Letter Sequence Acceptance Review |
---|
|
|
MONTHYEARRS-23-060, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors2023-06-0808 June 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors Project stage: Request ML23186A1412023-07-0505 July 2023 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Requested Licensing Action Amendment to Adopt TSTF-505 Project stage: Acceptance Review ML23186A1482023-07-0505 July 2023 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Requested Licensing Action Amendment to Adopt 10 CFR 50.69 Project stage: Acceptance Review ML23319A3342023-11-20020 November 2023 – Regulatory Audit in Support of License Amendment Requests to Adopt TSTF 505, Revision 2 and 10 CFR 50.69 Project stage: Other RS-24-019, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Completion Times TSTF2024-03-19019 March 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Completion Times TSTF Project stage: Response to RAI RS-24-042, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion2024-05-10010 May 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Project stage: Response to RAI ML24110A0492024-05-28028 May 2024 Audit Report Related to the TSTF-505 and 10 CFR 50.59 Amendments Project stage: Other ML24162A0982024-07-0303 July 2024 – Issuance of Amendment Nos. 301 and 297 Adoption of 10 CFR 50.69 Risk Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors Project stage: Approval ML24183A1082024-08-0808 August 2024 – Issuance of Amendment Nos. 302 and 298 Adoption of Tstf-505, Provide Risk Informed Extended Completion Times – RITSTF Initiative 4b Project stage: Approval 2024-03-19
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24254A2082024-09-10010 September 2024 NRR E-mail Capture - Quad Cities, Unit Nos. 1 and 2 - Alternative to RV-08, Rev 1, SRV Testing Interval - Acceptance of Requested Licensing Action Re Relief Request Associated with Safety Relief Valve Testing Interval ML24250A1062024-09-0606 September 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 ML24197A0482024-07-12012 July 2024 Information Request for the Quad Cities Nuclear Station Biennial Problem Identification and Resolution Inspection ML24135A0182024-05-13013 May 2024 NRR E-mail Capture - Draft Request for Additional Information Quad Cities TSTF-505 Amendment ML24131A0612024-05-10010 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24086A5182024-04-30030 April 2024 E-mail to Christian Williams Decision on the Exemption Request for Quad Cities ML24086A4782024-04-24024 April 2024 Email to Christian Williams Availability of Environmental Assessment for the Quad Cities Exemption ML24114A1702024-04-15015 April 2024 Request for State Review of the Quad Cities HI-STORM Exemption Request Environmental Assessment ML24102A2422024-04-10010 April 2024 NRR E-mail Capture - Draft Request for Additional Information Quad Cities TSTF-505 and 50.69 Amendments ML24089A0102024-03-29029 March 2024 NRR E-mail Capture - Quad Cities Unit Nos. 1 and 2 - Alternative to Core Spray Pump Testing - Acceptance of Requested Licensing Action Relief Request Associated with the Sixth Inservice Testing Interval ML24066A1532024-03-0606 March 2024 NRR E-mail Capture - Request for Additional Information TSTF-505, R2, Provide Risk-Informed Extended Completion Times, RITSTF (Risk-Informed Technical Specification Task Force) Initiative 4b and 10 CFR 50.69 License Amendments ML23349A0362023-12-14014 December 2023 NRR E-mail Capture - Draft Request for Additional Information Re Quad Cities Emergency Amendment Related to Unit 1 Diesel Generator Inoperability ML23338A1192023-11-21021 November 2023 NRR E-mail Capture - Draft Request for Additional Information Quad Cities Relief Request I5R-26 ML23268A0022023-09-22022 September 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-264-A, Revision 0 ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC – Fleet Request – License Amendment Request to Adopt TSTF-580, Revision 1 ML23262A7432023-09-19019 September 2023 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 – Acceptance of Relief Request I5R-26 ML23186A1412023-07-0505 July 2023 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Requested Licensing Action Amendment to Adopt TSTF-505 ML23186A1482023-07-0505 July 2023 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Requested Licensing Action Amendment to Adopt 10 CFR 50.69 ML23163A2292023-06-12012 June 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-580, Revision 1 ML23118A1652023-04-28028 April 2023 NRR E-mail Capture - Request for Additional Information Quad Cities, Unit 2, Alternative Request I6R-11 ML23083B9572023-03-24024 March 2023 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Requested Licensing Action Amendment to Adopt TSTF-564 ML23055A0392023-02-24024 February 2023 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Amendment to Adopt TSTF-416 ML23052A0772023-02-21021 February 2023 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance Timely Renewal Exemption Request ML22357A0392022-12-23023 December 2022 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of I6R-10 Related to Repair of Penetration N-11B ML22354A2622022-12-20020 December 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Request to Use Certain Provisions of the 2019 Edition of the ASME BPV Code, Section XI ML23004A0262022-12-16016 December 2022 NRR E-mail Capture - Draft Request for Additional Information - Quad Cities Alternative RV-04, Inservice Testing of High Pressure