By letters dated August 15 and October 29, 2013 (Agencywide Documents Access and Management Systems Accession Number [ADAMS] ML13235A047 and ML13308B907, respectively), Entergy Nuclear Operations, Inc., the licensee, submitted information summarizing the results of the 2013 steam generator tube inspections performed at Indian Point Nuclear Generating Unit No. 3. Additional information concerning the 2013 steam generator tube inspections is included in the Nuclear Regulatory Commission letter dated April 16, 2013 (ADAMS ML13102A044). | By letters dated August 15 and October 29, 2013 (Agencywide Documents Access and Management Systems Accession Number [ADAMS] ML13235A047 and ML13308B907, respectively), Entergy Nuclear Operations, Inc., the licensee, submitted information summarizing the results of the 2013 steam generator tube inspections performed at Indian Point Nuclear Generating Unit No. 3. Additional information concerning the 2013 steam generator tube inspections is included in the Nuclear Regulatory Commission letter dated April 16, 2013 (ADAMS ML13102A044). | ||
The staff of the Steam Generator Tube Integrity and Chemical Engineering Branch of the Office of Nuclear Reactor Regulation has completed its review of these reports and concludes that the licensee provided the information required by the Indian Point Technical Specifications and that no additional follow-up is required. The Staff Summary is enclosed. | The staff of the Steam Generator Tube Integrity and Chemical Engineering Branch of the Office of Nuclear Reactor Regulation has completed its review of these reports and concludes that the licensee provided the information required by the Indian Point Technical Specifications and that no additional follow-up is required. The Staff Summary is enclosed. | ||
Sincerely, | Sincerely, Douglas V. Pickett, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-286 | ||
Douglas V. Pickett, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-286 | |||
==Enclosure:== | ==Enclosure:== | ||
Line 68: | Line 66: | ||
Staff Summary cc w/encl: Distribution via Listserv DISTRIBUTION: | Staff Summary cc w/encl: Distribution via Listserv DISTRIBUTION: | ||
PUBLIC RidsNrrDeEsgb CHunt, ESGB LPL 1-1 R/F RidsAcrsAcnw_MaiiCTR KKarwoski, DE RidsNrrDorl RidsRgn1 MaiiCenter ABurritt, R1 RidsNrrDorllpl1-1 RidsNrrPMindianPoint RidsNrrLAKGoldstein | PUBLIC RidsNrrDeEsgb CHunt, ESGB LPL 1-1 R/F RidsAcrsAcnw_MaiiCTR KKarwoski, DE RidsNrrDorl RidsRgn1 MaiiCenter ABurritt, R1 RidsNrrDorllpl1-1 RidsNrrPMindianPoint RidsNrrLAKGoldstein ADAMS ACCESSION NO* ML14015A417 OFFICE LPL 1-1/PM LPL 1-1/LA ESGB/BC LPL 1-1/BC NAME DPickett KGoldstein GKulesa by memo dated BBeasley DATE 01/23/2014 01/23/2014 01/ 09/2014 01/30 /2014 OFFICIAL RECORD COPY}} | ||
ADAMS ACCESSION NO* ML14015A417 OFFICE LPL 1-1/PM LPL 1-1/LA ESGB/BC LPL 1-1/BC NAME DPickett KGoldstein GKulesa by memo dated BBeasley DATE 01/23/2014 01/23/2014 01/ 09/2014 01/30 /2014 OFFICIAL RECORD COPY}} |
Latest revision as of 11:13, 5 February 2020
ML15160A404 | |
Person / Time | |
---|---|
Site: | Indian Point |
Issue date: | 01/30/2014 |
From: | State of NY, Office of the Attorney General |
To: | Atomic Safety and Licensing Board Panel |
SECY RAS | |
References | |
RAS 27914, ASLBP 07-858-03-LR-BD01, 50-247-LR, 50-286-LR | |
Download: ML15160A404 (3) | |
Text
NYS000540 Submitted: June 9, 2015 UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 30, 2014 Vice President, Operations Entergy Nuclear Operations, Inc.
Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249
SUBJECT:
INDIAN POINT NUCLEAR GENERATING UNIT NO.3 -STAFF
SUMMARY
OF THE STEAM GENERATOR TUBE INSERVICE INSPECTIONS FOR THE SPRING 2013 REFUELING OUTAGE (TAC NO. MF2614)
Dear Sir or Madam:
By letters dated August 15 and October 29, 2013 (Agencywide Documents Access and Management Systems Accession Number [ADAMS] ML13235A047 and ML13308B907, respectively), Entergy Nuclear Operations, Inc., the licensee, submitted information summarizing the results of the 2013 steam generator tube inspections performed at Indian Point Nuclear Generating Unit No. 3. Additional information concerning the 2013 steam generator tube inspections is included in the Nuclear Regulatory Commission letter dated April 16, 2013 (ADAMS ML13102A044).
