ML043340269: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
 
Line 25: Line 25:
185 Old Ferry Road
185 Old Ferry Road
Brattleboro, VT 05302-0500
Brattleboro, VT 05302-0500
SUBJECT:       VERMONT YANKEE NUCLEAR POWER STATION
SUBJECT:
                NRC INSPECTION REPORT 05000271/2004008
VERMONT YANKEE NUCLEAR POWER STATION  
NRC INSPECTION REPORT 05000271/2004008
Dear Mr. Thayer:
Dear Mr. Thayer:
On September 3, 2004, the US Nuclear Regulatory Commission (NRC) completed an
On September 3, 2004, the US Nuclear Regulatory Commission (NRC) completed an
inspection at the Vermont Yankee Nuclear Power Station. The enclosed inspection report
inspection at the Vermont Yankee Nuclear Power Station. The enclosed inspection report
documents the inspection findings, which were discussed with members of your staff on
documents the inspection findings, which were discussed with members of your staff on
September 3, October 27, and November 23, 2004.
September 3, October 27, and November 23, 2004.
The inspection examined activities conducted under your license as they relate to safety and
The inspection examined activities conducted under your license as they relate to safety and
compliance with the Commissions rules and regulations and with the conditions of your license.
compliance with the Commissions rules and regulations and with the conditions of your license.  
In conducting the inspection, the team examined the adequacy of selected components and
In conducting the inspection, the team examined the adequacy of selected components and
operator actions to mitigate postulated design basis accidents, both under current licensing and
operator actions to mitigate postulated design basis accidents, both under current licensing and
planned power uprated conditions. The inspection also reviewed Entergys response to
planned power uprated conditions. The inspection also reviewed Entergys response to
selected operating experience issues, and assessed the adequacy of Vermont Yankees design
selected operating experience issues, and assessed the adequacy of Vermont Yankees design
and engineering processes.
and engineering processes.
The team concluded that the components and systems reviewed would be capable of
The team concluded that the components and systems reviewed would be capable of
performing their intended safety functions. The team also concluded that sufficient design
performing their intended safety functions. The team also concluded that sufficient design
controls had been implemented for design and engineering work, including that related to
controls had been implemented for design and engineering work, including that related to
Entergys extended power uprate. The team did identify several deficiencies related to design
Entergys extended power uprate. The team did identify several deficiencies related to design
control at Vermont Yankee; however, sample based extent-of-condition reviews indicated the
control at Vermont Yankee; however, sample based extent-of-condition reviews indicated the
original problems were not widespread or programmatic in nature. In addition, some of the
original problems were not widespread or programmatic in nature. In addition, some of the
specific findings included topics that were within the scope of the NRCs power uprate review,
specific findings included topics that were within the scope of the NRCs power uprate review,
and thus, will require the submittal of additional information to the NRCs technical staff to
and thus, will require the submittal of additional information to the NRCs technical staff to
support that review.
support that review.  
The enclosed report documents eight findings of very low safety significance (Green), all of
The enclosed report documents eight findings of very low safety significance (Green), all of
which were determined to involve a violation of NRC requirements. Because of their very low
which were determined to involve a violation of NRC requirements. Because of their very low
safety significance and because the findings were entered into your corrective action program,
safety significance and because the findings were entered into your corrective action program,
the NRC is treating them as non-cited violations (NCVs), consistent with Section VI.A of the
the NRC is treating them as non-cited violations (NCVs), consistent with Section VI.A of the
NRCs Enforcement Policy. If you contest these non-cited violations, you should provide a
NRCs Enforcement Policy. If you contest these non-cited violations, you should provide a
response within 30 days of the date of this inspection report, with the basis for your denial, to
response within 30 days of the date of this inspection report, with the basis for your denial, to
the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, D.C. 20555-
the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, D.C. 20555-
0001; with copies to the Regional Administrator Region I; the Director, Office of Enforcement,
0001; with copies to the Regional Administrator Region I; the Director, Office of Enforcement,


Mr. J. K. Thayer                                 2
Mr. J. K. Thayer
2
United States Nuclear Regulatory Commission, Washington, D.C. 20555-0001; and the NRC
United States Nuclear Regulatory Commission, Washington, D.C. 20555-0001; and the NRC
Resident Inspector at the Vermont Yankee Nuclear Power Station.
Resident Inspector at the Vermont Yankee Nuclear Power Station.
Line 63: Line 65:
enclosure, and your response (if any) will be available electronically for public inspection in the
enclosure, and your response (if any) will be available electronically for public inspection in the
NRC Public Document Room or from the Publicly Available Records (PARS) component of
NRC Public Document Room or from the Publicly Available Records (PARS) component of
NRCs document system (ADAMS). ADAMS is temporarily unavailable due to an ongoing
NRCs document system (ADAMS). ADAMS is temporarily unavailable due to an ongoing
security review; therefore, this document will also be posted on the NRC Web site at
security review; therefore, this document will also be posted on the NRC Web site at
http:\\www.nrc.gov\reactors\plant-specific-items\vermont-yankee-issues.html.
http:\\\\www.nrc.gov\\reactors\\plant-specific-items\\vermont-yankee-issues.html.
                                              Sincerely,
Sincerely,
                                              /RA/
/RA/
                                              Wayne D. Lanning, Director
Wayne D. Lanning, Director
                                              Division of Reactor Safety
Division of Reactor Safety
Docket No. 50-271
Docket No. 50-271
License No. DPR-28
License No. DPR-28
Enclosure: Inspection Report 05000271/2004008 w/Attachments
Enclosure: Inspection Report 05000271/2004008 w/Attachments


Mr. J. K. Thayer                               3
Mr. J. K. Thayer
3
cc w/encl:
cc w/encl:
M. R. Kansler, President, Entergy Nuclear Operations, Inc.
M. R. Kansler, President, Entergy Nuclear Operations, Inc.
Line 89: Line 92:
Administrator, Bureau of Radiological Health, State of New Hampshire
Administrator, Bureau of Radiological Health, State of New Hampshire
Chief, Safety Unit, Office of the Attorney General, Commonwealth of Mass.
Chief, Safety Unit, Office of the Attorney General, Commonwealth of Mass.
D. R. Lewis, Esquire, Shaw, Pittman, Potts & Trowbridge
D. R. Lewis, Esquire, Shaw, Pittman, Potts & Trowbridge  
G. D. Bisbee, Esquire, Deputy Attorney General, Environmental Protection Bureau
G. D. Bisbee, Esquire, Deputy Attorney General, Environmental Protection Bureau
J. Block, Esquire
J. Block, Esquire
J. P. Matteau, Executive Director, Windham Regional Commission
J. P. Matteau, Executive Director, Windham Regional Commission
Line 99: Line 102:
J. Sniezek, PWR SRC Consultant
J. Sniezek, PWR SRC Consultant
R. Toole, PWR SRC Consultant
R. Toole, PWR SRC Consultant
Commonwealth of Massachusetts, SLO Designee
Commonwealth of Massachusetts, SLO Designee  
State of New Hampshire, SLO Designee
State of New Hampshire, SLO Designee  
State of Vermont, SLO Designee
State of Vermont, SLO Designee  


              Mr. J. K. Thayer                                               4
Mr. J. K. Thayer
              Distribution w/encl: (via E-mail)
4
              S. Collins, RA
Distribution w/encl:
              J. Wiggins, DRA
(via E-mail)
              W. Lanning, DRS
S. Collins, RA
              R. Crlenjak, DRS
J. Wiggins, DRA
              L. Doerflein, DRS
W. Lanning, DRS
              C. Anderson, DRP
R. Crlenjak, DRS
              D. Florek, DRP
L. Doerflein, DRS
              J. Jolicoeur, RI OEDO
C. Anderson, DRP
              J. Clifford, NRR
D. Florek, DRP
              R. Ennis, PM, NRR
J. Jolicoeur, RI OEDO  
              V. Nerses, Backup PM, NRR
J. Clifford, NRR
              D. Pelton, DRP, Senior Resident Inspector
R. Ennis, PM, NRR
              A. Rancourt, DRP, Resident OA
V. Nerses, Backup PM, NRR
              Region I Docket Room (with concurrences)
D. Pelton, DRP, Senior Resident Inspector
A. Rancourt, DRP, Resident OA
Region I Docket Room (with concurrences)  
ADAMS ML043340269
ADAMS ML043340269
SISP Review Complete: WDL
SISP Review Complete:     WDL  
DOCUMENT NAME: E:\Filenet\ML043340269.wpd
DOCUMENT NAME: E:\\Filenet\\ML043340269.wpd
After declaring this document An Official Agency Record it will be released to the Public.
After declaring this document An Official Agency Record it will be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure   "E" = Copy with attachment/enclosure   "N" = No copy
OFFICE                                                                                             RI/DRS                     RI/DRS
OFFICE
NAME           CBaron/JJ for                 GSkinner/JJ for           SSpiegelman/JJ for         GBowman/GTB                 SDennis/SXD
RI/DRS
DATE           12/2/04                       12/2/04                   12/2/04                     12/2/04                     12/2/04
RI/DRS
OFFICE         RI/DRS                       RI/DRP                     NRR/PIPB                   RI/DRS                     RI/DRS
NAME
NAME           FBower/LTD for by telecon     MSnell/MPS                 JJacobson/JJ               WSchmidt/WLS               LDoerflein/LTD
CBaron/JJ for
DATE           12/1/04                       12/2/04                   12/2/04                     12/2/04                     12/ 1/04
GSkinner/JJ for
OFFICE         RI/DRS
SSpiegelman/JJ for
NAME           WLanning/WDL
GBowman/GTB
DATE           12/ 2/04
SDennis/SXD
DATE
12/2/04
12/2/04
12/2/04
12/2/04
12/2/04
OFFICE
RI/DRS
RI/DRP
NRR/PIPB
RI/DRS
RI/DRS
NAME
FBower/LTD for by telecon
MSnell/MPS
JJacobson/JJ
WSchmidt/WLS
LDoerflein/LTD
DATE
12/1/04
12/2/04
12/2/04
12/2/04
12/ 1/04
OFFICE
RI/DRS
NAME
WLanning/WDL
DATE
12/ 2/04


Mr. J. K. Thayer           5
Mr. J. K. Thayer
                OFFICIAL RECORD COPY
5
OFFICIAL RECORD COPY


                U.S. NUCLEAR REGULATORY COMMISSION
Enclosure
                                  REGION I
U.S. NUCLEAR REGULATORY COMMISSION
Docket No.   50-271
REGION I
License No. DPR-28
Docket No.
Report No.   05000271/2004008
50-271
Licensee:   Entergy Nuclear Vermont Yankee, LLC
License No.
Facility:   Vermont Yankee Nuclear Power Station
DPR-28
Location:   320 Governor Hunt Road
Report No.
            Vernon, Vermont
05000271/2004008
            05354-9766
Licensee:
Dates:       August 9 - 20 and August 30 - September 3, 2004
Entergy Nuclear Vermont Yankee, LLC
Inspectors: J. Jacobson, Team Leader, Inspection Program Branch, NRR
Facility:
            F. Bower, Senior Reactor Inspector, DRS, Region I
Vermont Yankee Nuclear Power Station
            G. Bowman, Reactor Inspector, DRS, Region I
Location:
            S. Dennis, Senior Operations Engineer, DRS, Region I
320 Governor Hunt Road
            M. Snell, Reactor Engineer, DRP, Region I
Vernon, Vermont
            C. Baron, NRC Contractor
05354-9766
            S. Spiegelman, NRC Contractor
Dates:
            G. Skinner, NRC Contractor
August 9 - 20 and August 30 - September 3, 2004
Observer:   W. Sherman, Vermont State Nuclear Engineer
Inspectors:
Approved by: Wayne D. Lanning, Director
J. Jacobson, Team Leader, Inspection Program Branch, NRR
            Division of Reactor Safety
F. Bower, Senior Reactor Inspector, DRS, Region I
            Region I
                                                                      Enclosure
G. Bowman, Reactor Inspector, DRS, Region I
S. Dennis, Senior Operations Engineer, DRS, Region I
M. Snell, Reactor Engineer, DRP, Region I
C. Baron, NRC Contractor
S. Spiegelman, NRC Contractor
G. Skinner, NRC Contractor
Observer:
W. Sherman, Vermont State Nuclear Engineer
Approved by:
Wayne D. Lanning, Director
Division of Reactor Safety
Region I


                                                CONTENTS
Enclosure
CONTENTS
EXECUTIVE SUMMARY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . i
EXECUTIVE SUMMARY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . i
SUMMARY OF FINDINGS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . iii
SUMMARY OF FINDINGS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . iii
REPORT DETAILS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
REPORT DETAILS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
      4OA2 Problem Identification and Resolution (PI&R) . . . . . . . . . . . . . . . . . . . . . . . . . . 1
4OA2 Problem Identification and Resolution (PI&R) . . . . . . . . . . . . . . . . . . . . . . . . . . 1
            1. Annual Sample Review . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.   Annual Sample Review . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
            2. Cross Reference to PI&R Findings Documented Elsewhere . . . . . . . . . . . . 1
2.   Cross Reference to PI&R Findings Documented Elsewhere . . . . . . . . . . . . 1
      4OA5 Other Activities - Temporary Instruction 2515/158 . . . . . . . . . . . . . . . . . . . . . . . 1
4OA5 Other Activities - Temporary Instruction 2515/158 . . . . . . . . . . . . . . . . . . . . . . . 1
            1. Inspection Sample Selection Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.   Inspection Sample Selection Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
            2. Results of Detailed Reviews . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
2.   Results of Detailed Reviews . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
                  2.1       Detailed Component and System Reviews . . . . . . . . . . . . . . . . . 2
2.1
                  2.1.1 Electrical Power Sources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Detailed Component and System Reviews . . . . . . . . . . . . . . . . . 2
                  2.1.2 Reactor Core Isolation Cooling (RCIC) System . . . . . . . . . . . . . 8
2.1.1
                  2.1.3 Residual Heat Removal System (RHR) . . . . . . . . . . . . . . . . . . 13
Electrical Power Sources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
                  2.1.4 Safety Relief Valves and Code Safety Valves . . . . . . . . . . . . . 13
2.1.2
                  2.1.5 Reactor Feedwater and Condensate Components . . . . . . . . . 13
Reactor Core Isolation Cooling (RCIC) System . . . . . . . . . . . . . 8
                  2.1.6 Reactor Building-to-Torus Vacuum Breaker System . . . . . . . . 14
2.1.3 Residual Heat Removal System (RHR) . . . . . . . . . . . . . . . . . . 13
                  2.1.7 Review of Transient Analysis Inputs . . . . . . . . . . . . . . . . . . . . . 15
2.1.4
                  2.2       Review of Operator Actions . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
Safety Relief Valves and Code Safety Valves . . . . . . . . . . . . . 13
                  2.3       Review of Operating Experience and Generic Issues . . . . . . . 20
2.1.5
      4OA6 Meetings, Including Exit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
Reactor Feedwater and Condensate Components . . . . . . . . . 13
ATTACHMENT A: SUMMARY OF ITEMS REVIEWED . . . . . . . . . . . . . . . . . . . . . . . . . . . .                               A-1
2.1.6
ATTACHMENT B: SUPPLEMENTAL INFORMATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                               B-1
Reactor Building-to-Torus Vacuum Breaker System
KEY POINTS OF CONTACT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .         B-1
. . . . . . . . 14
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED . . . . . . . . . . . . . . . . . . . . . . . . . . .                             B-2
2.1.7
LIST OF DOCUMENTS REVIEWED . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                 B-3
Review of Transient Analysis Inputs . . . . . . . . . . . . . . . . . . . . . 15
LIST OF ACRONYMS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   B-8
2.2
                                                                                                                    Enclosure
Review of Operator Actions . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
2.3
Review of Operating Experience and Generic Issues
. . . . . . . 20
4OA6 Meetings, Including Exit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
ATTACHMENT A: SUMMARY OF ITEMS REVIEWED . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-1
ATTACHMENT B: SUPPLEMENTAL INFORMATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B-1
KEY POINTS OF CONTACT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B-1
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED . . . . . . . . . . . . . . . . . . . . . . . . . . . B-2
LIST OF DOCUMENTS REVIEWED . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B-3
LIST OF ACRONYMS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B-8


                                      EXECUTIVE SUMMARY
Enclosure
i
EXECUTIVE SUMMARY
During the period from August 9 through September 3, 2004, the US Nuclear Regulatory
During the period from August 9 through September 3, 2004, the US Nuclear Regulatory
Commission (NRC) conducted a team inspection in accordance with Temporary Instruction
Commission (NRC) conducted a team inspection in accordance with Temporary Instruction
2515/158, Functional Review of Low Margin/Risk Significant Components and Human
2515/158, Functional Review of Low Margin/Risk Significant Components and Human
Actions, at the Vermont Yankee Nuclear Power Station. The team was comprised of eight
Actions, at the Vermont Yankee Nuclear Power Station. The team was comprised of eight
inspectors, including a team leader from the NRCs Office of Nuclear Reactor Regulation, four
inspectors, including a team leader from the NRCs Office of Nuclear Reactor Regulation, four
inspectors from the NRCs Region I Office, and three contractors. All of the inspectors and
inspectors from the NRCs Region I Office, and three contractors. All of the inspectors and
contractors met strict independence criteria developed for this inspection. Specifically, the NRC
contractors met strict independence criteria developed for this inspection. Specifically, the NRC
inspectors had not performed engineering inspections at Vermont Yankee within the last two
inspectors had not performed engineering inspections at Vermont Yankee within the last two
years and had not been assigned as resident inspectors at Vermont Yankee. The contractors
years and had not been assigned as resident inspectors at Vermont Yankee. The contractors
had never been directly employed by Entergy or Vermont Yankee, had not performed contract
had never been directly employed by Entergy or Vermont Yankee, had not performed contract
work for Entergy or Vermont Yankee in the past two years, and had not performed inspections
work for Entergy or Vermont Yankee in the past two years, and had not performed inspections
for the NRC at Vermont Yankee within the past two years. The inspection was the first of four
for the NRC at Vermont Yankee within the past two years. The inspection was the first of four
planned pilot inspections to be conducted throughout the country to assist the NRC in
planned pilot inspections to be conducted throughout the country to assist the NRC in
determining whether changes should be made to its Reactor Oversight Process (ROP) to
determining whether changes should be made to its Reactor Oversight Process (ROP) to
improve the effectiveness of its inspections and oversight in the design/engineering area.
improve the effectiveness of its inspections and oversight in the design/engineering area.
In selecting samples for review, the team focused on those components and operator actions
In selecting samples for review, the team focused on those components and operator actions
that contribute the greatest risk to an accident that could involve damage to the reactor core.
that contribute the greatest risk to an accident that could involve damage to the reactor core.  
Additional consideration was given to those components and operator actions impacted by the
Additional consideration was given to those components and operator actions impacted by the
licensees request for a 20 percent extended power uprate (EPU) license amendment. The
licensees request for a 20 percent extended power uprate (EPU) license amendment. The
team focused its reviews on those components and operator actions contained in the reactor
team focused its reviews on those components and operator actions contained in the reactor
core isolation cooling (RCIC), main feedwater, safety relief valve, onsite electrical power, and
core isolation cooling (RCIC), main feedwater, safety relief valve, onsite electrical power, and
off-site electrical power systems. In addition, inspection samples were added based upon
off-site electrical power systems. In addition, inspection samples were added based upon
operational experience and issues previously identified by the NRCs technical staff during the
operational experience and issues previously identified by the NRCs technical staff during the
course of their reviews associated with the licensees request for an EPU. A complete listing of
course of their reviews associated with the licensees request for an EPU. A complete listing of
all components, operator actions, and operating experience issues reviewed by the inspection
all components, operator actions, and operating experience issues reviewed by the inspection
team is contained in Attachment A to this report.
team is contained in Attachment A to this report.  
For each sample selected, the team reviewed design calculations, corrective action reports,
For each sample selected, the team reviewed design calculations, corrective action reports,
maintenance and modification histories, associated operating procedures, and performed
maintenance and modification histories, associated operating procedures, and performed
walkdowns of material conditions (as practical). The team concluded that the components and
walkdowns of material conditions (as practical). The team concluded that the components and
systems reviewed would be capable of performing their intended safety functions. The team
systems reviewed would be capable of performing their intended safety functions. The team
also concluded that sufficient design controls had been implemented for engineering work,
also concluded that sufficient design controls had been implemented for engineering work,
including that related to Entergys EPU. The overall material condition of the plant and of the
including that related to Entergys EPU. The overall material condition of the plant and of the
specific components reviewed was also noted as being good. The team identified eight findings
specific components reviewed was also noted as being good. The team identified eight findings
of very low safety significance, one unresolved item, and one minor finding. The eight findings
of very low safety significance, one unresolved item, and one minor finding. The eight findings
are listed in the Summary of Findings section of this report.
are listed in the Summary of Findings section of this report.
The team assessed the safety significance of each of the findings using the NRCs Significance
The team assessed the safety significance of each of the findings using the NRCs Significance
Determination Process (SDP). Using this process, each of the findings was determined to be of
Determination Process (SDP). Using this process, each of the findings was determined to be of
very low safety significance. Also, for each of the findings where current operability was in
very low safety significance. Also, for each of the findings where current operability was in
question, the licensee provided a basis for operability and entered the issue into their corrective
question, the licensee provided a basis for operability and entered the issue into their corrective
action program, as necessary to complete a more comprehensive assessment of the issue,
action program, as necessary to complete a more comprehensive assessment of the issue,
including any programmatic oversight weaknesses that might have prevented self-identification.
including any programmatic oversight weaknesses that might have prevented self-identification.  
In addition, for the findings associated with a design vulnerability of an RCIC pressure control
In addition, for the findings associated with a design vulnerability of an RCIC pressure control
valve, the control of the condensate storage tank (CST) temperature to the limits of transient
valve, the control of the condensate storage tank (CST) temperature to the limits of transient
                                                  i                                      Enclosure


Enclosure
ii
analysis assumptions, and the updating of the Safe Shutdown Capability Analysis, the team
analysis assumptions, and the updating of the Safe Shutdown Capability Analysis, the team
performed sample-based extent-of-condition reviews during the inspection to determine the
performed sample-based extent-of-condition reviews during the inspection to determine the
breadth of the issues identified. No additional findings were identified during these reviews,
breadth of the issues identified. No additional findings were identified during these reviews,
indicating the original problems identified were not widespread, and were likely not
indicating the original problems identified were not widespread, and were likely not
programmatic in nature. Additional licensee extent-of-condition reviews of the issues were
programmatic in nature. Additional licensee extent-of-condition reviews of the issues were
ongoing at the conclusion of the inspection.
ongoing at the conclusion of the inspection.
Some of the findings also concern topics that are within the scope of the NRCs power uprate
Some of the findings also concern topics that are within the scope of the NRCs power uprate
review and therefore will require the submittal of additional information to the NRCs technical
review and therefore will require the submittal of additional information to the NRCs technical
staff.
staff.
                                                ii                                    Enclosure


                                      SUMMARY OF FINDINGS
Enclosure
IR 05000271/2004008; 08/09/2004-09/03/2004; Vermont Yankee Nuclear Generating Station;
iii
Functional Review of Low Margin/Risk Significant Components and Human Actions.
SUMMARY OF FINDINGS
This inspection was conducted by five inspectors and three NRC contractors. Eight Green non-
IR 05000271/2004008; 08/09/2004-09/03/2004; Vermont Yankee Nuclear Generating Station;  
cited violations, one unresolved item, and one minor finding were identified. The significance of
Functional Review of Low Margin/Risk Significant Components and Human Actions.
This inspection was conducted by five inspectors and three NRC contractors. Eight Green non-
cited violations, one unresolved item, and one minor finding were identified. The significance of
most findings is indicated by their color (Green, White, Yellow, or Red) using Inspection Manual
most findings is indicated by their color (Green, White, Yellow, or Red) using Inspection Manual
Chapter (IMC) 0609, Significance Determination Process. Findings for which the SDP does
Chapter (IMC) 0609, Significance Determination Process. Findings for which the SDP does
not apply may be Green or be assigned a severity level after NRC management review. The
not apply may be Green or be assigned a severity level after NRC management review. The
NRCs program for overseeing the safe operation of commercial nuclear power reactors is
NRCs program for overseeing the safe operation of commercial nuclear power reactors is
described in NUREG-1649, Reactor Oversight Process, Revision 3, dated July 2000.
described in NUREG-1649, Reactor Oversight Process, Revision 3, dated July 2000.
A.     NRC-Identified Findings
A.
        Cornerstone: Mitigating Systems
NRC-Identified Findings
        !       Green. The team identified a non-cited violation of 10 CFR Part 50.63, Loss of
Cornerstone: Mitigating Systems
                All Alternating Current Power, because the licensee had not completed a coping
!
                analysis for the period of time the alternate alternating current (AC) source (the
Green. The team identified a non-cited violation of 10 CFR Part 50.63, Loss of
                Vernon Hydro-Electric Station) would be unavailable and had not demonstrated
All Alternating Current Power, because the licensee had not completed a coping
                by test the time required to make the alternate source available for a station
analysis for the period of time the alternate alternating current (AC) source (the
                blackout involving a grid collapse. This issue was more than minor because it
Vernon Hydro-Electric Station) would be unavailable and had not demonstrated
                was associated with the Mitigating Systems Cornerstone attribute of Equipment
by test the time required to make the alternate source available for a station
                Performance and affected the cornerstone objective of ensuring availability,
blackout involving a grid collapse. This issue was more than minor because it
                reliability, and capability of systems needed to respond to a station blackout.
was associated with the Mitigating Systems Cornerstone attribute of Equipment
                The issue screened as very low safety significance in Phase I of the SDP
Performance and affected the cornerstone objective of ensuring availability,
                because it was a design deficiency that was not found to result in a loss of
reliability, and capability of systems needed to respond to a station blackout.  
                function. Specifically, the team found that the licensees preliminary coping
The issue screened as very low safety significance in Phase I of the SDP
                analysis, performed during the inspection, demonstrated a four-hour coping time
because it was a design deficiency that was not found to result in a loss of
                which should be sufficient to envelope the time required to start and align the
function. Specifically, the team found that the licensees preliminary coping
                Vernon Station. (Section 4OA5.2.1.1)
analysis, performed during the inspection, demonstrated a four-hour coping time
        !       Green. The team identified a non-cited violation of Technical Specifications
which should be sufficient to envelope the time required to start and align the
                6.4.C, Procedures, because the licensee failed to establish adequate
Vernon Station. (Section 4OA5.2.1.1)
                procedures for determining the operability of the 115 kilovolt (kV) Keene line,
!
                which is designated as an alternate immediate access power source if the
Green. The team identified a non-cited violation of Technical Specifications
                345/115 kV auto transformer is lost. This issue was more than minor because it
6.4.C, Procedures, because the licensee failed to establish adequate
                was associated with the Mitigating Systems Cornerstone attribute of Procedural
procedures for determining the operability of the 115 kilovolt (kV) Keene line,
                Quality and affected the cornerstone objective of ensuring availability, reliability,
which is designated as an alternate immediate access power source if the
                and capability of systems needed to respond to a loss of off-site power. The
345/115 kV auto transformer is lost. This issue was more than minor because it
                issue screened as very low safety significance in Phase I of the SDP because it
was associated with the Mitigating Systems Cornerstone attribute of Procedural
                was a design deficiency that was not found to result in a loss of function.
Quality and affected the cornerstone objective of ensuring availability, reliability,
                Specifically, the team did not identify any instances where the lack of procedural
and capability of systems needed to respond to a loss of off-site power. The
                guidance had resulted in an inadequate assessment of off-site power operability
issue screened as very low safety significance in Phase I of the SDP because it
                or the inoperability of the electrical system or any components.
was a design deficiency that was not found to result in a loss of function.  
                (Section 4OA5.2.1.1)
Specifically, the team did not identify any instances where the lack of procedural
                                                    iii                                  Enclosure
guidance had resulted in an inadequate assessment of off-site power operability
or the inoperability of the electrical system or any components.  
(Section 4OA5.2.1.1)


! Green. The team identified a non-cited violation of 10 CFR Part 50, Appendix B,
Enclosure
  Criterion III, Design Control, because the licensee used incorrect and non-
iv
  conservative voltage values in calculations performed to assure that electrical
!
  equipment would remain operable under degraded voltage conditions. This
Green. The team identified a non-cited violation of 10 CFR Part 50, Appendix B,
  issue was more than minor because it was associated with the Mitigating
Criterion III, Design Control, because the licensee used incorrect and non-
  Systems Cornerstone attribute of Equipment Performance and affected the
conservative voltage values in calculations performed to assure that electrical
  cornerstone objective of ensuring availability, reliability, and capability of systems
equipment would remain operable under degraded voltage conditions. This
  needed to respond to a design basis accident. The issue screened as very low
issue was more than minor because it was associated with the Mitigating
  safety significance in Phase I of the SDP because it was a design deficiency that
Systems Cornerstone attribute of Equipment Performance and affected the
  was not found to result in a loss of function. Specifically, the team did not
cornerstone objective of ensuring availability, reliability, and capability of systems
  identify any instances where using the Technical Specification degraded voltage
needed to respond to a design basis accident. The issue screened as very low
  allowable setpoint values would have resulted in inoperable equipment.
safety significance in Phase I of the SDP because it was a design deficiency that
  (Section 4OA5.2.1.1)
was not found to result in a loss of function. Specifically, the team did not
! Green. The team identified a non-cited violation of 10 CFR Part 50, Appendix B,
identify any instances where using the Technical Specification degraded voltage
  Criterion III, Design Control, because the licensee did not implement measures
allowable setpoint values would have resulted in inoperable equipment.  
  to ensure that the design basis for the cooling water supply to the lube oil cooler
(Section 4OA5.2.1.1)
  of RCIC was correctly translated into the specifications, drawings, procedures, or
!
  instructions. Specifically, the installed pressure control valve in the lube oil
Green. The team identified a non-cited violation of 10 CFR Part 50, Appendix B,
  cooler water supply line was not independent of air systems, and the installed
Criterion III, Design Control, because the licensee did not implement measures
  piping between the pressure control valve and lube oil cooler did not contain a
to ensure that the design basis for the cooling water supply to the lube oil cooler
  restricting orifice. This issue was more than minor because it was associated
of RCIC was correctly translated into the specifications, drawings, procedures, or
  with the Mitigating Systems Cornerstone attribute of Equipment Performance
instructions. Specifically, the installed pressure control valve in the lube oil
  and affected the cornerstone objective of ensuring the reliability of the RCIC
cooler water supply line was not independent of air systems, and the installed
  system. The issue screened as very low safety significance in Phase I of the
piping between the pressure control valve and lube oil cooler did not contain a
  SDP because it was a design deficiency that was not found to result in a loss of
restricting orifice. This issue was more than minor because it was associated
  function. This deficiency would not have resulted in the RCIC system becoming
with the Mitigating Systems Cornerstone attribute of Equipment Performance
  inoperable due to a loss of air to the lube oil cooler pressure control valve.
and affected the cornerstone objective of ensuring the reliability of the RCIC
  (Section 4OA5.2.1.2).
system. The issue screened as very low safety significance in Phase I of the
  A contributing cause of this finding is related to the cross cutting area of Problem
SDP because it was a design deficiency that was not found to result in a loss of
  Identification and Resolution. The licensee had previously reviewed the failure
function. This deficiency would not have resulted in the RCIC system becoming
  positions of air-operated equipment and issued a report, Compressed Air
inoperable due to a loss of air to the lube oil cooler pressure control valve.  
  Systems, dated July 16, 1989. During this review, the licensee did not identify
(Section 4OA5.2.1.2).
  that the pressure control valve was not independent of the instrument air system.
A contributing cause of this finding is related to the cross cutting area of Problem
! Green. The team identified a non-cited violation of 10 CFR Part 50, Appendix B,
Identification and Resolution. The licensee had previously reviewed the failure
  Criterion XVI, Corrective Action, because the licensee failed to correct a
positions of air-operated equipment and issued a report, Compressed Air
  longstanding non-conformance in the operation of pressure control valve PCV-
Systems, dated July 16, 1989. During this review, the licensee did not identify
  13-23. The team determined through interviews with Vermont Yankee staff that
that the pressure control valve was not independent of the instrument air system.
  during initial start-up testing, problems were identified with the automatic
  operation of this valve which affected its ability to properly supply cooling flow to
!
  the RCIC lube oil cooler. This issue was more than minor because it was
Green. The team identified a non-cited violation of 10 CFR Part 50, Appendix B,
  associated with the Mitigating Systems attribute of Equipment Performance and
Criterion XVI, Corrective Action, because the licensee failed to correct a
  affected the cornerstone objective of ensuring the reliability of the RCIC system.
longstanding non-conformance in the operation of pressure control valve PCV-
  The issue screened as very low safety significance in Phase I of the SDP
13-23. The team determined through interviews with Vermont Yankee staff that
  because it was a design deficiency that was not found to result in a loss of
during initial start-up testing, problems were identified with the automatic
  function. The licensee had implemented manual actions as a compensatory
operation of this valve which affected its ability to properly supply cooling flow to
                                      iv                                      Enclosure
the RCIC lube oil cooler. This issue was more than minor because it was
associated with the Mitigating Systems attribute of Equipment Performance and
affected the cornerstone objective of ensuring the reliability of the RCIC system.  
The issue screened as very low safety significance in Phase I of the SDP
because it was a design deficiency that was not found to result in a loss of
function. The licensee had implemented manual actions as a compensatory


  measure for the operation of PCV-13-23 through the addition of procedural
Enclosure
  steps. (Section 4OA5.2.1.2)
v
! Green. The team identified a non-cited violation of 10 CFR Part 50, Appendix B,
measure for the operation of PCV-13-23 through the addition of procedural
  Criterion III, Design Control, because the licensee had neither established the
steps. (Section 4OA5.2.1.2)
  correct condensate storage tank (CST) temperature limit for use in the plant
!
  transient analyses nor translated the CST temperature limit into plant
Green. The team identified a non-cited violation of 10 CFR Part 50, Appendix B,
  procedures. This issue was more than minor because it was associated with the
Criterion III, Design Control, because the licensee had neither established the
  Mitigating Systems Cornerstone attribute of Equipment Performance and
correct condensate storage tank (CST) temperature limit for use in the plant
  affected the cornerstone objective of ensuring the reliability of the core spray
transient analyses nor translated the CST temperature limit into plant
  system. The issue screened as very low safety significance in Phase I of the
procedures. This issue was more than minor because it was associated with the
  SDP because it was a design deficiency that was not found to result in a loss of
Mitigating Systems Cornerstone attribute of Equipment Performance and
  function. Although available net positive suction head (NPSH) margin for the
affected the cornerstone objective of ensuring the reliability of the core spray
  core spray pumps was lowered, adequate margin remained due to the
system. The issue screened as very low safety significance in Phase I of the
  conservatism that existed in other aspects of the licensees NPSH analysis.
SDP because it was a design deficiency that was not found to result in a loss of
  (Section 4OA5.2.1.7)
function. Although available net positive suction head (NPSH) margin for the
  A contributing cause of this finding is also related to the cross-cutting area of
core spray pumps was lowered, adequate margin remained due to the
  Problem Identification and Resolution. The licensee identified this issue in
conservatism that existed in other aspects of the licensees NPSH analysis.
  December 2002, but concluded that the non-conservative CST temperature had
(Section 4OA5.2.1.7)
  little to no effect on the transient analyses.
A contributing cause of this finding is also related to the cross-cutting area of
! Green. The team identified a non-cited violation of 10 CFR Part 50, Appendix B,
Problem Identification and Resolution. The licensee identified this issue in
  Criterion III, Design Control, because between June 2001 to September 2004,
December 2002, but concluded that the non-conservative CST temperature had
  the licensee did not adequately coordinate between the operations department
little to no effect on the transient analyses.
  and the engineering organization regarding procedure revisions that increased
!
  the length of time required to place the reactor core isolation cooling system in
Green. The team identified a non-cited violation of 10 CFR Part 50, Appendix B,
  service from the alternate shutdown panels. This issue was more than minor
Criterion III, Design Control, because between June 2001 to September 2004,
  because it was associated with the Mitigating Systems Cornerstone attribute of
the licensee did not adequately coordinate between the operations department
  Human Performance and affected the cornerstone objective of ensuring the
and the engineering organization regarding procedure revisions that increased
  availability of the RCIC system. Furthermore, this finding resulted in the use of
the length of time required to place the reactor core isolation cooling system in
  the December 1999 value of time to place RCIC in service from the alternate
service from the alternate shutdown panels. This issue was more than minor
  shutdown panel in documents submitted to the NRC as part of the Vermont
because it was associated with the Mitigating Systems Cornerstone attribute of
  Yankee Power Uprate Safety Analysis Report. The issue screened as very low
Human Performance and affected the cornerstone objective of ensuring the
  safety significance in Phase I of the SDP because it was a design deficiency that
availability of the RCIC system. Furthermore, this finding resulted in the use of
  was not found to result in a loss of function. Although the available time margin
the December 1999 value of time to place RCIC in service from the alternate
  was lowered, sufficient margin remained to allow operator action to manually
shutdown panel in documents submitted to the NRC as part of the Vermont
  start the RCIC system prior to reactor level reaching the top of active fuel.
Yankee Power Uprate Safety Analysis Report. The issue screened as very low
  (Section 4OA5.2.2)
safety significance in Phase I of the SDP because it was a design deficiency that
! Green. The team identified a non-cited violation of 10 CFR Part 50, Appendix B,
was not found to result in a loss of function. Although the available time margin
  Criterion XI, Test Control, because the licensee had conducted motor-operated
was lowered, sufficient margin remained to allow operator action to manually
  valve (MOV) diagnostic tests using procedures that did not include acceptance
start the RCIC system prior to reactor level reaching the top of active fuel.  
  limits, which were correlated to and based on applicable (stem thrust and torque)
(Section 4OA5.2.2)
  design documents. Additionally, MOV diagnostic testing had been conducted
!
  solely from the motor control centers using test instrumentation that had not
Green. The team identified a non-cited violation of 10 CFR Part 50, Appendix B,
  been validated to ensure its adequacy. The finding was more than minor
Criterion XI, Test Control, because the licensee had conducted motor-operated
  because it affected the Mitigating Systems Cornerstone attribute of Equipment
valve (MOV) diagnostic tests using procedures that did not include acceptance
  Performance and affected the cornerstone objective of ensuring the availability,
limits, which were correlated to and based on applicable (stem thrust and torque)
                                      v                                      Enclosure
design documents. Additionally, MOV diagnostic testing had been conducted
solely from the motor control centers using test instrumentation that had not
been validated to ensure its adequacy. The finding was more than minor
because it affected the Mitigating Systems Cornerstone attribute of Equipment
Performance and affected the cornerstone objective of ensuring the availability,


          reliability, and capability of systems and components that respond to initiating
Enclosure
          events. Specifically, the unvalidated test method had the potential to affect the
vi
          reliability of safety-related motor-operated valves. The issue screened as very
reliability, and capability of systems and components that respond to initiating
          low safety significance in Phase I of the SDP because it was a qualification
events. Specifically, the unvalidated test method had the potential to affect the
          deficiency that was not found to result in a loss of function. The team did not
reliability of safety-related motor-operated valves. The issue screened as very
          identify any examples of degraded or inoperable valves during the inspection
low safety significance in Phase I of the SDP because it was a qualification
          and noted that the design basis calculations for the MOVs reviewed had
deficiency that was not found to result in a loss of function. The team did not
          available thrust margin of greater than 60 percent. (Section 4OA5.2.3)
identify any examples of degraded or inoperable valves during the inspection
B. Licensee Identified Violations
and noted that the design basis calculations for the MOVs reviewed had
  None.
available thrust margin of greater than 60 percent. (Section 4OA5.2.3)
                                              vi                                  Enclosure
B.
Licensee Identified Violations
None.


                                      REPORT DETAILS
Enclosure
REPORT DETAILS
4OA2 Problem Identification and Resolution (PI&R)
4OA2 Problem Identification and Resolution (PI&R)
2.   Annual Sample Review
2.
    Not applicable.
Annual Sample Review
3.   Cross Reference to PI&R Findings Documented Elsewhere
Not applicable.
    Section 2.1.2 (b) 1 of this report describes a finding associated with a design
3.
    vulnerability of the reactor core isolation cooling (RCIC) system lube oil cooling pressure
Cross Reference to PI&R Findings Documented Elsewhere
    control valve in that the valve design was not independent of station service air as
Section 2.1.2 (b) 1 of this report describes a finding associated with a design
    described in the Updated Final Safety Analysis Report. The licensee had previously
vulnerability of the reactor core isolation cooling (RCIC) system lube oil cooling pressure
    reviewed the failure positions of air-operated equipment and issued a report,
control valve in that the valve design was not independent of station service air as
    Compressed Air Systems, dated July 16, 1989. This longstanding deficiency was not
described in the Updated Final Safety Analysis Report. The licensee had previously
    identified by this review or by other station service air reviews.
reviewed the failure positions of air-operated equipment and issued a report,
    Section 2.1.7 (b) of this report describes a finding associated with maintaining the
Compressed Air Systems, dated July 16, 1989. This longstanding deficiency was not
    condensate storage tank temperature within limits assumed in the facilitys transient
identified by this review or by other station service air reviews.  
    analysis. The licensee had identified conditions where the tank temperature had
Section 2.1.7 (b) of this report describes a finding associated with maintaining the
    exceeded the transient analysis assumptions but had not taken sufficient corrective
condensate storage tank temperature within limits assumed in the facilitys transient
    actions.
analysis. The licensee had identified conditions where the tank temperature had
exceeded the transient analysis assumptions but had not taken sufficient corrective
actions.
4OA5 Other Activities - Temporary Instruction 2515/158
4OA5 Other Activities - Temporary Instruction 2515/158
1.   Inspection Sample Selection Process
1.
    In selecting samples for review, the team focused on the most risk-significant
Inspection Sample Selection Process
    components and operator actions. The team selected these components and operator
In selecting samples for review, the team focused on the most risk-significant
    actions by using the risk information contained in the licensees Probabilistic Risk
components and operator actions. The team selected these components and operator
    Assessment (PRA) and the US Nuclear Regulatory Commissions (NRCs) Simplified
actions by using the risk information contained in the licensees Probabilistic Risk
    Plant Analysis Risk (SPAR) models. An initial sample was chosen from those
Assessment (PRA) and the US Nuclear Regulatory Commissions (NRCs) Simplified
    components and operator actions that had a risk achievement worth factor greater than
Plant Analysis Risk (SPAR) models. An initial sample was chosen from those
    two. These components and operator actions are important to safety since their
components and operator actions that had a risk achievement worth factor greater than
    assumed failure would result in at least doubling the risk of an accident that could result
two. These components and operator actions are important to safety since their
    in core damage. Consideration was also given to those components and operator
assumed failure would result in at least doubling the risk of an accident that could result
    actions most impacted by the licensees request for a 20 percent extended power uprate
in core damage. Consideration was also given to those components and operator
    (EPU) license amendment.
actions most impacted by the licensees request for a 20 percent extended power uprate
    Many of the samples selected were located within the reactor core isolation cooling,
(EPU) license amendment.
    main feedwater, safety relief valve, onsite electrical power, and off-site electrical power
Many of the samples selected were located within the reactor core isolation cooling,
    systems. In addition, inspection samples were added based upon operational
main feedwater, safety relief valve, onsite electrical power, and off-site electrical power
    experience reviews. The team was also briefed by the NRCs technical staff conducting
systems. In addition, inspection samples were added based upon operational
    the EPU licensing review on issues that had arisen during their reviews, indicating areas
experience reviews. The team was also briefed by the NRCs technical staff conducting
    that might warrant additional inspection. A complete listing of all components, operator
the EPU licensing review on issues that had arisen during their reviews, indicating areas
    actions and operating experience issues reviewed by the inspection team is contained in
that might warrant additional inspection. A complete listing of all components, operator
    Attachment A to this report. A total of 91 samples were chosen for the teams initial
actions and operating experience issues reviewed by the inspection team is contained in
    review.
Attachment A to this report. A total of 91 samples were chosen for the teams initial
                                                                                        Enclosure
review.


                                                2
2
    A preliminary review was performed on the 91 samples to determine whether any low-
Enclosure
    margin concerns existed. For the purpose of this inspection, margin concerns included
A preliminary review was performed on the 91 samples to determine whether any low-
    original design issues, margin reductions due to the proposed EPU or margin reductions
margin concerns existed. For the purpose of this inspection, margin concerns included
    identified as a result of material condition issues. Consideration was also given to the
original design issues, margin reductions due to the proposed EPU or margin reductions
    uniqueness and complexity of the design, operating experience, and the available
identified as a result of material condition issues. Consideration was also given to the
    defense-in-depth margins. Based upon the above considerations, 45 of the original 91
uniqueness and complexity of the design, operating experience, and the available
    samples were selected for a more detailed review. An overall summary of the reviews
defense-in-depth margins. Based upon the above considerations, 45 of the original 91
    performed and the specific inspection findings identified is included in the following
samples were selected for a more detailed review. An overall summary of the reviews
    sections of the report.
performed and the specific inspection findings identified is included in the following
2.   Results of Detailed Reviews
sections of the report.
    The team performed detailed reviews on the 45 components, operator actions and
2.
    operating experience issues. For components, the team reviewed the adequacy of the
Results of Detailed Reviews
    original design, modifications to the original design, maintenance and corrective action
The team performed detailed reviews on the 45 components, operator actions and
    program histories, and associated operating and surveillance procedures. As practical,
operating experience issues. For components, the team reviewed the adequacy of the
    the team also performed walkdowns of the selected components. For operator actions,
original design, modifications to the original design, maintenance and corrective action
    the team reviewed the adequacy of operating procedures and compared design basis
program histories, and associated operating and surveillance procedures. As practical,
    time requirements against actual demonstrated timelines. For the operating experience
the team also performed walkdowns of the selected components. For operator actions,
    issues chosen for detailed review, the team assessed the issues applicability to
the team reviewed the adequacy of operating procedures and compared design basis
    Vermont Yankee and the licensees disposition of the issue. The following sections of
time requirements against actual demonstrated timelines. For the operating experience
    the report provide a summary of the detailed reviews, including any findings identified by
issues chosen for detailed review, the team assessed the issues applicability to
    the inspection team.
Vermont Yankee and the licensees disposition of the issue. The following sections of
2.1 Detailed Component and System Reviews
the report provide a summary of the detailed reviews, including any findings identified by
    2.1.1   Electrical Power Sources
the inspection team.  
      a.     Inspection Scope
  2.1
              The team reviewed the adequacy of the onsite and off-site electrical power
Detailed Component and System Reviews
              sources that supply power to the safety-related components chosen for detailed
2.1.1
              review. Particular focus was paid to the off-site power sources and grid stability,
Electrical Power Sources
              to the extent they would be impacted by an EPU. The teams review
  a.
              encompassed the licensees plans to limit the initial power increase to
Inspection Scope
              15 percent, as a capacitor bank necessary to provide reactive power to the grid
The team reviewed the adequacy of the onsite and off-site electrical power
              to ensure stability had yet to be installed. Other attributes of the electrical
sources that supply power to the safety-related components chosen for detailed
              systems reviewed during the inspection were operating procedures, setpoints for
review. Particular focus was paid to the off-site power sources and grid stability,
              degraded voltage relays, battery capacity, circuit breaker coordination, fast and
to the extent they would be impacted by an EPU. The teams review
              slow transfer schemes, Technical Specifications (TS) and other related
encompassed the licensees plans to limit the initial power increase to
              calculations.
15 percent, as a capacitor bank necessary to provide reactive power to the grid
              The team conducted a walkdown of the safety-related switchgear rooms and the
to ensure stability had yet to be installed. Other attributes of the electrical
              electrical controls in the main control room with station engineering personnel.
systems reviewed during the inspection were operating procedures, setpoints for
              The review was conducted to identify any alignment discrepancies or visible
degraded voltage relays, battery capacity, circuit breaker coordination, fast and
              signs of significant deficient material conditions.
slow transfer schemes, Technical Specifications (TS) and other related
                                                                                        Enclosure
calculations.
The team conducted a walkdown of the safety-related switchgear rooms and the
electrical controls in the main control room with station engineering personnel.  
The review was conducted to identify any alignment discrepancies or visible
signs of significant deficient material conditions.  


                                        3
3
    The team also performed a detailed, focused review of the ability of the Vernon
Enclosure
    Hydro-Electric Station to supply emergency power to Vermont Yankee in the
The team also performed a detailed, focused review of the ability of the Vernon
    event of a station blackout (SBO) caused by a grid disturbance, as required by
Hydro-Electric Station to supply emergency power to Vermont Yankee in the
    10 CFR Part 50.63, Loss of all Alternating Current Power, and as clarified by
event of a station blackout (SBO) caused by a grid disturbance, as required by
    Regulatory Guide 1.155, Station Blackout, and NUMARC 87-00, Revision 1. The
10 CFR Part 50.63, Loss of all Alternating Current Power, and as clarified by
    team reviewed procedures associated with the operator actions necessary to tie
Regulatory Guide 1.155, Station Blackout, and NUMARC 87-00, Revision 1. The
    in the Vernon Station, procedures associated with the operation and
team reviewed procedures associated with the operator actions necessary to tie
    maintenance of the Vernon Station, and regional grid operator system
in the Vernon Station, procedures associated with the operation and
    restoration procedures. The team also visited the remote control location for the
maintenance of the Vernon Station, and regional grid operator system
    Vernon Station, and interviewed station personnel. Lastly, the team conducted a
restoration procedures. The team also visited the remote control location for the
    conference call with the regional grid operator responsible for controlling the
Vernon Station, and interviewed station personnel. Lastly, the team conducted a
    operation of circuit breakers and switches in the Vernon switchyard.
conference call with the regional grid operator responsible for controlling the
b.   Findings
operation of circuit breakers and switches in the Vernon switchyard.
(1) Availability of Power from Vernon Station
  b.
    Introduction. The team identified a Green non-cited violation of 10 CFR Part
Findings  
    50.63, Loss of All Alternating Current Power, because the licensee had not
    (1)
    completed a coping analysis and had not demonstrated, by test, the time
Availability of Power from Vernon Station
    required to make the alternate alternating current (AC) source available for an
Introduction. The team identified a Green non-cited violation of 10 CFR Part
    electrical grid collapse resulting in a station blackout.
50.63, Loss of All Alternating Current Power, because the licensee had not
    Description. 10 CFR Part 50.63 requires that licensees be able to recover from
completed a coping analysis and had not demonstrated, by test, the time
    an SBO that results from a loss of all AC electrical power (both the normal off-
required to make the alternate alternating current (AC) source available for an
    site power sources and the on-site emergency diesel generators). In Section
electrical grid collapse resulting in a station blackout.  
    C.2, Offsite Power, Regulatory Guide 1.155 defines the minimum potential
    causes to be considered for a loss of off-site power that results in an SBO. One
Description. 10 CFR Part 50.63 requires that licensees be able to recover from
    listed cause is grid undervoltage and collapse. For SBO scenarios where the
an SBO that results from a loss of all AC electrical power (both the normal off-
    licensee cannot demonstrate by test that an alternate AC source would be
site power sources and the on-site emergency diesel generators). In Section
    available within 10 minutes, 10 CFR Part 50.63 requires the licensee to complete
C.2, Offsite Power, Regulatory Guide 1.155 defines the minimum potential
    a coping analysis for the period of time it would take for power to be restored.
causes to be considered for a loss of off-site power that results in an SBO. One
    At Vermont Yankee, the licensee credits the Vernon Hydro-Electric Station as its
listed cause is grid undervoltage and collapse. For SBO scenarios where the
    alternate AC source to respond to a station blackout within 10 minutes. If a grid
licensee cannot demonstrate by test that an alternate AC source would be
    collapse occurs, the Vernon Station would trip offline and have to be restarted.
available within 10 minutes, 10 CFR Part 50.63 requires the licensee to complete
    The Vernon Station is considered a black start facility by the regional grid
a coping analysis for the period of time it would take for power to be restored.  
    operator. As such, the Vernon Station is required to certify it can be ready to
At Vermont Yankee, the licensee credits the Vernon Hydro-Electric Station as its
    supply power within 90 minutes after tripping off line. However, in order to
alternate AC source to respond to a station blackout within 10 minutes. If a grid
    supply power to Vermont Yankee under such conditions, the Vernon switchyard
collapse occurs, the Vernon Station would trip offline and have to be restarted.
    would have to be configured to isolate the Vernon Station from the rest of the
The Vernon Station is considered a black start facility by the regional grid
    grid. The operation of the circuit breakers necessary to complete such actions is
operator. As such, the Vernon Station is required to certify it can be ready to
    not controlled by either the licensee or the Vernon Station, but is controlled by
supply power within 90 minutes after tripping off line. However, in order to
    the regional grid operator. The team held a conference call with the grid
supply power to Vermont Yankee under such conditions, the Vernon switchyard
    operators. During the call, the team learned that no specific procedures or
would have to be configured to isolate the Vernon Station from the rest of the
    communication protocols had been set up to deal with a station blackout at
grid. The operation of the circuit breakers necessary to complete such actions is
    Vermont Yankee. The only reference to Vermont Yankee was a general
not controlled by either the licensee or the Vernon Station, but is controlled by
                                                                              Enclosure
the regional grid operator. The team held a conference call with the grid
operators. During the call, the team learned that no specific procedures or
communication protocols had been set up to deal with a station blackout at
Vermont Yankee. The only reference to Vermont Yankee was a general


                                  4
4
Enclosure
statement in a procedure that said that nuclear generators should receive critical
statement in a procedure that said that nuclear generators should receive critical
priority. During the call, the team also learned that the grid operator did not
priority. During the call, the team also learned that the grid operator did not
differentiate between situations where normal off-site power was lost to a nuclear
differentiate between situations where normal off-site power was lost to a nuclear
unit but emergency diesels remain available, and those situations where the
unit but emergency diesels remain available, and those situations where the
emergency diesel generators failed to start and the station was in a true blackout
emergency diesel generators failed to start and the station was in a true blackout
condition. The team learned that no specific training, testing, or simulations had
condition. The team learned that no specific training, testing, or simulations had
been conducted to simulate the actions that would have to be taken to respond
been conducted to simulate the actions that would have to be taken to respond
to an SBO at Vermont Yankee caused by a grid collapse.
to an SBO at Vermont Yankee caused by a grid collapse.
As a result of the teams concerns, the licensee issued condition reports (CRs)
As a result of the teams concerns, the licensee issued condition reports (CRs)
CR-VTY-2004-2677 and 2004-2738. The licensee also created a preliminary
CR-VTY-2004-2677 and 2004-2738. The licensee also created a preliminary
timeline which estimated the time to restore power under such conditions as
timeline which estimated the time to restore power under such conditions as
being between 20 minutes and 2 hours. The licensee also performed an
being between 20 minutes and 2 hours. The licensee also performed an
operability evaluation in accordance with Generic Letter 91-18, which included a
operability evaluation in accordance with Generic Letter 91-18, which included a
preliminary four-hour coping analysis. The licensee provided the team a copy of
preliminary four-hour coping analysis. The licensee provided the team a copy of
the preliminary coping analysis and copies of the original NRC Safety Evaluation
the preliminary coping analysis and copies of the original NRC Safety Evaluation
Report (SER) for the station blackout rule dated September 1, 1992. The team
Report (SER) for the station blackout rule dated September 1, 1992. The team
reviewed the preliminary coping analysis and found the methodology used to be
reviewed the preliminary coping analysis and found the methodology used to be
reasonable. Review of the NRC SER indicated that questions were asked by the
reasonable. Review of the NRC SER indicated that questions were asked by the
NRC staff regarding a regional grid disturbance during the original station
NRC staff regarding a regional grid disturbance during the original station
blackout review, and that the licensees response was that power would be
blackout review, and that the licensees response was that power would be
restored within one hour. Based upon the above facts, the team determined that
restored within one hour. Based upon the above facts, the team determined that
the one hour time stated in the SER could no longer be ensured. Furthermore,
the one hour time stated in the SER could no longer be ensured. Furthermore,
contrary to 10 CFR Part 50.63, the licensee had not completed a coping analysis
contrary to 10 CFR Part 50.63, the licensee had not completed a coping analysis
for the period of time it would take to restore the alternate source.
for the period of time it would take to restore the alternate source.
Analysis. The team determined that this issue was a performance deficiency
Analysis. The team determined that this issue was a performance deficiency
since the licensee had not demonstrated by test that the Vernon Station could
since the licensee had not demonstrated by test that the Vernon Station could
supply power to Vermont Yankee within one hour after the onset of a station
supply power to Vermont Yankee within one hour after the onset of a station
blackout and had not completed a coping analysis for the period of time the
blackout and had not completed a coping analysis for the period of time the
Vernon Station would be unavailable, as required by 10 CFR Part 50.63. Also,
Vernon Station would be unavailable, as required by 10 CFR Part 50.63. Also,
the licensee did not remain cognizant of how design changes, made by the
the licensee did not remain cognizant of how design changes, made by the
operator of the Vernon Station, affected the ability of the Vernon Station to
operator of the Vernon Station, affected the ability of the Vernon Station to
supply emergency power to Vermont Yankee in a timely manner. This issue was
supply emergency power to Vermont Yankee in a timely manner. This issue was
more than minor because it was associated with the Mitigating Systems
more than minor because it was associated with the Mitigating Systems
Cornerstone attribute of Equipment Performance and affected the cornerstone
Cornerstone attribute of Equipment Performance and affected the cornerstone
objective of ensuring availability, reliability, and capability of systems needed to
objective of ensuring availability, reliability, and capability of systems needed to
respond to a station blackout resulting from a grid collapse. The issue screened
respond to a station blackout resulting from a grid collapse. The issue screened
as very low safety significance (Green) in Phase I of the SDP because it was a
as very low safety significance (Green) in Phase I of the SDP because it was a
design deficiency that was not found to result in a loss of function. Specifically,
design deficiency that was not found to result in a loss of function. Specifically,
the team found that the licensees preliminary coping analysis, performed during
the team found that the licensees preliminary coping analysis, performed during
the inspection, demonstrated a four-hour coping time that should be sufficient to
the inspection, demonstrated a four-hour coping time that should be sufficient to
envelope the time required to start and align the Vernon Station.
envelope the time required to start and align the Vernon Station.
Enforcement. 10 CFR Part 50.63(c)(2), requires that a coping analysis be
Enforcement. 10 CFR Part 50.63(c)(2), requires that a coping analysis be
performed if the designated alternate AC source cannot be made available within
performed if the designated alternate AC source cannot be made available within
10 minutes. It also requires that the time required to make the alternate AC
10 minutes. It also requires that the time required to make the alternate AC
                                                                            Enclosure


                                      5
5
    source available be demonstrated by test. Contrary to the above, the licensee
Enclosure
    had not completed a coping analysis for the period of time the alternate AC
source available be demonstrated by test. Contrary to the above, the licensee
    source would be unavailable and had not demonstrated by test the time required
had not completed a coping analysis for the period of time the alternate AC
    to make the alternate source available for a station blackout involving a grid
source would be unavailable and had not demonstrated by test the time required
    collapse. Because this finding is of very low safety significance and the licensee
to make the alternate source available for a station blackout involving a grid
    entered this issue into its corrective action program (CR-VTY-2004-2677 and
collapse. Because this finding is of very low safety significance and the licensee
    2004-2738), it is considered a non-cited violation consistent with Section VI.A.1
entered this issue into its corrective action program (CR-VTY-2004-2677 and
    of the NRCs Enforcement Policy. (NCV 05000271/2004008-01 Availability of
2004-2738), it is considered a non-cited violation consistent with Section VI.A.1
    Power from Vernon Station)
of the NRCs Enforcement Policy. (NCV 05000271/2004008-01 Availability of
(2) Procedures for Assessing Off-site Power Operability
Power from Vernon Station)
    Introduction. The team identified a Green non-cited violation of Technical
    (2)
    Specifications 6.4, Procedures, because the licensee did not establish
Procedures for Assessing Off-site Power Operability
    adequate procedures for assessing the operability of the 115 kilovolt (kV) Keene
Introduction. The team identified a Green non-cited violation of Technical
    line.
Specifications 6.4, Procedures, because the licensee did not establish
    Description. At Vermont Yankee, the immediate access off-site power source is
adequate procedures for assessing the operability of the 115 kilovolt (kV) Keene
    normally derived from the 345 kV switchyard through the 345/115 kV transformer
line.  
    T-4-1A. The 115 kV Keene line may also be conditionally used as an alternate
Description. At Vermont Yankee, the immediate access off-site power source is
    immediate access source for satisfying TS requirements for off-site power
normally derived from the 345 kV switchyard through the 345/115 kV transformer
    supplies, depending on grid and plant conditions. Specifically, Technical
T-4-1A. The 115 kV Keene line may also be conditionally used as an alternate
    Specification Bases 3.10.A, states that the availability of the Keene line is
immediate access source for satisfying TS requirements for off-site power
    dependent on its pre-loading which must be limited by the system dispatchers
supplies, depending on grid and plant conditions. Specifically, Technical
    prior to it being declared an immediate access source.
Specification Bases 3.10.A, states that the availability of the Keene line is
    The team reviewed Procedure ON 3155, Loss of Auto Transformer, and noted
dependent on its pre-loading which must be limited by the system dispatchers
    that Step 2b, instructs operators to contact ISO New England to determine the
prior to it being declared an immediate access source.  
    115 kV Keene line load limit but does not provide explicit criteria for evaluating
The team reviewed Procedure ON 3155, Loss of Auto Transformer, and noted
    the lines operability. The team also noted Note 5 on the load nomograph
that Step 2b, instructs operators to contact ISO New England to determine the
    included in procedure ON 3155, Reference D, Guidelines for Operating the
115 kV Keene line load limit but does not provide explicit criteria for evaluating
    Vermont Yankee 115 kV System with the VTY4 Auto Transformer Out of
the lines operability. The team also noted Note 5 on the load nomograph
    Service, stated the assumption that, All Vermont Yankee motor startups
included in procedure ON 3155, Reference D, Guidelines for Operating the
    performed sequentially, not simultaneously. During accident loading with off-
Vermont Yankee 115 kV System with the VTY4 Auto Transformer Out of
    site power available, all safety loads are designed to block start simultaneously,
Service, stated the assumption that, All Vermont Yankee motor startups
    so this assumption would never be met.
performed sequentially, not simultaneously. During accident loading with off-
    The team noted the procedure also contained invalid criteria for assessing the
site power available, all safety loads are designed to block start simultaneously,
    operability of the downstream safety buses. Step 11 allowed operation of bus 3
so this assumption would never be met.
    or 4 with voltages as low as 3600 volts (V) AC. This voltage was below the TS
The team noted the procedure also contained invalid criteria for assessing the
    allowable setting of 3660 VAC for the degraded voltage relays. Under non-
operability of the downstream safety buses. Step 11 allowed operation of bus 3
    accident conditions, operation of the buses at this minimum voltage would result
or 4 with voltages as low as 3600 volts (V) AC. This voltage was below the TS
    in automatic actuation of the degraded voltage relays, separating the buses from
allowable setting of 3660 VAC for the degraded voltage relays. Under non-
    off-site power. Under post-accident conditions, the degraded voltage protection
accident conditions, operation of the buses at this minimum voltage would result
    relays are locked out and operation of the buses at 3600 VAC could result in
in automatic actuation of the degraded voltage relays, separating the buses from
    equipment mis-operation or damage.
off-site power. Under post-accident conditions, the degraded voltage protection
                                                                              Enclosure
relays are locked out and operation of the buses at 3600 VAC could result in
equipment mis-operation or damage.


                                        6
6
    Analysis. The team determined this to be a performance deficiency since the
Enclosure
    operating procedures did not provide adequate guidance for determining
Analysis. The team determined this to be a performance deficiency since the
    operability of the 115 kV Keene line. This issue was more than minor because it
operating procedures did not provide adequate guidance for determining
    was associated with the Mitigating Systems Cornerstone attribute of Procedure
operability of the 115 kV Keene line. This issue was more than minor because it
    Quality and affected the cornerstone objective of ensuring availability, reliability,
was associated with the Mitigating Systems Cornerstone attribute of Procedure
    and capability of systems needed to respond to a loss of off-site power. The
Quality and affected the cornerstone objective of ensuring availability, reliability,
    issue screened as very low safety significance (Green) in Phase I of the SDP
and capability of systems needed to respond to a loss of off-site power. The
    because the failure to translate design requirements into operating procedures
issue screened as very low safety significance (Green) in Phase I of the SDP
    was a design deficiency that was not found to result in a loss of function.
because the failure to translate design requirements into operating procedures
    Specifically, the team did not identify any instances where the lack of procedural
was a design deficiency that was not found to result in a loss of function.  
    guidance had resulted in an inadequate assessment of off-site power operability
Specifically, the team did not identify any instances where the lack of procedural
    or the inoperability of the electrical system or any components.
guidance had resulted in an inadequate assessment of off-site power operability
    Enforcement. Technical Specifications 6.4.C, Procedures, requires that written
or the inoperability of the electrical system or any components.
    procedures be established, implemented, and maintained for actions to be taken
Enforcement. Technical Specifications 6.4.C, Procedures, requires that written
    to correct specific and unforeseen potential malfunctions of systems or
procedures be established, implemented, and maintained for actions to be taken
    components. Contrary to the above, the licensee did not establish adequate
to correct specific and unforeseen potential malfunctions of systems or
    procedures for assessing the operability of the 115 kV Keene line. Since this
components. Contrary to the above, the licensee did not establish adequate
    finding is of very low safety significance and has been entered into the licensees
procedures for assessing the operability of the 115 kV Keene line. Since this
    corrective action program (CR-VTY-2004-2803 and CR-VTY-2004-2804), it is
finding is of very low safety significance and has been entered into the licensees
    considered a non-cited violation, consistent with Section VI.A.1 of the NRC
corrective action program (CR-VTY-2004-2803 and CR-VTY-2004-2804), it is
    Enforcement Policy. (NCV 05000271/2004008-02 Procedures for Assessing
considered a non-cited violation, consistent with Section VI.A.1 of the NRC
    Off-site Power Operability)
Enforcement Policy. (NCV 05000271/2004008-02 Procedures for Assessing
(3) Degraded Voltage Relay Setpoint Calculations
Off-site Power Operability)
    Introduction. The team identified a Green non-cited violation of 10 CFR Part 50
    (3)
    Appendix B, Criterion III, Design Control, because the licensee did not use the
Degraded Voltage Relay Setpoint Calculations
    Technical Specification allowed voltage value in the calculations used to ensure
Introduction. The team identified a Green non-cited violation of 10 CFR Part 50
    the degraded voltage relay dropout function would provide adequate voltage to
Appendix B, Criterion III, Design Control, because the licensee did not use the
    safety-related electrical equipment.
Technical Specification allowed voltage value in the calculations used to ensure
    Description. As described in Section 8.5 of the Vermont Yankee Updated Final
the degraded voltage relay dropout function would provide adequate voltage to
    Safety Analysis Report (UFSAR), the licensee has installed degraded voltage
safety-related electrical equipment.
    relays, which are designed to protect the stations electrical equipment from
Description. As described in Section 8.5 of the Vermont Yankee Updated Final
    damage that could occur due to degraded voltage. The licensees Technical
Safety Analysis Report (UFSAR), the licensee has installed degraded voltage
    Specifications (TS) allow a minimum degraded voltage relay setpoint of 3660
relays, which are designed to protect the stations electrical equipment from
    VAC; however, the licensees analysis of record, VYC-1088 Vermont Yankee
damage that could occur due to degraded voltage. The licensees Technical
    4160/480 Volt Short Circuit/ Voltage Study, did not evaluate the operability of
Specifications (TS) allow a minimum degraded voltage relay setpoint of 3660
    the connected electrical components at this minimum TS value. Instead, the
VAC; however, the licensees analysis of record, VYC-1088 Vermont Yankee
    lowest voltage evaluated by VYC-1088 was based on the minimum expected
4160/480 Volt Short Circuit/ Voltage Study, did not evaluate the operability of
    switchyard voltages, which were 3951 VAC for bus 3 and 3809 VAC for bus 4.
the connected electrical components at this minimum TS value. Instead, the
    Consequently, motors were evaluated for voltage considerably above the
lowest voltage evaluated by VYC-1088 was based on the minimum expected
    minimum voltage that could occur based on the TS value.
switchyard voltages, which were 3951 VAC for bus 3 and 3809 VAC for bus 4.  
                                                                            Enclosure
Consequently, motors were evaluated for voltage considerably above the
minimum voltage that could occur based on the TS value.  


                                          7
7
    As a result, calculation VYC-1053 and VYC-1314, which determine worst-case
Enclosure
    motor-operated valve (MOV) and motor control center (MCC) voltages, were also
As a result, calculation VYC-1053 and VYC-1314, which determine worst-case
    non-conservative. In response to the teams concerns, the licensee initiated CR-
motor-operated valve (MOV) and motor control center (MCC) voltages, were also
    VTY-2004-2596. The operability determination (OD) for CR-VTY-2004-2596
non-conservative. In response to the teams concerns, the licensee initiated CR-
    identified two motors that did not meet calculation acceptance criteria and
VTY-2004-2596. The operability determination (OD) for CR-VTY-2004-2596
    provided justification for their operability. This OD also provided justification for
identified two motors that did not meet calculation acceptance criteria and
    lower MCC control circuit voltages than previously analyzed. The licensee also
provided justification for their operability. This OD also provided justification for
    initiated CR-VTY-2004-2734 to address the effects of the postulated lower
lower MCC control circuit voltages than previously analyzed. The licensee also
    voltage on MOV operation. The effect on the MOVs was not expected to be
initiated CR-VTY-2004-2734 to address the effects of the postulated lower
    significant due to the otherwise generally conservative approach used for MOV
voltage on MOV operation. The effect on the MOVs was not expected to be
    calculations.
significant due to the otherwise generally conservative approach used for MOV
    Analysis. The team determined this to be a performance deficiency because the
calculations.  
    licensees calculations did not ensure the operability of electrical equipment at
Analysis. The team determined this to be a performance deficiency because the
    the minimum TS value for the degraded voltage relay dropout setting. This issue
licensees calculations did not ensure the operability of electrical equipment at
    was more than minor because it was associated with the Mitigating Systems
the minimum TS value for the degraded voltage relay dropout setting. This issue
    Cornerstone attribute of Equipment Performance and affected the cornerstone
was more than minor because it was associated with the Mitigating Systems
    objective of ensuring availability, reliability, and capability of systems needed to
Cornerstone attribute of Equipment Performance and affected the cornerstone
    respond to a design basis accident. The issue screened as very low safety
objective of ensuring availability, reliability, and capability of systems needed to
    significance (Green) in Phase I of the SDP because it was a design deficiency
respond to a design basis accident. The issue screened as very low safety
    that was not found to result in a loss of function. Specifically, the team did not
significance (Green) in Phase I of the SDP because it was a design deficiency
    identify any instances where using the Technical Specification degraded voltage
that was not found to result in a loss of function. Specifically, the team did not
    allowable setpoint values would have resulted in inoperable equipment.
identify any instances where using the Technical Specification degraded voltage
    Enforcement. 10 CFR Part 50, Appendix B, Criterion III, Design Control,
allowable setpoint values would have resulted in inoperable equipment.
    requires that measures be established to assure that applicable regulatory
Enforcement. 10 CFR Part 50, Appendix B, Criterion III, Design Control,
    requirements and the design basis for structures, systems and components are
requires that measures be established to assure that applicable regulatory
    correctly translated into specifications, drawings, procedures and instructions.
requirements and the design basis for structures, systems and components are
    Contrary to the above, the licensee used incorrect and non-conservative voltage
correctly translated into specifications, drawings, procedures and instructions.  
    values in calculations performed to ensure that electrical equipment would
Contrary to the above, the licensee used incorrect and non-conservative voltage
    remain operable under degraded voltage conditions. Since this finding is of very
values in calculations performed to ensure that electrical equipment would
    low safety significance and has been entered into the licensees corrective action
remain operable under degraded voltage conditions. Since this finding is of very
    program (CR-VTY-2004-2596 and CR-VTY-2004-2734), it is considered a non-
low safety significance and has been entered into the licensees corrective action
    cited violation, consistent with Section VI.A.1 of the NRC Enforcement Policy.
program (CR-VTY-2004-2596 and CR-VTY-2004-2734), it is considered a non-
    (NCV 05000271/2004008-03 - Degraded Voltage Relay Setpoint
cited violation, consistent with Section VI.A.1 of the NRC Enforcement Policy.
    Calculations)
(NCV 05000271/2004008-03 - Degraded Voltage Relay Setpoint
(4) Ungrounded 480 VAC Electrical System.
Calculations)
    The team identified an unresolved item (URI) associated with the 480 VAC
    (4)
    circuit-breakers designed to detect and interrupt electrical malfunctions. An
Ungrounded 480 VAC Electrical System.
    unresolved item is an issue requiring further information to determine if it is
The team identified an unresolved item (URI) associated with the 480 VAC
    acceptable, if it is a finding or if it constitutes a deviation or violation of NRC
circuit-breakers designed to detect and interrupt electrical malfunctions. An
    requirements. In this case, additional review will be required to determine if the
unresolved item is an issue requiring further information to determine if it is
    facility is in accordance with its design and/or licensing basis, since this was part
acceptable, if it is a finding or if it constitutes a deviation or violation of NRC
                                                                                    Enclosure
requirements. In this case, additional review will be required to determine if the
facility is in accordance with its design and/or licensing basis, since this was part


                                        8
8
      of the original design of the facility. Also, additional review will be required to
Enclosure
      determine the safety significance of this issue.
of the original design of the facility. Also, additional review will be required to
      The Vermont Yankee 480 VAC system consists of two 480 VAC load center
determine the safety significance of this issue.
      buses supplied through separate 4160/480 V transformers from the redundant
The Vermont Yankee 480 VAC system consists of two 480 VAC load center
      4160 VAC safety buses. The transformers are connected delta-delta and the
buses supplied through separate 4160/480 V transformers from the redundant
      480 VAC system is ungrounded. Several non-safety related loads are supplied
4160 VAC safety buses. The transformers are connected delta-delta and the
      from the safety-related load center buses and from safety-related MCCs. These
480 VAC system is ungrounded. Several non-safety related loads are supplied
      non-safety loads are not automatically disconnected during postulated accidents
from the safety-related load center buses and from safety-related MCCs. These
      but rather are shed manually depending on the specific accident scenario. The
non-safety loads are not automatically disconnected during postulated accidents
      load centers are equipped with 600 ampere circuit-breakers with long-time and
but rather are shed manually depending on the specific accident scenario. The
      short-time, or long-time and instantaneous trip devices. The MCCs are equipped
load centers are equipped with 600 ampere circuit-breakers with long-time and
      with magnetic breakers with thermal overloads or thermal/magnetic breakers.
short-time, or long-time and instantaneous trip devices. The MCCs are equipped
      Each bus is provided with a ground detection system which consists of three
with magnetic breakers with thermal overloads or thermal/magnetic breakers.  
      ground detection voltmeters and three potential transformers. The system only
Each bus is provided with a ground detection system which consists of three
      provides local indication at the MCCs and does not annunciate in the control
ground detection voltmeters and three potential transformers. The system only
      room. The control room relies on the auxiliary operator round sheet voltage
provides local indication at the MCCs and does not annunciate in the control
      recordings of the ground detection voltmeters to be informed of any ground fault
room. The control room relies on the auxiliary operator round sheet voltage
      on the 480 V system. The ground detector does not actuate any protective
recordings of the ground detection voltmeters to be informed of any ground fault
      devices or indicate the location of the fault.
on the 480 V system. The ground detector does not actuate any protective
      The team identified that since the 480 VAC electrical system at Vermont Yankee
devices or indicate the location of the fault.
      is ungrounded, an arcing/intermittent ground fault could cause excessive
The team identified that since the 480 VAC electrical system at Vermont Yankee
      voltages to be impressed upon the system. Such a ground could begin on non-
is ungrounded, an arcing/intermittent ground fault could cause excessive
      safety related equipment that is unprotected from the effects of a postulated high
voltages to be impressed upon the system. Such a ground could begin on non-
      energy line break or seismic event. The installed electrical protective devices
safety related equipment that is unprotected from the effects of a postulated high
      designed to provide isolation between the safety and non-safety related loads
energy line break or seismic event. The installed electrical protective devices
      may not open during this scenario because the ungrounded system may not
designed to provide isolation between the safety and non-safety related loads
      provide a return current path until a second ground was formed. While such a
may not open during this scenario because the ungrounded system may not
      ground could possibly be detected with the installed ground detection
provide a return current path until a second ground was formed. While such a
      instrumentation, there would likely be insufficient time to detect and isolate the
ground could possibly be detected with the installed ground detection
      ground before damage could occur to safety-related motors due to the possible
instrumentation, there would likely be insufficient time to detect and isolate the
      excessive voltages. (URI 05000271/2004008-04 - Ungrounded 480 VAC
ground before damage could occur to safety-related motors due to the possible
      Electrical System)
excessive voltages. (URI 05000271/2004008-04 - Ungrounded 480 VAC
2.1.2 Reactor Core Isolation Cooling (RCIC) System
Electrical System)
a.   Inspection Scope
2.1.2
      During the inspection, the team reviewed selected RCIC system components to
Reactor Core Isolation Cooling (RCIC) System
      ensure they would be capable of performing their required design functions for
  a.
      both current licensing basis conditions and the proposed EPU conditions. The
Inspection Scope
      team reviewed the RCIC pump and turbine, auxiliary equipment, various system
During the inspection, the team reviewed selected RCIC system components to
      valves, and instrumentation and controls. The team conducted plant equipment
ensure they would be capable of performing their required design functions for
      walkdowns, reviewed plant operating and test procedures, condition reports, test
both current licensing basis conditions and the proposed EPU conditions. The
                                                                                  Enclosure
team reviewed the RCIC pump and turbine, auxiliary equipment, various system
valves, and instrumentation and controls. The team conducted plant equipment
walkdowns, reviewed plant operating and test procedures, condition reports, test


                                9
9
Enclosure
results, maintenance history, vendor manuals, drawings, design calculations and
results, maintenance history, vendor manuals, drawings, design calculations and
applicable sections of the UFSAR and the TS.
applicable sections of the UFSAR and the TS.
                                                                    Enclosure


                                      10
10
b.   Findings
Enclosure
(1) Control Valve for RCIC Lube Oil Cooler
  b.  
    Introduction. The team identified a Green non-cited violation of 10 CFR Part 50,
Findings
    Appendix B, Criterion III, Design Control, because the cooling water supply to
    (1)
    the lube oil cooler of the RCIC system was not installed as described in the RCIC
Control Valve for RCIC Lube Oil Cooler
    system design basis. Specifically, the pressure control valve for the lube oil
Introduction. The team identified a Green non-cited violation of 10 CFR Part 50,
    cooler water supply was not independent of air systems, and the piping between
Appendix B, Criterion III, Design Control, because the cooling water supply to
    the pressure control valve and lube oil cooler did not contain a restricting orifice.
the lube oil cooler of the RCIC system was not installed as described in the RCIC
    Description. During a review of drawing G-191174, Sheet 2, Flow Diagram -
system design basis. Specifically, the pressure control valve for the lube oil  
    Reactor Core Isolation Cooling, Revision 23, the team noted that a pressure
cooler water supply was not independent of air systems, and the piping between
    control valve, PCV-13-23, was shown as having a connection to station
the pressure control valve and lube oil cooler did not contain a restricting orifice.
    instrument air. The team noted that USFAR Section 4.7.5 stated that all
    components necessary for initiating operation of RCIC were completely
Description. During a review of drawing G-191174, Sheet 2, Flow Diagram -
    independent of auxiliary ac power and station service air. The station instrument
Reactor Core Isolation Cooling, Revision 23, the team noted that a pressure
    air and service air systems are interconnected and are supplied from four AC
control valve, PCV-13-23, was shown as having a connection to station
    powered air compressors connected in parallel. Both the station instrument air
instrument air. The team noted that USFAR Section 4.7.5 stated that all
    and service air systems are classified as non-nuclear safety related. The team
components necessary for initiating operation of RCIC were completely
    questioned the effect of the loss of the air supply to this valve. PCV-13-23 was
independent of auxiliary ac power and station service air. The station instrument
    installed in the 2-inch cooling water supply line to the RCIC pump lube oil cooler
air and service air systems are interconnected and are supplied from four AC
    to regulate the flow of the cooling water supply from the RCIC pump discharge.
powered air compressors connected in parallel. Both the station instrument air
    A relief valve, SR-13-26, was installed between PCV-13-23 and the lube oil
and service air systems are classified as non-nuclear safety related. The team
    cooler for overpressure protection.
questioned the effect of the loss of the air supply to this valve. PCV-13-23 was
    In response to the teams questions, the licensees engineering personnel
installed in the 2-inch cooling water supply line to the RCIC pump lube oil cooler
    investigated this condition and determined that PCV-13-23 would fail in the fully
to regulate the flow of the cooling water supply from the RCIC pump discharge.  
    open position upon a loss of air. The licensee performed a hydraulic analysis of
A relief valve, SR-13-26, was installed between PCV-13-23 and the lube oil
    the affected portion of the RCIC system during the inspection. The analysis
cooler for overpressure protection.
    determined that fully opening the pressure control valve would have resulted in a
In response to the teams questions, the licensees engineering personnel
    flow of approximately 170 gpm through the valve, as opposed to the design flow
investigated this condition and determined that PCV-13-23 would fail in the fully
    of 16 gpm. The analysis also determined that the lube oil cooler, which has a
open position upon a loss of air. The licensee performed a hydraulic analysis of
    design pressure of 150 pounds per square inch gauge (psig), would have been
the affected portion of the RCIC system during the inspection. The analysis
    exposed to a maximum pressure of approximately 1100 psig. Both relief valve
determined that fully opening the pressure control valve would have resulted in a
    SR-13-26 and relief valve SR-13-27, installed on the RCIC pump barometric
flow of approximately 170 gpm through the valve, as opposed to the design flow
    condenser, would have opened to pass the expected flowrate. The licensees
of 16 gpm. The analysis also determined that the lube oil cooler, which has a
    investigation determined that this condition has existed since the original
design pressure of 150 pounds per square inch gauge (psig), would have been
    operation of the RCIC system.
exposed to a maximum pressure of approximately 1100 psig. Both relief valve
    The licensee documented this issue in condition report CR-VTY-2004-2535 and
SR-13-26 and relief valve SR-13-27, installed on the RCIC pump barometric
    performed an operability determination, which the team reviewed. The
condenser, would have opened to pass the expected flowrate. The licensees
    operability determination stated that a loss of air was considered unlikely during
investigation determined that this condition has existed since the original
    any of the events where the RCIC system was credited. It also concluded that, if
operation of the RCIC system.
    the air supply was lost, the lube oil cooler and associated piping components
The licensee documented this issue in condition report CR-VTY-2004-2535 and
    would not rupture when exposed to the expected pressures. This was based, in
performed an operability determination, which the team reviewed. The
    part, on vendor testing which showed that there was significant margin above
operability determination stated that a loss of air was considered unlikely during
                                                                              Enclosure
any of the events where the RCIC system was credited. It also concluded that, if
the air supply was lost, the lube oil cooler and associated piping components
would not rupture when exposed to the expected pressures. This was based, in
part, on vendor testing which showed that there was significant margin above


                                  11
11
1100 psig before these components would rupture. With regard to the potential
Enclosure
1100 psig before these components would rupture. With regard to the potential
loss of RCIC system capacity, the determination concluded that the RCIC pump
loss of RCIC system capacity, the determination concluded that the RCIC pump
would have sufficient capacity to provide the required flow to the reactor vessel
would have sufficient capacity to provide the required flow to the reactor vessel
even with the expected flow diversion. The licensee also initiated condition report
even with the expected flow diversion. The licensee also initiated condition report
CR-VTY-2004-2536 because the RCIC design basis document identified PCV-
CR-VTY-2004-2536 because the RCIC design basis document identified PCV-
13-23 as a self-contained pressure control valve.
13-23 as a self-contained pressure control valve.
The licensee performed a limited extent-of-condition review during the inspection
The licensee performed a limited extent-of-condition review during the inspection
to verify that a similar condition did not exist for other air-operated components.
to verify that a similar condition did not exist for other air-operated components.  
No additional concerns were identified by the licensee during this review. The
No additional concerns were identified by the licensee during this review. The
team also performed an independent sampled-based review and did not identify
team also performed an independent sampled-based review and did not identify
any additional issues. The licensee stated that a full extent-of-condition review
any additional issues. The licensee stated that a full extent-of-condition review
would be performed as part of the resolution of CR-VTY-2004-2535. At the time
would be performed as part of the resolution of CR-VTY-2004-2535. At the time
of the inspection, the licensee was developing a plan to correct this design
of the inspection, the licensee was developing a plan to correct this design
deficiency.
deficiency.
Line 814: Line 908:
oil cooler did not contain a restricting orifice as described in the UFSAR. UFSAR
oil cooler did not contain a restricting orifice as described in the UFSAR. UFSAR
Figure 4.7-3 indicated that a flow-restricting orifice was installed downstream of
Figure 4.7-3 indicated that a flow-restricting orifice was installed downstream of
valve PCV-13-23. No such orifice exists in the system. The licensee initiated
valve PCV-13-23. No such orifice exists in the system. The licensee initiated
condition report CR-VTY-2004-2537 to document this concern.
condition report CR-VTY-2004-2537 to document this concern.
Analysis. The team determined this issue was a performance deficiency since
Analysis. The team determined this issue was a performance deficiency since
the licensee had not instituted measures to ensure that the RCIC system was
the licensee had not instituted measures to ensure that the RCIC system was
installed consistent with its design and licensing basis. This issue was more
installed consistent with its design and licensing basis. This issue was more
than minor because it was associated with the Mitigating Systems Cornerstone
than minor because it was associated with the Mitigating Systems Cornerstone
attribute of Equipment Performance and affected the objective of ensuring the
attribute of Equipment Performance and affected the objective of ensuring the
reliability of the RCIC system. The issue screened as very low safety
reliability of the RCIC system. The issue screened as very low safety
significance in Phase I of the SDP, because it was a design deficiency that was
significance in Phase I of the SDP, because it was a design deficiency that was
not found to result in a loss of function. This deficiency would not have resulted
not found to result in a loss of function. This deficiency would not have resulted
in the RCIC system becoming inoperable due to a loss of air to the lube oil cooler
in the RCIC system becoming inoperable due to a loss of air to the lube oil cooler
pressure control valve.
pressure control valve.
A contributing cause of this finding is related to the cross cutting area of Problem
A contributing cause of this finding is related to the cross cutting area of Problem
Identification and Resolution. The licensee had previously reviewed the failure
Identification and Resolution. The licensee had previously reviewed the failure
positions of air-operated equipment and issued a report, Compressed Air
positions of air-operated equipment and issued a report, Compressed Air
Systems, dated July 16, 1989. During this review, the licensee did not identify
Systems, dated July 16, 1989. During this review, the licensee did not identify
that the pressure control valve was not independent of the instrument air system.
that the pressure control valve was not independent of the instrument air system.  
In addition, the licensee did not fully assess all aspects of the issue associated
In addition, the licensee did not fully assess all aspects of the issue associated
with the pressure control valve being supplied by instrument air rather than being
with the pressure control valve being supplied by instrument air rather than being
self contained in its initial operability determination associated with CR-VTY-
self contained in its initial operability determination associated with CR-VTY-
2004-2535. The licensee had to complete two additional supplemental
2004-2535. The licensee had to complete two additional supplemental
operability determinations to resolve the teams concerns.
operability determinations to resolve the teams concerns.
Enforcement. 10 CFR Part 50 Appendix B, Criterion III, Design Control,
Enforcement. 10 CFR Part 50 Appendix B, Criterion III, Design Control,
requires, in part, that design control measures be established and implemented
requires, in part, that design control measures be established and implemented
to assure that applicable regulatory requirements and the design basis for
to assure that applicable regulatory requirements and the design basis for
                                                                          Enclosure


                                      12
12
    structures, systems, and components are correctly translated into specifications,
Enclosure
    drawings, procedures, and instructions. Contrary to the above, the licensee did
structures, systems, and components are correctly translated into specifications,
    not implement measures to ensure that the design basis for the cooling water
drawings, procedures, and instructions. Contrary to the above, the licensee did
    supply to the lube oil cooler of RCIC was correctly translated into the
not implement measures to ensure that the design basis for the cooling water
    specifications, drawings, procedures, or instructions. Specifically, the installed
supply to the lube oil cooler of RCIC was correctly translated into the
    pressure control valve in the lube oil cooler water supply line was not
specifications, drawings, procedures, or instructions. Specifically, the installed
    independent of air systems, and the installed piping between the pressure
pressure control valve in the lube oil cooler water supply line was not
    control valve and lube oil cooler did not contain a restricting orifice. Because this
independent of air systems, and the installed piping between the pressure
    violation is of very low safety significance and has been entered into the
control valve and lube oil cooler did not contain a restricting orifice. Because this
    licensee's corrective action program (CR-VTY-2004-2535), this violation is being
violation is of very low safety significance and has been entered into the
    treated as a non-cited violation consistent with Section VI.A of the NRC
licensee's corrective action program (CR-VTY-2004-2535), this violation is being
    Enforcement Policy. (NCV 05000271/2004008-05 Cooling Water Supply
treated as a non-cited violation consistent with Section VI.A of the NRC
    Portion of RCIC Not Installed per Design Basis)
Enforcement Policy. (NCV 05000271/2004008-05 Cooling Water Supply
(2) Failure To Correct Non-Conforming RCIC Pressure Control Valve
Portion of RCIC Not Installed per Design Basis)
    Introduction. The team identified a Green non-cited violation of 10 CFR Part 50,
(2)
    Appendix B, Criterion XVI, Corrective Action, because the licensee failed to
Failure To Correct Non-Conforming RCIC Pressure Control Valve  
    correct a longstanding non-conformance associated with PCV-13-23, the control
Introduction. The team identified a Green non-cited violation of 10 CFR Part 50,
    valve that supplies cooling water to the RCIC lube oil cooler.
Appendix B, Criterion XVI, Corrective Action, because the licensee failed to
    Description. During review of Operating Procedure (OP) 2121, Reactor Core
correct a longstanding non-conformance associated with PCV-13-23, the control
    Isolation Cooling System, and OP 4121, Reactor Core Isolation Cooling
valve that supplies cooling water to the RCIC lube oil cooler.
    System Surveillance, the team identified that these procedures contained steps
Description. During review of Operating Procedure (OP) 2121, Reactor Core
    to manually operate PCV-13-23 during RCIC operation. The team questioned
Isolation Cooling System, and OP 4121, Reactor Core Isolation Cooling
    the reason for these steps, given that the RCIC system is designed to function
System Surveillance, the team identified that these procedures contained steps
    automatically as described in UFSAR Section 4.7.4.
to manually operate PCV-13-23 during RCIC operation. The team questioned
    The team determined that during initial start-up testing, problems were identified
the reason for these steps, given that the RCIC system is designed to function
    with the automatic operation of this valve. These problems affected its ability to
automatically as described in UFSAR Section 4.7.4.
    properly regulate the supply of cooling flow to the lube oil cooler. During the
The team determined that during initial start-up testing, problems were identified
    inspection, the licensee could not provide the team with an open condition report
with the automatic operation of this valve. These problems affected its ability to
    identifying this problem. Additionally, the licensee did not have an analysis to
properly regulate the supply of cooling flow to the lube oil cooler. During the
    show that setting PCV-13-23 as described in the procedure would ensure an
inspection, the licensee could not provide the team with an open condition report
    adequate flow of cooling water to the lube oil cooler. Rather, the licensee used
identifying this problem. Additionally, the licensee did not have an analysis to
    the fact that RCIC bearing temperatures have been acceptable during
show that setting PCV-13-23 as described in the procedure would ensure an
    surveillance testing to justify that lube oil cooling was sufficient. However, the
adequate flow of cooling water to the lube oil cooler. Rather, the licensee used
    team noted that the conditions that exist during surveillance testing may be
the fact that RCIC bearing temperatures have been acceptable during
    different from those existing under design conditions (for example, use of a
surveillance testing to justify that lube oil cooling was sufficient. However, the
    higher temperature suppression pool as a suction source and operation with
team noted that the conditions that exist during surveillance testing may be
    maximum expected RCIC room temperature). These conditions would result in
different from those existing under design conditions (for example, use of a
    higher bearing temperatures when RCIC is operating under design conditions.
higher temperature suppression pool as a suction source and operation with
    The team reviewed alarm response procedures for the RCIC bearing
maximum expected RCIC room temperature). These conditions would result in
    temperature alarms and determined that they were adequate to prevent damage
higher bearing temperatures when RCIC is operating under design conditions.
    to major RCIC components if the cooling flow was inadequate. However, the
The team reviewed alarm response procedures for the RCIC bearing
                                                                              Enclosure
temperature alarms and determined that they were adequate to prevent damage
to major RCIC components if the cooling flow was inadequate. However, the


                                      13
13
    manual operation of PCV-13-23 represents a longstanding operator work-around
Enclosure
    that creates an additional operator burden and could challenge equipment
manual operation of PCV-13-23 represents a longstanding operator work-around
    reliability if called upon to operate during an event.
that creates an additional operator burden and could challenge equipment
    Analysis. The team determined that the licensees failure to correct a
reliability if called upon to operate during an event.
    longstanding non-conformance with PCV-13-23 was a performance deficiency.
Analysis. The team determined that the licensees failure to correct a
    Specifically, operation of this valve in a mode other than automatic may have
longstanding non-conformance with PCV-13-23 was a performance deficiency.  
    challenged system operation if needed for an actual event. This issue was more
Specifically, operation of this valve in a mode other than automatic may have
    than minor because it was associated with the Mitigating Systems attribute of
challenged system operation if needed for an actual event. This issue was more
    Equipment Performance and affected the cornerstone objective of ensuring the
than minor because it was associated with the Mitigating Systems attribute of
    reliability of the RCIC system. The issue screened as very low safety
Equipment Performance and affected the cornerstone objective of ensuring the
    significance (Green) in Phase I of the SDP, because it was a design deficiency
reliability of the RCIC system. The issue screened as very low safety
    that was not found to result in a loss of function. While PCV-13-23 did not
significance (Green) in Phase I of the SDP, because it was a design deficiency
    function automatically as designed, the licensee had implemented manual
that was not found to result in a loss of function. While PCV-13-23 did not
    actions as a compensatory measure for the operation of this valve.
function automatically as designed, the licensee had implemented manual
    Enforcement. 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action,
actions as a compensatory measure for the operation of this valve.
    requires that measures be established to assure that conditions adverse to
Enforcement. 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action,
    quality, such as failures, malfunctions, deficiencies, deviations, defective material
requires that measures be established to assure that conditions adverse to
    and equipment, and non-conformances are promptly identified and corrected.
quality, such as failures, malfunctions, deficiencies, deviations, defective material
    Contrary to the above, the licensee failed to correct a longstanding non-
and equipment, and non-conformances are promptly identified and corrected.  
    conformance associated with PCV-13-23, the control valve that supplies cooling
Contrary to the above, the licensee failed to correct a longstanding non-
    water to the RCIC lube oil cooler. Because this issue is of very low safety
conformance associated with PCV-13-23, the control valve that supplies cooling
    significance and has been entered into the licensees corrective action program
water to the RCIC lube oil cooler. Because this issue is of very low safety
    (CR-VY-2004-2535), this issue is being treated as a non-cited violation,
significance and has been entered into the licensees corrective action program
    consistent with Section VI.A of the NRC Enforcement Policy.
(CR-VY-2004-2535), this issue is being treated as a non-cited violation,
    (NCV 05000271/2004008-06 Failure To Correct Non-Conforming RCIC
consistent with Section VI.A of the NRC Enforcement Policy.
    Pressure Control Valve)
(NCV 05000271/2004008-06 Failure To Correct Non-Conforming RCIC
(3) Potential Preconditioning of RCIC MOVs
Pressure Control Valve)  
    The team identified a minor finding related to Vermont Yankees method of
(3)
    testing RCIC system MOVs. The team determined that a procedural
Potential Preconditioning of RCIC MOVs
    requirement to conduct the quarterly RCIC system pump operability test prior to
The team identified a minor finding related to Vermont Yankees method of
    system MOV surveillance testing resulted in the operation of several RCIC
testing RCIC system MOVs. The team determined that a procedural
    system valves immediately before their required stroke-time testing. This
requirement to conduct the quarterly RCIC system pump operability test prior to
    practice could have affected the results of the stroke-time testing by
system MOV surveillance testing resulted in the operation of several RCIC
    preconditioning the valves and this potential impact was not evaluated by the
system valves immediately before their required stroke-time testing. This
    licensee. This issue was evaluated using Inspection Manual Chapter 0612 and
practice could have affected the results of the stroke-time testing by
    determined to be minor because it applied to a limited number of valves, most of
preconditioning the valves and this potential impact was not evaluated by the
    the valves would not have affected system operability, a review of these valves
licensee. This issue was evaluated using Inspection Manual Chapter 0612 and
    performance history indicated that there was significant margin to stroke-time
determined to be minor because it applied to a limited number of valves, most of
    limits, and no operability issues were noted during past testing.
the valves would not have affected system operability, a review of these valves
                                                                              Enclosure
performance history indicated that there was significant margin to stroke-time
limits, and no operability issues were noted during past testing.


                                        14
14
Enclosure
2.1.3 Residual Heat Removal System (RHR)
2.1.3 Residual Heat Removal System (RHR)
a.   Inspection Scope
  a.  
      During the inspection, the team reviewed selected components of the RHR
Inspection Scope
      system to ensure the system and components would be capable of performing
During the inspection, the team reviewed selected components of the RHR
      their required design functions, for both current conditions and those conditions
system to ensure the system and components would be capable of performing
      that would exist under the proposed EPU. In its power uprate submittal to the
their required design functions, for both current conditions and those conditions
      NRC, the licensee stated that it would need to take credit for the containment
that would exist under the proposed EPU. In its power uprate submittal to the
      overpressure that would exist under postulated accident conditions in order to
NRC, the licensee stated that it would need to take credit for the containment
      ensure adequate net positive suction head (NPSH) was available to the RHR
overpressure that would exist under postulated accident conditions in order to
      pumps. The team did not assess the appropriateness of allowing credit for
ensure adequate net positive suction head (NPSH) was available to the RHR
      containment overpressure. The team did, however, perform specific reviews of
pumps. The team did not assess the appropriateness of allowing credit for
      the licensees calculations to ensure that the RHR pumps would have adequate
containment overpressure. The team did, however, perform specific reviews of
      NPSH assuming such credit is given. The teams review included pressure
the licensees calculations to ensure that the RHR pumps would have adequate
      losses associated with the RHR suction strainers, potential bubble ingestion and
NPSH assuming such credit is given. The teams review included pressure
      the potential for torus vortexing.
losses associated with the RHR suction strainers, potential bubble ingestion and
b.   Findings
the potential for torus vortexing.  
      No findings of significance were identified.
  b.  
2.1.4 Safety Relief Valves and Code Safety Valves
Findings
a.   Inspection Scope
No findings of significance were identified.
      Due to the increased steam flow that would result from the licensees proposed
2.1.4
      EPU, the team conducted a detailed review of General Electric (GE) Topical
Safety Relief Valves and Code Safety Valves
      Report T0900, which evaluated the adequacy of the safety relief valves (SRVs)
  a.  
      for EPU conditions. The team reviewed the GE analysis and licensee
Inspection Scope
      modification package associated with the installation of a third American Society
Due to the increased steam flow that would result from the licensees proposed
      of Mechanical Engineers (ASME) Code safety valve with increased relief
EPU, the team conducted a detailed review of General Electric (GE) Topical
      capacity for EPU conditions. The team also reviewed the out-of-service and
Report T0900, which evaluated the adequacy of the safety relief valves (SRVs)
      calibration history for the existing SRVs. Lastly, the team reviewed the back-up
for EPU conditions. The team reviewed the GE analysis and licensee
      nitrogen bottle system, which was added to ensure an adequate supply of
modification package associated with the installation of a third American Society
      nitrogen to the SRVs.
of Mechanical Engineers (ASME) Code safety valve with increased relief
b.   Findings
capacity for EPU conditions. The team also reviewed the out-of-service and
      No findings of significance were identified.
calibration history for the existing SRVs. Lastly, the team reviewed the back-up
2.1.5 Reactor Feedwater and Condensate Components
nitrogen bottle system, which was added to ensure an adequate supply of
a.   Inspection Scope
nitrogen to the SRVs.
      Due to the increased feedwater flow that would be required under the licensees
  b.  
      proposed EPU, the team assessed the adequacy of modifications to the reactor
Findings
                                                                              Enclosure
No findings of significance were identified.
2.1.5
Reactor Feedwater and Condensate Components  
  a.  
Inspection Scope
Due to the increased feedwater flow that would be required under the licensees
proposed EPU, the team assessed the adequacy of modifications to the reactor


                                        15
15
      feedwater system. Because of the increased feedwater flow requirements, the
Enclosure
      licensee would need to run all three reactor feedwater pumps under EPU
feedwater system. Because of the increased feedwater flow requirements, the
      conditions, reducing the capability to mitigate feedwater transients. Included
licensee would need to run all three reactor feedwater pumps under EPU
      within the teams review was a recent seal replacement on a feedwater pump
conditions, reducing the capability to mitigate feedwater transients. Included
      and modifications to the reactor feedwater pump low-suction pressure trip and
within the teams review was a recent seal replacement on a feedwater pump
      reactor recirculation system runback. The team also reviewed flow control valve
and modifications to the reactor feedwater pump low-suction pressure trip and
      FCV-102-4 and its associated controls, since failure of this valve to open could
reactor recirculation system runback. The team also reviewed flow control valve
      disable low flow capability for the condensate pumps, resulting in a loss of
FCV-102-4 and its associated controls, since failure of this valve to open could
      feedwater flow during low-flow demands.
disable low flow capability for the condensate pumps, resulting in a loss of
      The team reviewed aspects of the licensees Flow Assisted Corrosion (FAC)
feedwater flow during low-flow demands.  
      Program and reviewed the adequacy of the thermal sleeves located at
The team reviewed aspects of the licensees Flow Assisted Corrosion (FAC)
      connections between the RCIC and feedwater systems and the reactor vessel.
Program and reviewed the adequacy of the thermal sleeves located at
      The team conducted a walkdown of the main feedwater and condensate pumps
connections between the RCIC and feedwater systems and the reactor vessel.  
      and adjacent piping with Vermont Yankee engineering personnel. Lastly, the
The team conducted a walkdown of the main feedwater and condensate pumps
      team inspected the feed and condensate panels in the main control room. The
and adjacent piping with Vermont Yankee engineering personnel. Lastly, the
      reviews were conducted to identify any alignment discrepancies or visible signs
team inspected the feed and condensate panels in the main control room. The
      of deficient material conditions.
reviews were conducted to identify any alignment discrepancies or visible signs
b.   Findings
of deficient material conditions.
      No findings of significance were identified.
  b.  
2.1.6 Reactor Building-to-Torus Vacuum Breaker System
Findings
a.   Inspection Scope
No findings of significance were identified.
      The team reviewed the components associated with the reactor building-to-torus
2.1.6
      vacuum breaker system. This system includes two redundant air-operated
Reactor Building-to-Torus Vacuum Breaker System
      vacuum breaker valves, each in series with a check valve. This system functions
  a.  
      to relieve pressure from the reactor building to the torus to protect the structural
Inspection Scope
      integrity of the torus. Additionally, the system must remain leak-tight from the
The team reviewed the components associated with the reactor building-to-torus
      torus to the reactor building to maintain primary containment isolation. In
vacuum breaker system. This system includes two redundant air-operated
      reviewing these components, the team assessed condition reports, operating
vacuum breaker valves, each in series with a check valve. This system functions
      procedures, test results, maintenance and modification history, drawings and
to relieve pressure from the reactor building to the torus to protect the structural
      applicable sections of the UFSAR and TS. The teams review included
integrity of the torus. Additionally, the system must remain leak-tight from the
      verification that these components would be capable of performing their required
torus to the reactor building to maintain primary containment isolation. In
      design functions for both current licensing basis conditions and the proposed
reviewing these components, the team assessed condition reports, operating
      EPU conditions.
procedures, test results, maintenance and modification history, drawings and
      The team also completed a walkdown of the reactor building-to-torus vacuum
applicable sections of the UFSAR and TS. The teams review included
      breakers and their air-operators, check valves and associated piping.
verification that these components would be capable of performing their required
      Additionally, the team reviewed operator burden and work-around lists to identify
design functions for both current licensing basis conditions and the proposed
      any deficiencies that could affect operation of these components.
EPU conditions.
                                                                                Enclosure
The team also completed a walkdown of the reactor building-to-torus vacuum
breakers and their air-operators, check valves and associated piping.  
Additionally, the team reviewed operator burden and work-around lists to identify
any deficiencies that could affect operation of these components.  


                                        16
16
b.   Findings
Enclosure
      No findings of significance were identified.
  b.  
2.1.7 Review of Transient Analysis Inputs
Findings
a.   Inspection Scope
No findings of significance were identified.
      During the inspection, the team reviewed selected plant parameters used by the
      licensee as inputs into its transient analyses. Included in this review were
2.1.7
      analyses performed solely to support the proposed EPU. In conjunction with this
Review of Transient Analysis Inputs
      review, the team conducted plant equipment walkdowns, reviewed plant
  a.  
      procedures and calculations, and discussed calculations and parameters with
Inspection Scope
      plant design engineers.
During the inspection, the team reviewed selected plant parameters used by the
b.   Findings
licensee as inputs into its transient analyses. Included in this review were
      Introduction. The team identified a finding of very low safety significance
analyses performed solely to support the proposed EPU. In conjunction with this
      involving a non-cited violation of 10 CFR Part 50, Appendix B, Criterion III,
review, the team conducted plant equipment walkdowns, reviewed plant
      Design Control, because the licensee had neither established the correct
procedures and calculations, and discussed calculations and parameters with
      condensate storage tank (CST) temperature limit for use in the plant transient
plant design engineers.  
      analyses nor translated this CST temperature into plant procedures.
  b.  
      Description. During the inspection, the team noted that although the CST
Findings
      temperature was monitored on operator logs, the licensee had not established a
Introduction. The team identified a finding of very low safety significance
      maximum temperature limit for the CST. A CST temperature limit of 90 degrees
involving a non-cited violation of 10 CFR Part 50, Appendix B, Criterion III,
      Fahrenheit (EF) was used as an input to several plant transient analyses,
Design Control, because the licensee had neither established the correct
      including Transient Analysis VYC-1825, Analysis of Suppression Pool
condensate storage tank (CST) temperature limit for use in the plant transient
      Temperature for Relief Valve Discharge Transients, Revision 0. The CST
analyses nor translated this CST temperature into plant procedures.  
      temperature used for this analysis was based on the maximum ambient summer
Description. During the inspection, the team noted that although the CST
      temperature of approximately 90EF and did not take into account the recirculated
temperature was monitored on operator logs, the licensee had not established a
      hotwell water that has on occasion raised the CST temperature to approximately
maximum temperature limit for the CST. A CST temperature limit of 90 degrees
      120EF.
Fahrenheit (EF) was used as an input to several plant transient analyses,
      In addition, the team noted that in December 2002, the licensee had also
including Transient Analysis VYC-1825, Analysis of Suppression Pool
      identified that there was no maximum CST temperature limit and that CST
Temperature for Relief Valve Discharge Transients, Revision 0. The CST
      temperature had previously exceeded the temperature assumed in the high
temperature used for this analysis was based on the maximum ambient summer
      pressure coolant injection (HPCI) and RCIC design basis documents for
temperature of approximately 90EF and did not take into account the recirculated
      calculating pump NPSH. The licensee documented this condition in CR-VTY-
hotwell water that has on occasion raised the CST temperature to approximately
      2002-2942. At that time, the licensee performed a limited evaluation and
120EF.
      determined that the non-conservative CST temperature had little to no effect on
In addition, the team noted that in December 2002, the licensee had also
      the transient analyses. The team reviewed this evaluation and determined that
identified that there was no maximum CST temperature limit and that CST
      transient analysis VYC-1825, which assessed the adequacy of the NPSH of the
temperature had previously exceeded the temperature assumed in the high
      pumps supplied from the CST or the suppression pool, would be affected by the
pressure coolant injection (HPCI) and RCIC design basis documents for
      increased CST temperature.
calculating pump NPSH. The licensee documented this condition in CR-VTY-
                                                                              Enclosure
2002-2942. At that time, the licensee performed a limited evaluation and
determined that the non-conservative CST temperature had little to no effect on
the transient analyses. The team reviewed this evaluation and determined that
transient analysis VYC-1825, which assessed the adequacy of the NPSH of the
pumps supplied from the CST or the suppression pool, would be affected by the
increased CST temperature.


                                  17
17
Enclosure
In response to the teams concerns, the licensee reviewed the transient analyses
In response to the teams concerns, the licensee reviewed the transient analyses
and identified that the relief valve discharge transient was the most limiting. The
and identified that the relief valve discharge transient was the most limiting. The
Line 1,051: Line 1,162:
increase in suppression pool temperature, which reduced the net positive suction
increase in suppression pool temperature, which reduced the net positive suction
head margin for the most limiting component, the core spray pumps, from 0.5
head margin for the most limiting component, the core spray pumps, from 0.5
feet to 0.0 feet. The team reviewed the input parameters to the NPSH
feet to 0.0 feet. The team reviewed the input parameters to the NPSH
calculation for the core spray pumps and determined that because of
calculation for the core spray pumps and determined that because of
conservatism in other aspects of the calculation, the core spray pumps would still
conservatism in other aspects of the calculation, the core spray pumps would still
Line 1,057: Line 1,168:
The team determined that in the licensees EPU submittal to the NRC, the
The team determined that in the licensees EPU submittal to the NRC, the
licensee had not taken into account the higher CST temperature for all transient
licensee had not taken into account the higher CST temperature for all transient
scenarios. As a result of this issue, the licensee began an extent-of-condition
scenarios. As a result of this issue, the licensee began an extent-of-condition
review of all calculations, drawings, and inputs to transient analyses where a
review of all calculations, drawings, and inputs to transient analyses where a
non-conservative maximum CST temperature was used, both for current plant
non-conservative maximum CST temperature was used, both for current plant
conditions (CR-VTY-2004-2600) and for analyses associated with the planned
conditions (CR-VTY-2004-2600) and for analyses associated with the planned
EPU (CR-VTY-2004-2799). The licensee also instituted a tentative maximum
EPU (CR-VTY-2004-2799). The licensee also instituted a tentative maximum
temperature limit of 120EF for the CST.
temperature limit of 120EF for the CST.
Analysis. The team determined this issue was a performance deficiency since
Analysis. The team determined this issue was a performance deficiency since
the licensee had not used the correct CST temperature in the plant transient
the licensee had not used the correct CST temperature in the plant transient
analysis and had not translated the CST temperature limit into the station
analysis and had not translated the CST temperature limit into the station
procedures. Specifically, using the correct CST temperature in the relief valve
procedures. Specifically, using the correct CST temperature in the relief valve
discharge transient analysis resulted in a higher suppression pool temperature
discharge transient analysis resulted in a higher suppression pool temperature
and lowered the available net positive suction head to the core spray pumps.
and lowered the available net positive suction head to the core spray pumps.  
This issue was more than minor because it was associated with the Mitigating
This issue was more than minor because it was associated with the Mitigating
Systems Cornerstone attribute of Equipment Performance and affected the
Systems Cornerstone attribute of Equipment Performance and affected the
cornerstone objective of ensuring the reliability of the core spray system. The
cornerstone objective of ensuring the reliability of the core spray system. The
issue screened as very low safety significance (Green) in Phase I of the SDP,
issue screened as very low safety significance (Green) in Phase I of the SDP,
because it was a design deficiency that was not found to result in a loss of
because it was a design deficiency that was not found to result in a loss of
function. Although available NPSH margin was lowered, adequate NPSH for the
function. Although available NPSH margin was lowered, adequate NPSH for the
core spray pumps remained due to the conservatism that existed in other
core spray pumps remained due to the conservatism that existed in other
aspects of the licensees NPSH analysis.
aspects of the licensees NPSH analysis.
A contributing cause of this finding is also related to the cross-cutting area of
A contributing cause of this finding is also related to the cross-cutting area of
Problem Identification and Resolution. The licensee identified this issue in
Problem Identification and Resolution. The licensee identified this issue in
December 2002, but concluded that the non-conservative CST temperature had
December 2002, but concluded that the non-conservative CST temperature had
little to no effect on the transient analyses.
little to no effect on the transient analyses.
Enforcement. 10 CFR Part 50 Appendix B, Criterion III, Design Control,
Enforcement. 10 CFR Part 50 Appendix B, Criterion III, Design Control,
requires, in part, that design control measures be established and implemented
requires, in part, that design control measures be established and implemented
to assure that applicable regulatory requirements and the design basis for
to assure that applicable regulatory requirements and the design basis for
structures, systems, and components are correctly translated into specifications,
structures, systems, and components are correctly translated into specifications,
drawings, procedures, and instructions. Contrary to the above, the licensee had
drawings, procedures, and instructions. Contrary to the above, the licensee had
neither established the correct condensate storage tank (CST) temperature limit
neither established the correct condensate storage tank (CST) temperature limit
for use in the plant transient analyses nor translated the CST temperature limit
for use in the plant transient analyses nor translated the CST temperature limit
into plant procedures. Because this finding is of very low safety significance and
into plant procedures. Because this finding is of very low safety significance and
                                                                          Enclosure


                                              18
18
          has been entered into the licensee's corrective action program (CR-VTY-2004-
Enclosure
          2600, CR-VTY-2004-2793, and CR-VTY-2004-2799), this finding is being treated
has been entered into the licensee's corrective action program (CR-VTY-2004-
          as a non-cited violation consistent with Section VI.A of the NRC Enforcement
2600, CR-VTY-2004-2793, and CR-VTY-2004-2799), this finding is being treated
          Policy. (NCV 05000271/2004008-07 Failure to Implement Adequate Design
as a non-cited violation consistent with Section VI.A of the NRC Enforcement
          Control for Condensate Storage Tank Temperature)
Policy. (NCV 05000271/2004008-07 Failure to Implement Adequate Design
2.2 Review of Operator Actions
Control for Condensate Storage Tank Temperature)
    a.   Inspection Scope
  2.2
          During the inspection, the team reviewed risk-significant, time-critical operator
Review of Operator Actions  
          actions that had little margin between the time required and time available to
  a.
          complete the action. The team determined the review scope and performed the
Inspection Scope
          detailed review of critical operator actions using risk information contained in the
During the inspection, the team reviewed risk-significant, time-critical operator
          licensees PRA, Operator Task Validation Studies, Emergency Operating
actions that had little margin between the time required and time available to
          Procedures (EOPs), Power Uprate Safety Analysis Report (PUSAR), Appendix R
complete the action. The team determined the review scope and performed the
          Analyses, Off-Normal and Operating Procedures, and the licensees CR
detailed review of critical operator actions using risk information contained in the
          database. The team performed a detailed review of the following time-critical
licensees PRA, Operator Task Validation Studies, Emergency Operating
          and low-margin operator actions:
Procedures (EOPs), Power Uprate Safety Analysis Report (PUSAR), Appendix R
          *       Monitoring of the Vernon tie line to ensure availability as a station
Analyses, Off-Normal and Operating Procedures, and the licensees CR
                  blackout source.
database. The team performed a detailed review of the following time-critical
          *       Manual initiation of the RCIC system using alternate shutdown panels.
and low-margin operator actions:
          *       Initiation of the standby liquid control (SLC) system with the main
*
                  condenser failed.
Monitoring of the Vernon tie line to ensure availability as a station
          *       Manual initiation or control of feedwater and condensate flow under
blackout source.
                  normal and transient conditions, in single element or three element
*
                  control.
Manual initiation of the RCIC system using alternate shutdown panels.
          *       Manual initiation of RCIC system from the control room.
*
          For all the above operator action scenarios, the team verified that operating
Initiation of the standby liquid control (SLC) system with the main
          procedures were consistent with operator actions for a given event or accident
condenser failed.  
          condition and that the operators had been adequately trained and evaluated for
*
          each action. The team also reviewed the fidelity between EOPs, pump NPSH
Manual initiation or control of feedwater and condensate flow under
          calculations and containment spray operation to ensure proper EOP
normal and transient conditions, in single element or three element
          implementation. Control room instrumentation and alarms were also reviewed by
control.
          the team to verify their functionality and to verify alarm response procedures
*
          were accurate to reflect the current plant configuration. Additionally, the team
Manual initiation of RCIC system from the control room.
          performed a walkdown of accessible field portions of the reviewed systems to
For all the above operator action scenarios, the team verified that operating
          assess material condition and to verify that field actions could be performed by
procedures were consistent with operator actions for a given event or accident
          the operators as described in plant procedures.
condition and that the operators had been adequately trained and evaluated for
                                                                                      Enclosure
each action. The team also reviewed the fidelity between EOPs, pump NPSH
calculations and containment spray operation to ensure proper EOP
implementation. Control room instrumentation and alarms were also reviewed by
the team to verify their functionality and to verify alarm response procedures
were accurate to reflect the current plant configuration. Additionally, the team
performed a walkdown of accessible field portions of the reviewed systems to
assess material condition and to verify that field actions could be performed by
the operators as described in plant procedures.


                                    19
19
  The team also reviewed each operator action to assess the impact the proposed
Enclosure
  EPU could have on further reducing the margin available for task completion and
The team also reviewed each operator action to assess the impact the proposed
  to verify that the associated EPU plant modifications would be reviewed by the
EPU could have on further reducing the margin available for task completion and
  licensee for their effect on the operators ability to complete the critical actions
to verify that the associated EPU plant modifications would be reviewed by the
  within the required time parameters.
licensee for their effect on the operators ability to complete the critical actions
b. Findings
within the required time parameters.  
  Introduction. The team identified a Green non-cited violation of 10 CFR Part 50,
  b.  
  Appendix B, Criterion III, Design Control, because the licensee did not
Findings
  adequately coordinate between the operations department and the engineering
Introduction. The team identified a Green non-cited violation of 10 CFR Part 50,
  organization procedure revisions that increased the length of time required to
Appendix B, Criterion III, Design Control, because the licensee did not
  place the reactor core isolation cooling system in service from the alternate
adequately coordinate between the operations department and the engineering
  shutdown panels. As a consequence, the licensee did not revise its Vermont
organization procedure revisions that increased the length of time required to
  Yankee Safe Shutdown Capability Analysis (SSCA).
place the reactor core isolation cooling system in service from the alternate
  Description. The Vermont Yankee SSCA relies on the reactor core isolation
shutdown panels. As a consequence, the licensee did not revise its Vermont
  cooling (RCIC) system to be placed in service from the alternate shutdown
Yankee Safe Shutdown Capability Analysis (SSCA).
  panels prior to reactor water level reaching the top of active fuel following a loss
Description. The Vermont Yankee SSCA relies on the reactor core isolation
  of feedwater flow. In December 1999, the Vermont Yankee SSCA documented
cooling (RCIC) system to be placed in service from the alternate shutdown
  that, for the present day 100 percent power level, it would take 25.3 minutes for
panels prior to reactor water level reaching the top of active fuel following a loss
  reactor water level to reach the top of active fuel following a loss of feedwater
of feedwater flow. In December 1999, the Vermont Yankee SSCA documented
  and that it would take approximately 15 minutes to place the RCIC system in
that, for the present day 100 percent power level, it would take 25.3 minutes for
  service from the alternate shutdown panels. The Vermont Yankee SSCA
reactor water level to reach the top of active fuel following a loss of feedwater
  concluded adequate margin (approximately 10 minutes) existed to ensure that
and that it would take approximately 15 minutes to place the RCIC system in
  the RCIC is placed in service prior to reactor water level reaching the top of
service from the alternate shutdown panels. The Vermont Yankee SSCA
  active fuel.
concluded adequate margin (approximately 10 minutes) existed to ensure that
  In June 2001 the Operations Department conducted an additional review of the
the RCIC is placed in service prior to reactor water level reaching the top of
  time it would take to place RCIC in service from the alternate shutdown panels.
active fuel.
  The Operations Department determined that, using the version of the procedure
In June 2001 the Operations Department conducted an additional review of the
  in effect in June 2001, it would take 19.3 minutes to place RCIC in service from
time it would take to place RCIC in service from the alternate shutdown panels.  
  the alternate shutdown panels .
The Operations Department determined that, using the version of the procedure
  During the inspection, using the version of the procedure in effect during the
in effect in June 2001, it would take 19.3 minutes to place RCIC in service from
  inspection period, the team performed a field walkdown with licensed operators
the alternate shutdown panels .
  to validate that RCIC could be placed into service from the alternate shutdown
During the inspection, using the version of the procedure in effect during the
  panels within 19.3 minutes. The team noted that since June 2001, the licensee
inspection period, the team performed a field walkdown with licensed operators
  had added steps in the procedure to comply with Electrical Safety Standards.
to validate that RCIC could be placed into service from the alternate shutdown
  Based on the teams validation, the total time to place RCIC in service from the
panels within 19.3 minutes. The team noted that since June 2001, the licensee
  alternate shutdown panels was determined to be approximately 21 minutes. The
had added steps in the procedure to comply with Electrical Safety Standards.  
  team concluded that this time was still within the 25.3 minute limit stated in the
Based on the teams validation, the total time to place RCIC in service from the
  Vermont Yankee SSCA.
alternate shutdown panels was determined to be approximately 21 minutes. The
  Additionally, the team found that the licensee had not revised the December
team concluded that this time was still within the 25.3 minute limit stated in the
  1999 Vermont Yankee SSCA to reflect the June 2001 time estimate or present
Vermont Yankee SSCA.
  day version of the procedure to place RCIC in service from the alternate
Additionally, the team found that the licensee had not revised the December
                                                                                Enclosure
1999 Vermont Yankee SSCA to reflect the June 2001 time estimate or present
day version of the procedure to place RCIC in service from the alternate


                                  20
20
shutdown panels. The team also determined that the licensees engineering
Enclosure
shutdown panels. The team also determined that the licensees engineering
organization was unaware that the time to complete the task had increased from
organization was unaware that the time to complete the task had increased from
approximately 15 to 21 minutes and had effectively reduced the time margin
approximately 15 to 21 minutes and had effectively reduced the time margin
available for event mitigation from about 10 minutes to 4 minutes at the current
available for event mitigation from about 10 minutes to 4 minutes at the current
full power level. As a consequence, the engineering organization had not
full power level. As a consequence, the engineering organization had not
revised the Vermont Yankee SSCA.
revised the Vermont Yankee SSCA.
The team reviewed the impact the licensees proposed EPU would have on this
The team reviewed the impact the licensees proposed EPU would have on this
issue. Based on an EPU power level, the licensee calculated it would take 21.3
issue. Based on an EPU power level, the licensee calculated it would take 21.3
minutes for reactor water level to reach the top of active fuel following a loss of
minutes for reactor water level to reach the top of active fuel following a loss of
feedwater. Therefore, the team concluded that for the proposed EPU, the ability
feedwater. Therefore, the team concluded that for the proposed EPU, the ability
to place the RCIC in service from the alternate shutdown panels (21 minutes)
to place the RCIC in service from the alternate shutdown panels (21 minutes)
prior to reactor water level reaching the top of active fuel (21.3 minutes) is
prior to reactor water level reaching the top of active fuel (21.3 minutes) is
questionable. Additionally, the team found that the December 1999 value of the
questionable. Additionally, the team found that the December 1999 value of the
time to place RCIC in service from the alternate shutdown panel was used in
time to place RCIC in service from the alternate shutdown panel was used in
licensee Technical Evaluation (TE) 2003-065, Appendix R PUSAR Input. The
licensee Technical Evaluation (TE) 2003-065, Appendix R PUSAR Input. The
TE was then used as an input to the Vermont Yankee Power Uprate Safety
TE was then used as an input to the Vermont Yankee Power Uprate Safety
Analysis Report (PUSAR) and submitted to the NRC as part of the power uprate
Analysis Report (PUSAR) and submitted to the NRC as part of the power uprate
application. The licensee initiated CR-VTY-2004-2552 and 2004-2614 in
application. The licensee initiated CR-VTY-2004-2552 and 2004-2614 in
response to these issues.
response to these issues.
Analysis. The team considered this finding to be a performance deficiency since
Analysis. The team considered this finding to be a performance deficiency since
the licensee did not coordinate between the operations department and
the licensee did not coordinate between the operations department and
engineering department regarding procedure revisions which increased the time
engineering department regarding procedure revisions which increased the time
required to place the RCIC in service from the alternate shutdown panels. This
required to place the RCIC in service from the alternate shutdown panels. This
issue was more than minor because it was associated with the Mitigating
issue was more than minor because it was associated with the Mitigating
Systems Cornerstone attribute of Human Performance and affected the
Systems Cornerstone attribute of Human Performance and affected the
cornerstone objective of ensuring the availability of the RCIC system.
cornerstone objective of ensuring the availability of the RCIC system.  
Furthermore, this finding resulted in the use of the December 1999 value of time
Furthermore, this finding resulted in the use of the December 1999 value of time
to place RCIC in service from the alternate shutdown panel in documents
to place RCIC in service from the alternate shutdown panel in documents
submitted to the NRC as part of the Vermont Yankee PUSAR. The issue
submitted to the NRC as part of the Vermont Yankee PUSAR. The issue
screened as very low safety significance (Green) in Phase I of the SDP because
screened as very low safety significance (Green) in Phase I of the SDP because
it was a design deficiency that was not found to result in a loss of function. At
it was a design deficiency that was not found to result in a loss of function. At
the present 100 percent power level, RCIC could be placed in service from the
the present 100 percent power level, RCIC could be placed in service from the
alternate shutdown panels prior to reactor level reaching the top of active fuel.
alternate shutdown panels prior to reactor level reaching the top of active fuel.
Enforcement. 10 Part CFR 50, Appendix B, Criterion III, Design Control,
Enforcement. 10 Part CFR 50, Appendix B, Criterion III, Design Control,
requires, in part, that revision of documents shall be coordinated among
requires, in part, that revision of documents shall be coordinated among
participating organizations. Contrary to above, between June 2001 to
participating organizations. Contrary to above, between June 2001 to
September 2004, the licensee did not adequately coordinate between the
September 2004, the licensee did not adequately coordinate between the
operations department and the engineering organization regarding procedure
operations department and the engineering organization regarding procedure
revisions that increased the length of time required to place the reactor core
revisions that increased the length of time required to place the reactor core
isolation cooling system in service from the alternate shutdown panels. Because
isolation cooling system in service from the alternate shutdown panels. Because
this finding is of very low safety significance and has been entered into the
this finding is of very low safety significance and has been entered into the
licensees corrective action program, it is being treated as a non-cited violation,
licensees corrective action program, it is being treated as a non-cited violation,
consistent with Section VI.A of the NRC Enforcement Policy. (NCV
consistent with Section VI.A of the NRC Enforcement Policy. (NCV
                                                                          Enclosure


                                            21
21
          05000271/2004008-08 Failure to Coordinate Information Related to Safe
Enclosure
          Shutdown Capability Analysis Report)
05000271/2004008-08 Failure to Coordinate Information Related to Safe
2.3 Review of Operating Experience and Generic Issues
Shutdown Capability Analysis Report)
    a.   Inspection Scope
  2.3
          During the inspection, the team reviewed selected operating experience issues
Review of Operating Experience and Generic Issues
          that had been identified at other facilities for their possible applicability to
  a.
          Vermont Yankee. Several issues that appeared to be applicable to Vermont
Inspection Scope
          Yankee were selected for a more in-depth review. Additional consideration was
During the inspection, the team reviewed selected operating experience issues
          given to those issues that might be impacted by the licensees planned EPU.
that had been identified at other facilities for their possible applicability to
          The issues that received a detailed review by the team included:
Vermont Yankee. Several issues that appeared to be applicable to Vermont
          *       An NRC inspection finding at the Point Beach Nuclear Power Station,
Yankee were selected for a more in-depth review. Additional consideration was
                  documented in IR 50-266/2004-004, concerning the use of a non-
given to those issues that might be impacted by the licensees planned EPU.  
                  conservative CST temperature in accident and transient analyses.
The issues that received a detailed review by the team included:
          *       Licensee Event Report (LER) 2003-003-00, issued on September 29,
*
                  2003, from the Byron Station where the licensee had exceeded its
An NRC inspection finding at the Point Beach Nuclear Power Station,
                  licensed maximum power level due to inaccuracies in feedwater
documented in IR 50-266/2004-004, concerning the use of a non-
                  ultrasonic flow measurements caused by signal noise contamination.
conservative CST temperature in accident and transient analyses.
          *       An NRC inspection finding from the Peach Bottom Station, documented
*
                  in IR 50-277/2002-011, concerning inadequate Emergency Operating
Licensee Event Report (LER) 2003-003-00, issued on September 29,
                  Procedures to return the suction of the High Pressure Coolant Injection
2003, from the Byron Station where the licensee had exceeded its
                  (HPCI) system from the suppression pool to the CST in order to ensure
licensed maximum power level due to inaccuracies in feedwater
                  self-cooled HPCI lube oil temperatures remained within analyzed limits.
ultrasonic flow measurements caused by signal noise contamination.
          *       Information Notice 2001-13, Inadequate Standby Liquid Control Relief
*
                  Valve Margin, issued on August 10, 2001, concerning a problem
An NRC inspection finding from the Peach Bottom Station, documented
                  identified at the Susquehanna Station involving inadequate SLC system
in IR 50-277/2002-011, concerning inadequate Emergency Operating
                  relief valve margin after a power uprate increased the relief valve setpoint
Procedures to return the suction of the High Pressure Coolant Injection
                  pressure, thereby increasing SLC discharge pressure. This was
(HPCI) system from the suppression pool to the CST in order to ensure
                  complicated by using a non-conservative maximum reactor vessel
self-cooled HPCI lube oil temperatures remained within analyzed limits.
                  pressure in accident analysis.
*
          *       NRC Generic Letter (GL) 96-05, Periodic Verification of Design-Basis
Information Notice 2001-13, Inadequate Standby Liquid Control Relief
                  Capability of Safety-Related Power-Operated Valves, pertaining to the
Valve Margin, issued on August 10, 2001, concerning a problem
                  periodic testing of motor-operated valves. With regard to this GL, the
identified at the Susquehanna Station involving inadequate SLC system
                  team reviewed the NRC safety evaluation report that documented the
relief valve margin after a power uprate increased the relief valve setpoint
                  NRC staffs understanding of the licensees commitments and plans for
pressure, thereby increasing SLC discharge pressure. This was
                  establishing a periodic verification program. The team also reviewed
complicated by using a non-conservative maximum reactor vessel
                  procedures, test and maintenance records, corrective action documents,
pressure in accident analysis.
                  and correspondence relative to four RCIC system MOVs.
*
                                                                                      Enclosure
NRC Generic Letter (GL) 96-05, Periodic Verification of Design-Basis
Capability of Safety-Related Power-Operated Valves, pertaining to the
periodic testing of motor-operated valves. With regard to this GL, the
team reviewed the NRC safety evaluation report that documented the
NRC staffs understanding of the licensees commitments and plans for
establishing a periodic verification program. The team also reviewed
procedures, test and maintenance records, corrective action documents,
and correspondence relative to four RCIC system MOVs.  


22
22
  Enclosure
Enclosure


                                      23
23
b.1 Findings
Enclosure
    Introduction. The team identified a Green non-cited violation of 10 CFR Part 50,
  b.1  
    Appendix B, Criterion XI, Test Control, because the licensee conducted
Findings
    periodic testing of MOVs using test instrumentation that had not been validated
Introduction. The team identified a Green non-cited violation of 10 CFR Part 50,
    to be adequate for its intended function. Additionally, the test procedures did not
Appendix B, Criterion XI, Test Control, because the licensee conducted
    incorporate requirements and acceptance limits contained in applicable design
periodic testing of MOVs using test instrumentation that had not been validated
    documents.
to be adequate for its intended function. Additionally, the test procedures did not
    Description. In its SER dated December 14, 2000, the NRC provided its basis
incorporate requirements and acceptance limits contained in applicable design
    for accepting Vermont Yankees response to NRC GL 96-05, Periodic
documents.
    Verification of Design-Basis Capability of Safety-Related Power-Operated
Description. In its SER dated December 14, 2000, the NRC provided its basis
    Valves. The SER documented the licensees intentions to use motor current
for accepting Vermont Yankees response to NRC GL 96-05, Periodic
    data acquired from the MCCs as a way of detecting actuator and valve
Verification of Design-Basis Capability of Safety-Related Power-Operated
    degradation. The SER also documented Vermont Yankees intention to verify
Valves. The SER documented the licensees intentions to use motor current
    this testing methodology by comparing the data with direct torque and thrust
data acquired from the MCCs as a way of detecting actuator and valve
    measurements at the valve over extended intervals. In addition, the SER stated
degradation. The SER also documented Vermont Yankees intention to verify
    the licensee would have to determine MCC test instrumentation accuracies and
this testing methodology by comparing the data with direct torque and thrust
    sensitivities to MOV degradation, as well as evaluate changes in MCC data and
measurements at the valve over extended intervals. In addition, the SER stated
    MOV thrust and torque performance.
the licensee would have to determine MCC test instrumentation accuracies and
    During the inspection, the team concluded that Vermont Yankee had not
sensitivities to MOV degradation, as well as evaluate changes in MCC data and
    validated the adequacy of the MCC diagnostic test instrumentation with respect
MOV thrust and torque performance.
    to its ability to provide detect actuator torque and stem thrust degradation that
During the inspection, the team concluded that Vermont Yankee had not
    would indicate actuator or valve degradation. A cooperative effort with
validated the adequacy of the MCC diagnostic test instrumentation with respect
    Crane-MOVATS to perform the required validation was terminated in March
to its ability to provide detect actuator torque and stem thrust degradation that
    2004, when the parties determined that a statistically meaningful and valid
would indicate actuator or valve degradation. A cooperative effort with
    correlation of MCC to direct diagnostic test data that would allow setting switches
Crane-MOVATS to perform the required validation was terminated in March
    could not be completed. As a result of the teams concerns, the licensee entered
2004, when the parties determined that a statistically meaningful and valid
    this issue into the corrective action program on CR-VTY-2004-2802.
correlation of MCC to direct diagnostic test data that would allow setting switches
    The team also identified that separate procedures (OP 5217 and OP 5287) had
could not be completed. As a result of the teams concerns, the licensee entered
    been established to obtain and evaluate MCC diagnostic test data; however,
this issue into the corrective action program on CR-VTY-2004-2802.  
    neither of these procedures included specific acceptance criteria tied to stem
The team also identified that separate procedures (OP 5217 and OP 5287) had
    thrust or available design margin. The SER stated that an acceptance
been established to obtain and evaluate MCC diagnostic test data; however,
    procedure for MCC testing was under development to specify parameters to be
neither of these procedures included specific acceptance criteria tied to stem
    monitored for trending, including specific acceptance criteria. The team
thrust or available design margin. The SER stated that an acceptance
    observed that the lack of acceptance criteria could lead to the inconsistent
procedure for MCC testing was under development to specify parameters to be
    evaluation of the data between different reviewers. Also, the documentation of
monitored for trending, including specific acceptance criteria. The team
    problem identification and resolution of issues identified through test data review
observed that the lack of acceptance criteria could lead to the inconsistent
    was missing or unclear. An inspector-identified example of entering improper
evaluation of the data between different reviewers. Also, the documentation of
    test data into the MOV test package was entered into the corrective action
problem identification and resolution of issues identified through test data review
    program on CR-VTY-2004-2623.
was missing or unclear. An inspector-identified example of entering improper
    The team also identified that no administrative or procedural prohibition had
test data into the MOV test package was entered into the corrective action
    been implemented against using MCC testing to set MOV switches, and that the
program on CR-VTY-2004-2623.
    procedures specifically allowed establishing a baseline with MCC testing
The team also identified that no administrative or procedural prohibition had
                                                                            Enclosure
been implemented against using MCC testing to set MOV switches, and that the
procedures specifically allowed establishing a baseline with MCC testing


                                  24
24
(OP 5287). The MOV program had been revised in 2002 to eliminate any
Enclosure
(OP 5287). The MOV program had been revised in 2002 to eliminate any
periodicity requirements for at-the-valve diagnostic testing that can measure
periodicity requirements for at-the-valve diagnostic testing that can measure
torque and thrust to known accuracies. The team identified and the licensee
torque and thrust to known accuracies. The team identified and the licensee
confirmed that the MCC test equipment had been used in at least one instance
confirmed that the MCC test equipment had been used in at least one instance
to set MOV switches on one of the four RCIC valves reviewed. Also, the team
to set MOV switches on one of the four RCIC valves reviewed. Also, the team
identified several cases where diagnostic testing following replacement of the
identified several cases where diagnostic testing following replacement of the
valve packing was limited to MCC testing. The team noted that packing
valve packing was limited to MCC testing. The team noted that packing
replacement affects stem friction and consequently changes in stem thrust.
replacement affects stem friction and consequently changes in stem thrust.  
Since the MCC testing instrumentation had not been validated, the team
Since the MCC testing instrumentation had not been validated, the team
concluded that the change in stem friction from initial set-up was indeterminate
concluded that the change in stem friction from initial set-up was indeterminate
for these valves.
for these valves.  
Analysis. The performance deficiency was the failure to validate motor-operated
Analysis. The performance deficiency was the failure to validate motor-operated
valve test instrumentation to ensure its adequacy and to establish test
valve test instrumentation to ensure its adequacy and to establish test
procedures with adequate acceptance criteria tied to stem thrust or available
procedures with adequate acceptance criteria tied to stem thrust or available
design margin. Specifically, there was no analysis demonstrating that testing
design margin. Specifically, there was no analysis demonstrating that testing
conducted at the MCC ensured the development of proper operating thrust at the
conducted at the MCC ensured the development of proper operating thrust at the
valve to ensure the MOV would perform satisfactorily under design basis
valve to ensure the MOV would perform satisfactorily under design basis
conditions. This issue was more than minor because it was associated with the
conditions. This issue was more than minor because it was associated with the
Mitigating Systems Cornerstone attribute of Equipment Performance and
Mitigating Systems Cornerstone attribute of Equipment Performance and
affected the cornerstone objective of ensuring the availability, reliability, and
affected the cornerstone objective of ensuring the availability, reliability, and
capability of systems and components that respond to initiating events.
capability of systems and components that respond to initiating events.  
Specifically, the unvalidated test method had the potential to affect the reliability
Specifically, the unvalidated test method had the potential to affect the reliability
of safety-related motor-operated valves. The issue screened as very low safety
of safety-related motor-operated valves. The issue screened as very low safety
significance (Green) in Phase I of the SDP, because it was a qualification
significance (Green) in Phase I of the SDP, because it was a qualification
deficiency that was not found to result in a loss of function. The team did not
deficiency that was not found to result in a loss of function. The team did not
identify any examples of degraded or inoperable valves during the inspection
identify any examples of degraded or inoperable valves during the inspection
and noted that the design basis calculations for the MOVs reviewed had
and noted that the design basis calculations for the MOVs reviewed had
available thrust margin of greater than 60 percent.
available thrust margin of greater than 60 percent.  
The inspectors also identified that a contributing cause of the finding was related
The inspectors also identified that a contributing cause of the finding was related
to the human performance cross-cutting area, in that, the licensee did not
to the human performance cross-cutting area, in that, the licensee did not
manage NRC commitments and conditions documented in the SER for the
manage NRC commitments and conditions documented in the SER for the
GL 96-05 MOV periodic verification program.
GL 96-05 MOV periodic verification program.
Enforcement. 10 CFR Part 50, Appendix B, Criterion XI, Test Control, requires
Enforcement. 10 CFR Part 50, Appendix B, Criterion XI, Test Control, requires
that a test program be established to ensure that all testing required to
that a test program be established to ensure that all testing required to
demonstrate that systems and components will perform satisfactorily in service is
demonstrate that systems and components will perform satisfactorily in service is
performed in accordance with written test procedures which incorporate the
performed in accordance with written test procedures which incorporate the
requirements and acceptance limits contained in applicable design documents.
requirements and acceptance limits contained in applicable design documents.  
The test procedures shall include provisions for ensuring that adequate test
The test procedures shall include provisions for ensuring that adequate test
instrumentation is available and used. Contrary to the above, Vermont Yankee
instrumentation is available and used. Contrary to the above, Vermont Yankee
had conducted MOV diagnostic tests using procedures that did not include
had conducted MOV diagnostic tests using procedures that did not include
acceptance limits which were correlated to and based on applicable (stem thrust
acceptance limits which were correlated to and based on applicable (stem thrust
and torque) design documents. Additionally, MOV diagnostic testing had been
and torque) design documents. Additionally, MOV diagnostic testing had been
conducted solely from the motor control centers using test instrumentation that
conducted solely from the motor control centers using test instrumentation that
had not been validated to ensure its adequacy. Because this finding is of very
had not been validated to ensure its adequacy. Because this finding is of very
                                                                            Enclosure


                                            25
25
          low safety significance and has been into Vermont Yankees corrective action
Enclosure
          program (CR-VTY-2004-2802 and CR-VTY-2004-2644), it is being treated as a
low safety significance and has been into Vermont Yankees corrective action
          non-cited violation, consistent with Section VI.A of the NRCs Enforcement
program (CR-VTY-2004-2802 and CR-VTY-2004-2644), it is being treated as a
          Policy. (NCV 05000271/2004008-09 Failure To Establish Adequate MOV
non-cited violation, consistent with Section VI.A of the NRCs Enforcement
          Periodic Test Program)
Policy. (NCV 05000271/2004008-09 Failure To Establish Adequate MOV
      b.2 Observations
Periodic Test Program)
          The team also had other observations regarding the licensees NOV program.
  b.2  
          The team concluded these observations did not impact valve operability due to
Observations
          existing value capability margins.
The team also had other observations regarding the licensees NOV program.  
          The team identified that Vermont Yankee had not maintained current the risk
The team concluded these observations did not impact valve operability due to
          ranking of MOVs. At the time that the SER was issued, the licensees risk
existing value capability margins.
          ranking of the MOVs was considered acceptable. During a review of program
The team identified that Vermont Yankee had not maintained current the risk
          documents during this inspection, the team noted that low- and medium-risk
ranking of MOVs. At the time that the SER was issued, the licensees risk
          MOVs were specified for test at every other refueling outage, whereas, high-risk
ranking of the MOVs was considered acceptable. During a review of program
          MOVs were specified for testing every refueling outage. For the RCIC system
documents during this inspection, the team noted that low- and medium-risk
          MOVs reviewed, the team noted that several valves had the same risk
MOVs were specified for test at every other refueling outage, whereas, high-risk
          achievement worth (RAW), but they were assigned different risk rankings in the
MOVs were specified for testing every refueling outage. For the RCIC system
          MOV program documents and consequently were not tested at the same
MOVs reviewed, the team noted that several valves had the same risk
          periodicity. Discussions with Vermont Yankees risk analyst indicated that the
achievement worth (RAW), but they were assigned different risk rankings in the
          licensees PRA had been updated in 2000 and May 2004; however, the updated
MOV program documents and consequently were not tested at the same
          PRA data were not reflected back into the MOV risk ranking. This issue was
periodicity. Discussions with Vermont Yankees risk analyst indicated that the
          entered into the corrective action program on CR-VTY-2004-2798.
licensees PRA had been updated in 2000 and May 2004; however, the updated
          The team also concluded that Vermont Yankees trending methods to identify
PRA data were not reflected back into the MOV risk ranking. This issue was
          degradation from design basis conditions were informal. The SER documented
entered into the corrective action program on CR-VTY-2004-2798.  
          the existence of established procedures to review and trend MOV failure and
The team also concluded that Vermont Yankees trending methods to identify
          diagnostic test data every two years. Primary MOV parameters identified for
degradation from design basis conditions were informal. The SER documented
          trending were various thrust values, stem friction coefficient, load sensitive
the existence of established procedures to review and trend MOV failure and
          behavior and dynamic margin. The SER noted that Vermont Yankee would
diagnostic test data every two years. Primary MOV parameters identified for
          perform quantitative and qualitative assessments looking for overall changes in
trending were various thrust values, stem friction coefficient, load sensitive
          MOV performance, including the use of diagnostic trace overlays and analysis.
behavior and dynamic margin. The SER noted that Vermont Yankee would
          The team found that the procedure referenced in the SER (DP 0210) had been
perform quantitative and qualitative assessments looking for overall changes in
          canceled. The trending of alternating current MOVs was moved to the
MOV performance, including the use of diagnostic trace overlays and analysis.  
          procedure for evaluating MCC test data; however, a procedure for trending direct
The team found that the procedure referenced in the SER (DP 0210) had been
          current MOVs had not been established. Currently, Vermont Yankees trending
canceled. The trending of alternating current MOVs was moved to the
          program consists of reviewing the data from a diagnostic test to the results of the
procedure for evaluating MCC test data; however, a procedure for trending direct
          previous test, which may not identify degradation from the established baseline
current MOVs had not been established. Currently, Vermont Yankees trending
          or identify slow but continual degradation. This issue was entered into the
program consists of reviewing the data from a diagnostic test to the results of the
          corrective action program on CR-VTY-2004-2644.
previous test, which may not identify degradation from the established baseline
or identify slow but continual degradation. This issue was entered into the
corrective action program on CR-VTY-2004-2644.  
4OA6 Meetings, Including Exit
4OA6 Meetings, Including Exit
                                                                                    Enclosure


                                        26
26
Enclosure
The team presented the issues identified during the inspection to Mr. Dreyfuss and other
The team presented the issues identified during the inspection to Mr. Dreyfuss and other
members of the licensees staff at a team debrief on September 3, 2004.
members of the licensees staff at a team debrief on September 3, 2004.
On October 27, 2004, the inspection team leader provided the preliminary results of the
On October 27, 2004, the inspection team leader provided the preliminary results of the
inspection, including risk significance and enforcement, to Mr. Bronson, Mr. Dreyfuss,
inspection, including risk significance and enforcement, to Mr. Bronson, Mr. Dreyfuss,
and other members of licensees staff in a teleconference call.
and other members of licensees staff in a teleconference call.
The preliminary results of the inspection were also included in a letter to Vermont
The preliminary results of the inspection were also included in a letter to Vermont
Yankee Nuclear Power Station dated November 5, 2004, which was originally issued in
Yankee Nuclear Power Station dated November 5, 2004, which was originally issued in
preparation for a planned public exit meeting.
preparation for a planned public exit meeting.
A final closeout discussion on the inspection was held with Mr. Thayer, Mr. Bronson and
A final closeout discussion on the inspection was held with Mr. Thayer, Mr. Bronson and
other members of the licensees staff via teleconference on November 23, 2004. The
other members of the licensees staff via teleconference on November 23, 2004. The
Vermont State Nuclear Engineer was invited to the closeout discussion, but was not
Vermont State Nuclear Engineer was invited to the closeout discussion, but was not
available to attend.
available to attend.
                                                                                Enclosure


                                                      ATTACHMENT A
Attachment
                                                Summary of Items Reviewed
ATTACHMENT A
SSC/OA/OE                 Description                                   Detailed Review Completed / Basis For Exclusion
Summary of Items Reviewed
115 kV - Breaker K1       Transformer T-4 feed to 115 kV bus: required No automatic actions required except fault clearing;
SSC/OA/OE
                          to supply power from the 345 kV switchyard    safety busses would disconnect or be prevented
Description
                          to the Startup Transformers.                  from connecting to circuit after a fault.
Detailed Review Completed / Basis For Exclusion
115 kV - K.1 Logic Relay RCIC logic relay K.1 fails to operate on       The inspectors found no specific operator action for
115 kV - Breaker K1
                          demand. Rationale: Malfunction of RCIC        this component and that a failure of the logic relay
Transformer T-4 feed to 115 kV bus: required
                          turbine trip instrumentation could cause loss  would result in control room alarms which would be
to supply power from the 345 kV switchyard
                          of RCIC System.                                responded to by the operators. The inspectors found
to the Startup Transformers.
                                                                        that related control room alarms were functioning
No automatic actions required except fault clearing;
                                                                        properly, and that the associated alarm response
safety busses would disconnect or be prevented
                                                                        procedures were current.
from connecting to circuit after a fault.  
125 V Battery B-1 and A-1 Station Battery: Supplies power to the station Detailed review completed.
115 kV - K.1 Logic Relay  
                          125 VDC loads when the battery chargers
RCIC logic relay K.1 fails to operate on
                          are not available.
demand. Rationale: Malfunction of RCIC
24 Vdc - ES-24DC-2       Power Supply Converter: Supplies power to     No low margin or other issues identified.
turbine trip instrumentation could cause loss
                          the 24 VDC ECCS Analog Trip System.
of RCIC System.
345 kV - Breaker 381-1   Northfield 345 kV line to 345 kV North Bus:   Detailed review completed.
The inspectors found no specific operator action for
                          required to provide power from the Northfield
this component and that a failure of the logic relay
                          381 to the 345 kV switchyard.
would result in control room alarms which would be
4 Kv - Breaker 12         Bus 1 Feed Breaker from UAT: required to       No low margin issues identified.
responded to by the operators. The inspectors found
                          open on generator trip to enable access of
that related control room alarms were functioning
                          one safety train to the offsite source through
properly, and that the associated alarm response
                          the SUT
procedures were current.
                                                                                                                    Attachment
125 V Battery B-1 and A-1  
Station Battery: Supplies power to the station
125 VDC loads when the battery chargers
are not available.
Detailed review completed.
24 Vdc - ES-24DC-2  
Power Supply Converter: Supplies power to
the 24 VDC ECCS Analog Trip System.
No low margin or other issues identified.
345 kV - Breaker 381-1
Northfield 345 kV line to 345 kV North Bus:
required to provide power from the Northfield
381 to the 345 kV switchyard.
Detailed review completed.
4 Kv - Breaker 12  
Bus 1 Feed Breaker from UAT: required to
open on generator trip to enable access of
one safety train to the offsite source through
the SUT  
No low margin issues identified.


                                                      A-2
A-2
SSC/OA/OE         Description                                   Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
4 Kv - Breaker 13 Bus 1 Feed Breaker from SUT: required to       Detailed review completed.
Description
                  close on generator trip to enable access of
Detailed Review Completed / Basis For Exclusion
                  one safety train to the offsite source through
Attachment
                  the SUT .
4 Kv - Breaker 13  
4 Kv - Breaker 22 Bus 2 Feed Breaker from UAT: required to       The inspectors found that the only operator action
Bus 1 Feed Breaker from SUT: required to
                  open on generator trip to enable access of    for this component was breaker open/close
close on generator trip to enable access of
                  one safety train to the offsite source through operation. Additionally, the inspectors found that the
one safety train to the offsite source through
                  the SUT.                                      related control room alarms were functioning
the SUT .
                                                                  properly and that the associated alarm response
Detailed review completed.
                                                                  procedures were current. The inspectors found no
4 Kv - Breaker 22  
                                                                  issues with this component related to operator
Bus 2 Feed Breaker from UAT: required to
                                                                  actions.
open on generator trip to enable access of
4 Kv - Breaker 23 Bus 2 Feed Breaker from SUT: required to       Detailed review completed.
one safety train to the offsite source through
                  close on generator trip to enable access of
the SUT.
                  one safety train to the offsite source through
The inspectors found that the only operator action
                  the SUT.
for this component was breaker open/close
4 Kv - Breaker 3V Vernon Supply Breaker to Bus 3: required to   No specific issues identified with breaker. Other
operation. Additionally, the inspectors found that the
                  supply power from the Alternate AC Power      issues reviewed as part of overall Station Blackout
related control room alarms were functioning
                  source to one 4160V safety bus.                Capability.
properly and that the associated alarm response
4 Kv - Breaker 3V4 Vernon Tie Breaker: required to supply         Detailed review completed.
procedures were current. The inspectors found no
                  power from the Alternate AC Power source
issues with this component related to operator
                  to either 4160V safety bus.
actions.  
4 kV UV Relays     4160V Undervoltage Relays: required to         Detailed review completed.
4 Kv - Breaker 23  
                  provide adequate voltage to safety-related
Bus 2 Feed Breaker from SUT: required to
                  AC loads, reset setpoint must be optimized
close on generator trip to enable access of
                  to prevent spurious loss of offsite power.
one safety train to the offsite source through
                                                                                                              Attachment
the SUT.
Detailed review completed.
4 Kv - Breaker 3V  
Vernon Supply Breaker to Bus 3: required to
supply power from the Alternate AC Power
source to one 4160V safety bus.
No specific issues identified with breaker. Other
issues reviewed as part of overall Station Blackout
Capability.  
4 Kv - Breaker 3V4  
Vernon Tie Breaker: required to supply
power from the Alternate AC Power source
to either 4160V safety bus.
Detailed review completed.
4 kV UV Relays  
4160V Undervoltage Relays: required to  
provide adequate voltage to safety-related
AC loads, reset setpoint must be optimized
to prevent spurious loss of offsite power.  
Detailed review completed.


                                                            A-3
A-3
SSC/OA/OE               Description                                   Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
69 kV - Vernon Generator Vernon Hydroelectric generator station:       Detailed review completed.
Description
                        required to supply power from the Alternate
Detailed Review Completed / Basis For Exclusion
                        AC Power source to either 4160V safety bus.
Attachment
69 kV to 4160 V Vernon   Vernon Tie Transformer: required to supply   Detailed review completed.
69 kV - Vernon Generator  
Transformer              power from the Alternate AC Power source
Vernon Hydroelectric generator station:
                        to either 4160V safety bus.
required to supply power from the Alternate
125 VDC Distribution     Supplies 125 VDC loads.                       Detailed review completed.
AC Power source to either 4160V safety bus.
Panels
Detailed review completed.
Alignment of RHRSW to   Operator fails to align the RHRSW injection   Aligning RHRSW injection to the RPV is one of the
69 kV to 4160 V Vernon
the RPV                  to RPV.                                      methods which can be used for RPV injection to
Transformer
                                                                      prevent core damage in accordance with EOPs
Vernon Tie Transformer: required to supply
                                                                      given an ATWS scenario. The validated time
power from the Alternate AC Power source
                                                                      through simulator observation was 1 minute to
to either 4160V safety bus.
                                                                      complete the actions for alignment. Additionally,
Detailed review completed.
                                                                      prior to using RHR SW for RPV injection, other
125 VDC Distribution
                                                                      systems such as condensate/feedwater , CRD, and
Panels
                                                                      RHR will be used to attempt to fill the RPV. The
Supplies 125 VDC loads.  
                                                                      operators are regularly trained and evaluated in this
Detailed review completed.
                                                                      event scenario further reducing the likelihood of the
Alignment of RHRSW to
                                                                      task not being completed within the required time.
the RPV
Bus Transfer Scheme     Circuit breakers, synchronism check relays,   Detailed review completed.
Operator fails to align the RHRSW injection
                        timing relays, and voltage relays required to
to RPV.
                        enable transfer of 4160V buses from the Unit
Aligning RHRSW injection to the RPV is one of the
                        Aux Transformer to the Startup
methods which can be used for RPV injection to
                        Transformers.
prevent core damage in accordance with EOPs
                                                                                                                  Attachment
given an ATWS scenario. The validated time
through simulator observation was 1 minute to
complete the actions for alignment. Additionally,
prior to using RHR SW for RPV injection, other
systems such as condensate/feedwater , CRD, and
RHR will be used to attempt to fill the RPV. The
operators are regularly trained and evaluated in this
event scenario further reducing the likelihood of the
task not being completed within the required time.  
Bus Transfer Scheme  
Circuit breakers, synchronism check relays,
timing relays, and voltage relays required to
enable transfer of 4160V buses from the Unit
Aux Transformer to the Startup
Transformers.
Detailed review completed.


                                                        A-4
A-4
SSC/OA/OE             Description                           Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
Closure of Vernon Tie Operator fails to close the Vernon tie One of the primary AC power recovery actions in the
Description
Breakers              breakers.                              event of a loss of normal power is to use the
Detailed Review Completed / Basis For Exclusion
                                                            dedicated tie line from the Vernon hydro Station to
Attachment
                                                            power either 4260VAC Bus 3 or 4 (vital power). The
Closure of Vernon Tie
                                                            action is performed by the operators in the main
Breakers
                                                            control room by manipulating switches for 2 DC
Operator fails to close the Vernon tie
                                                            powered breakers. Validation studies and operator
breakers.
                                                            observation in the simulator have shown that the
One of the primary AC power recovery actions in the
                                                            task can be accomplished in less than 4 minutes.
event of a loss of normal power is to use the
                                                            Adequate margin exists currently and for the CPPU
dedicated tie line from the Vernon hydro Station to
                                                            to accomplish the action. Additionally, operator
power either 4260VAC Bus 3 or 4 (vital power). The
                                                            response to loss of power events is trained regularly
action is performed by the operators in the main
                                                            in the simulator and classroom. While no issues
control room by manipulating switches for 2 DC
                                                            identified with VY operator actions, a finding was
powered breakers. Validation studies and operator
                                                            identified with the licensee's overall station blackout
observation in the simulator have shown that the
                                                            response.
task can be accomplished in less than 4 minutes.  
                                                                                                          Attachment
Adequate margin exists currently and for the CPPU
to accomplish the action. Additionally, operator
response to loss of power events is trained regularly
in the simulator and classroom. While no issues
identified with VY operator actions, a finding was
identified with the licensee's overall station blackout
response.  


                                                          A-5
A-5
SSC/OA/OE             Description                                   Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
Condensate Pump       Review condensate operation before and       No low margin or other issues identified.
Description
                      after the power uprate (including recirc pump
Detailed Review Completed / Basis For Exclusion
                      runback modification).
Attachment
                      The Condensate and Feedwater system
Condensate Pump
                      does not directly perform any safety-related
Review condensate operation before and
                      function. Portions of the Feedwater system
after the power uprate (including recirc pump
                      and check valves provide Reactor Coolant
runback modification).  
                      Pressure Boundary and Containment
The Condensate and Feedwater system
                      Isolation functions. The condensate pumps
does not directly perform any safety-related
                      1) supply water to the Feedwater pumps and
function. Portions of the Feedwater system
                      2) provide sufficient NPSH for operation of
and check valves provide Reactor Coolant
                      the FW pumps. The loss of a condensate
Pressure Boundary and Containment
                      pump could be a contributing factor to a
Isolation functions. The condensate pumps
                      transient initiation.
1) supply water to the Feedwater pumps and
                      The condensate pumps are directly impacted
2) provide sufficient NPSH for operation of
                      by the EPU due to the need to increase the
the FW pumps. The loss of a condensate
                      flow volume by approximately 20%.
pump could be a contributing factor to a
Containment Pressure   During a loss of coolant event or an ATWS     Detailed review completed.
transient initiation.  
                      the containment pressure will be elevated
The condensate pumps are directly impacted
                      and the suppression pool level will increase.
by the EPU due to the need to increase the
CST Transient Analysis Transient analysis Condensate Storage Tank   Detailed review completed.
flow volume by approximately 20%.
Temperature            Temperature non-conservative compared to
No low margin or other issues identified.  
Non-conservative      actual maximum operating temperatures.
Containment Pressure  
                      This issue stems from a similar event at
During a loss of coolant event or an ATWS
                      Point Beach.
the containment pressure will be elevated
                                                                                                              Attachment
and the suppression pool level will increase.
Detailed review completed.
CST Transient Analysis  
Temperature
Non-conservative
Transient analysis Condensate Storage Tank
Temperature non-conservative compared to
actual maximum operating temperatures.
This issue stems from a similar event at
Point Beach.
Detailed review completed.


                                                            A-6
A-6
SSC/OA/OE                 Description                                   Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
CST Level Instrumentation Rationale: Important for maintaining required Detailed review completed.
Description
                          CST inventory for RCICS and controlling
Detailed Review Completed / Basis For Exclusion
                          automatic transfer of RCICS suction to the
Attachment
                          suppression pool.
CST Level Instrumentation  
CV-109                   Failure of check valve CV-109 (valve         Detailed review completed.
Rationale: Important for maintaining required
                          between the N2 bottle and the SRV) to open.
CST inventory for RCICS and controlling
                          Failure of this check valve to open will
automatic transfer of RCICS suction to the
                          prevent N2 supply to the Main Steam Safety
suppression pool.
                          Relief Valves.
Detailed review completed.
CV-19                     RCIC check valve CV-19 (RCIC suction         A detailed review was not performed for this check
CV-109  
                          check valve from the CST) fails to open on   valve because no performance problems were
Failure of check valve CV-109 (valve
                          demand. This valve must open to provide       indicated from the maintenance history.
between the N2 bottle and the SRV) to open.
                          flow from CST to RCIC pump suction, and
Failure of this check valve to open will
                          close to prevent flow from torus to CST
prevent N2 supply to the Main Steam Safety
                          during RCIC pump suction transfer.
Relief Valves.
                                                                                                                  Attachment
Detailed review completed.
CV-19  
RCIC check valve CV-19 (RCIC suction
check valve from the CST) fails to open on
demand. This valve must open to provide
flow from CST to RCIC pump suction, and
close to prevent flow from torus to CST
during RCIC pump suction transfer.  
A detailed review was not performed for this check
valve because no performance problems were
indicated from the maintenance history.


                                                    A-7
A-7
SSC/OA/OE       Description                                       Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
CV-2-1A, 1B, 1C RFP discharge check valves. They are risk         A detailed review was not performed for these check
Description
                significant because if they fail to close         valves because no performance problems were
Detailed Review Completed / Basis For Exclusion
                following an RFP trip they could make other       indicated from the maintenance history.
Attachment
                RFPs inoperable.
CV-2-1A, 1B, 1C  
                Prior to EPU two pumps are operational.
RFP discharge check valves. They are risk
                After EPU three pumps will be operational.
significant because if they fail to close
                When two pumps are operational, one of the
following an RFP trip they could make other
                MOVs, 4A, 4B or 4C will be closed for the
RFPs inoperable.  
                non-operational pump as such, this is not a
Prior to EPU two pumps are operational.
                current potential event. However, after EPU
After EPU three pumps will be operational.
                the third valve will not be closed thus this is a
When two pumps are operational, one of the
                potential failure scenario.
MOVs, 4A, 4B or 4C will be closed for the
CV-22           RCIC check valve CV-22 (RCIC injection           Detailed review completed.
non-operational pump as such, this is not a
                path discharge check valve) fails to open on
current potential event. However, after EPU
                demand. This valve must open for RCIC
the third valve will not be closed thus this is a
                injection flow. The valve must also fully close
potential failure scenario.
                when the pump is not in operation to prevent
A detailed review was not performed for these check
                back-leakage and a possible waterhammer.
valves because no performance problems were
                                                                                                            Attachment
indicated from the maintenance history.  
CV-22  
RCIC check valve CV-22 (RCIC injection
path discharge check valve) fails to open on
demand. This valve must open for RCIC
injection flow. The valve must also fully close
when the pump is not in operation to prevent
back-leakage and a possible waterhammer.  
Detailed review completed.


                                              A-8
A-8
SSC/OA/OE Description                                     Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
CV-2-27B This valve is the feedwater isolation valve     A detailed review was not performed for this check
Description
          upstream of the RCIC injection path. The risk   valve because no performance problems were
Detailed Review Completed / Basis For Exclusion
          significant function of the component is to     indicated from the maintenance history.
Attachment
          close to prevent RCIC from flowing back into
CV-2-27B  
          the feedwater system.
This valve is the feedwater isolation valve
          EPU uprate will increase the flow through this
upstream of the RCIC injection path. The risk
          check valve by approximately 20%, however
significant function of the component is to
          the function of the valve is not altered.
close to prevent RCIC from flowing back into
CV-2-28B Feedwater check valve CV-28B ('B'               A detailed review was not performed for this check
the feedwater system.
          feedwater line check valve inside               valve because no performance problems were
          containment) fails to open on demand. This     indicated from the maintenance history.
EPU uprate will increase the flow through this
          valve is located on drawing G-191167, H-5.
check valve by approximately 20%, however
          Failure to open will prevent flow from either
the function of the valve is not altered.
          the RCIC or the Feedwater system.
A detailed review was not performed for this check
          EPU uprate will increase the flow through this
valve because no performance problems were
          check valve by approximately 20%, however
indicated from the maintenance history.  
          the function of the valve is not altered.
CV-2-28B  
CV-2-96A Feedwater check valve V96A fails to open on A detailed review was not performed for this check
Feedwater check valve CV-28B ('B'
          demand. Failure of this valve will prevent flow valve because no performance problems were
feedwater line check valve inside
          from either the RCIC or the FW system.          indicated from the maintenance history.
containment) fails to open on demand. This
          EPU uprate will increase the flow through this
valve is located on drawing G-191167, H-5.
          check valve by approximately 20%, however
Failure to open will prevent flow from either
          the function of the valve is not altered.
the RCIC or the Feedwater system.  
                                                                                                    Attachment
EPU uprate will increase the flow through this
check valve by approximately 20%, however
the function of the valve is not altered.
A detailed review was not performed for this check
valve because no performance problems were
indicated from the maintenance history.  
CV-2-96A  
Feedwater check valve V96A fails to open on
demand. Failure of this valve will prevent flow
from either the RCIC or the FW system.  
EPU uprate will increase the flow through this
check valve by approximately 20%, however
the function of the valve is not altered.  
A detailed review was not performed for this check
valve because no performance problems were
indicated from the maintenance history.


                                                          A-9
A-9
SSC/OA/OE             Description                                     Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
CV-40                 RCIC check valve CV-40 (RCIC suction             A detailed review was not performed for this check
Description
                      check valve from the suppression pool) fails     valve because no performance problems were
Detailed Review Completed / Basis For Exclusion
                      to open on demand. This valve must open to       indicated from the maintenance history or walkdown.
Attachment
                      provide a flow path from the torus to the
CV-40  
                      RCIC pump suction.
RCIC check valve CV-40 (RCIC suction
CV-6/7                 RCIC check valves CV- 6/7 (RCIC turbine         Detailed review completed.
check valve from the suppression pool) fails
                      exhaust check valves to torus) fails to open
to open on demand. This valve must open to
                      on demand.
provide a flow path from the torus to the
CV-72-109             Failure of check valve CV-109 (N2 bottle         Detailed review completed.
RCIC pump suction.
                      supply check valve to the plant N2 system) to
A detailed review was not performed for this check
                      close. The component is risk significant
valve because no performance problems were
                      because if the check valve failed to close, the
indicated from the maintenance history or walkdown.  
                      N2 bottle could bleed down to the plant N2
CV-6/7  
                      system.
RCIC check valves CV- 6/7 (RCIC turbine
Digital Feedwater     Following the modification that installed the   Detailed review completed.
exhaust check valves to torus) fails to open
Control/Single Element digital feedwater control system, the licensee
on demand.
Control                had problems with loss of inputs to the
Detailed review completed.
                      three-element controller (steam flow). This
CV-72-109  
                      resulted in a reactor level transient. Since the
Failure of check valve CV-109 (N2 bottle
                      event the plant had been operating in
supply check valve to the plant N2 system) to
                      single-element control. Evaluate the
close. The component is risk significant
                      modification and the acceptability of
because if the check valve failed to close, the
                      operating in single-element. Also determine if
N2 bottle could bleed down to the plant N2
                      operation in single-element control would
system.
                      challenge the licensee's assumption that the
Detailed review completed.
                      plant would not scram following a single
Digital Feedwater
                      reactor feed pump trip, post-uprate.
Control/Single Element
                                                                                                                  Attachment
Control
Following the modification that installed the
digital feedwater control system, the licensee
had problems with loss of inputs to the
three-element controller (steam flow). This
resulted in a reactor level transient. Since the
event the plant had been operating in
single-element control. Evaluate the
modification and the acceptability of
operating in single-element. Also determine if
operation in single-element control would
challenge the licensee's assumption that the
plant would not scram following a single
reactor feed pump trip, post-uprate.  
Detailed review completed.


                                                            A-10
A-10
SSC/OA/OE               Description                                   Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
DPIS-83/84             Spurious high steam flow signal. This steam   These instruments are not included because there is
Description
                        flow instrument isolates RCIC steam in the    significant margin in the setpoint to detect a steam
Detailed Review Completed / Basis For Exclusion
                        event of a line rupture (indicated by high    line rupture, as well as margin between the normal
Attachment
                        flow). Spurious isolation would result in the operating point and the setpoint.
DPIS-83/84  
                        loss of RCIC flow.
Spurious high steam flow signal. This steam
EOP/NPSH Fidelity       Verify fidelity between Emergency Operation   Detailed review completed.
flow instrument isolates RCIC steam in the
                        Procedures and NPSH calculations and
event of a line rupture (indicated by high
                        Containment Spray operation.
flow). Spurious isolation would result in the
FCV-2-4                 FCV.4 (condensate pump minimum flow           Detailed review completed.
loss of RCIC flow.
                        valve) fails to open on demand.
These instruments are not included because there is
FCV-2-4 Instrumentation Failure of FCV.4 (condensate pump             Detailed review completed.
significant margin in the setpoint to detect a steam
                        minimum flow valve) control instrumentation.
line rupture, as well as margin between the normal
Feed/Condensate Control Operator fails to initiate and/or control     Detailed review completed.
operating point and the setpoint.  
                        feedwater/condensate.
EOP/NPSH Fidelity  
FT-58/FE-56             RCIC pump discharge flow instrument. This     Detailed review completed.
Verify fidelity between Emergency Operation
                        instrument is associated with the RCIC
Procedures and NPSH calculations and
                        turbine control logic.
Containment Spray operation.
GE SIL 351             GE SIL 351 - HPCI and RCIC Turbine           Vermont Yankee implemented SIL 351R.2 and
Detailed review completed.
                        Control System Calibration.                  provided the procedural changes recommended in
FCV-2-4  
                                                                      the SIL for the HPCI system (OP 5337 Rev. 7). SIL
FCV.4 (condensate pump minimum flow
                                                                      351 does not apply to RCIC since RCIC does not
valve) fails to open on demand
                                                                      use a ramp generator (RGSC). This SIL is primarily
Detailed review completed.
                                                                      procedural change recommendations and is not a
FCV-2-4 Instrumentation  
                                                                      high risk/low margin system.
Failure of FCV.4 (condensate pump
                                                                                                                  Attachment
minimum flow valve) control instrumentation.
Detailed review completed.
Feed/Condensate Control  
Operator fails to initiate and/or control
feedwater/condensate.
Detailed review completed.
FT-58/FE-56  
RCIC pump discharge flow instrument. This
instrument is associated with the RCIC
turbine control logic.
Detailed review completed.
GE SIL 351
GE SIL 351 - HPCI and RCIC Turbine
Control System Calibration.
Vermont Yankee implemented SIL 351R.2 and
provided the procedural changes recommended in
the SIL for the HPCI system (OP 5337 Rev. 7). SIL
351 does not apply to RCIC since RCIC does not
use a ramp generator (RGSC). This SIL is primarily
procedural change recommendations and is not a
high risk/low margin system.  


                                                        A-11
A-11
SSC/OA/OE             Description                                 Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
GE SIL 377             GE SIL 377 RCIC Startup Transient           GE SIL 377 recommended a bypass for the steam
Description
                      Improvement with Steam Bypass (June 24,    supply line to the turbine for improved startup
Detailed Review Completed / Basis For Exclusion
                      1982).                                      performance during a transient where RCIC is
Attachment
                                                                  needed. This does not apply to Vermont Yankee
GE SIL 377
                                                                  since the SIL was a recommendation for plants who
GE SIL 377 RCIC Startup Transient
                                                                  have issues with cold startup of the RCIC system.
Improvement with Steam Bypass (June 24,
                                                                  Upon talking to the system engineer, these issues
1982).
                                                                  have not existed for at least 20 years at VY.
GE SIL 377 recommended a bypass for the steam
GE SIL 467 (Bistable   GE SIL 467 and IEN 86-110 - Bistable       The first occurrence of bistable vortexing at Vermont
supply line to the turbine for improved startup
Vortexing)            vortexing is still a phenomenon that occurs Yankee was following beginning of cycle 12 when
performance during a transient where RCIC is
                      periodically at VY.                        recirculation system piping was replaced; however,
needed. This does not apply to Vermont Yankee
                                                                  this is a low risk event and thus does not meet the
since the SIL was a recommendation for plants who
                                                                  high risk / low margin criteria for this inspection.
have issues with cold startup of the RCIC system.
                                                                  Vermont Yankee has had problems with bistable
Upon talking to the system engineer, these issues
                                                                  vortexing in the past and responded in depth to this
have not existed for at least 20 years at VY.  
                                                                  SIL. The licensee responded to the SIL, added
GE SIL 467 (Bistable
                                                                  discussion on bistable vortexing at VY and action
Vortexing)
                                                                  items for operators when bistable vortexing occurs.
GE SIL 467 and IEN 86-110 - Bistable
                                                                  A review of Vermont Yankee's response to SIL 467,
vortexing is still a phenomenon that occurs
                                                                  showed VY satisfied GE's recommended actions
periodically at VY.
                                                                  and placed guidance in OP 2110, Recirculation
The first occurrence of bistable vortexing at Vermont
                                                                  Procedure to aid the operators in identifying bistable
Yankee was following beginning of cycle 12 when
                                                                  vortexing.
recirculation system piping was replaced; however,
GL 96-05, MOV Periodic GL 96-05 - Implementation of program for   Detailed review completed.
this is a low risk event and thus does not meet the
Verification          MOV Periodic Verification (As applicable to
high risk / low margin criteria for this inspection.
                      the selected sample of valves RCIC-MOV-
Vermont Yankee has had problems with bistable
                      15, 16, 131 and 132)
vortexing in the past and responded in depth to this
                                                                                                                Attachment
SIL. The licensee responded to the SIL, added
discussion on bistable vortexing at VY and action
items for operators when bistable vortexing occurs.
A review of Vermont Yankee's response to SIL 467,
showed VY satisfied GE's recommended actions
and placed guidance in OP 2110, Recirculation
Procedure to aid the operators in identifying bistable
vortexing.  
GL 96-05, MOV Periodic
Verification
GL 96-05 - Implementation of program for
MOV Periodic Verification (As applicable to
the selected sample of valves RCIC-MOV-
15, 16, 131 and 132)  
Detailed review completed.


                                                        A-12
A-12
SSC/OA/OE             Description                                     Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
IN 2001-13 (SLC Relief Information Notice 2001-13 (8/10/01) -         Detailed review completed.
Description
Valve Margin)          Inadequate Standby Liquid Control System
Detailed Review Completed / Basis For Exclusion
                      Relief Valve Margin (Susquehanna, Units 1
Attachment
                      and 2) Susquehanna's power uprate
IN 2001-13 (SLC Relief
                      increased SRV setpoint pressure thus
Valve Margin)
                      increasing SLC discharge pressure.
Information Notice 2001-13 (8/10/01) -
                      However, the maximum SLC pump
Inadequate Standby Liquid Control System
                      discharge pressure used a non-conservative
Relief Valve Margin (Susquehanna, Units 1
                      maximum reactor vessel pressure in accident
and 2) Susquehanna's power uprate
                      analysis.
increased SRV setpoint pressure thus
LER 3871995009         LER 1995-009-00 (7/3/95) - Condition           Feedflow used in the analysis for power uprate is
increasing SLC discharge pressure.
(LCO 3.0.3 Entry)      Prohibited by the Plant's Technical             consistent with current feedflow indications.
However, the maximum SLC pump
                      Specifications (Susquehanna, Unit 1) - Non-
discharge pressure used a non-conservative
                      conservative plant input into reactor core flow
maximum reactor vessel pressure in accident
                      calculation.
analysis.
LER 3251997005         LER 1997-005-01 (8/8/97) - Feedwater Flow       Vermont Yankee does not have and is not required
Detailed review completed.
(FW Indication Error)  Indication Discrepancy (Brunswick Steam        to have chemical tracer mass flow rate tests. This is
LER 3871995009
                      Electric Plant, Unit 1).                        more conservative then having the tracers since the
(LCO 3.0.3 Entry)
                                                                      chemical tracer mass flow rate tests are
LER 1995-009-00 (7/3/95) - Condition
                                                                      controversial and have had past issues. VY is
Prohibited by the Plant's Technical
                                                                      waiting for industry or regulatory guidance on this
Specifications (Susquehanna, Unit 1) - Non-
                                                                      issue before adding this test.
conservative plant input into reactor core flow
LER 2961998001         LER 1998-001-00 (4/1/1998) - Computer           Vermont Yankee does use the GOTHIC computer
calculation.
(LOCA Sensor Problem)  Modeling Indicates Sensors May Not Detect      code to analyze high energy pipe breaks; however,
Feedflow used in the analysis for power uprate is
                      All Possible Break Locations (Browns Ferry,    this is a low risk issue and presented no significant
consistent with current feedflow indications.  
                      Unit 3).                                        safety issue at Browns Ferry.
LER 3251997005
                                                                                                                  Attachment
(FW Indication Error)
LER 1997-005-01 (8/8/97) - Feedwater Flow
Indication Discrepancy (Brunswick Steam
Electric Plant, Unit 1).
Vermont Yankee does not have and is not required
to have chemical tracer mass flow rate tests. This is
more conservative then having the tracers since the
chemical tracer mass flow rate tests are
controversial and have had past issues. VY is
waiting for industry or regulatory guidance on this
issue before adding this test.  
LER 2961998001
(LOCA Sensor Problem)
LER 1998-001-00 (4/1/1998) - Computer
Modeling Indicates Sensors May Not Detect
All Possible Break Locations (Browns Ferry,
Unit 3).
Vermont Yankee does use the GOTHIC computer
code to analyze high energy pipe breaks; however,
this is a low risk issue and presented no significant
safety issue at Browns Ferry.  


                                                          A-13
A-13
SSC/OA/OE               Description                                   Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
LER 2601999009         LER 1999-009-00 (10/14/99) - Manual           The EHC leak was on a very specific 3/8 inch
Description
(Scram Due to EHC Leak) Reactor Scram Due to EHC Leak (Browns          nominal outer diameter tubing connection which
Detailed Review Completed / Basis For Exclusion
                        Ferry Nuclear Power Station, Unit 2).          consisted of socket weld glands and standard nuts
Attachment
                                                                      to connect the accumulator to a pressure
LER 2601999009
                                                                      transmitter. The leak was due to poor fabrication and
(Scram Due to EHC Leak)
                                                                      poor work practices specific to Browns Ferry.
LER 1999-009-00 (10/14/99) - Manual
LER 2372001005 (1/7/02) LER 2001-005-00 (1/7/02) - Unit 2 Scram       Vermont Yankee responded to GE SIL 423, in 1998,
Reactor Scram Due to EHC Leak (Browns
                        Due to Increased First Stage Turbine          by implementing corrective actions.
Ferry Nuclear Power Station, Unit 2).
                        Pressure (Dresden, Unit 2).
The EHC leak was on a very specific 3/8 inch
LER 4612002002          LER 2002-002-00 (7/11/02) - Inadequate         This operating experience does not apply since
nominal outer diameter tubing connection which
(Inadequate PM on FW    Preventive Maintenance Program for the         Vermont Yankee does not have turbine driven
consisted of socket weld glands and standard nuts
System)                Feedwater System Results in Lockup of a       feedwater pumps, and this issue does not apply to
to connect the accumulator to a pressure
                        Turbine-Driven Reactor Feed Pump and           other turbine driven pumps in the plant.
transmitter. The leak was due to poor fabrication and
                        Scram on High Reactor Pressure Vessel
poor work practices specific to Browns Ferry.  
                        Water Level During Extended Power Uprate
LER 2372001005 (1/7/02)  
                        Testing (Clinton Power Station). Feedwater
LER 2001-005-00 (1/7/02) - Unit 2 Scram
                        increased due to the power uprate; however,
Due to Increased First Stage Turbine
                        the feedwater limit switch did not increase to
Pressure (Dresden, Unit 2).
                        accommodate this increase in flow.
Vermont Yankee responded to GE SIL 423, in 1998,
                                                                                                                  Attachment
by implementing corrective actions.
LER 4612002002
(Inadequate PM on FW
System)  
LER 2002-002-00 (7/11/02) - Inadequate
Preventive Maintenance Program for the
Feedwater System Results in Lockup of a
Turbine-Driven Reactor Feed Pump and
Scram on High Reactor Pressure Vessel
Water Level During Extended Power Uprate
Testing (Clinton Power Station). Feedwater
increased due to the power uprate; however,
the feedwater limit switch did not increase to
accommodate this increase in flow.  
This operating experience does not apply since
Vermont Yankee does not have turbine driven
feedwater pumps, and this issue does not apply to
other turbine driven pumps in the plant.


                                                  A-14
A-14
SSC/OA/OE         Description                               Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
LER 3412002005   LER 2002-05 (1/16/03) - Discovery of     This OE does not apply to Vermont Yankee since
Description
(Non-Conservative Non-Conservative Setpoint for the        power oscillations are monitored using approved
Detailed Review Completed / Basis For Exclusion
Setpoint)        Thermal-Hydraulic Stability Option III    BWROG Option 1D not Option III. Vermont Yankee
Attachment
                  Oscillation Power Range Monitor (OPRM)    does not have Oscillation Power Range Monitors,
LER 3412002005
                  Period Based Algorithm, Tmin              Period Based Detection Algorithms, and Tmin
(Non-Conservative
                  (Fermi, Unit 2).                          values. Option III is used for larger BWRs that have
Setpoint)
                                                            local power oscillations. Since Vermont Yankee has
LER 2002-05 (1/16/03) - Discovery of
                                                            a small BWR core, only core-wide oscillations occur
Non-Conservative Setpoint for the
                                                            (not local oscillations).
Thermal-Hydraulic Stability Option III
                                                            The inspector met with an individual from power
Oscillation Power Range Monitor (OPRM)
                                                            uprate (and used to work in reactor engineering) and
Period Based Algorithm, Tmin
                                                            discussed, in detail, core monitoring using Option 1D
(Fermi, Unit 2).
                                                            for the new ARTS/MELLA core design and the
This OE does not apply to Vermont Yankee since
                                                            power uprate core design.
power oscillations are monitored using approved
LER 4542003003   LER 2003-003-00 (9/29/03) - Licensed     Detailed review completed.
BWROG Option 1D not Option III. Vermont Yankee
(Maximum Power    Maximum Power Level Exceeded Due to
does not have Oscillation Power Range Monitors,
Exceeded)        Inaccuracies in Feedwater Ultrasonic Flow
Period Based Detection Algorithms, and Tmin
                  Measurements Caused by Signal Noise
values. Option III is used for larger BWRs that have
                  Contamination (Byron).
local power oscillations. Since Vermont Yankee has
LER 3411992009   LER-92-009-00 (11/20/92) - Safety Relief VY has had no issues with setpoint drift on the SRVs
a small BWR core, only core-wide oscillations occur
                  Valves Set Pressure Outside Technical    or RVs in containment. Setpoint drift considered in
(not local oscillations).  
                  Specifications (Fermi, Unit 2).          this LER was an indication of disc-to-seat sticking
The inspector met with an individual from power
                                                            due to corrosion binding on the SRVs and RVs at
uprate (and used to work in reactor engineering) and
                                                            Fermi thus making these valves fail their set
discussed, in detail, core monitoring using Option 1D
                                                            pressures tests.
for the new ARTS/MELLA core design and the
                                                                                                      Attachment
power uprate core design.  
LER 4542003003  
(Maximum Power
Exceeded)
LER 2003-003-00 (9/29/03) - Licensed
Maximum Power Level Exceeded Due to
Inaccuracies in Feedwater Ultrasonic Flow
Measurements Caused by Signal Noise
Contamination (Byron).
Detailed review completed.
LER 3411992009  
LER-92-009-00 (11/20/92) - Safety Relief
Valves Set Pressure Outside Technical
Specifications (Fermi, Unit 2).
VY has had no issues with setpoint drift on the SRVs
or RVs in containment. Setpoint drift considered in
this LER was an indication of disc-to-seat sticking
due to corrosion binding on the SRVs and RVs at
Fermi thus making these valves fail their set
pressures tests.  


                                                        A-15
A-15
SSC/OA/OE           Description                                 Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
LSHH-4A             Level switch LSHH 4A contacts fail/short.   Operator can take manual action to overcome this
Description
                                                                  failure. The consequence of the failure of the switch
Detailed Review Completed / Basis For Exclusion
                    High Water Make up - Condenser level         is not significant because the operator can take
Attachment
                    Control Switch Fails high - auto make       manual control.
LSHH-4A  
                    malfunctions to the CST - Operator Action is
Level switch LSHH 4A contacts fail/short.
                    required.
High Water Make up - Condenser level
                    No EPU impact.
Control Switch Fails high - auto make
Manual Initiation of Operator fails to manually initiate HPCI and Detailed review completed.
malfunctions to the CST - Operator Action is
HPCI/RCIC            RCIC systems.
required.
Manual Operation of Operator fails to manually open the SRVs for Emergency Operating Procedures (EOP) require
No EPU impact.
SRVs (Medium LOCA)  a medium LOCA.                              operator action to manually open the SRVs to
Operator can take manual action to overcome this
                                                                  depressurize the reactor under medium break LOCA
failure. The consequence of the failure of the switch
                                                                  conditions. Validation studies and operator
is not significant because the operator can take
                                                                  observations in the simulator have shown that given
manual control.  
                                                                  various factors that influence human performance
Manual Initiation of
                                                                  (stress, training, equipment failures, etc.), the task to
HPCI/RCIC
                                                                  open the SRVs manually would be accomplished in
Operator fails to manually initiate HPCI and
                                                                  less than 7 minutes which is lower than the 33
RCIC systems.
                                                                  minutes (or 24 minutes for CPPU) needed to assure
Detailed review completed.
                                                                  > 1/3 core coverage. Additionally, operator training
Manual Operation of  
                                                                  frequently focuses on this event making it unlikely
SRVs (Medium LOCA)
                                                                  that the operator would fail to perform the task within
Operator fails to manually open the SRVs for
                                                                  the required time.
a medium LOCA.
                                                                                                                Attachment
Emergency Operating Procedures (EOP) require
operator action to manually open the SRVs to
depressurize the reactor under medium break LOCA
conditions. Validation studies and operator
observations in the simulator have shown that given
various factors that influence human performance
(stress, training, equipment failures, etc.), the task to
open the SRVs manually would be accomplished in
less than 7 minutes which is lower than the 33
minutes (or 24 minutes for CPPU) needed to assure
> 1/3 core coverage. Additionally, operator training
frequently focuses on this event making it unlikely
that the operator would fail to perform the task within
the required time.  