Coolant Injection Drain Pot Solenoid Valves (EPD L-2022-LLR-0070) ML22348A0452022-12-14014 December 2022 NRR E-mail Capture - Draft Request for Additional Information Regarding Quad Cities Alternative I6R-09 ML22301A0902022-10-28028 October 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-301, Revision 2 ML22290A0662022-10-17017 October 2022 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Alternative RV-04 Related to HPCI Drain Pot Solenoid Valve Testing ML23079A0272022-10-0505 October 2022 Licensee Outline Submittal Email (Quad Cities, 2023) ML22256A0112022-09-12012 September 2022 NRR E-mail Capture - Request for Additional Information LaSalle County Station, Units 1 and 2 and Quad Cities Nuclear Power Station, Units 1 and 2 License Amendments Related to Fuel Storage ML22224A0222022-08-12012 August 2022 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Alternative I6R-09 Related to Use of Certain 2013 Edition ASME Code Requirements ML22200A0782022-07-19019 July 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request to Use Honeywell Mururoa V4F1 R Supplied Air Suits ML22206A0352022-07-13013 July 2022 NRR E-mail Capture - Draft RAI Quad Cities Alternative Related to Sblc Nozzle Inspection ML22193A0412022-07-11011 July 2022 NRR E-mail Capture - RAI Quad Cities License Amendment to Expand the Use of Prime Methods ML22187A1832022-07-0606 July 2022 NRR E-mail Capture - Completion of Activities Related to EPID L-2022-LLD-003, Quad Cities Potential NOED ML22182A1992022-07-0101 July 2022 NRR E-mail Capture - RAI Alternative RV-11, Code Case OMN-28 ML22164A8582022-06-13013 June 2022 NRR E-mail Capture - RAI Alternative RV-09, MSSVs ML22164A8562022-06-13013 June 2022 NRR E-mail Capture - RAI Quad Cities Alternative RV-08, Safety Relief Valves ML22164A7852022-06-13013 June 2022 NRR E-mail Capture - RAI Quad Cities Amendment for Spent Fuel Pool Storage Analysis ML22101A0932022-04-11011 April 2022 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Relief I6R-01 Related to SLC Nozzle Inner Radius Inspection ML22077A4122022-03-18018 March 2022 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Alternative RV-06 Related to MSSV Setpoint Testing ML22076A0322022-03-17017 March 2022 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Alternative RV-03 Related to PIV Leak Test Frequency ML22075A0752022-03-16016 March 2022 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Alternative RV-07 Related to MSIV Stroke Testing ML22068A1512022-03-0909 March 2022 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Alternative RV-10 Related to Code Case OMN-28, MOV Testing ML22068A0552022-03-0909 March 2022 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Alternative RV-09 Related to MSSV Testing ML22068A0062022-03-0909 March 2022 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Alternative RV-11 Related to OMN-28, Valve Position Verification ML22067A2172022-03-0808 March 2022 NRR E-mail Capture - Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Alternative Related to MSRV Testing ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 2024-09-06
[Table view] |
Text
From: Robert Kuntz Sent: Wednesday, July 5, 2023 1:20 PM To: rebecca.steinman@constellation.com
Subject:
Quad Cities Nuclear Power Station, Units 1 and 2: - Acceptance of Requested Licensing Action Re: Amendment to Adopt 10 CFR 50.69 (EPID L-2023-LLA-0085)
Ms. Steinman,
By letter dated June 8, 2023 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML23159A253), Constellation Energy Generation, LLC submitted a license amendment to adopt 10 CFR 50.69 Risk-Informed Categorization and Treatment of Structures, Systems, and Components For Nuclear Power Reactors for Quad Cities Nuclear Power Station, Units 1 and 2. The purpose of this e-mail is to provide the results of the U.S.
Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request.
The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an application for an amendment to a license (including the technical specifications) [or construction permit] must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed
[amendment/relief] in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.
Based on the information provided in your submittal and discussions during the pre-licensing meeting on March 2, 2023, the NRC staff has estimated that this licensing request will take approximately 750 hours0.00868 days <br />0.208 hours <br />0.00124 weeks <br />2.85375e-4 months <br /> to complete. The NRC staff expects to complete this review by Jully 5, 2024.
If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.
These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities.
If you have any questions, please contact me.
Robert Kuntz, Sr. Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Docket Nos.
50-254 and 50-265
cc: Listserv
Hearing Identifier: NRR_DRMA Email Number: 2148
Mail Envelope Properties (SJ0PR09MB108979D75B02AC669DA03F404992FA)
Subject:
Quad Cities Nuclear Power Station, Units 1 and 2 - Acceptance of Requested Licensing Action Re Amendment to Adopt 10 CFR 50.69 (EPID L-2023-LLA-0085)
Sent Date: 7/5/2023 1:20:00 PM Received Date: 7/5/2023 1:19:00 PM From: Robert Kuntz
Created By: Robert.Kuntz@nrc.gov
Recipients:
"rebecca.steinman@constellation.com" <Rebecca.Steinman@constellation.com>
Tracking Status: None
Post Office: SJ0PR09MB10897.namprd09.prod.outlook.com
Files Size Date & Time MESSAGE 3508 7/5/2023 1:19:00 PM
Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: