ML15133A316: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 14: Line 14:
| page count = 3
| page count = 3
| project = TAC:MF5579, TAC:MF5580
| project = TAC:MF5579, TAC:MF5580
| stage = Other
| stage = RAI
}}
}}



Revision as of 21:53, 2 April 2018

Edwin I. Hatch Nuclear Plant, Unit 2 - Request for Additional Information (TAC Nos. MF5579 and MF5580)
ML15133A316
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 05/18/2015
From: Martin R E
Plant Licensing Branch II
To: Pierce C R
Southern Nuclear Operating Co
Martin R E
References
TAC MF5579, TAC MF5580
Download: ML15133A316 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Mr. C. R. Pierce Regulatory Affairs Director May18,2015 Southern Nuclear Operating Company, Inc. P. 0. Box 1295/Bin -038 Birmingham, AL 35201-1295 SUBJECT: EDWIN I. HATCH NUCLEAR PLANT, UNITS 1 AND 2 -REQUEST FOR ADDITIONAL INFORMATION (TAC NOS. MF5579 AND MF5580) Dear Mr. Pierce: The U.S. Nuclear Regulatory Commission (NRC) staff reviewed the Southern Nuclear Operating Company, Inc. (SNC), license amendment request (LAR), dated January 13, 2015, (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 15014A411) to Revise Technical Specifications Regarding Generic Letter 2008-01, Managing Gas Accumulation in accordance with TSTF-523, Revision 2, for the Edwin I. Hatch Nuclear Plant, Units 1 and 2. The NRC staff has reviewed the LAR and has determined that additional information is necessary as set forth in the Enclosure. Please provide a schedule for submittal of your response to these questions. Docket Nos.: 50-321, 50-366 cc: Distribution via Listserv Sincerely, //)fl l tJ.-17L1-:-" Martin, Senior Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation REQUEST FOR ADDITIONAL INFORMATION EDWIN I. HATCH NUCLEAR PLANT. UNITS 1 AND 2 SOUTHERN NUCLEAR OPERATING COMPANY. INC. DOCKET NOS. 50-321AND50-366 The U.S. Nuclear Regulatory Commission (NRC) staff reviewed the Southern Nuclear Operating Company, Inc. (SNC), license amendment request (LAR), dated January 13, 2015, (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 15014A411) to Revise Technical Specifications Regarding Generic Letter 2008-01, Managing Gas Accumulation in accordance with TSTF-523, Revision 2, for the Edwin I. Hatch Nuclear Plant, Units 1 and 2. The NRC staff has reviewed the request and determined that additional information is necessary as noted below. 1. An acceptable surveillance must include allowance for gas accumulation until the next surveillance is scheduled. How is this requirement satisfied by the following: a. Satisfactorily operating a system or subsystem such as a residual heat removal shutdown cooling subsystem? b. Monitoring Reactor Core Isolation Cooling pump suction pressure? c. Use of a procedure designed to initially ensure that piping is adequately filled and vented? 2. Please describe the monitoring of other system parameters that could identify a change that could introduce gas into piping between surveillance intervals. 3. What are representative surveillance frequencies that exist under the Surveillance Frequency Control Program that differ from the TSTF-523 example of 31 days and what is the basis for those changes? Enclosure Mr. C. R. Pierce Regulatory Affairs Director May 18, 2015 Southern Nuclear Operating Company, Inc. P. 0. Box 1295/Bin -038 Birmingham, AL 35201-1295 SUBJECT: EDWIN I. HATCH NUCLEAR PLANT, UNITS 1 AND 2 -REQUEST FOR ADDITIONAL INFORMATION (TAC NOS. MF5579 AND MF5580) Dear Mr. Pierce: The U.S. Nuclear Regulatory Commission (NRC) staff reviewed the Southern Nuclear Operating Company, Inc. (SNC), license amendment request (LAR), dated January 13, 2015, (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 15014A411) to Revise Technical Specifications Regarding Generic Letter 2008-01, Managing Gas Accumulation in accordance with TSTF-523, Revision 2, for the Edwin I. Hatch Nuclear Plant, Units 1 and 2. The NRC staff has reviewed the LAR and has determined that additional information is necessary as set forth in the Enclosure. Please provide a schedule for submittal of your response to these questions. Docket Nos.: 50-321, 50-366 cc: Distribution via Listserv DISTRIBUTION: PUBLIC LPL2-1 R/F RidsAcrsAcnw MailCTR Resource RidsNrrDorlLpl2-1 Resource Sincerely, IRA! Bob Martin, Senior Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation RidsNrrLASFigueroa Resource RidsNrrPMHatch Resource RidsRgn2MailCenter Resource WLyon, NRR KWest, NRR ADA MSA ccess1on N ML 15133A316 o.: * *1 d t d M 6 2015 ema1 ae ay I OFFICE NRR/LPLll-1/PM NRR/LPLll-1 /LA NRR/SRXB/BC* NRR/LPLll-1 /BC NRR/LPLll-1/PM NAME BMartin SFigueroa CJackson RPascarelli BMartin DATE 05/18/15 05/14/15 05/06/15 05/18/15 05/18/15 OFFICIAL RECORD COPY