                                                            A-16
A-16
SSC/OA/OE               Description                                   Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
Manual Operation of SRVs Operator fails to manually open the SRVs for Emergency Operating Procedures (EOP) require
Description
(Small LOCA/Transient)  transient/small LOCA.                        operator action to manually open the SRVs to
Detailed Review Completed / Basis For Exclusion
                                                                      depressurize the reactor under transient and small
Attachment
                                                                      break LOCA conditions. Validation studies and
Manual Operation of SRVs
                                                                      operator observations in the simulator have shown
(Small LOCA/Transient)
                                                                      that given various factors that influence human
Operator fails to manually open the SRVs for
                                                                      performance (stress, training, equipment failures,
transient/small LOCA.
                                                                      etc.), the task to open the SRVs manually would be
Emergency Operating Procedures (EOP) require
                                                                      accomplished in less than 5 minutes which is much
operator action to manually open the SRVs to
                                                                      lower than the 66 minutes (or 48 minutes for CPPU)
depressurize the reactor under transient and small
                                                                      needed to assure > 1/3 core coverage. Additionally,
break LOCA conditions. Validation studies and
                                                                      operator training frequently focuses on this event
operator observations in the simulator have shown
                                                                      making it unlikely that the operator would fail to
that given various factors that influence human
                                                                      perform the task within the required time.
performance (stress, training, equipment failures,
Manual RCIC operation-   Appendix R Safe Shutdown Analysis -          Detailed review completed.
etc.), the task to open the SRVs manually would be
Appendix R Safe         Operator fails to manually initiate RCIC
accomplished in less than 5 minutes which is much
Shutdown                system using alternate shutdown panels
lower than the 66 minutes (or 48 minutes for CPPU)
                        (Generic Human Actions that are Risk
needed to assure > 1/3 core coverage. Additionally,
                        Important), and GE document NEDC-
operator training frequently focuses on this event
                        330090P, Table 10-5 (Assessment of Key
making it unlikely that the operator would fail to
                        Operator Action).
perform the task within the required time.  
MOV-131                 RCIC MOV 131 (RCIC turbine steam supply       Not included because valve has adequate design
Manual RCIC operation-
                        valve) fails to open on demand. This valve is margin to open when required.
Appendix R Safe
                        required to open to provide steam to the
Shutdown  
                        RCIC turbine for operation.
Appendix R Safe Shutdown Analysis -
                                                                                                                  Attachment
Operator fails to manually initiate RCIC
system using alternate shutdown panels
(Generic Human Actions that are Risk
Important), and GE document NEDC-
330090P, Table 10-5 (Assessment of Key
Operator Action).
Detailed review completed.
MOV-131  
RCIC MOV 131 (RCIC turbine steam supply
valve) fails to open on demand. This valve is
required to open to provide steam to the
RCIC turbine for operation.  
Not included because valve has adequate design
margin to open when required.


                                              A-17
A-17
SSC/OA/OE Description                                   Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
MOV-132   RCIC MOV 132 (cooling water valve to the       Not included because valve has adequate design
Description
          RCIC lube oil cooler) fails to open on         margin to open when required.
Detailed Review Completed / Basis For Exclusion
          demand. This valve is required to open to
Attachment
          provide cooling water to the RCIC pump lube
MOV-132  
          oil cooler. Failure to cool the lube oil could
RCIC MOV 132 (cooling water valve to the
          result in failure of the pump/turbine.
RCIC lube oil cooler) fails to open on
MOV-15/16 RCIC MOV 15/16 (steam supply to RCIC           Detailed review completed.
demand. This valve is required to open to
          turbine) fails closed during its mission time.
provide cooling water to the RCIC pump lube
          These valves are required to close in the
oil cooler. Failure to cool the lube oil could
          event of a line break in the RCIC turbine
result in failure of the pump/turbine.
          steam supply to isolate the HELB. These
Not included because valve has adequate design
          valves are also required to remain open
margin to open when required.
          when the RCIC pump is required to operate.
MOV-15/16  
MOV-18   RCIC MOV 18 (RCIC pump suction valve           Not included because valve has adequate design
RCIC MOV 15/16 (steam supply to RCIC
          from the CST) transfers closed during its     margin to close when required.
turbine) fails closed during its mission time.
          mission time. This valve is required to
These valves are required to close in the
          automatically close when the RCIC pump
event of a line break in the RCIC turbine
          suction is transferred from the CST to the
steam supply to isolate the HELB. These
          torus. This valve must remain open while the
valves are also required to remain open
          RCIC pump is operating from the CST.
when the RCIC pump is required to operate.
MOV-21/20 RCIC MOV 21 (inboard discharge valve to       Detailed review completed.
Detailed review completed.
          the reactor vessel) fails to open on demand.
MOV-18
          Also look at MOV-20 (the normally open
RCIC MOV 18 (RCIC pump suction valve
          outboard discharge isolation valve). These
from the CST) transfers closed during its
          valves must automatically open to provide
mission time. This valve is required to
          RCIC injection flow in response to an RCIC
automatically close when the RCIC pump
          initiation signal.
suction is transferred from the CST to the
                                                                                                Attachment
torus. This valve must remain open while the
RCIC pump is operating from the CST.
Not included because valve has adequate design
margin to close when required.  
MOV-21/20  
RCIC MOV 21 (inboard discharge valve to
the reactor vessel) fails to open on demand.
Also look at MOV-20 (the normally open
outboard discharge isolation valve). These
valves must automatically open to provide
RCIC injection flow in response to an RCIC
initiation signal.  
Detailed review completed.


                                                      A-18
A-18
SSC/OA/OE           Description                                   Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
MOV-27               This is the RCIC minimum flow valve. This     Detailed review completed.
Description
                    valve is required to open at low RCIC flow to
Detailed Review Completed / Basis For Exclusion
                    protect the pump.
Attachment
MOV-39               RCIC MOV 39 (RCIC suction valve from the     Detailed review completed.
MOV-27  
                    suppression pool) fails to open on demand.
This is the RCIC minimum flow valve. This
                    This valve is required to open when the RCIC
valve is required to open at low RCIC flow to
                    pump suction is transferred from the CST to
protect the pump.
                    the torus.
Detailed review completed.
MOV-41               RCIC MOV 41 (RCIC suction valve from the     Not included because valve has adequate design
MOV-39
                    suppression pool) fails to open on demand.    margin to open when required.
RCIC MOV 39 (RCIC suction valve from the
                    This valve is required to open when the RCIC
suppression pool) fails to open on demand.
                    pump suction is transferred from the CST to
This valve is required to open when the RCIC
                    the torus.
pump suction is transferred from the CST to
MOV-64-31           MOV 64-31 (manual makeup valve from the       Failure of this valve will prevent make-up from the
the torus.
                    CST to hotwell) fails to open on              hot-well to the CST. The loss of this valve would not
Detailed review completed.
                    demand.                                      be safety significant and there are no indications that
MOV-41  
                                                                  there is low margin on for this valve
RCIC MOV 41 (RCIC suction valve from the
Offsite Transmission Offsite Transmission System: preferred       Detailed review completed.
suppression pool) fails to open on demand.
System              source of power to the 4160V safety buses;
This valve is required to open when the RCIC
                    must remain stable and available following
pump suction is transferred from the CST to
                    the trip of the VY generator.
the torus.
                                                                                                              Attachment
Not included because valve has adequate design
margin to open when required.
MOV-64-31  
MOV 64-31 (manual makeup valve from the
CST to hotwell) fails to open on
demand. 
Failure of this valve will prevent make-up from the
hot-well to the CST. The loss of this valve would not
be safety significant and there are no indications that
there is low margin on for this valve  
Offsite Transmission
System
Offsite Transmission System: preferred
source of power to the 4160V safety buses;
must remain stable and available following
the trip of the VY generator.  
Detailed review completed.


                                                              A-19
A-19
SSC/OA/OE                 Description                                     Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
Operator Bypasses the     Operator Bypasses MSIV Isolation                 The allowable action time to bypass the MSIV
Description
MSIV Isolation Interlocks Interlocks. The justification is the decrease in low-low level isolation interlocks is based upon the
Detailed Review Completed / Basis For Exclusion
                          the Allowable Action Time for the operators      time it would take to reach the RPV low-low level
Attachment
                          at the EPU level (CPPU). It is based on input    setpoint for an ATWS with no injection. Validation
Operator Bypasses the
                          from the Human Performance technical staff,      studies by the licensee have shown that the task
MSIV Isolation Interlocks
                          Appendix A of NUREG 1764 (Generic                would be accomplished for transient and LOCA
Operator Bypasses MSIV Isolation
                          Human Actions that are Risk Important), and      events within the required time. The margin to
Interlocks. The justification is the decrease in
                          GE document NEDC-330090P, Table 10-5            accomplish the task is adequate, for current and
the Allowable Action Time for the operators
                          (Assessment of Key Operator Action).            CPPU conditions, given other operational factors
at the EPU level (CPPU). It is based on input
                                                                          and steps in the EOPs which must be taken into
from the Human Performance technical staff,
                                                                          account (e.g., a high main steam line radiation
Appendix A of NUREG 1764 (Generic
                                                                          isolation signal maintaining the valves closed).
Human Actions that are Risk Important), and
                                                                          Operators train and are evaluated and tested on a
GE document NEDC-330090P, Table 10-5
                                                                          regular basis for this scenario further reducing the
(Assessment of Key Operator Action).
                                                                          likelihood that the task would not be completed in
The allowable action time to bypass the MSIV
                                                                          the time required.
low-low level isolation interlocks is based upon the
Operator Inhibits ADS     Operator action to inhibit ADS. The             The operator action to inhibit ADS is one of the first
time it would take to reach the RPV low-low level
                          justification is the decrease in the Allowable   actions taken by the operators under certain
setpoint for an ATWS with no injection. Validation
                          Action Time for the operators at the EPU         transient conditions in the EOPs. The allowable
studies by the licensee have shown that the task
                          level (CPPU). It is based on input from the     action time is based on the time to reach the vessel
would be accomplished for transient and LOCA
                          Human Performance technical staff,              level low-low set point for ATWS without injection
events within the required time. The margin to
                          Appendix A of NUREG 1764 (Generic                plus two minutes for the ADS timer. Validation
accomplish the task is adequate, for current and
                          Human Actions that are Risk Important), and      studies and operator observation in the control room
CPPU conditions, given other operational factors
                          GE document NEDC-330090P, Table 10-5            have demonstrated that the action would be
and steps in the EOPs which must be taken into
                          (Assessment of Key Operator Action).            accomplished in less than 3 minutes. The margin to
account (e.g., a high main steam line radiation
                                                                          complete the task is not significantly changed under
isolation signal maintaining the valves closed).
                                                                          CPPU conditions. Additionally, operators are trained
Operators train and are evaluated and tested on a
                                                                          and tested regularly in this EOP action step.
regular basis for this scenario further reducing the
                                                                                                                        Attachment
likelihood that the task would not be completed in
the time required.  
Operator Inhibits ADS
Operator action to inhibit ADS. The
justification is the decrease in the Allowable
Action Time for the operators at the EPU
level (CPPU). It is based on input from the
Human Performance technical staff,
Appendix A of NUREG 1764 (Generic
Human Actions that are Risk Important), and
GE document NEDC-330090P, Table 10-5
(Assessment of Key Operator Action).
The operator action to inhibit ADS is one of the first
actions taken by the operators under certain
transient conditions in the EOPs. The allowable
action time is based on the time to reach the vessel
level low-low set point for ATWS without injection
plus two minutes for the ADS timer. Validation
studies and operator observation in the control room
have demonstrated that the action would be
accomplished in less than 3 minutes. The margin to
complete the task is not significantly changed under
CPPU conditions. Additionally, operators are trained
and tested regularly in this EOP action step.  


                                                          A-20
A-20
SSC/OA/OE           Description                                     Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
Passive Failure of   Review effect of increased feedwater flow on     Detailed review completed.
Description
Feedwater Piping    flow-accelerated corrosion rates following the
Detailed Review Completed / Basis For Exclusion
                    power uprate.
Attachment
PB IR 2002-011 (HPCI Peach Bottom Finding for IR 50-277/2002-         Detailed review completed.
Passive Failure of
Functional Issue)    011 (8/5/02) - Finding Related to High
Feedwater Piping
                    Pressure Coolant Injection Function (may
Review effect of increased feedwater flow on
                    apply to RCIC system at VY).
flow-accelerated corrosion rates following the
PCV-23               RCIC PCV 23 (RCIC air operated lube oil         Detailed review completed.
power uprate.
                    temperature control valve) fails to open on
Detailed review completed.
                    demand. This valve uses instrument air to
PB IR 2002-011 (HPCI
                    control its setpoint and fails fully open on a
Functional Issue)
                    loss of instrument air. This valve is required
Peach Bottom Finding for IR 50-277/2002-
                    to provide cooling water, at the correct
011 (8/5/02) - Finding Related to High
                    pressure, to the RCIC pump lube oil cooler
Pressure Coolant Injection Function (may
                    when the RCIC pump is operating.
apply to RCIC system at VY).
PS-67               Spurious RCIC low suction pressure trip         Not included because there is significant margin in
Detailed review completed.
                    signal. This instrument will cause the RCIC     the setpoint to prevent a spurious trip.
PCV-23  
                    pump to trip in the event of low pump suction
RCIC PCV 23 (RCIC air operated lube oil
                    pressure. Spurious trips will result in a loss
temperature control valve) fails to open on
                    of RCIC flow.
demand. This valve uses instrument air to
PSH-72A/B           Spurious RCIC turbine exhaust high pressure Not included because there is significant margin in
control its setpoint and fails fully open on a
                    trip. This instrument will trip the RCIC pump   the setpoint to prevent a spurious trip.
loss of instrument air. This valve is required
                    in the event of high pressure in the exhaust
to provide cooling water, at the correct
                    steam line. Spurious trips will result in a loss
pressure, to the RCIC pump lube oil cooler
                    of RCIC flow.
when the RCIC pump is operating.
                                                                                                                Attachment
Detailed review completed.
PS-67  
Spurious RCIC low suction pressure trip
signal. This instrument will cause the RCIC
pump to trip in the event of low pump suction
pressure. Spurious trips will result in a loss
of RCIC flow.
Not included because there is significant margin in
the setpoint to prevent a spurious trip.
PSH-72A/B
Spurious RCIC turbine exhaust high pressure
trip. This instrument will trip the RCIC pump
in the event of high pressure in the exhaust
steam line. Spurious trips will result in a loss
of RCIC flow.  
Not included because there is significant margin in
the setpoint to prevent a spurious trip.


                                              A-21
A-21
SSC/OA/OE Description                                   Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
PT-59/60 RCIC pump discharge pressure. This             Not included because there is significant margin in
Description
          instrument is associated with the RCIC        the setpoint.
Detailed Review Completed / Basis For Exclusion
          turbine control logic.
Attachment
PT-68     Spurious low steam line pressure signal.       Not included because the pressure switch setpoint
PT-59/60  
          This instrument will isolate steam flow to the has significant margin to prevent a spurious pump
RCIC pump discharge pressure. This
          RCIC turbine in the event of low steam         trip.
instrument is associated with the RCIC
          supply pressure, indicating a steam line
turbine control logic.
          break. Spurious isolation would result in a
Not included because there is significant margin in
          loss of RCIC flow.
the setpoint.
PT-70     Spurious RCIC trip on high turbine exhaust     Not included because there is significant margin in
PT-68  
          pressure signal. Component ID is PT-70.       the setpoint and operating pressure to prevent a
Spurious low steam line pressure signal.  
          Include exhaust rupture disks S3 and S4.      spurious trip.
This instrument will isolate steam flow to the
          This instrument will trip the RCIC pump in the
RCIC turbine in the event of low steam
          event of high pressure in the exhaust steam
supply pressure, indicating a steam line
          line. Spurious trips will result in a loss of
break. Spurious isolation would result in a
          RCIC flow.
loss of RCIC flow.
                                                                                                    Attachment
Not included because the pressure switch setpoint
has significant margin to prevent a spurious pump
trip.  
PT-70  
Spurious RCIC trip on high turbine exhaust
pressure signal. Component ID is PT-70.
Include exhaust rupture disks S3 and S4.  
This instrument will trip the RCIC pump in the
event of high pressure in the exhaust steam
line. Spurious trips will result in a loss of
RCIC flow.  
Not included because there is significant margin in
the setpoint and operating pressure to prevent a
spurious trip.


                                                        A-22
A-22
SSC/OA/OE               Description                                 Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
Manual operation of MOV Operator fails to manually open MOV 64-31   The operator action to manually open valve MOV
Description
64-31                  (used to manually transfer makeup from the  64-31, Hotwell Emergency Makeup Valve, is
Detailed Review Completed / Basis For Exclusion
                        CST to the condenser).                      performed in the main control room. The action is
Attachment
                                                                    required when turbine bypass is not available
Manual operation of MOV
                                                                    (during an MSIV closure event). In that case
64-31
                                                                    automatic makeup to the hotwell from the
Operator fails to manually open MOV 64-31
                                                                    Condensate Storage Tank (CST) may not be
(used to manually transfer makeup from the
                                                                    sufficient to keep up with reactor vessel makeup
CST to the condenser).
                                                                    requirements (feedwater pumps providing vessel
The operator action to manually open valve MOV
                                                                    level makeup). Validation studies and operator
64-31, Hotwell Emergency Makeup Valve, is
                                                                    observations have estimated a 1 minute time to
performed in the main control room. The action is
                                                                    manipulate the valve from the control room. If the
required when turbine bypass is not available
                                                                    valve is required to be opened from the field the
(during an MSIV closure event). In that case
                                                                    estimates are less than 15 minutes, however, other
automatic makeup to the hotwell from the
                                                                    EOP mitigation strategies such as use of low
Condensate Storage Tank (CST) may not be
                                                                    pressure ECCS pumps, would assure core coverage
sufficient to keep up with reactor vessel makeup
                                                                    if the valve could not be opened.
requirements (feedwater pumps providing vessel
RB/Torus Vacuum         Reactor Building to Torus vacuum breakers.  Detailed review completed.
level makeup). Validation studies and operator
Breakers                The vacuum breakers are required to open to
observations have estimated a 1 minute time to
                        prevent a vacuum in the containment. These
manipulate the valve from the control room. If the
                        also must remain closed to ensure
valve is required to be opened from the field the
                        containment integrity and to prevent loss of
estimates are less than 15 minutes, however, other
                        overpressure for ECCS NPSH.
EOP mitigation strategies such as use of low
RCIC Pump P-47-1A and   RCIC pump P-47-1A fails to start on         Detailed review completed.
pressure ECCS pumps, would assure core coverage
Turbine TU-2-1-A        demand. This sample includes the turbine
if the valve could not be opened.  
                        driven RCIC pump, the governor valve, and
RB/Torus Vacuum
                        trip throttle valve.
Breakers
                                                                                                                Attachment
Reactor Building to Torus vacuum breakers.
The vacuum breakers are required to open to
prevent a vacuum in the containment. These
also must remain closed to ensure
containment integrity and to prevent loss of
overpressure for ECCS NPSH.
Detailed review completed.
RCIC Pump P-47-1A and
Turbine TU-2-1-A
RCIC pump P-47-1A fails to start on
demand. This sample includes the turbine
driven RCIC pump, the governor valve, and
trip throttle valve.  
Detailed review completed.


                                                      A-23
A-23
SSC/OA/OE           Description                                   Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
Reactor Feed Pump   Failure of the feedwater pump will fail to   Detailed review completed.
Description
                    deliver flow required for normal operation or
Detailed Review Completed / Basis For Exclusion
                    to mitigate an accident.
Attachment
                    Prior to EPU 2 of three feedwater pumps are
Reactor Feed Pump  
                    required to support the Feedwater system
Failure of the feedwater pump will fail to
                    requirements. As such there is a 50% spare
deliver flow required for normal operation or
                    capability. For EPU three pumps are required
to mitigate an accident.  
                    to operated due to the increase requirements
Prior to EPU 2 of three feedwater pumps are
                    of feedwater flow.
required to support the Feedwater system
RHR Pump           Review RHR pump NPSH calculation,             Detailed review completed.
requirements. As such there is a 50% spare
                    associated suction strainers, bubble
capability. For EPU three pumps are required
                    ingestion, and torus vortexing issues.
to operated due to the increase requirements
Safety Valve (New) Addition of third main steam safety valve for Detailed review completed.
of feedwater flow.
                    power uprate. Failure of SSV to open and
Detailed review completed.
                    relieve pressure during transients or
RHR Pump
                    small/medium break LOCA.
Review RHR pump NPSH calculation,
SLC Initiation with Operator fails to initiate SLC with the main Detailed review completed.
associated suction strainers, bubble
Condenser Failed    condenser failed. The justification is the
ingestion, and torus vortexing issues.
                    decrease in the Allowable Action Time for the
Detailed review completed.
                    operators at the EPU level (CPPU). It is
Safety Valve (New)
                    based on input from the Human Performance
Addition of third main steam safety valve for
                    technical staff, Appendix A of NUREG 1764
power uprate. Failure of SSV to open and
                    (Generic Human Actions that are Risk
relieve pressure during transients or
                    Important), and GE document
small/medium break LOCA.
                    NEDC-330090P, Table 10-5 (Assessment of
Detailed review completed.
                    Key Operator Action).
SLC Initiation with
                                                                                                          Attachment
Condenser Failed
Operator fails to initiate SLC with the main
condenser failed. The justification is the
decrease in the Allowable Action Time for the
operators at the EPU level (CPPU). It is
based on input from the Human Performance
technical staff, Appendix A of NUREG 1764
(Generic Human Actions that are Risk
Important), and GE document
NEDC-330090P, Table 10-5 (Assessment of
Key Operator Action).  
Detailed review completed.


                                                            A-24
A-24
SSC/OA/OE               Description                                   Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
Spurious High Steam Line Spurious RCIC trip on high steam line space   Not included because there is significant margin
Description
Space Temperature Trip  temperature (instrument TS 79 through 82).     between the setpoint and the operating temperature
Detailed Review Completed / Basis For Exclusion
                        These instruments would result in isolation of to prevent a spurious trip.
Attachment
                        the steam flow to the RCIC turbine in the
Spurious High Steam Line
                        event of a steam line break. A spurious trip
Space Temperature Trip
                        would result in loss of RCIC flow.
Spurious RCIC trip on high steam line space
Spurious High Steam     Spurious RCIC trip on a high steam tunnel     Not included because there is significant margin
temperature (instrument TS 79 through 82).
Tunnel Temperature Trip  temperature trip signal. These instruments     between the setpoint and the operating temperature
These instruments would result in isolation of
                        would result in isolation of the steam flow to to prevent a spurious trip.
the steam flow to the RCIC turbine in the
                        the RCIC turbine in the event of a steam line
event of a steam line break. A spurious trip
                        break. A spurious trip would result in loss of
would result in loss of RCIC flow.
                        RCIC flow.
Not included because there is significant margin
Spurious Reactor High   Spurious high reactor water level signal (trip Excluded because HPCI and the RFP trip signals
between the setpoint and the operating temperature
Level Trip              could affect both the RCIC pump or feed       are provided by different instruments and the
to prevent a spurious trip.  
                        water pump). These instruments would result   probability of a simultaneous failure of these
Spurious High Steam
                        in tripping the RCIC turbine in the event of   instruments is extremely low.
Tunnel Temperature Trip
                        high RPV level. A spurious trip would result
Spurious RCIC trip on a high steam tunnel
                        in loss of RCIC flow.
temperature trip signal. These instruments
SR-26                   SR-26 (RCIC supply to lube oil cooler relief   Detailed review completed.
would result in isolation of the steam flow to
                        valve) fails open. This component is
the RCIC turbine in the event of a steam line
                        designed to protect the RCIC lube oil cooler
break. A spurious trip would result in loss of
                        and may be important on a loss of IA when
RCIC flow.
                        the flow control valve fully opens (based on
Not included because there is significant margin
                        interview with RCIC System Manager).
between the setpoint and the operating temperature
SRVs                     Safety relief valves allow the reactor to be   Detailed review completed.
to prevent a spurious trip.  
                        depressurized.
Spurious Reactor High
                                                                                                                    Attachment
Level Trip
Spurious high reactor water level signal (trip
could affect both the RCIC pump or feed
water pump). These instruments would result
in tripping the RCIC turbine in the event of
high RPV level. A spurious trip would result
in loss of RCIC flow.
Excluded because HPCI and the RFP trip signals
are provided by different instruments and the
probability of a simultaneous failure of these
instruments is extremely low.  
SR-26
SR-26 (RCIC supply to lube oil cooler relief
valve) fails open. This component is
designed to protect the RCIC lube oil cooler
and may be important on a loss of IA when
the flow control valve fully opens (based on
interview with RCIC System Manager).
Detailed review completed.
SRVs  
Safety relief valves allow the reactor to be
depressurized.
Detailed review completed.


                                                  A-25
A-25
SSC/OA/OE       Description                               Detailed Review Completed / Basis For Exclusion
SSC/OA/OE
Vernon Tie Line Operator monitoring of Vernon tie line to Detailed review completed.
Description
                ensure availability as a station blackout
Detailed Review Completed / Basis For Exclusion
                source.
Attachment
                                                                                                  Attachment
Vernon Tie Line  
Operator monitoring of Vernon tie line to
ensure availability as a station blackout
source.
Detailed review completed.


                                    ATTACHMENT B
ATTACHMENT B
                            SUPPLEMENTAL INFORMATION
                              KEY POINTS OF CONTACT
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee Personnel
Licensee Personnel
D. Amidon         EFIN Engineer
D. Amidon
M. Arnett         Systems Engineer - Electrical
EFIN Engineer
K. Bronson         General Manager
M. Arnett
F. Burger         Corrective Action
Systems Engineer - Electrical
J. Callaghan       Design Engineering Manager
K. Bronson
M. Castronova     Design EFIN Supervisor
General Manager
J. Devincentis     Licensing Manager
F. Burger
J. Dreyfuss       Director of Engineering
Corrective Action  
E. Duda           Power Uprate Engineer
J. Callaghan
N. Fales           Systems Engineer - FW and Condensate
Design Engineering Manager
K. Farabaugh       Systems Engineering Supervisor
M. Castronova
J. Fitzpatrick     Design Mechanical/Structural Engineering - FAC
Design EFIN Supervisor
M. Flynn           Design Engineer - Electrical
J. Devincentis
D. Girroir         Systems Engineering Supervisor
Licensing Manager
S. Goodwin         Design Mechanical/Structural Engineering Supervisor
J. Dreyfuss
A. Graves         Design Admin Assistant
Director of Engineering
C. Hansen         Design Engineer - Components
E. Duda
A. Haumann         Design Engineer - Electrical
Power Uprate Engineer  
B. Hobbs           Power Uprate - Engineering Supervisor
N. Fales
M. Janus           Design Engineer - Electrical
Systems Engineer - FW and Condensate
P. Johnson         Design Engineer - Electrical
K. Farabaugh
J. Kritzer         Operations/Reactor Engineer
Systems Engineering Supervisor
M. Lefrancois     Systems Engineering Supervisor
J. Fitzpatrick
P. Longo           Design Engineer - Components
Design Mechanical/Structural Engineering - FAC  
L. Lukens         Systems Engineering Supervisor
M. Flynn
M. McKenney       Maintenance Support Engineering
Design Engineer - Electrical
J. Melvin         Systems Engineer - SLC
D. Girroir
M. Metell         Entergy-Vermont Yankee Response Team Leader
Systems Engineering Supervisor  
B. Naeck           Systems Engineer - RCIC
S. Goodwin
C. Nichols         Power Uprate Engineering Manager
Design Mechanical/Structural Engineering Supervisor
T. O'Connor       Design Engineer - Mechanical/Structural
A. Graves
M. Palionis       PRA Engineer
Design Admin Assistant
P. Perez           Design Engineer - Fluid Systems
C. Hansen
P. Rainey         Design Engineer - Fluid Systems
Design Engineer - Components  
A. Robertshaw     Design Engineer - Fluid Systems
A. Haumann
J. Rogers         Design Fluid Systems Engineering Supervisor
Design Engineer - Electrical
R. Rusin           Design Engineering Supervisor - Components
B. Hobbs
B. Slifer         Power Uprate Engineer
Power Uprate - Engineering Supervisor  
J. Stasolla       Systems Engineer - Electrical
M. Janus
Design Engineer - Electrical
P. Johnson
Design Engineer - Electrical
J. Kritzer
Operations/Reactor Engineer
M. Lefrancois
Systems Engineering Supervisor  
P. Longo  
Design Engineer - Components  
L. Lukens  
Systems Engineering Supervisor
M. McKenney
Maintenance Support Engineering
J. Melvin
Systems Engineer - SLC  
M. Metell
Entergy-Vermont Yankee Response Team Leader
B. Naeck  
Systems Engineer - RCIC  
C. Nichols
Power Uprate Engineering Manager  
T. O'Connor
Design Engineer - Mechanical/Structural  
M. Palionis
PRA Engineer
P. Perez  
Design Engineer - Fluid Systems
P. Rainey
Design Engineer - Fluid Systems
A. Robertshaw
Design Engineer - Fluid Systems
J. Rogers
Design Fluid Systems Engineering Supervisor
R. Rusin
Design Engineering Supervisor - Components
B. Slifer
Power Uprate Engineer  
J. Stasolla
Systems Engineer - Electrical


                                          B-2
B-2
J. Taylor         Corrective Action
J. Taylor  
J. Thayer         Site Vice President
Corrective Action
G. Thomas         Power Uprate - Contractor Interface
J. Thayer  
J. Twarog         Operations Shift Engineering Supervisor
Site Vice President
R. Vibert         Design Electrical Engineering Supervisor
G. Thomas
C. Wamser         Operations Manager
Power Uprate - Contractor Interface
R. Wanczyk       Director of Nuclear Safety
J. Twarog
G. Wierzbowski   Systems Engineering Manager
Operations Shift Engineering Supervisor
A. Wonderlick     Systems Engineer - Electrical
R. Vibert
Design Electrical Engineering Supervisor
C. Wamser
Operations Manager
R. Wanczyk
Director of Nuclear Safety
G. Wierzbowski  
Systems Engineering Manager
A. Wonderlick
Systems Engineer - Electrical
Other
Other
W. Farnsworth             Training Coordinator - REMVEC / National Grid
W. Farnsworth
D. Goodwin       Operations Supervisor US-GEN
Training Coordinator - REMVEC / National Grid  
W. Houston       Manager of Transmission - REMVEC / National Grid
D. Goodwin
W. Sherman       Vermont State Nuclear Engineer
Operations Supervisor US-GEN  
                LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
W. Houston
Manager of Transmission - REMVEC / National Grid  
W. Sherman
Vermont State Nuclear Engineer
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
Opened
Opened
05000271/2004008-04             URI           Ungrounded 480 VAC Electrical System.
05000271/2004008-04
                                                (Section 4OA5.2.1.1.b.3)
URI
Ungrounded 480 VAC Electrical System.
(Section 4OA5.2.1.1.b.3)
Opened and Closed
Opened and Closed
05000271/2004008-01             NCV           Availability of Power from the Vernon
05000271/2004008-01
                                                Station. (Section 4AO5.2.1.1.(b).1)
NCV
05000271/2004008-02             NCV           Procedures for Assessing Off-site Power
Availability of Power from the Vernon
                                                Operability. (Section 4AO5.2.1.1.(b).2)
Station. (Section 4AO5.2.1.1.(b).1)
05000271/2004008-03             NCV           Degraded Relay Setpoint Calculations.
05000271/2004008-02
                                                (Section 4AO5.2.1.1.(b).3)
NCV
05000271/2004008-05             NCV           Cooling Water Supply Portion of RCIC Not
Procedures for Assessing Off-site Power
                                                Installed per Design Basis.
Operability. (Section 4AO5.2.1.1.(b).2)
                                                (Section 4AO5.2.1.2.(b).1)
05000271/2004008-03
05000271/2004008-06             NCV           Failure to Correct Non-Conforming RCIC
NCV
                                                Pressure Control Valve. (Section
Degraded Relay Setpoint Calculations.
                                                4A05.2.1.2(b).2)
(Section 4AO5.2.1.1.(b).3)
05000271/2004008-05
NCV
Cooling Water Supply Portion of RCIC Not
Installed per Design Basis.  
(Section 4AO5.2.1.2.(b).1)
05000271/2004008-06
NCV
Failure to Correct Non-Conforming RCIC
Pressure Control Valve. (Section
4A05.2.1.2(b).2)


                                            B-3
B-3
05000271/2004008-07                 NCV         Failure to Implement Adequate Design
05000271/2004008-07
                                                Control for Condensate Storage Tank
NCV
                                                Temperature. (Section 4AO5.2.1.7.(b))
Failure to Implement Adequate Design
05000271/2004008-08                 NCV         Failure to Revise Safe Shutdown Capability
Control for Condensate Storage Tank
                                                Analysis Report. (Section 4AO5.2.2.(b))
Temperature. (Section 4AO5.2.1.7.(b))
05000271/2004008-09                 NCV         Failure to Establish Adequate MOV Periodic
05000271/2004008-08
                                                Test Program. (Section 4AO5.2.3.(b))
NCV
                            LIST OF DOCUMENTS REVIEWED
Failure to Revise Safe Shutdown Capability
Analysis Report. (Section 4AO5.2.2.(b))
05000271/2004008-09
NCV
Failure to Establish Adequate MOV Periodic
Test Program. (Section 4AO5.2.3.(b))
LIST OF DOCUMENTS REVIEWED
Procedures and Tests
Procedures and Tests
Emergency Operating Procedures
Emergency Operating Procedures
EOP-1 - RPV Control, Rev. 2
EOP-1 - RPV Control, Rev. 2  
EOP-2 - ATWS, Rev. 4
EOP-2 - ATWS, Rev. 4
EOP-3 - Primary Containment Control, Rev. 3
EOP-3 - Primary Containment Control, Rev. 3
EOP-5 - RPV-ED, Rev. 3
EOP-5 - RPV-ED, Rev. 3
Operating Procedures
Operating Procedures
OP-0023, Installation and Testing of Cable and Conduit, Rev. 8
OP-0023, Installation and Testing of Cable and Conduit, Rev. 8
OP-2113, Main and Auxiliary Steam, Rev. 20
OP-2113, Main and Auxiliary Steam, Rev. 20  
OP-2114, Operation of the Standby Liquid Control System, Rev. 22
OP-2114, Operation of the Standby Liquid Control System, Rev. 22
OP-2115, Primary Containment, Rev. 44
OP-2115, Primary Containment, Rev. 44
Line 2,178: Line 2,739:
OP-2119, Nitrogen Supply System, Rev. 13
OP-2119, Nitrogen Supply System, Rev. 13
OP-2121, Reactor Core Isolation Cooling System (RCIC), Rev. 29
OP-2121, Reactor Core Isolation Cooling System (RCIC), Rev. 29
OP-2124, Residual Heat Removal System, Rev. 52
OP-2124, Residual Heat Removal System, Rev. 52  
OP-2140, 345 KV Electrical System, Rev. 25
OP-2140, 345 KV Electrical System, Rev. 25
OP-2141, 115KV Switchyard, Rev. 17
OP-2141, 115KV Switchyard, Rev. 17
OP-2142, 4KV Electrical System, Rev. 21
OP-2142, 4KV Electrical System, Rev. 21  
OP-2145, Normal 125 VDC Operation, Rev. 24
OP-2145, Normal 125 VDC Operation, Rev. 24
OP-2149, Normal 24 VDC Operation, Rev. 7
OP-2149, Normal 24 VDC Operation, Rev. 7
Line 2,187: Line 2,748:
OP-2172, Feedwater System, Rev. 23
OP-2172, Feedwater System, Rev. 23
OP-3126, Shutdown Using Alternative Methods, Rev. 16
OP-3126, Shutdown Using Alternative Methods, Rev. 16
OP-4255, Calibration of 4kV Bus Degraded Grid Undervoltage Relays, Rev. 11
OP-4255, Calibration of 4kV Bus Degraded Grid Undervoltage Relays, Rev. 11  
OP 5217, MOV Motor Control Center (MC2) Testing, Rev. 2
OP 5217, MOV Motor Control Center (MC2) Testing, Rev. 2
OP 5287, Evaluation of MOV Motor Control Center (MC2) Testing, Rev. 2
OP 5287, Evaluation of MOV Motor Control Center (MC2) Testing, Rev. 2
Line 2,193: Line 2,754:
OP 5220, Limitorque Operator PM, Rev. 25
OP 5220, Limitorque Operator PM, Rev. 25


                                              B-4
B-4
Operational Transient
Operational Transient
OT-3113, Reactor Low Level, Rev. 13
OT-3113, Reactor Low Level, Rev. 13
OT-3114, Reactor High Level, Rev. 13
OT-3114, Reactor High Level, Rev. 13  
OT-3115, Rx Low Pressure, Rev. 8
OT-3115, Rx Low Pressure, Rev. 8  
OT-3116, Rx High Pressure, Rev. 8
OT-3116, Rx High Pressure, Rev. 8
OT-3121, Inadvertent Opening of a Relief Valve, Rev. 13
OT-3121, Inadvertent Opening of a Relief Valve, Rev. 13
Line 2,207: Line 2,768:
AP 6038, Component Level Review of Vermont Yankee Motor-Operated Valves (MOVs), Rev.1
AP 6038, Component Level Review of Vermont Yankee Motor-Operated Valves (MOVs), Rev.1
AP 6039, Electrical Design Basis Review of Vermont Yankee Motor-Operated Valves (MOVs),
AP 6039, Electrical Design Basis Review of Vermont Yankee Motor-Operated Valves (MOVs),
        Original Issue
Original Issue
AP 6037, System and Functional Design Basis Review of Vermont Yankee Motor-Operated
AP 6037, System and Functional Design Basis Review of Vermont Yankee Motor-Operated
      Valves (MOVs), Original Issue
Valves (MOVs), Original Issue
AP 6040, Vermont Yankee Motor-Operated Valve Electrical Configuration, Original Issue
AP 6040, Vermont Yankee Motor-Operated Valve Electrical Configuration, Original Issue
AP 6041, Vermont Yankee Engineering Evaluations of MOV Diagnostic Testing and Feedback
AP 6041, Vermont Yankee Engineering Evaluations of MOV Diagnostic Testing and Feedback
      of Results into MOV Component Calculations, Rev. 1
of Results into MOV Component Calculations, Rev. 1
PP 7004, Vermont Yankee Nuclear Power Station Motor Operated Valve Program, Rev. 1
PP 7004, Vermont Yankee Nuclear Power Station Motor Operated Valve Program, Rev. 1
PP 7005, Periodic Verification of Motor Operated Valves, Original Issue
PP 7005, Periodic Verification of Motor Operated Valves, Original Issue
Line 2,221: Line 2,782:
RCIC hydraulic calculations (VYE-1064 and VYE-1423)
RCIC hydraulic calculations (VYE-1064 and VYE-1423)
Structural Integrity Inc. Report SIR-04-020 Rev 0, File VY-10Q-401, Updated Stress and
Structural Integrity Inc. Report SIR-04-020 Rev 0, File VY-10Q-401, Updated Stress and
      Fatigue Analysis for the Vermont Yankee Feedwater Nozzles, March 2004
Fatigue Analysis for the Vermont Yankee Feedwater Nozzles, March 2004
Structural Integrity Inc. File VY10Q-302 Loads and Transient Definitions, Rev. 0
Structural Integrity Inc. File VY10Q-302 Loads and Transient Definitions, Rev. 0
Structural Integrity Inc. Calculation Package VY-10Q-303, Uprated Feedwater Nozzle Stress
Structural Integrity Inc. Calculation Package VY-10Q-303, Uprated Feedwater Nozzle Stress
      and Fatigue Analysis, Rev. 0
and Fatigue Analysis, Rev. 0
Structural Integrity Inc. Calculation VY-10Q-301 Feedwater Nozzle Finite Element Model and
Structural Integrity Inc. Calculation VY-10Q-301 Feedwater Nozzle Finite Element Model and
      Heat Transfer Coefficients, Rev. 0
Heat Transfer Coefficients, Rev. 0
Vendor Calculation DC-A34600-03, RHR and CS Suction Strainer Bubble Ingestion, Rev. 0
Vendor Calculation DC-A34600-03, RHR and CS Suction Strainer Bubble Ingestion, Rev. 0  
Vermont Yankee Calculations
Vermont Yankee Calculations
VYC-415, Appendix R RCIC, HPCI, and ECCS Room Cooling, Rev. 0
VYC-415, Appendix R RCIC, HPCI, and ECCS Room Cooling, Rev. 0
Line 2,233: Line 2,794:
VYC-706, Condensate Storage Tank Level (RCIC) Monitoring, Rev. 1, CCN 01 and 02
VYC-706, Condensate Storage Tank Level (RCIC) Monitoring, Rev. 1, CCN 01 and 02


                                              B-5
B-5
VYC-709, RCIC System Flow Control and Indication Loop Accuracy, Rev. 1
VYC-709, RCIC System Flow Control and Indication Loop Accuracy, Rev. 1
VYC-715, Degraded Bus Voltage Monitoring loop Accuracy, Rev. 1
VYC-715, Degraded Bus Voltage Monitoring loop Accuracy, Rev. 1
VYC-808, Core Spray and RHR Pump Net Positive Suction Head Margin Following a LOCA
VYC-808, Core Spray and RHR Pump Net Positive Suction Head Margin Following a LOCA
      with Fibrous Debris on the Intake Strainers, Rev. 0, and CCN 4, 5 and 6 and its
with Fibrous Debris on the Intake Strainers, Rev. 0, and CCN 4, 5 and 6 and its
      supporting references
supporting references
VYC-830, Voltage Drop Calculations for VY Distribution Panels DC-1 and DC-2, Rev. 9
VYC-830, Voltage Drop Calculations for VY Distribution Panels DC-1 and DC-2, Rev. 9
      and CCN No. 5.
and CCN No. 5.
VYC-1005, Crack Growth Calculation for the Vermont Yankee FW Nozzles, Rev. 2
VYC-1005, Crack Growth Calculation for the Vermont Yankee FW Nozzles, Rev. 2
VYC-1053, Motor Operated Valve (MOV) Voltage Analysis, Rev. 8 and CCN 02
VYC-1053, Motor Operated Valve (MOV) Voltage Analysis, Rev. 8 and CCN 02  
VYC-1088, Vermont Yankee 4160/480 Volt Short Circuit/ Voltage Study, Rev. 3
VYC-1088, Vermont Yankee 4160/480 Volt Short Circuit/ Voltage Study, Rev. 3
VYC-1293, System Level Review of Reactor Core Isolation Cooling MOVs for GL 89-10,
VYC-1293, System Level Review of Reactor Core Isolation Cooling MOVs for GL 89-10,
        Rev. 3
Rev. 3  
VYC-1347, Main Steam Tunnel Heatup Calculation, Rev. 0
VYC-1347, Main Steam Tunnel Heatup Calculation, Rev. 0
VYC-1349, 125V Direct Current DC Voltage Drop Study, Rev. 2 and CCN 05
VYC-1349, 125V Direct Current DC Voltage Drop Study, Rev. 2 and CCN 05
VYC-1512, Station Blackout Voltage Drop and Short Circuit Study, Rev. 2
VYC-1512, Station Blackout Voltage Drop and Short Circuit Study, Rev. 2
VYC-1700, 4.16kV Bus Protective Relay Settings Verification, Rev. 1
VYC-1700, 4.16kV Bus Protective Relay Settings Verification, Rev. 1
VYC-1726, Reactor Core Isolation Cooling Pump Test Acceptance Values, Rev. 1 and
VYC-1726, Reactor Core Isolation Cooling Pump Test Acceptance Values, Rev. 1 and
      CCN 01
CCN 01
VYC-1816, RCIC Pump Net Positive Suction Head (NPSH), Rev. 0 and CCN 01
VYC-1816, RCIC Pump Net Positive Suction Head (NPSH), Rev. 0 and CCN 01
VYC-1825, Analysis of Suppression Pool Temperature for Relief Valve Discharge Transients,
VYC-1825, Analysis of Suppression Pool Temperature for Relief Valve Discharge Transients,
      Rev. 0 and CCN 1
Rev. 0 and CCN 1
VYC-1844, HPCI and RCIC Vortex Height, Rev. 1
VYC-1844, HPCI and RCIC Vortex Height, Rev. 1
VYC-1857, Fast and Residual Voltage Bus Transfer Analysis, Rev. I
VYC-1857, Fast and Residual Voltage Bus Transfer Analysis, Rev. I
VYC-1920, RHR and CS Suction Strainer Vortex/Minimum Submergence, Rev. 0 (DE&S
VYC-1920, RHR and CS Suction Strainer Vortex/Minimum Submergence, Rev. 0 (DE&S
      Calculation DC-A34600-02 Rev. 0)
Calculation DC-A34600-02 Rev. 0)
VYC-1924, Vermont Yankee ECCS Suction Strainer Head Loss Performance
VYC-1924, Vermont Yankee ECCS Suction Strainer Head Loss Performance  
      Assessment, RHR and CS Debris Head Loss Calculations, Rev. 0 (DE&S Calc
Assessment, RHR and CS Debris Head Loss Calculations, Rev. 0 (DE&S Calc
      DC-A32600-006 Rev. 0)
DC-A32600-006 Rev. 0)  
VYC-1950, Hydrodynamic Mass and Acceleration Drag Volume of Vermont Yankee ECCS
VYC-1950, Hydrodynamic Mass and Acceleration Drag Volume of Vermont Yankee ECCS
      Strainers, Rev. 0
Strainers, Rev. 0
VYC-1959, Analysis of Tests for Investigation (of) the Effects of Coatings Debris on
VYC-1959, Analysis of Tests for Investigation (of) the Effects of Coatings Debris on
      ECCS Strainer Performance for Vermont Yankee, Rev. 1 (DE&S Report ITS/VY-
ECCS Strainer Performance for Vermont Yankee, Rev. 1 (DE&S Report ITS/VY-
      98-01, Rev.1)
98-01, Rev.1)
VYC-2153, 125 VDC Battery A-1 Electrical System Calculation, Rev. 0 and CCN 03
VYC-2153, 125 VDC Battery A-1 Electrical System Calculation, Rev. 0 and CCN 03
VYC-2154, 125 VDC Battery B-1 Electrical System Calculation, Rev. 0
VYC-2154, 125 VDC Battery B-1 Electrical System Calculation, Rev. 0  
VYC-2314, Minimum Containment Overpressure for Non-Loca Events, Rev. 0 and
VYC-2314, Minimum Containment Overpressure for Non-Loca Events, Rev. 0 and  
      CCN 01 and 02
CCN 01 and 02
VYPC 98-010, Component Level Review of Reactor Core Isolation Cooling (RCIC) MOVs for
VYPC 98-010, Component Level Review of Reactor Core Isolation Cooling (RCIC) MOVs for
      GL 89-10, Rev. 2
GL 89-10, Rev. 2
Studies and Evaluations
Studies and Evaluations  
Franklin Institute Technical Report F-C2653-01 Design and Stress Analysis of the Vermont
Franklin Institute Technical Report F-C2653-01 Design and Stress Analysis of the Vermont
      Yankee NPS Clean-up / Feedwater Recombination Tee
Yankee NPS Clean-up / Feedwater Recombination Tee
General Electric (GE) Topical Report T0900
General Electric (GE) Topical Report T0900  
GE-NE-0000-0009-9951-01 Rev 1, Task 0302 Reactor Vessel Integrity Stress Analysis
GE-NE-0000-0009-9951-01 Rev 1, Task 0302 Reactor Vessel Integrity Stress Analysis    
      (Excludes the radius of the forging)
(Excludes the radius of the forging)


