign material introduced/identified in
the reactor vessel or reactor coolant system since the beginning of the last refueling
outage. In addition, include a list of corrective action records associated with reactor
vessel and internals inspections since the beginning of the last refueling outage.
9. Copy of any Title 10 of the Code of Federal Regulations, Part 21 reports applicable
to your structures, systems, or components within the scope of Section XI of the
ASME Code that have been identified since the beginning of the last refueling
outage.
10. Point of contact information (name and site number) for the Inservice Inspection
Program, Aging Management Programs, Site Welding Engineer, and Reactor
Internals Inspection ProgramsSite and vendor leads.
B.
Onsite Information to be Provided to the Inspector on the First Day of the
Inspection (e.g., Following the Entrance Meeting). Please Provide Hard Copies
(e.g., Paper Records) of the Following Documents.
1. For welds selected by the inspector from A.1.b and A.6 above, provide copies of the
following documents:
a. Document of the weld number and location (e.g., system, train, branch);
b. Document with a detail of the weld construction (e.g., drawing);
c. Applicable portions of the Design Specification and applicable Code of
construction for the weldment (e.g., B31.1 or ASME Section III);
d. Applicable Code Edition and Addenda for weld procedure qualification;
e. Applicable weld procedure specifications and completed weld data sheets used
to fabricate the welds;
BASELINE INSERVICE INSPECTION DOCUMENT REQUEST
3
f. Copies of procedure qualification records supporting the weld procedure
specifications;
g. Copies of welders performance qualification records;
h. Copies of mechanical test reports identified in the procedure qualification
records above;
i.
Copies of the non-conformance reports for the selected welds;
j.
Access to radiographs and equipment to view radiographs of the selected welds;
k. ASME Code Section XI repair replacement plan and reconciliation for
replacement components/materials;
l.
Certified Material Test Reports for replacement pressure boundary materials; and
m. Copies of the NDE required by the construction Code and the pre-service
examination records required by the ASME Code Section XI for the selected welds.
2. For the ISI-related corrective action issues selected by the inspector from Item A.6
above, provide a copy of the corrective actions and supporting documentation.
3. For the NDE reports with relevant indications on Code Class 1 and 2 Systems
selected by the inspector from Item A.5 above, provide a copy of the examination
records and associated corrective action documents.
4. Updated schedules for Item A.1 (including schedule showing contingency repair
plans if available).
5. Fabrication Drawings (D size) of the reactor vessel welds if any are to be examined
during the outage. Also provide any drawings used by NDE vendors to locate these
welds.
6. Provide copies of the following standards at the onsite U.S. Nuclear Regulatory
Commission inspection location for the duration of the inspection:
a. Sections V, IX, and XI of the ASME Code with Editions applicable to the
ISI Program and the Repair/Replacement Program; and
b. Copy of the performance demonstration initiative (PDI) generic procedures with
the latest applicable Revisions that support site qualified ultrasonic examination
of piping welds and components (e.g., PDI-UT-1, PDI-UT-2, PDI-UT-3,
PDI-UT-10 etc.).
7. Provide training (e.g., Scaffolding, Fall Protection, Foreign Material Exclusion)
if required to access the NDE selected by the inspector for observation.
If you have questions regarding the information requested, please contact the lead inspector.