The staff of the Steam Generator Tube Integrity and Chemical Engineering Branch of the Office of Nuclear Reactor Regulation has completed its review of these reports and concludes that the licensee provided the information required by the Indian Point Technical Specifications and that no additional follow-up is required. The Staff Summary is enclosed.
Sincerely, Douglas V. Pickett, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-286
Enclosure:
Staff Summary cc w/encl: Distribution via Listserv
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 INDIAN POINT NUCLEAR GENERATING UNIT NO.3 STAFF
SUMMARY
OF THE STEAM GENERATOR TUBE INSERVICE INSPECTIONS FOR THE SPRING 2013 REFUELING OUTAGE OFFICE OF NUCLEAR REACTOR REGULATION DOCKET NO. 50-286 By letters dated August 15 and October 29, 2013 (Agencywide Documents Access and Management Systems Accession Number [ADAMS] ML13235A047 and ML13308B907, respectively), Entergy Nuclear Operations, Inc., the licensee, submitted information summarizing the results of the 2013 steam generator tube inspections performed at Indian Point Nuclear Generating Unit No. 3. Additional information concerning the 2013 steam generator tube inspections is included in the Nuclear Regulatory Commission (NRC) letter dated April 16, 2013 (ADAMS ML13102A044).
The four steam generators at Indian Point 3 were replaced in 1989 with Westinghouse model 44F steam generators. Each steam generator contains 3214 thermally treated Alloy 690 tubes.
Each tube has a nominal outside diameter of 0.875-inch and a nominal wall thickness of 0.050-inch. The tubes were hydraulically expanded at both ends for the full length of the tubesheet and are supported by a number of stainless steel tube support plates. The tubes installed in rows 1 through 8 were thermally stress-relieved after bending.
The licensee provided the scope, extent, methods, and results of their steam generator tube inspections in the documents referenced above. In addition, the licensee described corrective actions (e.g., tube plugging) taken in response to the inspection findings.
Based on a review of the information provided, the NRC staff concludes that the licensee provided the information required by the Technical Specifications. In addition, the staff concludes that there are no technical issues that warrant follow-up action at this time since the inspections appear to be consistent with the objective of detecting potential tube degradation and the inspection results appear to be consistent with industry operating experience at similarly designed and operated units.
Principal Contributor: C. Hunt Date: January 30, 2014
January 30, 2014 Vice President, Operations Entergy Nuclear Operations, Inc.
Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249
SUBJECT:
INDIAN POINT NUCLEAR GENERATING UNIT NO.3 -STAFF
SUMMARY
OF THE STEAM GENERATOR TUBE INSERVICE INSPECTIONS FOR THE SPRING 2013 REFUELING OUTAGE (TAC NO. MF2614)
Dear Sir or Madam:
By letters dated August 15 and October 29, 2013 (Agencywide Documents Access and Management Systems Accession Number [ADAMS] ML13235A047 and ML13308B907, respectively), Entergy Nuclear Operations, Inc., the licensee, submitted information summarizing the results of the 2013 steam generator tube inspections performed at Indian Point Nuclear Generating Unit No. 3. Additional information concerning the 2013 steam generator tube inspections is included in the Nuclear Regulatory Commission letter dated April 16, 2013 (ADAMS ML13102A044).
The staff of the Steam Generator Tube Integrity and Chemical Engineering Branch of the Office of Nuclear Reactor Regulation has completed its review of these reports and concludes that the licensee provided the information required by the Indian Point Technical Specifications and that no additional follow-up is required. The Staff Summary is enclosed.
Sincerely, Ira/
Douglas V. Pickett, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-286
Enclosure:
Staff Summary cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsNrrDeEsgb CHunt, ESGB LPL 1-1 R/F RidsAcrsAcnw_MaiiCTR KKarwoski, DE RidsNrrDorl RidsRgn1 MaiiCenter ABurritt, R1 RidsNrrDorllpl1-1 RidsNrrPMindianPoint RidsNrrLAKGoldstein ADAMS ACCESSION NO* ML14015A417 OFFICE LPL 1-1/PM LPL 1-1/LA ESGB/BC LPL 1-1/BC NAME DPickett KGoldstein GKulesa by memo dated BBeasley DATE 01/23/2014 01/23/2014 01/ 09/2014 01/30 /2014 OFFICIAL RECORD COPY