                                          B-6
B-6
GE-NEDC-330090P, Assessment of Key Operator Actions, Table 10-5
GE-NEDC-330090P, Assessment of Key Operator Actions, Table 10-5
Strainer Head Loss Performance Assessment, RHR and CS Debris Head Loss, Rev 0.
Strainer Head Loss Performance Assessment, RHR and CS Debris Head Loss, Rev 0.  
VYNPS:EPU T0400: DBA-LOCA for Long Term NPSH Evaluation
VYNPS:EPU T0400: DBA-LOCA for Long Term NPSH Evaluation
Yankee Uprate System Impact Study, dated November 11, 2003
Yankee Uprate System Impact Study, dated November 11, 2003


                                          B-7
B-7
Condition Reports
Condition Reports
CR-96-117           CR-00-1575           CR-02-1860             CR-04-448
CR-96-117
CR-96-129           CR-00-1596           CR-02-2193             CR-04-815
CR-00-1575
CR-96-136           CR-01-880           CR-02-2194             CR-04-1234
CR-02-1860
CR-98-467           CR-01-889           CR-02-2716             CR-04-1484
CR-04-448
CR-98-1171         CR-01-890           CR-02-2733             CR-04-1522
CR-96-129
CR-98-2066         CR-01-1007           CR-02-2942             CR-04-2600
CR-00-1596
CR-99-175           CR-01-1232           CR-03-441               CR-04-2621
CR-02-2193
CR-99-618           CR-01-1340           CR-03-962               CR-04-2623
CR-04-815
CR-00-94           CR-01-1834           CR-03-1491             CR-04-2644
CR-96-136  
CR-00-306           CR-01-2084           CR-03-1855             CR-04-2723
CR-01-880
CR-00-468           CR-01-2186           CR-03-1910             CR-04-2798
CR-02-2194
CR-00-1509         CR-01-2214           CR-03-2810             CR-04-2799
CR-04-1234
CR-00-1567         CR-02-151           CR-04-433               CR-04-2802
CR-98-467
CR-01-889
CR-02-2716
CR-04-1484
CR-98-1171
CR-01-890
CR-02-2733
CR-04-1522
CR-98-2066
CR-01-1007
CR-02-2942
CR-04-2600
CR-99-175
CR-01-1232
CR-03-441
CR-04-2621
CR-99-618
CR-01-1340
CR-03-962
CR-04-2623
CR-00-94
CR-01-1834
CR-03-1491
CR-04-2644
CR-00-306
CR-01-2084
CR-03-1855
CR-04-2723
CR-00-468
CR-01-2186
CR-03-1910
CR-04-2798
CR-00-1509
CR-01-2214
CR-03-2810
CR-04-2799
CR-00-1567
CR-02-151
CR-04-433
CR-04-2802
Drawings
Drawings
Drawing B-191301 Sh. 1150, Core Spray System B Aux. Relays Sh 1, Rev. 13
Drawing B-191301 Sh. 1150, Core Spray System B Aux. Relays Sh 1, Rev. 13
Line 2,306: Line 2,906:
Drawing B-191301 Sh. 317, 4kV SWGR Aux. Relay Ckt., Rev. 10
Drawing B-191301 Sh. 317, 4kV SWGR Aux. Relay Ckt., Rev. 10
Drawing B-191301 Sh. 327, 4kV SWGR #3 Tie to 4kV SWGR #1 Bkr. #3T1, Rev. 8.
Drawing B-191301 Sh. 327, 4kV SWGR #3 Tie to 4kV SWGR #1 Bkr. #3T1, Rev. 8.
Drawing B-191301 Sh. 328A, 4Kv SWGR #3 Compt, 10 Diesel Generator DG1-1B Bkr & LNP
Drawing B-191301 Sh. 328A, 4Kv SWGR #3 Compt, 10 Diesel Generator DG1-1B Bkr & LNP
      Ckt., Rev. 11
Ckt., Rev. 11
Drawing G-191157 Sheet 2 Location L-9, Flow Diagram Condensate, Feedwater and Air
Drawing G-191157 Sheet 2 Location L-9, Flow Diagram Condensate, Feedwater and Air
      Evacuation Systems, Rev. 5
Evacuation Systems, Rev. 5
Drawing G-191174, Sheet 2, Flow Diagram - Reactor Core Isolation Cooling, Rev. 23
Drawing G-191174, Sheet 2, Flow Diagram - Reactor Core Isolation Cooling, Rev. 23
Drawing B-191261, Sheet 26C, Impulse Piping to Rack RK-6, Rev. 6
Drawing B-191261, Sheet 26C, Impulse Piping to Rack RK-6, Rev. 6
Line 2,315: Line 2,915:
Drawing G-191298 Sh.2, Main One Line Phasor Diagram, Rev. 8
Drawing G-191298 Sh.2, Main One Line Phasor Diagram, Rev. 8
DS801-2, Generator SN 180X383 Reactive Capability Curve, dated February 11, 2003
DS801-2, Generator SN 180X383 Reactive Capability Curve, dated February 11, 2003
Drawing 6202-001, General Plan Pressure Suppression Containment Vessel C Residual Heat
Drawing 6202-001, General Plan Pressure Suppression Containment Vessel C Residual Heat
      Removal System - Bubble Ingestion from Safety Relief Valve and LOCA, Rev. 3
Removal System - Bubble Ingestion from Safety Relief Valve and LOCA, Rev. 3
Operability Determinations
Operability Determinations
CR-VTY-1999-00990; Damaged Threads, Originated: 8/17/1999, Closed: 10/6/1999
CR-VTY-1999-00990; Damaged Threads, Originated: 8/17/1999, Closed: 10/6/1999  
CR-VTY-2001-00966; Leak Rate Test Results Exceeded the Acceptance Criteria, Originated:
CR-VTY-2001-00966; Leak Rate Test Results Exceeded the Acceptance Criteria, Originated:  
      5/04/2001, Closed: 6/29/2001
5/04/2001, Closed: 6/29/2001
CR-VTY-2002-02258; IST Leak Rate Test Results Exceed the Acceptance Criteria,
CR-VTY-2002-02258; IST Leak Rate Test Results Exceed the Acceptance Criteria,  
      Originated: 10/09/2002, Closed: 4/10/2004
Originated: 10/09/2002, Closed: 4/10/2004
CR-VTY-2004-01607; Breaker 381 Fails to Stay Closed (it trips free), Originated: 5/2/2004,
CR-VTY-2004-01607; Breaker 381 Fails to Stay Closed (it trips free), Originated: 5/2/2004,
      Closed 5/18/2004
Closed 5/18/2004
CR-VTY-2004-2596; The Design Basis for Degraded Grid UV Relay not Adequately
CR-VTY-2004-2596; The Design Basis for Degraded Grid UV Relay not Adequately
      Documented in Calculation, Originated: 8/16/2004, Closed: Still Open
Documented in Calculation, Originated: 8/16/2004, Closed: Still Open


B-8
B-8
                                            B-9
 
B-9
Modifications and Work Orders
Modifications and Work Orders
DBD Pending Change Numbers RCIC 2004-002 and HPCI 2004-003
DBD Pending Change Numbers RCIC 2004-002 and HPCI 2004-003
EDCR 81-22 in accordance with NUREG-0737, Item II.K.3.22
EDCR 81-22 in accordance with NUREG-0737, Item II.K.3.22
EDCR 97-404, MOV Electrical and Pressure Locking Modifications, dated June 17, 1998
EDCR 97-404, MOV Electrical and Pressure Locking Modifications, dated June 17, 1998
EDCR 94-406, MOV Improvements, dated July 13, 1995
EDCR 94-406, MOV Improvements, dated July 13, 1995  
Modification Package MM-2003-015, Reactor Feed Pump Suction Pressure Trip Changes for
Modification Package MM-2003-015, Reactor Feed Pump Suction Pressure Trip Changes for
        EPU
EPU  
Modification Package MM-2003-016, Reactor Recirculation System Run Back For Feedwater
Modification Package MM-2003-016, Reactor Recirculation System Run Back For Feedwater
        and Condensate System Transients
and Condensate System Transients
Modification Package MM-2004-015, Improve SLC Relief Valve Tolerances to Meet New SLC
Modification Package MM-2004-015, Improve SLC Relief Valve Tolerances to Meet New SLC
        System Operating Pressure Requirements
System Operating Pressure Requirements  
Vermont Yankee Design Change VYDC 2003-013, Addition of 3rd Main Steam Safety Valve,
Vermont Yankee Design Change VYDC 2003-013, Addition of 3rd Main Steam Safety Valve,
        dated 7/9/2003
dated 7/9/2003
Vermont Yankee Design Change VYDC 2001-003, RCIC Turbine Exhaust Check Valve
Vermont Yankee Design Change VYDC 2001-003, RCIC Turbine Exhaust Check Valve
        Replacement, dated 10/28/2004
Replacement, dated 10/28/2004
Correspondence
Correspondence
Memorandum, E. Betti to S. Miller, Feedwater Leakage Monitoring Data Analysis, dated
Memorandum, E. Betti to S. Miller, Feedwater Leakage Monitoring Data Analysis, dated  
        January 30, 1991
January 30, 1991
Memorandum, E. Betti to S. Miller, Monthly Feedwater Leakage Monitoring Data Report
Memorandum, E. Betti to S. Miller, Monthly Feedwater Leakage Monitoring Data Report
        Analysis, dated December 6, 1993
Analysis, dated December 6, 1993
Letter FVY 82-105, VY to NRC, Feedwater Spargers - Response to NRCs Request for
Letter FVY 82-105, VY to NRC, Feedwater Spargers - Response to NRCs Request for  
        Additional Information, dated September 21, 1982
Additional Information, dated September 21, 1982
Letter BVY 94-07, VY to NRC, Request for Relief from NUREG-0619 Inspection
Letter BVY 94-07, VY to NRC, Request for Relief from NUREG-0619 Inspection  
        Requirements, dated February 11, 1994
Requirements, dated February 11, 1994
Letter NVY 95-142, VY to NRC, Feedwater Nozzle Inspection Relief Request - Vermont
Letter NVY 95-142, VY to NRC, Feedwater Nozzle Inspection Relief Request - Vermont  
        Yankee Nuclear Power Station (TAC No. M92940), dated October 12, 1995
Yankee Nuclear Power Station (TAC No. M92940), dated October 12, 1995
Calculation VYC1005, Revision 1, Crack Growth Calculation for the Vermont Yankee FW
Calculation VYC1005, Revision 1, Crack Growth Calculation for the Vermont Yankee FW
        Nozzles, Attachment 1, GE-NE-523-A71-0594 with NRC SER dated
Nozzles, Attachment 1, GE-NE-523-A71-0594 with NRC SER dated
        March 10, 2000
March 10, 2000
Letter BVY 01-02, VY to NRC, Alternative Feedwater Nozzle Inspection, dated
Letter BVY 01-02, VY to NRC, Alternative Feedwater Nozzle Inspection, dated  
        January 22, 2001
January 22, 2001
Letter, NRC to VY, Vermont Yankee Nuclear Power Station Safety - Evaluation of Licensee
Letter, NRC to VY, Vermont Yankee Nuclear Power Station Safety - Evaluation of Licensee
        Response to Generic Letter 9605 (TAC NO. M97114), dated December 14, 2000
Response to Generic Letter 9605 (TAC NO. M97114), dated December 14, 2000
Letter BVY 96-143, VY to NRC, Vermont Yankee 60-day Response to Generic Letter 96-05,
Letter BVY 96-143, VY to NRC, Vermont Yankee 60-day Response to Generic Letter 96-05,
        dated November 15, 1996
dated November 15, 1996
Letter BVY 97-36, VY to NRC, Vermont Yankee 180-day Response to Generic Letter 96-05,
Letter BVY 97-36, VY to NRC, Vermont Yankee 180-day Response to Generic Letter 96-05,
        dated November 15, 1996
dated November 15, 1996
Summary of Changes in Leak Detection Data, Report Generated August 30, 2004
Summary of Changes in Leak Detection Data, Report Generated August 30, 2004
Summary of Changes in Leak Detection Data, Report Generated September 1, 2004
Summary of Changes in Leak Detection Data, Report Generated September 1, 2004
GE Letter VYNPS-AEP-346 Revisions 0, 1 and 2
GE Letter VYNPS-AEP-346 Revisions 0, 1 and 2


                                              B-10
B-10
Event Reports
Event Reports
Event Report 20030340, Root Cause Analysis, The Outboard Seal on RFP C Failed
Event Report 20030340, Root Cause Analysis, The Outboard Seal on RFP C Failed
Other Documents
Other Documents
Generic Letter (GL) 89-10, Safety-Related Motor-Operated Valve Testing and Surveillance,
Generic Letter (GL) 89-10, Safety-Related Motor-Operated Valve Testing and Surveillance,
      dated June 28, 1989
dated June 28, 1989
Generic Letter (GL) 96-05, Periodic Verification of Design-Basis Capability of Safety-Related
Generic Letter (GL) 96-05, Periodic Verification of Design-Basis Capability of Safety-Related
      Power Operated Valves, dated September 18, 1996
Power Operated Valves, dated September 18, 1996
Information Notice (IN) 2001-13, Inadequate Standby Liquid Control System Relief Valve
Information Notice (IN) 2001-13, Inadequate Standby Liquid Control System Relief Valve
      Margin, dated August 10, 2001.
Margin, dated August 10, 2001.
Operational Decision-Making Issue (ODMI) Action Plan 2003-1812
Operational Decision-Making Issue (ODMI) Action Plan 2003-1812
NRC SER, Degraded Grid Voltage Protection for Class 1E Power Systems, dated
NRC SER, Degraded Grid Voltage Protection for Class 1E Power Systems, dated  
      March 31, 1986
March 31, 1986
Regulatory Guide 1.82, Water Sources for Long-Term Recirculation Cooling following a Loss-
Regulatory Guide 1.82, Water Sources for Long-Term Recirculation Cooling following a Loss-
      of-Coolant Accident, Revision 3, dated November 2003
of-Coolant Accident, Revision 3, dated November 2003
Vermont Yankee Updated Final Safety Analysis Report (UFSAR), Revision 18
Vermont Yankee Updated Final Safety Analysis Report (UFSAR), Revision 18
Vermont Yankee Individual Plant Examination (IPE) Document
Vermont Yankee Individual Plant Examination (IPE) Document
Vermont Yankee Appendix R Safe Shutdown Capability Analysis (SSCA), dated December 23,
Vermont Yankee Appendix R Safe Shutdown Capability Analysis (SSCA), dated December 23,
      1999
1999
Vermont Yankee Technical Specifications, through Amendment No. 219
Vermont Yankee Technical Specifications, through Amendment No. 219
                                    LIST OF ACRONYMS
LIST OF ACRONYMS
AC           Alternating Current
AC
ASME         American Society of Mechanical Engineers
Alternating Current
CR           Condition Report
ASME
CST           Condensate Storage Tank
American Society of Mechanical Engineers
EPU           Extended Power Uprate
CR
EOP           Emergency Operating Procedure
Condition Report
FAC           Flow Assisted Corrosion
CST
GE           General Electric
Condensate Storage Tank
GL           Generic Letter
EPU
HPCI         High Pressure Coolant Injection
Extended Power Uprate
kV           Kilovolt
EOP  
LER           Licensee Event Report
Emergency Operating Procedure
MCC           Motor Control Center
FAC
MOV           Motor-Operated Valve
Flow Assisted Corrosion
NCV           Non-Cited Violation
GE  
NPSH         Net Positive Suction Head
General Electric
NRC           US Nuclear Regulatory Commission
GL
OD           Operability Determination
Generic Letter
psig         Pounds Per Square Inch Gauge
HPCI
PRA           Probabilistic Risk Assessment
High Pressure Coolant Injection
kV
Kilovolt
LER
Licensee Event Report
MCC
Motor Control Center
MOV
Motor-Operated Valve
NCV
Non-Cited Violation
NPSH
Net Positive Suction Head
NRC
US Nuclear Regulatory Commission  
OD
Operability Determination
psig
Pounds Per Square Inch Gauge
PRA
Probabilistic Risk Assessment


                                      B-11
B-11
PUSAR   Power Uprate Safety Analysis Report
PUSAR
RAW     Risk Achievement Worth
Power Uprate Safety Analysis Report
RCIC   Reactor Core Isolation Cooling
RAW
RHR     Residual Heat Removal
Risk Achievement Worth
ROP     Reactor Oversight Process
RCIC
SBO     Station Blackout
Reactor Core Isolation Cooling
SDP     Significance Determination Process
RHR
SLC     Standby Liquid Control
Residual Heat Removal
SPAR   Simplified Plant Analysis Risk
ROP
SRV     Safety/Relief Valve
Reactor Oversight Process
TE     Technical Evaluation
SBO  
TS     Technical Specifications
Station Blackout
UFSAR   Updated Final Safety Analysis Report
SDP
V       Volt
Significance Determination Process
VY     Vermont Yankee
SLC
VY SSCA Vermont Yankee Safe Shutdown Capability Analysis
Standby Liquid Control  
SPAR
Simplified Plant Analysis Risk
SRV
Safety/Relief Valve
TE
Technical Evaluation
TS
Technical Specifications
UFSAR
Updated Final Safety Analysis Report
V
Volt
VY
Vermont Yankee
VY SSCA
Vermont Yankee Safe Shutdown Capability Analysis
}}
}}

Latest revision as of 23:33, 15 January 2025

IR 05000271-04-008; 08/09/2004-09/03/2004; Vermont Yankee Nuclear Generating Station; Functional Review of Low Margin/Risk Significant Components and Human Actions
ML043340269
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 12/02/2004
From: Lanning W
Division of Nuclear Materials Safety I
To: Thayer J
Entergy Nuclear Operations
References
IR-04-008
Download: ML043340269 (70)


See also: IR 05000271/2004008

Text

December 2, 2004

Mr. Jay K. Thayer

Site Vice President

Entergy Nuclear Operations, Inc.

Vermont Yankee Nuclear Power Station

P.O. Box 0500

185 Old Ferry Road

Brattleboro, VT 05302-0500

SUBJECT:

VERMONT YANKEE NUCLEAR POWER STATION

NRC INSPECTION REPORT 05000271/2004008

Dear Mr. Thayer:

On September 3, 2004, the US Nuclear Regulatory Commission (NRC) completed an

inspection at the Vermont Yankee Nuclear Power Station. The enclosed inspection report

documents the inspection findings, which were discussed with members of your staff on

September 3, October 27, and November 23, 2004.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

In conducting the inspection, the team examined the adequacy of selected components and

operator actions to mitigate postulated design basis accidents, both under current licensing and

planned power uprated conditions. The inspection also reviewed Entergys response to

selected operating experience issues, and assessed the adequacy of Vermont Yankees design

and engineering processes.

The team concluded that the components and systems reviewed would be capable of

performing their intended safety functions. The team also concluded that sufficient design

controls had been implemented for design and engineering work, including that related to

Entergys extended power uprate. The team did identify several deficiencies related to design

control at Vermont Yankee; however, sample based extent-of-condition reviews indicated the

original problems were not widespread or programmatic in nature. In addition, some of the

specific findings included topics that were within the scope of the NRCs power uprate review,

and thus, will require the submittal of additional information to the NRCs technical staff to

support that review.

The enclosed report documents eight findings of very low safety significance (Green), all of

which were determined to involve a violation of NRC requirements. Because of their very low

safety significance and because the findings were entered into your corrective action program,

the NRC is treating them as non-cited violations (NCVs), consistent with Section VI.A of the

NRCs Enforcement Policy. If you contest these non-cited violations, you should provide a

response within 30 days of the date of this inspection report, with the basis for your denial, to

the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, D.C. 20555-

0001; with copies to the Regional Administrator Region I; the Director, Office of Enforcement,

Mr. J. K. Thayer

2

United States Nuclear Regulatory Commission, Washington, D.C. 20555-0001; and the NRC

Resident Inspector at the Vermont Yankee Nuclear Power Station.

In accordance with 10 CFR 2.390 of the NRCs "Rules of Practice," a copy of this letter, its

enclosure, and your response (if any) will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records (PARS) component of

NRCs document system (ADAMS). ADAMS is temporarily unavailable due to an ongoing

security review; therefore, this document will also be posted on the NRC Web site at

http:\\\\www.nrc.gov\\reactors\\plant-specific-items\\vermont-yankee-issues.html.

Sincerely,

/RA/

Wayne D. Lanning, Director

Division of Reactor Safety

Docket No. 50-271

License No. DPR-28

Enclosure: Inspection Report 05000271/2004008 w/Attachments

Mr. J. K. Thayer

3

cc w/encl:

M. R. Kansler, President, Entergy Nuclear Operations, Inc.

G. J. Taylor, Chief Executive Officer, Entergy Operations

J. T. Herron, Senior Vice President and Chief Operating Officer

D. L. Pace, Vice President, Engineering

B. OGrady, Vice President, Operations Support

J. M. DeVincentis, Manager, Licensing, Vermont Yankee Nuclear Power Station

Operating Experience Coordinator - Vermont Yankee Nuclear Power Station

J. F. McCann, Director, Nuclear Safety Assurance

M. J. Colomb, Director of Oversight, Entergy Nuclear Operations, Inc.

J. M. Fulton, Assistant General Counsel, Entergy Nuclear Operations, Inc.

S. Lousteau, Treasury Department, Entergy Services, Inc.

Administrator, Bureau of Radiological Health, State of New Hampshire

Chief, Safety Unit, Office of the Attorney General, Commonwealth of Mass.

D. R. Lewis, Esquire, Shaw, Pittman, Potts & Trowbridge

G. D. Bisbee, Esquire, Deputy Attorney General, Environmental Protection Bureau

J. Block, Esquire

J. P. Matteau, Executive Director, Windham Regional Commission

M. Daley, New England Coalition on Nuclear Pollution, Inc. (NECNP)

D. Katz, Citizens Awareness Network (CAN)

R. Shadis, New England Coalition Staff

G. Sachs, President/Staff Person, c/o Stopthesale

J. Sniezek, PWR SRC Consultant

R. Toole, PWR SRC Consultant

Commonwealth of Massachusetts, SLO Designee

State of New Hampshire, SLO Designee

State of Vermont, SLO Designee

Mr. J. K. Thayer

4

Distribution w/encl:

(via E-mail)

S. Collins, RA

J. Wiggins, DRA

W. Lanning, DRS

R. Crlenjak, DRS

L. Doerflein, DRS

C. Anderson, DRP

D. Florek, DRP

J. Jolicoeur, RI OEDO

J. Clifford, NRR

R. Ennis, PM, NRR

V. Nerses, Backup PM, NRR

D. Pelton, DRP, Senior Resident Inspector

A. Rancourt, DRP, Resident OA

Region I Docket Room (with concurrences)

ADAMS ML043340269

SISP Review Complete: WDL

DOCUMENT NAME: E:\\Filenet\\ML043340269.wpd

After declaring this document An Official Agency Record it will be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy

OFFICE

RI/DRS

RI/DRS

NAME

CBaron/JJ for

GSkinner/JJ for

SSpiegelman/JJ for

GBowman/GTB

SDennis/SXD

DATE

12/2/04

12/2/04

12/2/04

12/2/04

12/2/04

OFFICE

RI/DRS

RI/DRP

NRR/PIPB

RI/DRS

RI/DRS

NAME

FBower/LTD for by telecon

MSnell/MPS

JJacobson/JJ

WSchmidt/WLS

LDoerflein/LTD

DATE

12/1/04

12/2/04

12/2/04

12/2/04

12/ 1/04

OFFICE

RI/DRS

NAME

WLanning/WDL

DATE

12/ 2/04

Mr. J. K. Thayer

5

OFFICIAL RECORD COPY

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

REGION I

Docket No.

50-271

License No.

DPR-28

Report No.

05000271/2004008

Licensee:

Entergy Nuclear Vermont Yankee, LLC

Facility:

Vermont Yankee Nuclear Power Station

Location:

320 Governor Hunt Road

Vernon, Vermont

05354-9766

Dates:

August 9 - 20 and August 30 - September 3, 2004

Inspectors:

J. Jacobson, Team Leader, Inspection Program Branch, NRR

F. Bower, Senior Reactor Inspector, DRS, Region I

G. Bowman, Reactor Inspector, DRS, Region I

S. Dennis, Senior Operations Engineer, DRS, Region I

M. Snell, Reactor Engineer, DRP, Region I

C. Baron, NRC Contractor

S. Spiegelman, NRC Contractor

G. Skinner, NRC Contractor

Observer:

W. Sherman, Vermont State Nuclear Engineer

Approved by:

Wayne D. Lanning, Director

Division of Reactor Safety

Region I

Enclosure

CONTENTS

EXECUTIVE SUMMARY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . i

SUMMARY OF FINDINGS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . iii

REPORT DETAILS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

4OA2 Problem Identification and Resolution (PI&R) . . . . . . . . . . . . . . . . . . . . . . . . . . 1

1. Annual Sample Review . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

2. Cross Reference to PI&R Findings Documented Elsewhere . . . . . . . . . . . . 1

4OA5 Other Activities - Temporary Instruction 2515/158 . . . . . . . . . . . . . . . . . . . . . . . 1

1. Inspection Sample Selection Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

2. Results of Detailed Reviews . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2

2.1

Detailed Component and System Reviews . . . . . . . . . . . . . . . . . 2

2.1.1

Electrical Power Sources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2

2.1.2

Reactor Core Isolation Cooling (RCIC) System . . . . . . . . . . . . . 8

2.1.3 Residual Heat Removal System (RHR) . . . . . . . . . . . . . . . . . . 13

2.1.4

Safety Relief Valves and Code Safety Valves . . . . . . . . . . . . . 13

2.1.5

Reactor Feedwater and Condensate Components . . . . . . . . . 13

2.1.6

Reactor Building-to-Torus Vacuum Breaker System

. . . . . . . . 14

2.1.7

Review of Transient Analysis Inputs . . . . . . . . . . . . . . . . . . . . . 15

2.2

Review of Operator Actions . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

2.3

Review of Operating Experience and Generic Issues

. . . . . . . 20

4OA6 Meetings, Including Exit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23

ATTACHMENT A: SUMMARY OF ITEMS REVIEWED . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-1

ATTACHMENT B: SUPPLEMENTAL INFORMATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B-1

KEY POINTS OF CONTACT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B-1

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED . . . . . . . . . . . . . . . . . . . . . . . . . . . B-2

LIST OF DOCUMENTS REVIEWED . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B-3

LIST OF ACRONYMS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B-8

Enclosure

i

EXECUTIVE SUMMARY

During the period from August 9 through September 3, 2004, the US Nuclear Regulatory

Commission (NRC) conducted a team inspection in accordance with Temporary Instruction

2515/158, Functional Review of Low Margin/Risk Significant Components and Human

Actions, at the Vermont Yankee Nuclear Power Station. The team was comprised of eight

inspectors, including a team leader from the NRCs Office of Nuclear Reactor Regulation, four

inspectors from the NRCs Region I Office, and three contractors. All of the inspectors and

contractors met strict independence criteria developed for this inspection. Specifically, the NRC

inspectors had not performed engineering inspections at Vermont Yankee within the last two

years and had not been assigned as resident inspectors at Vermont Yankee. The contractors

had never been directly employed by Entergy or Vermont Yankee, had not performed contract

work for Entergy or Vermont Yankee in the past two years, and had not performed inspections

for the NRC at Vermont Yankee within the past two years. The inspection was the first of four

planned pilot inspections to be conducted throughout the country to assist the NRC in

determining whether changes should be made to its Reactor Oversight Process (ROP) to

improve the effectiveness of its inspections and oversight in the design/engineering area.

In selecting samples for review, the team focused on those components and operator actions

that contribute the greatest risk to an accident that could involve damage to the reactor core.

Additional consideration was given to those components and operator actions impacted by the

licensees request for a 20 percent extended power uprate (EPU) license amendment. The

team focused its reviews on those components and operator actions contained in the reactor

core isolation cooling (RCIC), main feedwater, safety relief valve, onsite electrical power, and

off-site electrical power systems. In addition, inspection samples were added based upon

operational experience and issues previously identified by the NRCs technical staff during the

course of their reviews associated with the licensees request for an EPU. A complete listing of

all components, operator actions, and operating experience issues reviewed by the inspection

team is contained in Attachment A to this report.

For each sample selected, the team reviewed design calculations, corrective action reports,

maintenance and modification histories, associated operating procedures, and performed

walkdowns of material conditions (as practical). The team concluded that the components and

systems reviewed would be capable of performing their intended safety functions. The team

also concluded that sufficient design controls had been implemented for engineering work,

including that related to Entergys EPU. The overall material condition of the plant and of the

specific components reviewed was also noted as being good. The team identified eight findings

of very low safety significance, one unresolved item, and one minor finding. The eight findings

are listed in the Summary of Findings section of this report.

The team assessed the safety significance of each of the findings using the NRCs Significance

Determination Process (SDP). Using this process, each of the findings was determined to be of

very low safety significance. Also, for each of the findings where current operability was in

question, the licensee provided a basis for operability and entered the issue into their corrective

action program, as necessary to complete a more comprehensive assessment of the issue,

including any programmatic oversight weaknesses that might have prevented self-identification.

In addition, for the findings associated with a design vulnerability of an RCIC pressure control

valve, the control of the condensate storage tank (CST) temperature to the limits of transient

Enclosure

ii

analysis assumptions, and the updating of the Safe Shutdown Capability Analysis, the team

performed sample-based extent-of-condition reviews during the inspection to determine the

breadth of the issues identified. No additional findings were identified during these reviews,

indicating the original problems identified were not widespread, and were likely not

programmatic in nature. Additional licensee extent-of-condition reviews of the issues were

ongoing at the conclusion of the inspection.

Some of the findings also concern topics that are within the scope of the NRCs power uprate

review and therefore will require the submittal of additional information to the NRCs technical

staff.

Enclosure

iii

SUMMARY OF FINDINGS

IR 05000271/2004008; 08/09/2004-09/03/2004; Vermont Yankee Nuclear Generating Station;

Functional Review of Low Margin/Risk Significant Components and Human Actions.

This inspection was conducted by five inspectors and three NRC contractors. Eight Green non-

cited violations, one unresolved item, and one minor finding were identified. The significance of

most findings is indicated by their color (Green, White, Yellow, or Red) using Inspection Manual

Chapter (IMC) 0609, Significance Determination Process. Findings for which the SDP does

not apply may be Green or be assigned a severity level after NRC management review. The

NRCs program for overseeing the safe operation of commercial nuclear power reactors is

described in NUREG-1649, Reactor Oversight Process, Revision 3, dated July 2000.

A.

NRC-Identified Findings

Cornerstone: Mitigating Systems

!

Green. The team identified a non-cited violation of 10 CFR Part 50.63, Loss of

All Alternating Current Power, because the licensee had not completed a coping

analysis for the period of time the alternate alternating current (AC) source (the

Vernon Hydro-Electric Station) would be unavailable and had not demonstrated

by test the time required to make the alternate source available for a station

blackout involving a grid collapse. This issue was more than minor because it

was associated with the Mitigating Systems Cornerstone attribute of Equipment

Performance and affected the cornerstone objective of ensuring availability,

reliability, and capability of systems needed to respond to a station blackout.

The issue screened as very low safety significance in Phase I of the SDP

because it was a design deficiency that was not found to result in a loss of

function. Specifically, the team found that the licensees preliminary coping

analysis, performed during the inspection, demonstrated a four-hour coping time

which should be sufficient to envelope the time required to start and align the

Vernon Station. (Section 4OA5.2.1.1)

!

Green. The team identified a non-cited violation of Technical Specifications

6.4.C, Procedures, because the licensee failed to establish adequate

procedures for determining the operability of the 115 kilovolt (kV) Keene line,

which is designated as an alternate immediate access power source if the

345/115 kV auto transformer is lost. This issue was more than minor because it

was associated with the Mitigating Systems Cornerstone attribute of Procedural

Quality and affected the cornerstone objective of ensuring availability, reliability,

and capability of systems needed to respond to a loss of off-site power. The

issue screened as very low safety significance in Phase I of the SDP because it

was a design deficiency that was not found to result in a loss of function.

Specifically, the team did not identify any instances where the lack of procedural

guidance had resulted in an inadequate assessment of off-site power operability

or the inoperability of the electrical system or any components.

(Section 4OA5.2.1.1)

Enclosure

iv

!

Green. The team identified a non-cited violation of 10 CFR Part 50, Appendix B,

Criterion III, Design Control, because the licensee used incorrect and non-

conservative voltage values in calculations performed to assure that electrical

equipment would remain operable under degraded voltage conditions. This

issue was more than minor because it was associated with the Mitigating

Systems Cornerstone attribute of Equipment Performance and affected the

cornerstone objective of ensuring availability, reliability, and capability of systems

needed to respond to a design basis accident. The issue screened as very low

safety significance in Phase I of the SDP because it was a design deficiency that

was not found to result in a loss of function. Specifically, the team did not

identify any instances where using the Technical Specification degraded voltage

allowable setpoint values would have resulted in inoperable equipment.

(Section 4OA5.2.1.1)

!

Green. The team identified a non-cited violation of 10 CFR Part 50, Appendix B,

Criterion III, Design Control, because the licensee did not implement measures

to ensure that the design basis for the cooling water supply to the lube oil cooler

of RCIC was correctly translated into the specifications, drawings, procedures, or

instructions. Specifically, the installed pressure control valve in the lube oil

cooler water supply line was not independent of air systems, and the installed

piping between the pressure control valve and lube oil cooler did not contain a

restricting orifice. This issue was more than minor because it was associated

with the Mitigating Systems Cornerstone attribute of Equipment Performance

and affected the cornerstone objective of ensuring the reliability of the RCIC

system. The issue screened as very low safety significance in Phase I of the

SDP because it was a design deficiency that was not found to result in a loss of

function. This deficiency would not have resulted in the RCIC system becoming

inoperable due to a loss of air to the lube oil cooler pressure control valve.

(Section 4OA5.2.1.2).

A contributing cause of this finding is related to the cross cutting area of Problem

Identification and Resolution. The licensee had previously reviewed the failure

positions of air-operated equipment and issued a report, Compressed Air

Systems, dated July 16, 1989. During this review, the licensee did not identify

that the pressure control valve was not independent of the instrument air system.

!

Green. The team identified a non-cited violation of 10 CFR Part 50, Appendix B,

Criterion XVI, Corrective Action, because the licensee failed to correct a

longstanding non-conformance in the operation of pressure control valve PCV-

13-23. The team determined through interviews with Vermont Yankee staff that

during initial start-up testing, problems were identified with the automatic

operation of this valve which affected its ability to properly supply cooling flow to

the RCIC lube oil cooler. This issue was more than minor because it was

associated with the Mitigating Systems attribute of Equipment Performance and

affected the cornerstone objective of ensuring the reliability of the RCIC system.

The issue screened as very low safety significance in Phase I of the SDP

because it was a design deficiency that was not found to result in a loss of

function. The licensee had implemented manual actions as a compensatory

Enclosure

v

measure for the operation of PCV-13-23 through the addition of procedural

steps. (Section 4OA5.2.1.2)

!

Green. The team identified a non-cited violation of 10 CFR Part 50, Appendix B,

Criterion III, Design Control, because the licensee had neither established the

correct condensate storage tank (CST) temperature limit for use in the plant

transient analyses nor translated the CST temperature limit into plant

procedures. This issue was more than minor because it was associated with the

Mitigating Systems Cornerstone attribute of Equipment Performance and

affected the cornerstone objective of ensuring the reliability of the core spray

system. The issue screened as very low safety significance in Phase I of the

SDP because it was a design deficiency that was not found to result in a loss of

function. Although available net positive suction head (NPSH) margin for the

core spray pumps was lowered, adequate margin remained due to the

conservatism that existed in other aspects of the licensees NPSH analysis.

(Section 4OA5.2.1.7)

A contributing cause of this finding is also related to the cross-cutting area of

Problem Identification and Resolution. The licensee identified this issue in

December 2002, but concluded that the non-conservative CST temperature had

little to no effect on the transient analyses.

!

Green. The team identified a non-cited violation of 10 CFR Part 50, Appendix B,

Criterion III, Design Control, because between June 2001 to September 2004,

the licensee did not adequately coordinate between the operations department

and the engineering organization regarding procedure revisions that increased

the length of time required to place the reactor core isolation cooling system in

service from the alternate shutdown panels. This issue was more than minor

because it was associated with the Mitigating Systems Cornerstone attribute of

Human Performance and affected the cornerstone objective of ensuring the

availability of the RCIC system. Furthermore, this finding resulted in the use of

the December 1999 value of time to place RCIC in service from the alternate

shutdown panel in documents submitted to the NRC as part of the Vermont

Yankee Power Uprate Safety Analysis Report. The issue screened as very low

safety significance in Phase I of the SDP because it was a design deficiency that

was not found to result in a loss of function. Although the available time margin

was lowered, sufficient margin remained to allow operator action to manually

start the RCIC system prior to reactor level reaching the top of active fuel.

(Section 4OA5.2.2)

!

Green. The team identified a non-cited violation of 10 CFR Part 50, Appendix B,

Criterion XI, Test Control, because the licensee had conducted motor-operated

valve (MOV) diagnostic tests using procedures that did not include acceptance

limits, which were correlated to and based on applicable (stem thrust and torque)

design documents. Additionally, MOV diagnostic testing had been conducted

solely from the motor control centers using test instrumentation that had not

been validated to ensure its adequacy. The finding was more than minor

because it affected the Mitigating Systems Cornerstone attribute of Equipment

Performance and affected the cornerstone objective of ensuring the availability,

Enclosure

vi

reliability, and capability of systems and components that respond to initiating

events. Specifically, the unvalidated test method had the potential to affect the

reliability of safety-related motor-operated valves. The issue screened as very

low safety significance in Phase I of the SDP because it was a qualification

deficiency that was not found to result in a loss of function. The team did not

identify any examples of degraded or inoperable valves during the inspection

and noted that the design basis calculations for the MOVs reviewed had

available thrust margin of greater than 60 percent. (Section 4OA5.2.3)

B.

Licensee Identified Violations

None.

Enclosure

REPORT DETAILS

4OA2 Problem Identification and Resolution (PI&R)

2.

Annual Sample Review

Not applicable.

3.

Cross Reference to PI&R Findings Documented Elsewhere

Section 2.1.2 (b) 1 of this report describes a finding associated with a design

vulnerability of the reactor core isolation cooling (RCIC) system lube oil cooling pressure

control valve in that the valve design was not independent of station service air as

described in the Updated Final Safety Analysis Report. The licensee had previously

reviewed the failure positions of air-operated equipment and issued a report,

Compressed Air Systems, dated July 16, 1989. This longstanding deficiency was not

identified by this review or by other station service air reviews.

Section 2.1.7 (b) of this report describes a finding associated with maintaining the

condensate storage tank temperature within limits assumed in the facilitys transient

analysis. The licensee had identified conditions where the tank temperature had

exceeded the transient analysis assumptions but had not taken sufficient corrective

actions.

4OA5 Other Activities - Temporary Instruction 2515/158

1.

Inspection Sample Selection Process

In selecting samples for review, the team focused on the most risk-significant

components and operator actions. The team selected these components and operator

actions by using the risk information contained in the licensees Probabilistic Risk

Assessment (PRA) and the US Nuclear Regulatory Commissions (NRCs) Simplified

Plant Analysis Risk (SPAR) models. An initial sample was chosen from those

components and operator actions that had a risk achievement worth factor greater than

two. These components and operator actions are important to safety since their

assumed failure would result in at least doubling the risk of an accident that could result

in core damage. Consideration was also given to those components and operator

actions most impacted by the licensees request for a 20 percent extended power uprate

(EPU) license amendment.

Many of the samples selected were located within the reactor core isolation cooling,

main feedwater, safety relief valve, onsite electrical power, and off-site electrical power

systems. In addition, inspection samples were added based upon operational

experience reviews. The team was also briefed by the NRCs technical staff conducting

the EPU licensing review on issues that had arisen during their reviews, indicating areas

that might warrant additional inspection. A complete listing of all components, operator

actions and operating experience issues reviewed by the inspection team is contained in

Attachment A to this report. A total of 91 samples were chosen for the teams initial

review.

2

Enclosure

A preliminary review was performed on the 91 samples to determine whether any low-

margin concerns existed. For the purpose of this inspection, margin concerns included

original design issues, margin reductions due to the proposed EPU or margin reductions

identified as a result of material condition issues. Consideration was also given to the

uniqueness and complexity of the design, operating experience, and the available

defense-in-depth margins. Based upon the above considerations, 45 of the original 91

samples were selected for a more detailed review. An overall summary of the reviews

performed and the specific inspection findings identified is included in the following

sections of the report.

2.

Results of Detailed Reviews

The team performed detailed reviews on the 45 components, operator actions and

operating experience issues. For components, the team reviewed the adequacy of the

original design, modifications to the original design, maintenance and corrective action

program histories, and associated operating and surveillance procedures. As practical,

the team also performed walkdowns of the selected components. For operator actions,

the team reviewed the adequacy of operating procedures and compared design basis

time requirements against actual demonstrated timelines. For the operating experience

issues chosen for detailed review, the team assessed the issues applicability to

Vermont Yankee and the licensees disposition of the issue. The following sections of

the report provide a summary of the detailed reviews, including any findings identified by

the inspection team.

2.1

Detailed Component and System Reviews

2.1.1

Electrical Power Sources

a.

Inspection Scope

The team reviewed the adequacy of the onsite and off-site electrical power

sources that supply power to the safety-related components chosen for detailed

review. Particular focus was paid to the off-site power sources and grid stability,

to the extent they would be impacted by an EPU. The teams review

encompassed the licensees plans to limit the initial power increase to

15 percent, as a capacitor bank necessary to provide reactive power to the grid

to ensure stability had yet to be installed. Other attributes of the electrical

systems reviewed during the inspection were operating procedures, setpoints for

degraded voltage relays, battery capacity, circuit breaker coordination, fast and

slow transfer schemes, Technical Specifications (TS) and other related

calculations.

The team conducted a walkdown of the safety-related switchgear rooms and the

electrical controls in the main control room with station engineering personnel.

The review was conducted to identify any alignment discrepancies or visible

signs of significant deficient material conditions.

3

Enclosure

The team also performed a detailed, focused review of the ability of the Vernon

Hydro-Electric Station to supply emergency power to Vermont Yankee in the

event of a station blackout (SBO) caused by a grid disturbance, as required by

10 CFR Part 50.63, Loss of all Alternating Current Power, and as clarified by

Regulatory Guide 1.155, Station Blackout, and NUMARC 87-00, Revision 1. The

team reviewed procedures associated with the operator actions necessary to tie

in the Vernon Station, procedures associated with the operation and

maintenance of the Vernon Station, and regional grid operator system

restoration procedures. The team also visited the remote control location for the

Vernon Station, and interviewed station personnel. Lastly, the team conducted a

conference call with the regional grid operator responsible for controlling the

operation of circuit breakers and switches in the Vernon switchyard.

b.

Findings

(1)

Availability of Power from Vernon Station

Introduction. The team identified a Green non-cited violation of 10 CFR Part

50.63, Loss of All Alternating Current Power, because the licensee had not

completed a coping analysis and had not demonstrated, by test, the time

required to make the alternate alternating current (AC) source available for an

electrical grid collapse resulting in a station blackout.

Description. 10 CFR Part 50.63 requires that licensees be able to recover from

an SBO that results from a loss of all AC electrical power (both the normal off-

site power sources and the on-site emergency diesel generators). In Section

C.2, Offsite Power, Regulatory Guide 1.155 defines the minimum potential

causes to be considered for a loss of off-site power that results in an SBO. One

listed cause is grid undervoltage and collapse. For SBO scenarios where the

licensee cannot demonstrate by test that an alternate AC source would be

available within 10 minutes, 10 CFR Part 50.63 requires the licensee to complete

a coping analysis for the period of time it would take for power to be restored.

At Vermont Yankee, the licensee credits the Vernon Hydro-Electric Station as its

alternate AC source to respond to a station blackout within 10 minutes. If a grid

collapse occurs, the Vernon Station would trip offline and have to be restarted.

The Vernon Station is considered a black start facility by the regional grid

operator. As such, the Vernon Station is required to certify it can be ready to

supply power within 90 minutes after tripping off line. However, in order to

supply power to Vermont Yankee under such conditions, the Vernon switchyard

would have to be configured to isolate the Vernon Station from the rest of the

grid. The operation of the circuit breakers necessary to complete such actions is

not controlled by either the licensee or the Vernon Station, but is controlled by

the regional grid operator. The team held a conference call with the grid

operators. During the call, the team learned that no specific procedures or

communication protocols had been set up to deal with a station blackout at

Vermont Yankee. The only reference to Vermont Yankee was a general

4

Enclosure

statement in a procedure that said that nuclear generators should receive critical

priority. During the call, the team also learned that the grid operator did not

differentiate between situations where normal off-site power was lost to a nuclear

unit but emergency diesels remain available, and those situations where the

emergency diesel generators failed to start and the station was in a true blackout

condition. The team learned that no specific training, testing, or simulations had

been conducted to simulate the actions that would have to be taken to respond

to an SBO at Vermont Yankee caused by a grid collapse.

As a result of the teams concerns, the licensee issued condition reports (CRs)

CR-VTY-2004-2677 and 2004-2738. The licensee also created a preliminary

timeline which estimated the time to restore power under such conditions as

being between 20 minutes and 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />. The licensee also performed an

operability evaluation in accordance with Generic Letter 91-18, which included a

preliminary four-hour coping analysis. The licensee provided the team a copy of

the preliminary coping analysis and copies of the original NRC Safety Evaluation

Report (SER) for the station blackout rule dated September 1, 1992. The team

reviewed the preliminary coping analysis and found the methodology used to be

reasonable. Review of the NRC SER indicated that questions were asked by the

NRC staff regarding a regional grid disturbance during the original station

blackout review, and that the licensees response was that power would be

restored within one hour. Based upon the above facts, the team determined that

the one hour time stated in the SER could no longer be ensured. Furthermore,

contrary to 10 CFR Part 50.63, the licensee had not completed a coping analysis

for the period of time it would take to restore the alternate source.

Analysis. The team determined that this issue was a performance deficiency

since the licensee had not demonstrated by test that the Vernon Station could

supply power to Vermont Yankee within one hour after the onset of a station

blackout and had not completed a coping analysis for the period of time the

Vernon Station would be unavailable, as required by 10 CFR Part 50.63. Also,

the licensee did not remain cognizant of how design changes, made by the

operator of the Vernon Station, affected the ability of the Vernon Station to

supply emergency power to Vermont Yankee in a timely manner. This issue was

more than minor because it was associated with the Mitigating Systems

Cornerstone attribute of Equipment Performance and affected the cornerstone

objective of ensuring availability, reliability, and capability of systems needed to

respond to a station blackout resulting from a grid collapse. The issue screened

as very low safety significance (Green) in Phase I of the SDP because it was a

design deficiency that was not found to result in a loss of function. Specifically,

the team found that the licensees preliminary coping analysis, performed during

the inspection, demonstrated a four-hour coping time that should be sufficient to

envelope the time required to start and align the Vernon Station.

Enforcement. 10 CFR Part 50.63(c)(2), requires that a coping analysis be

performed if the designated alternate AC source cannot be made available within

10 minutes. It also requires that the time required to make the alternate AC

5

Enclosure

source available be demonstrated by test. Contrary to the above, the licensee

had not completed a coping analysis for the period of time the alternate AC

source would be unavailable and had not demonstrated by test the time required

to make the alternate source available for a station blackout involving a grid

collapse. Because this finding is of very low safety significance and the licensee

entered this issue into its corrective action program (CR-VTY-2004-2677 and

2004-2738), it is considered a non-cited violation consistent with Section VI.A.1

of the NRCs Enforcement Policy. (NCV 05000271/2004008-01 Availability of

Power from Vernon Station)

(2)

Procedures for Assessing Off-site Power Operability

Introduction. The team identified a Green non-cited violation of Technical

Specifications 6.4, Procedures, because the licensee did not establish

adequate procedures for assessing the operability of the 115 kilovolt (kV) Keene

line.

Description. At Vermont Yankee, the immediate access off-site power source is

normally derived from the 345 kV switchyard through the 345/115 kV transformer

T-4-1A. The 115 kV Keene line may also be conditionally used as an alternate

immediate access source for satisfying TS requirements for off-site power

supplies, depending on grid and plant conditions. Specifically, Technical

Specification Bases 3.10.A, states that the availability of the Keene line is

dependent on its pre-loading which must be limited by the system dispatchers

prior to it being declared an immediate access source.

The team reviewed Procedure ON 3155, Loss of Auto Transformer, and noted

that Step 2b, instructs operators to contact ISO New England to determine the

115 kV Keene line load limit but does not provide explicit criteria for evaluating

the lines operability. The team also noted Note 5 on the load nomograph

included in procedure ON 3155, Reference D, Guidelines for Operating the

Vermont Yankee 115 kV System with the VTY4 Auto Transformer Out of

Service, stated the assumption that, All Vermont Yankee motor startups

performed sequentially, not simultaneously. During accident loading with off-

site power available, all safety loads are designed to block start simultaneously,

so this assumption would never be met.

The team noted the procedure also contained invalid criteria for assessing the

operability of the downstream safety buses. Step 11 allowed operation of bus 3

or 4 with voltages as low as 3600 volts (V) AC. This voltage was below the TS

allowable setting of 3660 VAC for the degraded voltage relays. Under non-

accident conditions, operation of the buses at this minimum voltage would result

in automatic actuation of the degraded voltage relays, separating the buses from

off-site power. Under post-accident conditions, the degraded voltage protection

relays are locked out and operation of the buses at 3600 VAC could result in

equipment mis-operation or damage.

6

Enclosure

Analysis. The team determined this to be a performance deficiency since the

operating procedures did not provide adequate guidance for determining

operability of the 115 kV Keene line. This issue was more than minor because it

was associated with the Mitigating Systems Cornerstone attribute of Procedure

Quality and affected the cornerstone objective of ensuring availability, reliability,

and capability of systems needed to respond to a loss of off-site power. The

issue screened as very low safety significance (Green) in Phase I of the SDP

because the failure to translate design requirements into operating procedures

was a design deficiency that was not found to result in a loss of function.

Specifically, the team did not identify any instances where the lack of procedural

guidance had resulted in an inadequate assessment of off-site power operability

or the inoperability of the electrical system or any components.

Enforcement. Technical Specifications 6.4.C, Procedures, requires that written

procedures be established, implemented, and maintained for actions to be taken

to correct specific and unforeseen potential malfunctions of systems or

components. Contrary to the above, the licensee did not establish adequate

procedures for assessing the operability of the 115 kV Keene line. Since this

finding is of very low safety significance and has been entered into the licensees

corrective action program (CR-VTY-2004-2803 and CR-VTY-2004-2804), it is

considered a non-cited violation, consistent with Section VI.A.1 of the NRC

Enforcement Policy. (NCV 05000271/2004008-02 Procedures for Assessing

Off-site Power Operability)

(3)

Degraded Voltage Relay Setpoint Calculations

Introduction. The team identified a Green non-cited violation of 10 CFR Part 50

Appendix B, Criterion III, Design Control, because the licensee did not use the

Technical Specification allowed voltage value in the calculations used to ensure

the degraded voltage relay dropout function would provide adequate voltage to

safety-related electrical equipment.

Description. As described in Section 8.5 of the Vermont Yankee Updated Final

Safety Analysis Report (UFSAR), the licensee has installed degraded voltage

relays, which are designed to protect the stations electrical equipment from

damage that could occur due to degraded voltage. The licensees Technical

Specifications (TS) allow a minimum degraded voltage relay setpoint of 3660

VAC; however, the licensees analysis of record, VYC-1088 Vermont Yankee

4160/480 Volt Short Circuit/ Voltage Study, did not evaluate the operability of

the connected electrical components at this minimum TS value. Instead, the

lowest voltage evaluated by VYC-1088 was based on the minimum expected

switchyard voltages, which were 3951 VAC for bus 3 and 3809 VAC for bus 4.

Consequently, motors were evaluated for voltage considerably above the

minimum voltage that could occur based on the TS value.

7

Enclosure

As a result, calculation VYC-1053 and VYC-1314, which determine worst-case

motor-operated valve (MOV) and motor control center (MCC) voltages, were also

non-conservative. In response to the teams concerns, the licensee initiated CR-

VTY-2004-2596. The operability determination (OD) for CR-VTY-2004-2596

identified two motors that did not meet calculation acceptance criteria and

provided justification for their operability. This OD also provided justification for

lower MCC control circuit voltages than previously analyzed. The licensee also

initiated CR-VTY-2004-2734 to address the effects of the postulated lower

voltage on MOV operation. The effect on the MOVs was not expected to be

significant due to the otherwise generally conservative approach used for MOV

calculations.

Analysis. The team determined this to be a performance deficiency because the

licensees calculations did not ensure the operability of electrical equipment at

the minimum TS value for the degraded voltage relay dropout setting. This issue

was more than minor because it was associated with the Mitigating Systems

Cornerstone attribute of Equipment Performance and affected the cornerstone

objective of ensuring availability, reliability, and capability of systems needed to

respond to a design basis accident. The issue screened as very low safety

significance (Green) in Phase I of the SDP because it was a design deficiency

that was not found to result in a loss of function. Specifically, the team did not

identify any instances where using the Technical Specification degraded voltage

allowable setpoint values would have resulted in inoperable equipment.

Enforcement. 10 CFR Part 50, Appendix B, Criterion III, Design Control,

requires that measures be established to assure that applicable regulatory

requirements and the design basis for structures, systems and components are

correctly translated into specifications, drawings, procedures and instructions.

Contrary to the above, the licensee used incorrect and non-conservative voltage

values in calculations performed to ensure that electrical equipment would

remain operable under degraded voltage conditions. Since this finding is of very

low safety significance and has been entered into the licensees corrective action

program (CR-VTY-2004-2596 and CR-VTY-2004-2734), it is considered a non-

cited violation, consistent with Section VI.A.1 of the NRC Enforcement Policy.

(NCV 05000271/2004008-03 - Degraded Voltage Relay Setpoint

Calculations)

(4)

Ungrounded 480 VAC Electrical System.

The team identified an unresolved item (URI) associated with the 480 VAC

circuit-breakers designed to detect and interrupt electrical malfunctions. An

unresolved item is an issue requiring further information to determine if it is

acceptable, if it is a finding or if it constitutes a deviation or violation of NRC

requirements. In this case, additional review will be required to determine if the

facility is in accordance with its design and/or licensing basis, since this was part

8

Enclosure

of the original design of the facility. Also, additional review will be required to

determine the safety significance of this issue.

The Vermont Yankee 480 VAC system consists of two 480 VAC load center

buses supplied through separate 4160/480 V transformers from the redundant

4160 VAC safety buses. The transformers are connected delta-delta and the

480 VAC system is ungrounded. Several non-safety related loads are supplied

from the safety-related load center buses and from safety-related MCCs. These

non-safety loads are not automatically disconnected during postulated accidents

but rather are shed manually depending on the specific accident scenario. The

load centers are equipped with 600 ampere circuit-breakers with long-time and

short-time, or long-time and instantaneous trip devices. The MCCs are equipped

with magnetic breakers with thermal overloads or thermal/magnetic breakers.

Each bus is provided with a ground detection system which consists of three

ground detection voltmeters and three potential transformers. The system only

provides local indication at the MCCs and does not annunciate in the control

room. The control room relies on the auxiliary operator round sheet voltage

recordings of the ground detection voltmeters to be informed of any ground fault

on the 480 V system. The ground detector does not actuate any protective

devices or indicate the location of the fault.

The team identified that since the 480 VAC electrical system at Vermont Yankee

is ungrounded, an arcing/intermittent ground fault could cause excessive

voltages to be impressed upon the system. Such a ground could begin on non-

safety related equipment that is unprotected from the effects of a postulated high

energy line break or seismic event. The installed electrical protective devices

designed to provide isolation between the safety and non-safety related loads

may not open during this scenario because the ungrounded system may not

provide a return current path until a second ground was formed. While such a

ground could possibly be detected with the installed ground detection

instrumentation, there would likely be insufficient time to detect and isolate the

ground before damage could occur to safety-related motors due to the possible

excessive voltages. (URI 05000271/2004008-04 - Ungrounded 480 VAC

Electrical System)

2.1.2

Reactor Core Isolation Cooling (RCIC) System

a.

Inspection Scope

During the inspection, the team reviewed selected RCIC system components to

ensure they would be capable of performing their required design functions for

both current licensing basis conditions and the proposed EPU conditions. The

team reviewed the RCIC pump and turbine, auxiliary equipment, various system

valves, and instrumentation and controls. The team conducted plant equipment

walkdowns, reviewed plant operating and test procedures, condition reports, test

9

Enclosure

results, maintenance history, vendor manuals, drawings, design calculations and

applicable sections of the UFSAR and the TS.

10

Enclosure

b.

Findings

(1)

Control Valve for RCIC Lube Oil Cooler

Introduction. The team identified a Green non-cited violation of 10 CFR Part 50,

Appendix B, Criterion III, Design Control, because the cooling water supply to

the lube oil cooler of the RCIC system was not installed as described in the RCIC

system design basis. Specifically, the pressure control valve for the lube oil

cooler water supply was not independent of air systems, and the piping between

the pressure control valve and lube oil cooler did not contain a restricting orifice.

Description. During a review of drawing G-191174, Sheet 2, Flow Diagram -

Reactor Core Isolation Cooling, Revision 23, the team noted that a pressure

control valve, PCV-13-23, was shown as having a connection to station

instrument air. The team noted that USFAR Section 4.7.5 stated that all

components necessary for initiating operation of RCIC were completely

independent of auxiliary ac power and station service air. The station instrument

air and service air systems are interconnected and are supplied from four AC

powered air compressors connected in parallel. Both the station instrument air

and service air systems are classified as non-nuclear safety related. The team

questioned the effect of the loss of the air supply to this valve. PCV-13-23 was

installed in the 2-inch cooling water supply line to the RCIC pump lube oil cooler

to regulate the flow of the cooling water supply from the RCIC pump discharge.

A relief valve, SR-13-26, was installed between PCV-13-23 and the lube oil

cooler for overpressure protection.

In response to the teams questions, the licensees engineering personnel

investigated this condition and determined that PCV-13-23 would fail in the fully

open position upon a loss of air. The licensee performed a hydraulic analysis of

the affected portion of the RCIC system during the inspection. The analysis

determined that fully opening the pressure control valve would have resulted in a

flow of approximately 170 gpm through the valve, as opposed to the design flow

of 16 gpm. The analysis also determined that the lube oil cooler, which has a

design pressure of 150 pounds per square inch gauge (psig), would have been

exposed to a maximum pressure of approximately 1100 psig. Both relief valve

SR-13-26 and relief valve SR-13-27, installed on the RCIC pump barometric

condenser, would have opened to pass the expected flowrate. The licensees

investigation determined that this condition has existed since the original

operation of the RCIC system.

The licensee documented this issue in condition report CR-VTY-2004-2535 and

performed an operability determination, which the team reviewed. The

operability determination stated that a loss of air was considered unlikely during

any of the events where the RCIC system was credited. It also concluded that, if

the air supply was lost, the lube oil cooler and associated piping components

would not rupture when exposed to the expected pressures. This was based, in

part, on vendor testing which showed that there was significant margin above

11

Enclosure

1100 psig before these components would rupture. With regard to the potential

loss of RCIC system capacity, the determination concluded that the RCIC pump

would have sufficient capacity to provide the required flow to the reactor vessel

even with the expected flow diversion. The licensee also initiated condition report

CR-VTY-2004-2536 because the RCIC design basis document identified PCV-

13-23 as a self-contained pressure control valve.

The licensee performed a limited extent-of-condition review during the inspection

to verify that a similar condition did not exist for other air-operated components.

No additional concerns were identified by the licensee during this review. The

team also performed an independent sampled-based review and did not identify

any additional issues. The licensee stated that a full extent-of-condition review

would be performed as part of the resolution of CR-VTY-2004-2535. At the time

of the inspection, the licensee was developing a plan to correct this design

deficiency.

The team also noted that the piping between the pressure control valve and lube

oil cooler did not contain a restricting orifice as described in the UFSAR. UFSAR

Figure 4.7-3 indicated that a flow-restricting orifice was installed downstream of

valve PCV-13-23. No such orifice exists in the system. The licensee initiated

condition report CR-VTY-2004-2537 to document this concern.

Analysis. The team determined this issue was a performance deficiency since

the licensee had not instituted measures to ensure that the RCIC system was

installed consistent with its design and licensing basis. This issue was more

than minor because it was associated with the Mitigating Systems Cornerstone

attribute of Equipment Performance and affected the objective of ensuring the

reliability of the RCIC system. The issue screened as very low safety

significance in Phase I of the SDP, because it was a design deficiency that was

not found to result in a loss of function. This deficiency would not have resulted

in the RCIC system becoming inoperable due to a loss of air to the lube oil cooler

pressure control valve.

A contributing cause of this finding is related to the cross cutting area of Problem

Identification and Resolution. The licensee had previously reviewed the failure

positions of air-operated equipment and issued a report, Compressed Air

Systems, dated July 16, 1989. During this review, the licensee did not identify

that the pressure control valve was not independent of the instrument air system.

In addition, the licensee did not fully assess all aspects of the issue associated

with the pressure control valve being supplied by instrument air rather than being

self contained in its initial operability determination associated with CR-VTY-

2004-2535. The licensee had to complete two additional supplemental

operability determinations to resolve the teams concerns.

Enforcement. 10 CFR Part 50 Appendix B, Criterion III, Design Control,

requires, in part, that design control measures be established and implemented

to assure that applicable regulatory requirements and the design basis for

12

Enclosure

structures, systems, and components are correctly translated into specifications,

drawings, procedures, and instructions. Contrary to the above, the licensee did

not implement measures to ensure that the design basis for the cooling water

supply to the lube oil cooler of RCIC was correctly translated into the

specifications, drawings, procedures, or instructions. Specifically, the installed

pressure control valve in the lube oil cooler water supply line was not

independent of air systems, and the installed piping between the pressure

control valve and lube oil cooler did not contain a restricting orifice. Because this

violation is of very low safety significance and has been entered into the

licensee's corrective action program (CR-VTY-2004-2535), this violation is being

treated as a non-cited violation consistent with Section VI.A of the NRC

Enforcement Policy. (NCV 05000271/2004008-05 Cooling Water Supply

Portion of RCIC Not Installed per Design Basis)

(2)

Failure To Correct Non-Conforming RCIC Pressure Control Valve

Introduction. The team identified a Green non-cited violation of 10 CFR Part 50,

Appendix B, Criterion XVI, Corrective Action, because the licensee failed to

correct a longstanding non-conformance associated with PCV-13-23, the control

valve that supplies cooling water to the RCIC lube oil cooler.

Description. During review of Operating Procedure (OP) 2121, Reactor Core

Isolation Cooling System, and OP 4121, Reactor Core Isolation Cooling

System Surveillance, the team identified that these procedures contained steps

to manually operate PCV-13-23 during RCIC operation. The team questioned

the reason for these steps, given that the RCIC system is designed to function

automatically as described in UFSAR Section 4.7.4.

The team determined that during initial start-up testing, problems were identified

with the automatic operation of this valve. These problems affected its ability to

properly regulate the supply of cooling flow to the lube oil cooler. During the

inspection, the licensee could not provide the team with an open condition report

identifying this problem. Additionally, the licensee did not have an analysis to

show that setting PCV-13-23 as described in the procedure would ensure an

adequate flow of cooling water to the lube oil cooler. Rather, the licensee used

the fact that RCIC bearing temperatures have been acceptable during

surveillance testing to justify that lube oil cooling was sufficient. However, the

team noted that the conditions that exist during surveillance testing may be

different from those existing under design conditions (for example, use of a

higher temperature suppression pool as a suction source and operation with

maximum expected RCIC room temperature). These conditions would result in

higher bearing temperatures when RCIC is operating under design conditions.

The team reviewed alarm response procedures for the RCIC bearing

temperature alarms and determined that they were adequate to prevent damage

to major RCIC components if the cooling flow was inadequate. However, the

13

Enclosure

manual operation of PCV-13-23 represents a longstanding operator work-around

that creates an additional operator burden and could challenge equipment

reliability if called upon to operate during an event.

Analysis. The team determined that the licensees failure to correct a

longstanding non-conformance with PCV-13-23 was a performance deficiency.

Specifically, operation of this valve in a mode other than automatic may have

challenged system operation if needed for an actual event. This issue was more

than minor because it was associated with the Mitigating Systems attribute of

Equipment Performance and affected the cornerstone objective of ensuring the

reliability of the RCIC system. The issue screened as very low safety

significance (Green) in Phase I of the SDP, because it was a design deficiency

that was not found to result in a loss of function. While PCV-13-23 did not

function automatically as designed, the licensee had implemented manual

actions as a compensatory measure for the operation of this valve.

Enforcement. 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action,

requires that measures be established to assure that conditions adverse to

quality, such as failures, malfunctions, deficiencies, deviations, defective material

and equipment, and non-conformances are promptly identified and corrected.

Contrary to the above, the licensee failed to correct a longstanding non-

conformance associated with PCV-13-23, the control valve that supplies cooling

water to the RCIC lube oil cooler. Because this issue is of very low safety

significance and has been entered into the licensees corrective action program

(CR-VY-2004-2535), this issue is being treated as a non-cited violation,

consistent with Section VI.A of the NRC Enforcement Policy.

(NCV 05000271/2004008-06 Failure To Correct Non-Conforming RCIC

Pressure Control Valve)

(3)

Potential Preconditioning of RCIC MOVs

The team identified a minor finding related to Vermont Yankees method of

testing RCIC system MOVs. The team determined that a procedural

requirement to conduct the quarterly RCIC system pump operability test prior to

system MOV surveillance testing resulted in the operation of several RCIC

system valves immediately before their required stroke-time testing. This

practice could have affected the results of the stroke-time testing by

preconditioning the valves and this potential impact was not evaluated by the

licensee. This issue was evaluated using Inspection Manual Chapter 0612 and

determined to be minor because it applied to a limited number of valves, most of

the valves would not have affected system operability, a review of these valves

performance history indicated that there was significant margin to stroke-time

limits, and no operability issues were noted during past testing.

14

Enclosure

2.1.3 Residual Heat Removal System (RHR)

a.

Inspection Scope

During the inspection, the team reviewed selected components of the RHR

system to ensure the system and components would be capable of performing

their required design functions, for both current conditions and those conditions

that would exist under the proposed EPU. In its power uprate submittal to the

NRC, the licensee stated that it would need to take credit for the containment

overpressure that would exist under postulated accident conditions in order to

ensure adequate net positive suction head (NPSH) was available to the RHR

pumps. The team did not assess the appropriateness of allowing credit for

containment overpressure. The team did, however, perform specific reviews of

the licensees calculations to ensure that the RHR pumps would have adequate

NPSH assuming such credit is given. The teams review included pressure

losses associated with the RHR suction strainers, potential bubble ingestion and

the potential for torus vortexing.

b.

Findings

No findings of significance were identified.

2.1.4

Safety Relief Valves and Code Safety Valves

a.

Inspection Scope

Due to the increased steam flow that would result from the licensees proposed

EPU, the team conducted a detailed review of General Electric (GE) Topical

Report T0900, which evaluated the adequacy of the safety relief valves (SRVs)

for EPU conditions. The team reviewed the GE analysis and licensee

modification package associated with the installation of a third American Society

of Mechanical Engineers (ASME) Code safety valve with increased relief

capacity for EPU conditions. The team also reviewed the out-of-service and

calibration history for the existing SRVs. Lastly, the team reviewed the back-up

nitrogen bottle system, which was added to ensure an adequate supply of

nitrogen to the SRVs.

b.

Findings

No findings of significance were identified.

2.1.5

Reactor Feedwater and Condensate Components

a.

Inspection Scope

Due to the increased feedwater flow that would be required under the licensees

proposed EPU, the team assessed the adequacy of modifications to the reactor

15

Enclosure

feedwater system. Because of the increased feedwater flow requirements, the

licensee would need to run all three reactor feedwater pumps under EPU

conditions, reducing the capability to mitigate feedwater transients. Included

within the teams review was a recent seal replacement on a feedwater pump

and modifications to the reactor feedwater pump low-suction pressure trip and

reactor recirculation system runback. The team also reviewed flow control valve

FCV-102-4 and its associated controls, since failure of this valve to open could

disable low flow capability for the condensate pumps, resulting in a loss of

feedwater flow during low-flow demands.

The team reviewed aspects of the licensees Flow Assisted Corrosion (FAC)

Program and reviewed the adequacy of the thermal sleeves located at

connections between the RCIC and feedwater systems and the reactor vessel.

The team conducted a walkdown of the main feedwater and condensate pumps

and adjacent piping with Vermont Yankee engineering personnel. Lastly, the

team inspected the feed and condensate panels in the main control room. The

reviews were conducted to identify any alignment discrepancies or visible signs

of deficient material conditions.

b.

Findings

No findings of significance were identified.

2.1.6

Reactor Building-to-Torus Vacuum Breaker System

a.

Inspection Scope

The team reviewed the components associated with the reactor building-to-torus

vacuum breaker system. This system includes two redundant air-operated

vacuum breaker valves, each in series with a check valve. This system functions

to relieve pressure from the reactor building to the torus to protect the structural

integrity of the torus. Additionally, the system must remain leak-tight from the

torus to the reactor building to maintain primary containment isolation. In

reviewing these components, the team assessed condition reports, operating

procedures, test results, maintenance and modification history, drawings and

applicable sections of the UFSAR and TS. The teams review included

verification that these components would be capable of performing their required

design functions for both current licensing basis conditions and the proposed

EPU conditions.

The team also completed a walkdown of the reactor building-to-torus vacuum

breakers and their air-operators, check valves and associated piping.

Additionally, the team reviewed operator burden and work-around lists to identify

any deficiencies that could affect operation of these components.

16

Enclosure

b.

Findings

No findings of significance were identified.

2.1.7

Review of Transient Analysis Inputs

a.

Inspection Scope

During the inspection, the team reviewed selected plant parameters used by the

licensee as inputs into its transient analyses. Included in this review were

analyses performed solely to support the proposed EPU. In conjunction with this

review, the team conducted plant equipment walkdowns, reviewed plant

procedures and calculations, and discussed calculations and parameters with

plant design engineers.

b.

Findings

Introduction. The team identified a finding of very low safety significance

involving a non-cited violation of 10 CFR Part 50, Appendix B, Criterion III,

Design Control, because the licensee had neither established the correct

condensate storage tank (CST) temperature limit for use in the plant transient

analyses nor translated this CST temperature into plant procedures.

Description. During the inspection, the team noted that although the CST

temperature was monitored on operator logs, the licensee had not established a

maximum temperature limit for the CST. A CST temperature limit of 90 degrees

Fahrenheit (EF) was used as an input to several plant transient analyses,

including Transient Analysis VYC-1825, Analysis of Suppression Pool

Temperature for Relief Valve Discharge Transients, Revision 0. The CST

temperature used for this analysis was based on the maximum ambient summer

temperature of approximately 90EF and did not take into account the recirculated

hotwell water that has on occasion raised the CST temperature to approximately

120EF.

In addition, the team noted that in December 2002, the licensee had also

identified that there was no maximum CST temperature limit and that CST

temperature had previously exceeded the temperature assumed in the high

pressure coolant injection (HPCI) and RCIC design basis documents for

calculating pump NPSH. The licensee documented this condition in CR-VTY-

2002-2942. At that time, the licensee performed a limited evaluation and

determined that the non-conservative CST temperature had little to no effect on

the transient analyses. The team reviewed this evaluation and determined that

transient analysis VYC-1825, which assessed the adequacy of the NPSH of the

pumps supplied from the CST or the suppression pool, would be affected by the

increased CST temperature.

17

Enclosure

In response to the teams concerns, the licensee reviewed the transient analyses

and identified that the relief valve discharge transient was the most limiting. The

licensee determined that using the higher CST temperature of 120EF led to an

increase in suppression pool temperature, which reduced the net positive suction

head margin for the most limiting component, the core spray pumps, from 0.5

feet to 0.0 feet. The team reviewed the input parameters to the NPSH

calculation for the core spray pumps and determined that because of

conservatism in other aspects of the calculation, the core spray pumps would still

have adequate NPSH to remain operable.

The team determined that in the licensees EPU submittal to the NRC, the

licensee had not taken into account the higher CST temperature for all transient

scenarios. As a result of this issue, the licensee began an extent-of-condition

review of all calculations, drawings, and inputs to transient analyses where a

non-conservative maximum CST temperature was used, both for current plant

conditions (CR-VTY-2004-2600) and for analyses associated with the planned

EPU (CR-VTY-2004-2799). The licensee also instituted a tentative maximum

temperature limit of 120EF for the CST.

Analysis. The team determined this issue was a performance deficiency since

the licensee had not used the correct CST temperature in the plant transient

analysis and had not translated the CST temperature limit into the station

procedures. Specifically, using the correct CST temperature in the relief valve

discharge transient analysis resulted in a higher suppression pool temperature

and lowered the available net positive suction head to the core spray pumps.

This issue was more than minor because it was associated with the Mitigating

Systems Cornerstone attribute of Equipment Performance and affected the

cornerstone objective of ensuring the reliability of the core spray system. The

issue screened as very low safety significance (Green) in Phase I of the SDP,

because it was a design deficiency that was not found to result in a loss of

function. Although available NPSH margin was lowered, adequate NPSH for the

core spray pumps remained due to the conservatism that existed in other

aspects of the licensees NPSH analysis.

A contributing cause of this finding is also related to the cross-cutting area of

Problem Identification and Resolution. The licensee identified this issue in

December 2002, but concluded that the non-conservative CST temperature had

little to no effect on the transient analyses.

Enforcement. 10 CFR Part 50 Appendix B, Criterion III, Design Control,

requires, in part, that design control measures be established and implemented

to assure that applicable regulatory requirements and the design basis for

structures, systems, and components are correctly translated into specifications,

drawings, procedures, and instructions. Contrary to the above, the licensee had

neither established the correct condensate storage tank (CST) temperature limit

for use in the plant transient analyses nor translated the CST temperature limit

into plant procedures. Because this finding is of very low safety significance and

18

Enclosure

has been entered into the licensee's corrective action program (CR-VTY-2004-

2600, CR-VTY-2004-2793, and CR-VTY-2004-2799), this finding is being treated

as a non-cited violation consistent with Section VI.A of the NRC Enforcement

Policy. (NCV 05000271/2004008-07 Failure to Implement Adequate Design

Control for Condensate Storage Tank Temperature)

2.2

Review of Operator Actions

a.

Inspection Scope

During the inspection, the team reviewed risk-significant, time-critical operator

actions that had little margin between the time required and time available to

complete the action. The team determined the review scope and performed the

detailed review of critical operator actions using risk information contained in the

licensees PRA, Operator Task Validation Studies, Emergency Operating

Procedures (EOPs), Power Uprate Safety Analysis Report (PUSAR), Appendix R

Analyses, Off-Normal and Operating Procedures, and the licensees CR

database. The team performed a detailed review of the following time-critical

and low-margin operator actions:

Monitoring of the Vernon tie line to ensure availability as a station

blackout source.

Manual initiation of the RCIC system using alternate shutdown panels.

Initiation of the standby liquid control (SLC) system with the main

condenser failed.

Manual initiation or control of feedwater and condensate flow under

normal and transient conditions, in single element or three element

control.

Manual initiation of RCIC system from the control room.

For all the above operator action scenarios, the team verified that operating

procedures were consistent with operator actions for a given event or accident

condition and that the operators had been adequately trained and evaluated for

each action. The team also reviewed the fidelity between EOPs, pump NPSH

calculations and containment spray operation to ensure proper EOP

implementation. Control room instrumentation and alarms were also reviewed by

the team to verify their functionality and to verify alarm response procedures

were accurate to reflect the current plant configuration. Additionally, the team

performed a walkdown of accessible field portions of the reviewed systems to

assess material condition and to verify that field actions could be performed by

the operators as described in plant procedures.

19

Enclosure

The team also reviewed each operator action to assess the impact the proposed

EPU could have on further reducing the margin available for task completion and

to verify that the associated EPU plant modifications would be reviewed by the

licensee for their effect on the operators ability to complete the critical actions

within the required time parameters.

b.

Findings

Introduction. The team identified a Green non-cited violation of 10 CFR Part 50,

Appendix B, Criterion III, Design Control, because the licensee did not

adequately coordinate between the operations department and the engineering

organization procedure revisions that increased the length of time required to

place the reactor core isolation cooling system in service from the alternate

shutdown panels. As a consequence, the licensee did not revise its Vermont

Yankee Safe Shutdown Capability Analysis (SSCA).

Description. The Vermont Yankee SSCA relies on the reactor core isolation

cooling (RCIC) system to be placed in service from the alternate shutdown

panels prior to reactor water level reaching the top of active fuel following a loss

of feedwater flow. In December 1999, the Vermont Yankee SSCA documented

that, for the present day 100 percent power level, it would take 25.3 minutes for

reactor water level to reach the top of active fuel following a loss of feedwater

and that it would take approximately 15 minutes to place the RCIC system in

service from the alternate shutdown panels. The Vermont Yankee SSCA

concluded adequate margin (approximately 10 minutes) existed to ensure that

the RCIC is placed in service prior to reactor water level reaching the top of

active fuel.

In June 2001 the Operations Department conducted an additional review of the

time it would take to place RCIC in service from the alternate shutdown panels.

The Operations Department determined that, using the version of the procedure

in effect in June 2001, it would take 19.3 minutes to place RCIC in service from

the alternate shutdown panels .

During the inspection, using the version of the procedure in effect during the

inspection period, the team performed a field walkdown with licensed operators

to validate that RCIC could be placed into service from the alternate shutdown

panels within 19.3 minutes. The team noted that since June 2001, the licensee

had added steps in the procedure to comply with Electrical Safety Standards.

Based on the teams validation, the total time to place RCIC in service from the

alternate shutdown panels was determined to be approximately 21 minutes. The

team concluded that this time was still within the 25.3 minute limit stated in the

Vermont Yankee SSCA.

Additionally, the team found that the licensee had not revised the December

1999 Vermont Yankee SSCA to reflect the June 2001 time estimate or present

day version of the procedure to place RCIC in service from the alternate

20

Enclosure

shutdown panels. The team also determined that the licensees engineering

organization was unaware that the time to complete the task had increased from

approximately 15 to 21 minutes and had effectively reduced the time margin

available for event mitigation from about 10 minutes to 4 minutes at the current

full power level. As a consequence, the engineering organization had not

revised the Vermont Yankee SSCA.

The team reviewed the impact the licensees proposed EPU would have on this

issue. Based on an EPU power level, the licensee calculated it would take 21.3

minutes for reactor water level to reach the top of active fuel following a loss of

feedwater. Therefore, the team concluded that for the proposed EPU, the ability

to place the RCIC in service from the alternate shutdown panels (21 minutes)

prior to reactor water level reaching the top of active fuel (21.3 minutes) is

questionable. Additionally, the team found that the December 1999 value of the

time to place RCIC in service from the alternate shutdown panel was used in

licensee Technical Evaluation (TE) 2003-065, Appendix R PUSAR Input. The

TE was then used as an input to the Vermont Yankee Power Uprate Safety

Analysis Report (PUSAR) and submitted to the NRC as part of the power uprate

application. The licensee initiated CR-VTY-2004-2552 and 2004-2614 in

response to these issues.

Analysis. The team considered this finding to be a performance deficiency since

the licensee did not coordinate between the operations department and

engineering department regarding procedure revisions which increased the time

required to place the RCIC in service from the alternate shutdown panels. This

issue was more than minor because it was associated with the Mitigating

Systems Cornerstone attribute of Human Performance and affected the

cornerstone objective of ensuring the availability of the RCIC system.

Furthermore, this finding resulted in the use of the December 1999 value of time

to place RCIC in service from the alternate shutdown panel in documents

submitted to the NRC as part of the Vermont Yankee PUSAR. The issue

screened as very low safety significance (Green) in Phase I of the SDP because

it was a design deficiency that was not found to result in a loss of function. At

the present 100 percent power level, RCIC could be placed in service from the

alternate shutdown panels prior to reactor level reaching the top of active fuel.

Enforcement. 10 Part CFR 50, Appendix B, Criterion III, Design Control,

requires, in part, that revision of documents shall be coordinated among

participating organizations. Contrary to above, between June 2001 to

September 2004, the licensee did not adequately coordinate between the

operations department and the engineering organization regarding procedure

revisions that increased the length of time required to place the reactor core

isolation cooling system in service from the alternate shutdown panels. Because

this finding is of very low safety significance and has been entered into the

licensees corrective action program, it is being treated as a non-cited violation,

consistent with Section VI.A of the NRC Enforcement Policy. (NCV

21

Enclosure

05000271/2004008-08 Failure to Coordinate Information Related to Safe

Shutdown Capability Analysis Report)

2.3

Review of Operating Experience and Generic Issues

a.

Inspection Scope

During the inspection, the team reviewed selected operating experience issues

that had been identified at other facilities for their possible applicability to

Vermont Yankee. Several issues that appeared to be applicable to Vermont

Yankee were selected for a more in-depth review. Additional consideration was

given to those issues that might be impacted by the licensees planned EPU.

The issues that received a detailed review by the team included:

An NRC inspection finding at the Point Beach Nuclear Power Station,

documented in IR 50-266/2004-004, concerning the use of a non-

conservative CST temperature in accident and transient analyses.

Licensee Event Report (LER) 2003-003-00, issued on September 29,

2003, from the Byron Station where the licensee had exceeded its

licensed maximum power level due to inaccuracies in feedwater

ultrasonic flow measurements caused by signal noise contamination.

An NRC inspection finding from the Peach Bottom Station, documented

in IR 50-277/2002-011, concerning inadequate Emergency Operating

Procedures to return the suction of the High Pressure Coolant Injection

(HPCI) system from the suppression pool to the CST in order to ensure

self-cooled HPCI lube oil temperatures remained within analyzed limits.

Information Notice 2001-13, Inadequate Standby Liquid Control Relief

Valve Margin, issued on August 10, 2001, concerning a problem

identified at the Susquehanna Station involving inadequate SLC system

relief valve margin after a power uprate increased the relief valve setpoint

pressure, thereby increasing SLC discharge pressure. This was

complicated by using a non-conservative maximum reactor vessel

pressure in accident analysis.

NRC Generic Letter (GL) 96-05, Periodic Verification of Design-Basis

Capability of Safety-Related Power-Operated Valves, pertaining to the

periodic testing of motor-operated valves. With regard to this GL, the

team reviewed the NRC safety evaluation report that documented the

NRC staffs understanding of the licensees commitments and plans for

establishing a periodic verification program. The team also reviewed

procedures, test and maintenance records, corrective action documents,

and correspondence relative to four RCIC system MOVs.

22

Enclosure

23

Enclosure

b.1

Findings

Introduction. The team identified a Green non-cited violation of 10 CFR Part 50,

Appendix B, Criterion XI, Test Control, because the licensee conducted

periodic testing of MOVs using test instrumentation that had not been validated

to be adequate for its intended function. Additionally, the test procedures did not

incorporate requirements and acceptance limits contained in applicable design

documents.

Description. In its SER dated December 14, 2000, the NRC provided its basis

for accepting Vermont Yankees response to NRC GL 96-05, Periodic

Verification of Design-Basis Capability of Safety-Related Power-Operated

Valves. The SER documented the licensees intentions to use motor current

data acquired from the MCCs as a way of detecting actuator and valve

degradation. The SER also documented Vermont Yankees intention to verify

this testing methodology by comparing the data with direct torque and thrust

measurements at the valve over extended intervals. In addition, the SER stated

the licensee would have to determine MCC test instrumentation accuracies and

sensitivities to MOV degradation, as well as evaluate changes in MCC data and

MOV thrust and torque performance.

During the inspection, the team concluded that Vermont Yankee had not

validated the adequacy of the MCC diagnostic test instrumentation with respect

to its ability to provide detect actuator torque and stem thrust degradation that

would indicate actuator or valve degradation. A cooperative effort with

Crane-MOVATS to perform the required validation was terminated in March

2004, when the parties determined that a statistically meaningful and valid

correlation of MCC to direct diagnostic test data that would allow setting switches

could not be completed. As a result of the teams concerns, the licensee entered

this issue into the corrective action program on CR-VTY-2004-2802.

The team also identified that separate procedures (OP 5217 and OP 5287) had

been established to obtain and evaluate MCC diagnostic test data; however,

neither of these procedures included specific acceptance criteria tied to stem

thrust or available design margin. The SER stated that an acceptance

procedure for MCC testing was under development to specify parameters to be

monitored for trending, including specific acceptance criteria. The team

observed that the lack of acceptance criteria could lead to the inconsistent

evaluation of the data between different reviewers. Also, the documentation of

problem identification and resolution of issues identified through test data review

was missing or unclear. An inspector-identified example of entering improper

test data into the MOV test package was entered into the corrective action

program on CR-VTY-2004-2623.

The team also identified that no administrative or procedural prohibition had

been implemented against using MCC testing to set MOV switches, and that the

procedures specifically allowed establishing a baseline with MCC testing

24

Enclosure

(OP 5287). The MOV program had been revised in 2002 to eliminate any

periodicity requirements for at-the-valve diagnostic testing that can measure

torque and thrust to known accuracies. The team identified and the licensee

confirmed that the MCC test equipment had been used in at least one instance

to set MOV switches on one of the four RCIC valves reviewed. Also, the team

identified several cases where diagnostic testing following replacement of the

valve packing was limited to MCC testing. The team noted that packing

replacement affects stem friction and consequently changes in stem thrust.

Since the MCC testing instrumentation had not been validated, the team

concluded that the change in stem friction from initial set-up was indeterminate

for these valves.

Analysis. The performance deficiency was the failure to validate motor-operated

valve test instrumentation to ensure its adequacy and to establish test

procedures with adequate acceptance criteria tied to stem thrust or available

design margin. Specifically, there was no analysis demonstrating that testing

conducted at the MCC ensured the development of proper operating thrust at the

valve to ensure the MOV would perform satisfactorily under design basis

conditions. This issue was more than minor because it was associated with the

Mitigating Systems Cornerstone attribute of Equipment Performance and

affected the cornerstone objective of ensuring the availability, reliability, and

capability of systems and components that respond to initiating events.

Specifically, the unvalidated test method had the potential to affect the reliability

of safety-related motor-operated valves. The issue screened as very low safety

significance (Green) in Phase I of the SDP, because it was a qualification

deficiency that was not found to result in a loss of function. The team did not

identify any examples of degraded or inoperable valves during the inspection

and noted that the design basis calculations for the MOVs reviewed had

available thrust margin of greater than 60 percent.

The inspectors also identified that a contributing cause of the finding was related

to the human performance cross-cutting area, in that, the licensee did not

manage NRC commitments and conditions documented in the SER for the

GL 96-05 MOV periodic verification program.

Enforcement. 10 CFR Part 50, Appendix B, Criterion XI, Test Control, requires

that a test program be established to ensure that all testing required to

demonstrate that systems and components will perform satisfactorily in service is

performed in accordance with written test procedures which incorporate the

requirements and acceptance limits contained in applicable design documents.

The test procedures shall include provisions for ensuring that adequate test

instrumentation is available and used. Contrary to the above, Vermont Yankee

had conducted MOV diagnostic tests using procedures that did not include

acceptance limits which were correlated to and based on applicable (stem thrust

and torque) design documents. Additionally, MOV diagnostic testing had been

conducted solely from the motor control centers using test instrumentation that

had not been validated to ensure its adequacy. Because this finding is of very

25

Enclosure

low safety significance and has been into Vermont Yankees corrective action

program (CR-VTY-2004-2802 and CR-VTY-2004-2644), it is being treated as a

non-cited violation, consistent with Section VI.A of the NRCs Enforcement

Policy. (NCV 05000271/2004008-09 Failure To Establish Adequate MOV

Periodic Test Program)

b.2

Observations

The team also had other observations regarding the licensees NOV program.

The team concluded these observations did not impact valve operability due to

existing value capability margins.

The team identified that Vermont Yankee had not maintained current the risk

ranking of MOVs. At the time that the SER was issued, the licensees risk

ranking of the MOVs was considered acceptable. During a review of program

documents during this inspection, the team noted that low- and medium-risk

MOVs were specified for test at every other refueling outage, whereas, high-risk

MOVs were specified for testing every refueling outage. For the RCIC system

MOVs reviewed, the team noted that several valves had the same risk

achievement worth (RAW), but they were assigned different risk rankings in the

MOV program documents and consequently were not tested at the same

periodicity. Discussions with Vermont Yankees risk analyst indicated that the

licensees PRA had been updated in 2000 and May 2004; however, the updated

PRA data were not reflected back into the MOV risk ranking. This issue was

entered into the corrective action program on CR-VTY-2004-2798.

The team also concluded that Vermont Yankees trending methods to identify

degradation from design basis conditions were informal. The SER documented

the existence of established procedures to review and trend MOV failure and

diagnostic test data every two years. Primary MOV parameters identified for

trending were various thrust values, stem friction coefficient, load sensitive

behavior and dynamic margin. The SER noted that Vermont Yankee would

perform quantitative and qualitative assessments looking for overall changes in

MOV performance, including the use of diagnostic trace overlays and analysis.

The team found that the procedure referenced in the SER (DP 0210) had been

canceled. The trending of alternating current MOVs was moved to the

procedure for evaluating MCC test data; however, a procedure for trending direct

current MOVs had not been established. Currently, Vermont Yankees trending

program consists of reviewing the data from a diagnostic test to the results of the

previous test, which may not identify degradation from the established baseline

or identify slow but continual degradation. This issue was entered into the

corrective action program on CR-VTY-2004-2644.

4OA6 Meetings, Including Exit

26

Enclosure

The team presented the issues identified during the inspection to Mr. Dreyfuss and other

members of the licensees staff at a team debrief on September 3, 2004.

On October 27, 2004, the inspection team leader provided the preliminary results of the

inspection, including risk significance and enforcement, to Mr. Bronson, Mr. Dreyfuss,

and other members of licensees staff in a teleconference call.

The preliminary results of the inspection were also included in a letter to Vermont

Yankee Nuclear Power Station dated November 5, 2004, which was originally issued in

preparation for a planned public exit meeting.

A final closeout discussion on the inspection was held with Mr. Thayer, Mr. Bronson and

other members of the licensees staff via teleconference on November 23, 2004. The

Vermont State Nuclear Engineer was invited to the closeout discussion, but was not

available to attend.

Attachment

ATTACHMENT A

Summary of Items Reviewed

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

115 kV - Breaker K1

Transformer T-4 feed to 115 kV bus: required

to supply power from the 345 kV switchyard

to the Startup Transformers.

No automatic actions required except fault clearing;

safety busses would disconnect or be prevented

from connecting to circuit after a fault.

115 kV - K.1 Logic Relay

RCIC logic relay K.1 fails to operate on

demand. Rationale: Malfunction of RCIC

turbine trip instrumentation could cause loss

of RCIC System.

The inspectors found no specific operator action for

this component and that a failure of the logic relay

would result in control room alarms which would be

responded to by the operators. The inspectors found

that related control room alarms were functioning

properly, and that the associated alarm response

procedures were current.

125 V Battery B-1 and A-1

Station Battery: Supplies power to the station

125 VDC loads when the battery chargers

are not available.

Detailed review completed.

24 Vdc - ES-24DC-2

Power Supply Converter: Supplies power to

the 24 VDC ECCS Analog Trip System.

No low margin or other issues identified.

345 kV - Breaker 381-1

Northfield 345 kV line to 345 kV North Bus:

required to provide power from the Northfield

381 to the 345 kV switchyard.

Detailed review completed.

4 Kv - Breaker 12

Bus 1 Feed Breaker from UAT: required to

open on generator trip to enable access of

one safety train to the offsite source through

the SUT

No low margin issues identified.

A-2

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

4 Kv - Breaker 13

Bus 1 Feed Breaker from SUT: required to

close on generator trip to enable access of

one safety train to the offsite source through

the SUT .

Detailed review completed.

4 Kv - Breaker 22

Bus 2 Feed Breaker from UAT: required to

open on generator trip to enable access of

one safety train to the offsite source through

the SUT.

The inspectors found that the only operator action

for this component was breaker open/close

operation. Additionally, the inspectors found that the

related control room alarms were functioning

properly and that the associated alarm response

procedures were current. The inspectors found no

issues with this component related to operator

actions.

4 Kv - Breaker 23

Bus 2 Feed Breaker from SUT: required to

close on generator trip to enable access of

one safety train to the offsite source through

the SUT.

Detailed review completed.

4 Kv - Breaker 3V

Vernon Supply Breaker to Bus 3: required to

supply power from the Alternate AC Power

source to one 4160V safety bus.

No specific issues identified with breaker. Other

issues reviewed as part of overall Station Blackout

Capability.

4 Kv - Breaker 3V4

Vernon Tie Breaker: required to supply

power from the Alternate AC Power source

to either 4160V safety bus.

Detailed review completed.

4 kV UV Relays

4160V Undervoltage Relays: required to

provide adequate voltage to safety-related

AC loads, reset setpoint must be optimized

to prevent spurious loss of offsite power.

Detailed review completed.

A-3

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

69 kV - Vernon Generator

Vernon Hydroelectric generator station:

required to supply power from the Alternate

AC Power source to either 4160V safety bus.

Detailed review completed.

69 kV to 4160 V Vernon

Transformer

Vernon Tie Transformer: required to supply

power from the Alternate AC Power source

to either 4160V safety bus.

Detailed review completed.

125 VDC Distribution

Panels

Supplies 125 VDC loads.

Detailed review completed.

Alignment of RHRSW to

the RPV

Operator fails to align the RHRSW injection

to RPV.

Aligning RHRSW injection to the RPV is one of the

methods which can be used for RPV injection to

prevent core damage in accordance with EOPs

given an ATWS scenario. The validated time

through simulator observation was 1 minute to

complete the actions for alignment. Additionally,

prior to using RHR SW for RPV injection, other

systems such as condensate/feedwater , CRD, and

RHR will be used to attempt to fill the RPV. The

operators are regularly trained and evaluated in this

event scenario further reducing the likelihood of the

task not being completed within the required time.

Bus Transfer Scheme

Circuit breakers, synchronism check relays,

timing relays, and voltage relays required to

enable transfer of 4160V buses from the Unit

Aux Transformer to the Startup

Transformers.

Detailed review completed.

A-4

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

Closure of Vernon Tie

Breakers

Operator fails to close the Vernon tie

breakers.

One of the primary AC power recovery actions in the

event of a loss of normal power is to use the

dedicated tie line from the Vernon hydro Station to

power either 4260VAC Bus 3 or 4 (vital power). The

action is performed by the operators in the main

control room by manipulating switches for 2 DC

powered breakers. Validation studies and operator

observation in the simulator have shown that the

task can be accomplished in less than 4 minutes.

Adequate margin exists currently and for the CPPU

to accomplish the action. Additionally, operator

response to loss of power events is trained regularly

in the simulator and classroom. While no issues

identified with VY operator actions, a finding was

identified with the licensee's overall station blackout

response.

A-5

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

Condensate Pump

Review condensate operation before and

after the power uprate (including recirc pump

runback modification).

The Condensate and Feedwater system

does not directly perform any safety-related

function. Portions of the Feedwater system

and check valves provide Reactor Coolant

Pressure Boundary and Containment

Isolation functions. The condensate pumps

1) supply water to the Feedwater pumps and

2) provide sufficient NPSH for operation of

the FW pumps. The loss of a condensate

pump could be a contributing factor to a

transient initiation.

The condensate pumps are directly impacted

by the EPU due to the need to increase the

flow volume by approximately 20%.

No low margin or other issues identified.

Containment Pressure

During a loss of coolant event or an ATWS

the containment pressure will be elevated

and the suppression pool level will increase.

Detailed review completed.

CST Transient Analysis

Temperature

Non-conservative

Transient analysis Condensate Storage Tank

Temperature non-conservative compared to

actual maximum operating temperatures.

This issue stems from a similar event at

Point Beach.

Detailed review completed.

A-6

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

CST Level Instrumentation

Rationale: Important for maintaining required

CST inventory for RCICS and controlling

automatic transfer of RCICS suction to the

suppression pool.

Detailed review completed.

CV-109

Failure of check valve CV-109 (valve

between the N2 bottle and the SRV) to open.

Failure of this check valve to open will

prevent N2 supply to the Main Steam Safety

Relief Valves.

Detailed review completed.

CV-19

RCIC check valve CV-19 (RCIC suction

check valve from the CST) fails to open on

demand. This valve must open to provide

flow from CST to RCIC pump suction, and

close to prevent flow from torus to CST

during RCIC pump suction transfer.

A detailed review was not performed for this check

valve because no performance problems were

indicated from the maintenance history.

A-7

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

CV-2-1A, 1B, 1C

RFP discharge check valves. They are risk

significant because if they fail to close

following an RFP trip they could make other

RFPs inoperable.

Prior to EPU two pumps are operational.

After EPU three pumps will be operational.

When two pumps are operational, one of the

MOVs, 4A, 4B or 4C will be closed for the

non-operational pump as such, this is not a

current potential event. However, after EPU

the third valve will not be closed thus this is a

potential failure scenario.

A detailed review was not performed for these check

valves because no performance problems were

indicated from the maintenance history.

CV-22

RCIC check valve CV-22 (RCIC injection

path discharge check valve) fails to open on

demand. This valve must open for RCIC

injection flow. The valve must also fully close

when the pump is not in operation to prevent

back-leakage and a possible waterhammer.

Detailed review completed.

A-8

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

CV-2-27B

This valve is the feedwater isolation valve

upstream of the RCIC injection path. The risk

significant function of the component is to

close to prevent RCIC from flowing back into

the feedwater system.

EPU uprate will increase the flow through this

check valve by approximately 20%, however

the function of the valve is not altered.

A detailed review was not performed for this check

valve because no performance problems were

indicated from the maintenance history.

CV-2-28B

Feedwater check valve CV-28B ('B'

feedwater line check valve inside

containment) fails to open on demand. This

valve is located on drawing G-191167, H-5.

Failure to open will prevent flow from either

the RCIC or the Feedwater system.

EPU uprate will increase the flow through this

check valve by approximately 20%, however

the function of the valve is not altered.

A detailed review was not performed for this check

valve because no performance problems were

indicated from the maintenance history.

CV-2-96A

Feedwater check valve V96A fails to open on

demand. Failure of this valve will prevent flow

from either the RCIC or the FW system.

EPU uprate will increase the flow through this

check valve by approximately 20%, however

the function of the valve is not altered.

A detailed review was not performed for this check

valve because no performance problems were

indicated from the maintenance history.

A-9

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

CV-40

RCIC check valve CV-40 (RCIC suction

check valve from the suppression pool) fails

to open on demand. This valve must open to

provide a flow path from the torus to the

RCIC pump suction.

A detailed review was not performed for this check

valve because no performance problems were

indicated from the maintenance history or walkdown.

CV-6/7

RCIC check valves CV- 6/7 (RCIC turbine

exhaust check valves to torus) fails to open

on demand.

Detailed review completed.

CV-72-109

Failure of check valve CV-109 (N2 bottle

supply check valve to the plant N2 system) to

close. The component is risk significant

because if the check valve failed to close, the

N2 bottle could bleed down to the plant N2

system.

Detailed review completed.

Digital Feedwater

Control/Single Element

Control

Following the modification that installed the

digital feedwater control system, the licensee

had problems with loss of inputs to the

three-element controller (steam flow). This

resulted in a reactor level transient. Since the

event the plant had been operating in

single-element control. Evaluate the

modification and the acceptability of

operating in single-element. Also determine if

operation in single-element control would

challenge the licensee's assumption that the

plant would not scram following a single

reactor feed pump trip, post-uprate.

Detailed review completed.

A-10

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

DPIS-83/84

Spurious high steam flow signal. This steam

flow instrument isolates RCIC steam in the

event of a line rupture (indicated by high

flow). Spurious isolation would result in the

loss of RCIC flow.

These instruments are not included because there is

significant margin in the setpoint to detect a steam

line rupture, as well as margin between the normal

operating point and the setpoint.

EOP/NPSH Fidelity

Verify fidelity between Emergency Operation

Procedures and NPSH calculations and

Containment Spray operation.

Detailed review completed.

FCV-2-4

FCV.4 (condensate pump minimum flow

valve) fails to open on demand.

Detailed review completed.

FCV-2-4 Instrumentation

Failure of FCV.4 (condensate pump

minimum flow valve) control instrumentation.

Detailed review completed.

Feed/Condensate Control

Operator fails to initiate and/or control

feedwater/condensate.

Detailed review completed.

FT-58/FE-56

RCIC pump discharge flow instrument. This

instrument is associated with the RCIC

turbine control logic.

Detailed review completed.

GE SIL 351

GE SIL 351 - HPCI and RCIC Turbine

Control System Calibration.

Vermont Yankee implemented SIL 351R.2 and

provided the procedural changes recommended in

the SIL for the HPCI system (OP 5337 Rev. 7). SIL

351 does not apply to RCIC since RCIC does not

use a ramp generator (RGSC). This SIL is primarily

procedural change recommendations and is not a

high risk/low margin system.

A-11

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

GE SIL 377

GE SIL 377 RCIC Startup Transient

Improvement with Steam Bypass (June 24,

1982).

GE SIL 377 recommended a bypass for the steam

supply line to the turbine for improved startup

performance during a transient where RCIC is

needed. This does not apply to Vermont Yankee

since the SIL was a recommendation for plants who

have issues with cold startup of the RCIC system.

Upon talking to the system engineer, these issues

have not existed for at least 20 years at VY.

GE SIL 467 (Bistable

Vortexing)

GE SIL 467 and IEN 86-110 - Bistable

vortexing is still a phenomenon that occurs

periodically at VY.

The first occurrence of bistable vortexing at Vermont

Yankee was following beginning of cycle 12 when

recirculation system piping was replaced; however,

this is a low risk event and thus does not meet the

high risk / low margin criteria for this inspection.

Vermont Yankee has had problems with bistable

vortexing in the past and responded in depth to this

SIL. The licensee responded to the SIL, added

discussion on bistable vortexing at VY and action

items for operators when bistable vortexing occurs.

A review of Vermont Yankee's response to SIL 467,

showed VY satisfied GE's recommended actions

and placed guidance in OP 2110, Recirculation

Procedure to aid the operators in identifying bistable

vortexing.

GL 96-05, MOV Periodic

Verification

GL 96-05 - Implementation of program for

MOV Periodic Verification (As applicable to

the selected sample of valves RCIC-MOV-

15, 16, 131 and 132)

Detailed review completed.

A-12

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

IN 2001-13 (SLC Relief

Valve Margin)

Information Notice 2001-13 (8/10/01) -

Inadequate Standby Liquid Control System

Relief Valve Margin (Susquehanna, Units 1

and 2) Susquehanna's power uprate

increased SRV setpoint pressure thus

increasing SLC discharge pressure.

However, the maximum SLC pump

discharge pressure used a non-conservative

maximum reactor vessel pressure in accident

analysis.

Detailed review completed.

LER 3871995009

(LCO 3.0.3 Entry)

LER 1995-009-00 (7/3/95) - Condition

Prohibited by the Plant's Technical

Specifications (Susquehanna, Unit 1) - Non-

conservative plant input into reactor core flow

calculation.

Feedflow used in the analysis for power uprate is

consistent with current feedflow indications.

LER 3251997005

(FW Indication Error)

LER 1997-005-01 (8/8/97) - Feedwater Flow

Indication Discrepancy (Brunswick Steam

Electric Plant, Unit 1).

Vermont Yankee does not have and is not required

to have chemical tracer mass flow rate tests. This is

more conservative then having the tracers since the

chemical tracer mass flow rate tests are

controversial and have had past issues. VY is

waiting for industry or regulatory guidance on this

issue before adding this test.

LER 2961998001

(LOCA Sensor Problem)

LER 1998-001-00 (4/1/1998) - Computer

Modeling Indicates Sensors May Not Detect

All Possible Break Locations (Browns Ferry,

Unit 3).

Vermont Yankee does use the GOTHIC computer

code to analyze high energy pipe breaks; however,

this is a low risk issue and presented no significant

safety issue at Browns Ferry.

A-13

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

LER 2601999009

(Scram Due to EHC Leak)

LER 1999-009-00 (10/14/99) - Manual

Reactor Scram Due to EHC Leak (Browns

Ferry Nuclear Power Station, Unit 2).

The EHC leak was on a very specific 3/8 inch

nominal outer diameter tubing connection which

consisted of socket weld glands and standard nuts

to connect the accumulator to a pressure

transmitter. The leak was due to poor fabrication and

poor work practices specific to Browns Ferry.

LER 2372001005 (1/7/02)

LER 2001-005-00 (1/7/02) - Unit 2 Scram

Due to Increased First Stage Turbine

Pressure (Dresden, Unit 2).

Vermont Yankee responded to GE SIL 423, in 1998,

by implementing corrective actions.

LER 4612002002

(Inadequate PM on FW

System)

LER 2002-002-00 (7/11/02) - Inadequate

Preventive Maintenance Program for the

Feedwater System Results in Lockup of a

Turbine-Driven Reactor Feed Pump and

Scram on High Reactor Pressure Vessel

Water Level During Extended Power Uprate

Testing (Clinton Power Station). Feedwater

increased due to the power uprate; however,

the feedwater limit switch did not increase to

accommodate this increase in flow.

This operating experience does not apply since

Vermont Yankee does not have turbine driven

feedwater pumps, and this issue does not apply to

other turbine driven pumps in the plant.

A-14

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

LER 3412002005

(Non-Conservative

Setpoint)

LER 2002-05 (1/16/03) - Discovery of

Non-Conservative Setpoint for the

Thermal-Hydraulic Stability Option III

Oscillation Power Range Monitor (OPRM)

Period Based Algorithm, Tmin

(Fermi, Unit 2).

This OE does not apply to Vermont Yankee since

power oscillations are monitored using approved

BWROG Option 1D not Option III. Vermont Yankee

does not have Oscillation Power Range Monitors,

Period Based Detection Algorithms, and Tmin

values. Option III is used for larger BWRs that have

local power oscillations. Since Vermont Yankee has

a small BWR core, only core-wide oscillations occur

(not local oscillations).

The inspector met with an individual from power

uprate (and used to work in reactor engineering) and

discussed, in detail, core monitoring using Option 1D

for the new ARTS/MELLA core design and the

power uprate core design.

LER 4542003003

(Maximum Power

Exceeded)

LER 2003-003-00 (9/29/03) - Licensed

Maximum Power Level Exceeded Due to

Inaccuracies in Feedwater Ultrasonic Flow

Measurements Caused by Signal Noise

Contamination (Byron).

Detailed review completed.

LER 3411992009

LER-92-009-00 (11/20/92) - Safety Relief

Valves Set Pressure Outside Technical

Specifications (Fermi, Unit 2).

VY has had no issues with setpoint drift on the SRVs

or RVs in containment. Setpoint drift considered in

this LER was an indication of disc-to-seat sticking

due to corrosion binding on the SRVs and RVs at

Fermi thus making these valves fail their set

pressures tests.

A-15

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

LSHH-4A

Level switch LSHH 4A contacts fail/short.

High Water Make up - Condenser level

Control Switch Fails high - auto make

malfunctions to the CST - Operator Action is

required.

No EPU impact.

Operator can take manual action to overcome this

failure. The consequence of the failure of the switch

is not significant because the operator can take

manual control.

Manual Initiation of

HPCI/RCIC

Operator fails to manually initiate HPCI and

RCIC systems.

Detailed review completed.

Manual Operation of

SRVs (Medium LOCA)

Operator fails to manually open the SRVs for

a medium LOCA.

Emergency Operating Procedures (EOP) require

operator action to manually open the SRVs to

depressurize the reactor under medium break LOCA

conditions. Validation studies and operator

observations in the simulator have shown that given

various factors that influence human performance

(stress, training, equipment failures, etc.), the task to

open the SRVs manually would be accomplished in

less than 7 minutes which is lower than the 33

minutes (or 24 minutes for CPPU) needed to assure

> 1/3 core coverage. Additionally, operator training

frequently focuses on this event making it unlikely

that the operator would fail to perform the task within

the required time.

A-16

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

Manual Operation of SRVs

(Small LOCA/Transient)

Operator fails to manually open the SRVs for

transient/small LOCA.

Emergency Operating Procedures (EOP) require

operator action to manually open the SRVs to

depressurize the reactor under transient and small

break LOCA conditions. Validation studies and

operator observations in the simulator have shown

that given various factors that influence human

performance (stress, training, equipment failures,

etc.), the task to open the SRVs manually would be

accomplished in less than 5 minutes which is much

lower than the 66 minutes (or 48 minutes for CPPU)

needed to assure > 1/3 core coverage. Additionally,

operator training frequently focuses on this event

making it unlikely that the operator would fail to

perform the task within the required time.

Manual RCIC operation-

Appendix R Safe

Shutdown

Appendix R Safe Shutdown Analysis -

Operator fails to manually initiate RCIC

system using alternate shutdown panels

(Generic Human Actions that are Risk

Important), and GE document NEDC-

330090P, Table 10-5 (Assessment of Key

Operator Action).

Detailed review completed.

MOV-131

RCIC MOV 131 (RCIC turbine steam supply

valve) fails to open on demand. This valve is

required to open to provide steam to the

RCIC turbine for operation.

Not included because valve has adequate design

margin to open when required.

A-17

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

MOV-132

RCIC MOV 132 (cooling water valve to the

RCIC lube oil cooler) fails to open on

demand. This valve is required to open to

provide cooling water to the RCIC pump lube

oil cooler. Failure to cool the lube oil could

result in failure of the pump/turbine.

Not included because valve has adequate design

margin to open when required.

MOV-15/16

RCIC MOV 15/16 (steam supply to RCIC

turbine) fails closed during its mission time.

These valves are required to close in the

event of a line break in the RCIC turbine

steam supply to isolate the HELB. These

valves are also required to remain open

when the RCIC pump is required to operate.

Detailed review completed.

MOV-18

RCIC MOV 18 (RCIC pump suction valve

from the CST) transfers closed during its

mission time. This valve is required to

automatically close when the RCIC pump

suction is transferred from the CST to the

torus. This valve must remain open while the

RCIC pump is operating from the CST.

Not included because valve has adequate design

margin to close when required.

MOV-21/20

RCIC MOV 21 (inboard discharge valve to

the reactor vessel) fails to open on demand.

Also look at MOV-20 (the normally open

outboard discharge isolation valve). These

valves must automatically open to provide

RCIC injection flow in response to an RCIC

initiation signal.

Detailed review completed.

A-18

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

MOV-27

This is the RCIC minimum flow valve. This

valve is required to open at low RCIC flow to

protect the pump.

Detailed review completed.

MOV-39

RCIC MOV 39 (RCIC suction valve from the

suppression pool) fails to open on demand.

This valve is required to open when the RCIC

pump suction is transferred from the CST to

the torus.

Detailed review completed.

MOV-41

RCIC MOV 41 (RCIC suction valve from the

suppression pool) fails to open on demand.

This valve is required to open when the RCIC

pump suction is transferred from the CST to

the torus.

Not included because valve has adequate design

margin to open when required.

MOV-64-31

MOV 64-31 (manual makeup valve from the

CST to hotwell) fails to open on

demand.

Failure of this valve will prevent make-up from the

hot-well to the CST. The loss of this valve would not

be safety significant and there are no indications that

there is low margin on for this valve

Offsite Transmission

System

Offsite Transmission System: preferred

source of power to the 4160V safety buses;

must remain stable and available following

the trip of the VY generator.

Detailed review completed.

A-19

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

Operator Bypasses the

MSIV Isolation Interlocks

Operator Bypasses MSIV Isolation

Interlocks. The justification is the decrease in

the Allowable Action Time for the operators

at the EPU level (CPPU). It is based on input

from the Human Performance technical staff,

Appendix A of NUREG 1764 (Generic

Human Actions that are Risk Important), and

GE document NEDC-330090P, Table 10-5

(Assessment of Key Operator Action).

The allowable action time to bypass the MSIV

low-low level isolation interlocks is based upon the

time it would take to reach the RPV low-low level

setpoint for an ATWS with no injection. Validation

studies by the licensee have shown that the task

would be accomplished for transient and LOCA

events within the required time. The margin to

accomplish the task is adequate, for current and

CPPU conditions, given other operational factors

and steps in the EOPs which must be taken into

account (e.g., a high main steam line radiation

isolation signal maintaining the valves closed).

Operators train and are evaluated and tested on a

regular basis for this scenario further reducing the

likelihood that the task would not be completed in

the time required.

Operator Inhibits ADS

Operator action to inhibit ADS. The

justification is the decrease in the Allowable

Action Time for the operators at the EPU

level (CPPU). It is based on input from the

Human Performance technical staff,

Appendix A of NUREG 1764 (Generic

Human Actions that are Risk Important), and

GE document NEDC-330090P, Table 10-5

(Assessment of Key Operator Action).

The operator action to inhibit ADS is one of the first

actions taken by the operators under certain

transient conditions in the EOPs. The allowable

action time is based on the time to reach the vessel

level low-low set point for ATWS without injection

plus two minutes for the ADS timer. Validation

studies and operator observation in the control room

have demonstrated that the action would be

accomplished in less than 3 minutes. The margin to

complete the task is not significantly changed under

CPPU conditions. Additionally, operators are trained

and tested regularly in this EOP action step.

A-20

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

Passive Failure of

Feedwater Piping

Review effect of increased feedwater flow on

flow-accelerated corrosion rates following the

power uprate.

Detailed review completed.

PB IR 2002-011 (HPCI

Functional Issue)

Peach Bottom Finding for IR 50-277/2002-

011 (8/5/02) - Finding Related to High

Pressure Coolant Injection Function (may

apply to RCIC system at VY).

Detailed review completed.

PCV-23

RCIC PCV 23 (RCIC air operated lube oil

temperature control valve) fails to open on

demand. This valve uses instrument air to

control its setpoint and fails fully open on a

loss of instrument air. This valve is required

to provide cooling water, at the correct

pressure, to the RCIC pump lube oil cooler

when the RCIC pump is operating.

Detailed review completed.

PS-67

Spurious RCIC low suction pressure trip

signal. This instrument will cause the RCIC

pump to trip in the event of low pump suction

pressure. Spurious trips will result in a loss

of RCIC flow.

Not included because there is significant margin in

the setpoint to prevent a spurious trip.

PSH-72A/B

Spurious RCIC turbine exhaust high pressure

trip. This instrument will trip the RCIC pump

in the event of high pressure in the exhaust

steam line. Spurious trips will result in a loss

of RCIC flow.

Not included because there is significant margin in

the setpoint to prevent a spurious trip.

A-21

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

PT-59/60

RCIC pump discharge pressure. This

instrument is associated with the RCIC

turbine control logic.

Not included because there is significant margin in

the setpoint.

PT-68

Spurious low steam line pressure signal.

This instrument will isolate steam flow to the

RCIC turbine in the event of low steam

supply pressure, indicating a steam line

break. Spurious isolation would result in a

loss of RCIC flow.

Not included because the pressure switch setpoint

has significant margin to prevent a spurious pump

trip.

PT-70

Spurious RCIC trip on high turbine exhaust

pressure signal. Component ID is PT-70.

Include exhaust rupture disks S3 and S4.

This instrument will trip the RCIC pump in the

event of high pressure in the exhaust steam

line. Spurious trips will result in a loss of

RCIC flow.

Not included because there is significant margin in

the setpoint and operating pressure to prevent a

spurious trip.

A-22

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

Manual operation of MOV

64-31

Operator fails to manually open MOV 64-31

(used to manually transfer makeup from the

CST to the condenser).

The operator action to manually open valve MOV

64-31, Hotwell Emergency Makeup Valve, is

performed in the main control room. The action is

required when turbine bypass is not available

(during an MSIV closure event). In that case

automatic makeup to the hotwell from the

Condensate Storage Tank (CST) may not be

sufficient to keep up with reactor vessel makeup

requirements (feedwater pumps providing vessel

level makeup). Validation studies and operator

observations have estimated a 1 minute time to

manipulate the valve from the control room. If the

valve is required to be opened from the field the

estimates are less than 15 minutes, however, other

EOP mitigation strategies such as use of low

pressure ECCS pumps, would assure core coverage

if the valve could not be opened.

RB/Torus Vacuum

Breakers

Reactor Building to Torus vacuum breakers.

The vacuum breakers are required to open to

prevent a vacuum in the containment. These

also must remain closed to ensure

containment integrity and to prevent loss of

overpressure for ECCS NPSH.

Detailed review completed.

RCIC Pump P-47-1A and

Turbine TU-2-1-A

RCIC pump P-47-1A fails to start on

demand. This sample includes the turbine

driven RCIC pump, the governor valve, and

trip throttle valve.

Detailed review completed.

A-23

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

Reactor Feed Pump

Failure of the feedwater pump will fail to

deliver flow required for normal operation or

to mitigate an accident.

Prior to EPU 2 of three feedwater pumps are

required to support the Feedwater system

requirements. As such there is a 50% spare

capability. For EPU three pumps are required

to operated due to the increase requirements

of feedwater flow.

Detailed review completed.

RHR Pump

Review RHR pump NPSH calculation,

associated suction strainers, bubble

ingestion, and torus vortexing issues.

Detailed review completed.

Safety Valve (New)

Addition of third main steam safety valve for

power uprate. Failure of SSV to open and

relieve pressure during transients or

small/medium break LOCA.

Detailed review completed.

SLC Initiation with

Condenser Failed

Operator fails to initiate SLC with the main

condenser failed. The justification is the

decrease in the Allowable Action Time for the

operators at the EPU level (CPPU). It is

based on input from the Human Performance

technical staff, Appendix A of NUREG 1764

(Generic Human Actions that are Risk

Important), and GE document

NEDC-330090P, Table 10-5 (Assessment of

Key Operator Action).

Detailed review completed.

A-24

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

Spurious High Steam Line

Space Temperature Trip

Spurious RCIC trip on high steam line space

temperature (instrument TS 79 through 82).

These instruments would result in isolation of

the steam flow to the RCIC turbine in the

event of a steam line break. A spurious trip

would result in loss of RCIC flow.

Not included because there is significant margin

between the setpoint and the operating temperature

to prevent a spurious trip.

Spurious High Steam

Tunnel Temperature Trip

Spurious RCIC trip on a high steam tunnel

temperature trip signal. These instruments

would result in isolation of the steam flow to

the RCIC turbine in the event of a steam line

break. A spurious trip would result in loss of

RCIC flow.

Not included because there is significant margin

between the setpoint and the operating temperature

to prevent a spurious trip.

Spurious Reactor High

Level Trip

Spurious high reactor water level signal (trip

could affect both the RCIC pump or feed

water pump). These instruments would result

in tripping the RCIC turbine in the event of

high RPV level. A spurious trip would result

in loss of RCIC flow.

Excluded because HPCI and the RFP trip signals

are provided by different instruments and the

probability of a simultaneous failure of these

instruments is extremely low.

SR-26

SR-26 (RCIC supply to lube oil cooler relief

valve) fails open. This component is

designed to protect the RCIC lube oil cooler

and may be important on a loss of IA when

the flow control valve fully opens (based on

interview with RCIC System Manager).

Detailed review completed.

SRVs

Safety relief valves allow the reactor to be

depressurized.

Detailed review completed.

A-25

SSC/OA/OE

Description

Detailed Review Completed / Basis For Exclusion

Attachment

Vernon Tie Line

Operator monitoring of Vernon tie line to

ensure availability as a station blackout

source.

Detailed review completed.

ATTACHMENT B

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

D. Amidon

EFIN Engineer

M. Arnett

Systems Engineer - Electrical

K. Bronson

General Manager

F. Burger

Corrective Action

J. Callaghan

Design Engineering Manager

M. Castronova

Design EFIN Supervisor

J. Devincentis

Licensing Manager

J. Dreyfuss

Director of Engineering

E. Duda

Power Uprate Engineer

N. Fales

Systems Engineer - FW and Condensate

K. Farabaugh

Systems Engineering Supervisor

J. Fitzpatrick

Design Mechanical/Structural Engineering - FAC

M. Flynn

Design Engineer - Electrical

D. Girroir

Systems Engineering Supervisor

S. Goodwin

Design Mechanical/Structural Engineering Supervisor

A. Graves

Design Admin Assistant

C. Hansen

Design Engineer - Components

A. Haumann

Design Engineer - Electrical

B. Hobbs

Power Uprate - Engineering Supervisor

M. Janus

Design Engineer - Electrical

P. Johnson

Design Engineer - Electrical

J. Kritzer

Operations/Reactor Engineer

M. Lefrancois

Systems Engineering Supervisor

P. Longo

Design Engineer - Components

L. Lukens

Systems Engineering Supervisor

M. McKenney

Maintenance Support Engineering

J. Melvin

Systems Engineer - SLC

M. Metell

Entergy-Vermont Yankee Response Team Leader

B. Naeck

Systems Engineer - RCIC

C. Nichols

Power Uprate Engineering Manager

T. O'Connor

Design Engineer - Mechanical/Structural

M. Palionis

PRA Engineer

P. Perez

Design Engineer - Fluid Systems

P. Rainey

Design Engineer - Fluid Systems

A. Robertshaw

Design Engineer - Fluid Systems

J. Rogers

Design Fluid Systems Engineering Supervisor

R. Rusin

Design Engineering Supervisor - Components

B. Slifer

Power Uprate Engineer

J. Stasolla

Systems Engineer - Electrical

B-2

J. Taylor

Corrective Action

J. Thayer

Site Vice President

G. Thomas

Power Uprate - Contractor Interface

J. Twarog

Operations Shift Engineering Supervisor

R. Vibert

Design Electrical Engineering Supervisor

C. Wamser

Operations Manager

R. Wanczyk

Director of Nuclear Safety

G. Wierzbowski

Systems Engineering Manager

A. Wonderlick

Systems Engineer - Electrical

Other

W. Farnsworth

Training Coordinator - REMVEC / National Grid

D. Goodwin

Operations Supervisor US-GEN

W. Houston

Manager of Transmission - REMVEC / National Grid

W. Sherman

Vermont State Nuclear Engineer

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

05000271/2004008-04

URI

Ungrounded 480 VAC Electrical System.

(Section 4OA5.2.1.1.b.3)

Opened and Closed

05000271/2004008-01

NCV

Availability of Power from the Vernon

Station. (Section 4AO5.2.1.1.(b).1)05000271/2004008-02

NCV

Procedures for Assessing Off-site Power

Operability. (Section 4AO5.2.1.1.(b).2)05000271/2004008-03

NCV

Degraded Relay Setpoint Calculations.

(Section 4AO5.2.1.1.(b).3)05000271/2004008-05

NCV

Cooling Water Supply Portion of RCIC Not

Installed per Design Basis.

(Section 4AO5.2.1.2.(b).1)05000271/2004008-06

NCV

Failure to Correct Non-Conforming RCIC

Pressure Control Valve. (Section

4A05.2.1.2(b).2)

B-3

05000271/2004008-07

NCV

Failure to Implement Adequate Design

Control for Condensate Storage Tank

Temperature. (Section 4AO5.2.1.7.(b))05000271/2004008-08

NCV

Failure to Revise Safe Shutdown Capability

Analysis Report. (Section 4AO5.2.2.(b))05000271/2004008-09

NCV

Failure to Establish Adequate MOV Periodic

Test Program. (Section 4AO5.2.3.(b))

LIST OF DOCUMENTS REVIEWED

Procedures and Tests

Emergency Operating Procedures

EOP-1 - RPV Control, Rev. 2

EOP-2 - ATWS, Rev. 4

EOP-3 - Primary Containment Control, Rev. 3

EOP-5 - RPV-ED, Rev. 3

Operating Procedures

OP-0023, Installation and Testing of Cable and Conduit, Rev. 8

OP-2113, Main and Auxiliary Steam, Rev. 20

OP-2114, Operation of the Standby Liquid Control System, Rev. 22

OP-2115, Primary Containment, Rev. 44

OP-2116, Secondary Containment Integrity Control, Rev. 19

OP-2119, Nitrogen Supply System, Rev. 13

OP-2121, Reactor Core Isolation Cooling System (RCIC), Rev. 29

OP-2124, Residual Heat Removal System, Rev. 52

OP-2140, 345 KV Electrical System, Rev. 25

OP-2141, 115KV Switchyard, Rev. 17

OP-2142, 4KV Electrical System, Rev. 21

OP-2145, Normal 125 VDC Operation, Rev. 24

OP-2149, Normal 24 VDC Operation, Rev. 7

OP-2170, Condensate System, Rev. 23

OP-2172, Feedwater System, Rev. 23

OP-3126, Shutdown Using Alternative Methods, Rev. 16

OP-4255, Calibration of 4kV Bus Degraded Grid Undervoltage Relays, Rev. 11

OP 5217, MOV Motor Control Center (MC2) Testing, Rev. 2

OP 5287, Evaluation of MOV Motor Control Center (MC2) Testing, Rev. 2

OP 5219, Diagnostic Testing of Motor Operated Valves, Rev. 12

OP 5220, Limitorque Operator PM, Rev. 25

B-4

Operational Transient

OT-3113, Reactor Low Level, Rev. 13

OT-3114, Reactor High Level, Rev. 13

OT-3115, Rx Low Pressure, Rev. 8

OT-3116, Rx High Pressure, Rev. 8

OT-3121, Inadvertent Opening of a Relief Valve, Rev. 13

OT-3122, Loss of Normal Power, Rev. 20

Other

ENN-OP-104, Operability and Determination Procedure, Rev. 2

ENN-DC-325, Component Performance Monitoring, Rev. 0

ENN-DC-151, PSA Maintenance and Update, Rev. 0

AP 6038, Component Level Review of Vermont Yankee Motor-Operated Valves (MOVs), Rev.1

AP 6039, Electrical Design Basis Review of Vermont Yankee Motor-Operated Valves (MOVs),

Original Issue

AP 6037, System and Functional Design Basis Review of Vermont Yankee Motor-Operated

Valves (MOVs), Original Issue

AP 6040, Vermont Yankee Motor-Operated Valve Electrical Configuration, Original Issue

AP 6041, Vermont Yankee Engineering Evaluations of MOV Diagnostic Testing and Feedback

of Results into MOV Component Calculations, Rev. 1

PP 7004, Vermont Yankee Nuclear Power Station Motor Operated Valve Program, Rev. 1

PP 7005, Periodic Verification of Motor Operated Valves, Original Issue

CRP 9-8, Main Control Room Overhead Alarm Panel, Vernon BKR 3V4 Trip/Bus Voltage Low

ON 3155, Loss of Auto Transformer, Rev. 9

Calculations and Studies

Vendor Calculations

RCIC hydraulic calculations (VYE-1064 and VYE-1423)

Structural Integrity Inc. Report SIR-04-020 Rev 0, File VY-10Q-401, Updated Stress and

Fatigue Analysis for the Vermont Yankee Feedwater Nozzles, March 2004

Structural Integrity Inc. File VY10Q-302 Loads and Transient Definitions, Rev. 0

Structural Integrity Inc. Calculation Package VY-10Q-303, Uprated Feedwater Nozzle Stress

and Fatigue Analysis, Rev. 0

Structural Integrity Inc. Calculation VY-10Q-301 Feedwater Nozzle Finite Element Model and

Heat Transfer Coefficients, Rev. 0

Vendor Calculation DC-A34600-03, RHR and CS Suction Strainer Bubble Ingestion, Rev. 0

Vermont Yankee Calculations

VYC-415, Appendix R RCIC, HPCI, and ECCS Room Cooling, Rev. 0

VYC-462C, RCIC Steam Line Area High Temperature Setpoint, Rev. 0, and CCN 01

VYC-706, Condensate Storage Tank Level (RCIC) Monitoring, Rev. 1, CCN 01 and 02

B-5

VYC-709, RCIC System Flow Control and Indication Loop Accuracy, Rev. 1

VYC-715, Degraded Bus Voltage Monitoring loop Accuracy, Rev. 1

VYC-808, Core Spray and RHR Pump Net Positive Suction Head Margin Following a LOCA

with Fibrous Debris on the Intake Strainers, Rev. 0, and CCN 4, 5 and 6 and its

supporting references

VYC-830, Voltage Drop Calculations for VY Distribution Panels DC-1 and DC-2, Rev. 9

and CCN No. 5.

VYC-1005, Crack Growth Calculation for the Vermont Yankee FW Nozzles, Rev. 2

VYC-1053, Motor Operated Valve (MOV) Voltage Analysis, Rev. 8 and CCN 02

VYC-1088, Vermont Yankee 4160/480 Volt Short Circuit/ Voltage Study, Rev. 3

VYC-1293, System Level Review of Reactor Core Isolation Cooling MOVs for GL 89-10,

Rev. 3

VYC-1347, Main Steam Tunnel Heatup Calculation, Rev. 0

VYC-1349, 125V Direct Current DC Voltage Drop Study, Rev. 2 and CCN 05

VYC-1512, Station Blackout Voltage Drop and Short Circuit Study, Rev. 2

VYC-1700, 4.16kV Bus Protective Relay Settings Verification, Rev. 1

VYC-1726, Reactor Core Isolation Cooling Pump Test Acceptance Values, Rev. 1 and

CCN 01

VYC-1816, RCIC Pump Net Positive Suction Head (NPSH), Rev. 0 and CCN 01

VYC-1825, Analysis of Suppression Pool Temperature for Relief Valve Discharge Transients,

Rev. 0 and CCN 1

VYC-1844, HPCI and RCIC Vortex Height, Rev. 1

VYC-1857, Fast and Residual Voltage Bus Transfer Analysis, Rev. I

VYC-1920, RHR and CS Suction Strainer Vortex/Minimum Submergence, Rev. 0 (DE&S

Calculation DC-A34600-02 Rev. 0)

VYC-1924, Vermont Yankee ECCS Suction Strainer Head Loss Performance

Assessment, RHR and CS Debris Head Loss Calculations, Rev. 0 (DE&S Calc

DC-A32600-006 Rev. 0)

VYC-1950, Hydrodynamic Mass and Acceleration Drag Volume of Vermont Yankee ECCS

Strainers, Rev. 0

VYC-1959, Analysis of Tests for Investigation (of) the Effects of Coatings Debris on

ECCS Strainer Performance for Vermont Yankee, Rev. 1 (DE&S Report ITS/VY-

98-01, Rev.1)

VYC-2153, 125 VDC Battery A-1 Electrical System Calculation, Rev. 0 and CCN 03

VYC-2154, 125 VDC Battery B-1 Electrical System Calculation, Rev. 0

VYC-2314, Minimum Containment Overpressure for Non-Loca Events, Rev. 0 and

CCN 01 and 02

VYPC 98-010, Component Level Review of Reactor Core Isolation Cooling (RCIC) MOVs for

GL 89-10, Rev. 2

Studies and Evaluations

Franklin Institute Technical Report F-C2653-01 Design and Stress Analysis of the Vermont

Yankee NPS Clean-up / Feedwater Recombination Tee

General Electric (GE) Topical Report T0900

GE-NE-0000-0009-9951-01 Rev 1, Task 0302 Reactor Vessel Integrity Stress Analysis

(Excludes the radius of the forging)

B-6

GE-NEDC-330090P, Assessment of Key Operator Actions, Table 10-5

Strainer Head Loss Performance Assessment, RHR and CS Debris Head Loss, Rev 0.

VYNPS:EPU T0400: DBA-LOCA for Long Term NPSH Evaluation

Yankee Uprate System Impact Study, dated November 11, 2003

B-7

Condition Reports

CR-96-117

CR-00-1575

CR-02-1860

CR-04-448

CR-96-129

CR-00-1596

CR-02-2193

CR-04-815

CR-96-136

CR-01-880

CR-02-2194

CR-04-1234

CR-98-467

CR-01-889

CR-02-2716

CR-04-1484

CR-98-1171

CR-01-890

CR-02-2733

CR-04-1522

CR-98-2066

CR-01-1007

CR-02-2942

CR-04-2600

CR-99-175

CR-01-1232

CR-03-441

CR-04-2621

CR-99-618

CR-01-1340

CR-03-962

CR-04-2623

CR-00-94

CR-01-1834

CR-03-1491

CR-04-2644

CR-00-306

CR-01-2084

CR-03-1855

CR-04-2723

CR-00-468

CR-01-2186

CR-03-1910

CR-04-2798

CR-00-1509

CR-01-2214

CR-03-2810

CR-04-2799

CR-00-1567

CR-02-151

CR-04-433

CR-04-2802

Drawings

Drawing B-191301 Sh. 1150, Core Spray System B Aux. Relays Sh 1, Rev. 13

Drawing B-191301 Sh. 306, 4kV SWGR #3 Instr & Relaying, Rev. 16

Drawing B-191301 Sh. 317, 4kV SWGR Aux. Relay Ckt., Rev. 10

Drawing B-191301 Sh. 327, 4kV SWGR #3 Tie to 4kV SWGR #1 Bkr. #3T1, Rev. 8.

Drawing B-191301 Sh. 328A, 4Kv SWGR #3 Compt, 10 Diesel Generator DG1-1B Bkr & LNP

Ckt., Rev. 11

Drawing G-191157 Sheet 2 Location L-9, Flow Diagram Condensate, Feedwater and Air

Evacuation Systems, Rev. 5

Drawing G-191174, Sheet 2, Flow Diagram - Reactor Core Isolation Cooling, Rev. 23

Drawing B-191261, Sheet 26C, Impulse Piping to Rack RK-6, Rev. 6

Drawing G-191298 Sh.1, Main One Line Diagram, Rev. 32

Drawing G-191298 Sh.2, Main One Line Phasor Diagram, Rev. 8

DS801-2, Generator SN 180X383 Reactive Capability Curve, dated February 11, 2003

Drawing 6202-001, General Plan Pressure Suppression Containment Vessel C Residual Heat

Removal System - Bubble Ingestion from Safety Relief Valve and LOCA, Rev. 3

Operability Determinations

CR-VTY-1999-00990; Damaged Threads, Originated: 8/17/1999, Closed: 10/6/1999

CR-VTY-2001-00966; Leak Rate Test Results Exceeded the Acceptance Criteria, Originated:

5/04/2001, Closed: 6/29/2001

CR-VTY-2002-02258; IST Leak Rate Test Results Exceed the Acceptance Criteria,

Originated: 10/09/2002, Closed: 4/10/2004

CR-VTY-2004-01607; Breaker 381 Fails to Stay Closed (it trips free), Originated: 5/2/2004,

Closed 5/18/2004

CR-VTY-2004-2596; The Design Basis for Degraded Grid UV Relay not Adequately

Documented in Calculation, Originated: 8/16/2004, Closed: Still Open

B-8

B-9

Modifications and Work Orders

DBD Pending Change Numbers RCIC 2004-002 and HPCI 2004-003

EDCR 81-22 in accordance with NUREG-0737, Item II.K.3.22

EDCR 97-404, MOV Electrical and Pressure Locking Modifications, dated June 17, 1998

EDCR 94-406, MOV Improvements, dated July 13, 1995

Modification Package MM-2003-015, Reactor Feed Pump Suction Pressure Trip Changes for

EPU

Modification Package MM-2003-016, Reactor Recirculation System Run Back For Feedwater

and Condensate System Transients

Modification Package MM-2004-015, Improve SLC Relief Valve Tolerances to Meet New SLC

System Operating Pressure Requirements

Vermont Yankee Design Change VYDC 2003-013, Addition of 3rd Main Steam Safety Valve,

dated 7/9/2003

Vermont Yankee Design Change VYDC 2001-003, RCIC Turbine Exhaust Check Valve

Replacement, dated 10/28/2004

Correspondence

Memorandum, E. Betti to S. Miller, Feedwater Leakage Monitoring Data Analysis, dated

January 30, 1991

Memorandum, E. Betti to S. Miller, Monthly Feedwater Leakage Monitoring Data Report

Analysis, dated December 6, 1993

Letter FVY 82-105, VY to NRC, Feedwater Spargers - Response to NRCs Request for

Additional Information, dated September 21, 1982

Letter BVY 94-07, VY to NRC, Request for Relief from NUREG-0619 Inspection

Requirements, dated February 11, 1994

Letter NVY 95-142, VY to NRC, Feedwater Nozzle Inspection Relief Request - Vermont

Yankee Nuclear Power Station (TAC No. M92940), dated October 12, 1995

Calculation VYC1005, Revision 1, Crack Growth Calculation for the Vermont Yankee FW

Nozzles, Attachment 1, GE-NE-523-A71-0594 with NRC SER dated

March 10, 2000

Letter BVY 01-02, VY to NRC, Alternative Feedwater Nozzle Inspection, dated

January 22, 2001

Letter, NRC to VY, Vermont Yankee Nuclear Power Station Safety - Evaluation of Licensee

Response to Generic Letter 9605 (TAC NO. M97114), dated December 14, 2000

Letter BVY 96-143, VY to NRC, Vermont Yankee 60-day Response to Generic Letter 96-05,

dated November 15, 1996

Letter BVY 97-36, VY to NRC, Vermont Yankee 180-day Response to Generic Letter 96-05,

dated November 15, 1996

Summary of Changes in Leak Detection Data, Report Generated August 30, 2004

Summary of Changes in Leak Detection Data, Report Generated September 1, 2004

GE Letter VYNPS-AEP-346 Revisions 0, 1 and 2

B-10

Event Reports

Event Report 20030340, Root Cause Analysis, The Outboard Seal on RFP C Failed

Other Documents

Generic Letter (GL) 89-10, Safety-Related Motor-Operated Valve Testing and Surveillance,

dated June 28, 1989

Generic Letter (GL) 96-05, Periodic Verification of Design-Basis Capability of Safety-Related

Power Operated Valves, dated September 18, 1996

Information Notice (IN) 2001-13, Inadequate Standby Liquid Control System Relief Valve

Margin, dated August 10, 2001.

Operational Decision-Making Issue (ODMI) Action Plan 2003-1812

NRC SER, Degraded Grid Voltage Protection for Class 1E Power Systems, dated

March 31, 1986

Regulatory Guide 1.82, Water Sources for Long-Term Recirculation Cooling following a Loss-

of-Coolant Accident, Revision 3, dated November 2003

Vermont Yankee Updated Final Safety Analysis Report (UFSAR), Revision 18

Vermont Yankee Individual Plant Examination (IPE) Document

Vermont Yankee Appendix R Safe Shutdown Capability Analysis (SSCA), dated December 23,

1999

Vermont Yankee Technical Specifications, through Amendment No. 219

LIST OF ACRONYMS

AC

Alternating Current

ASME

American Society of Mechanical Engineers

CR

Condition Report

CST

Condensate Storage Tank

EPU

Extended Power Uprate

EOP

Emergency Operating Procedure

FAC

Flow Assisted Corrosion

GE

General Electric

GL

Generic Letter

HPCI

High Pressure Coolant Injection

kV

Kilovolt

LER

Licensee Event Report

MCC

Motor Control Center

MOV

Motor-Operated Valve

NCV

Non-Cited Violation

NPSH

Net Positive Suction Head

NRC

US Nuclear Regulatory Commission

OD

Operability Determination

psig

Pounds Per Square Inch Gauge

PRA

Probabilistic Risk Assessment

B-11

PUSAR

Power Uprate Safety Analysis Report

RAW

Risk Achievement Worth

RCIC

Reactor Core Isolation Cooling

RHR

Residual Heat Removal

ROP

Reactor Oversight Process

SBO

Station Blackout

SDP

Significance Determination Process

SLC

Standby Liquid Control

SPAR

Simplified Plant Analysis Risk

SRV

Safety/Relief Valve

TE

Technical Evaluation

TS

Technical Specifications

UFSAR

Updated Final Safety Analysis Report

V

Volt

VY

Vermont Yankee

VY SSCA

Vermont Yankee Safe Shutdown Capability Analysis