{{#Wiki_filter:Vice President, Operations Arkansas Nuclear One Entergy Operations, Inc. 1448 S.R. 333 Russellville, AR 72802 UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 14, 2016
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 14, 2016 Vice President, Operations Arkansas Nuclear One Entergy Operations, Inc.
1448 S.R. 333 Russellville, AR 72802


==SUBJECT:==
==SUBJECT:==
NUCLEAR REGULATORY COMMISSION PLAN FOR THE AUDIT OF ENTERGY OPERATIONS, INC.'S FLOOD HAZARD REEVALUATION REPORT SUBMITTAL RELATING TO THE NEAR-TERM TASK FORCE RECOMMENDATION 2.1-FLOODING FOR ARKANSAS NUCLEAR ONE, UNITS 1 AND 2 (CAC NOS. MF8380 AND MF8379)  
NUCLEAR REGULATORY COMMISSION PLAN FOR THE AUDIT OF ENTERGY OPERATIONS, INC.'S FLOOD HAZARD REEVALUATION REPORT SUBMITTAL RELATING TO THE NEAR-TERM TASK FORCE RECOMMENDATION 2.1-FLOODING FOR ARKANSAS NUCLEAR ONE, UNITS 1 AND 2 (CAC NOS. MF8380 AND MF8379)


==Dear Sir or Madam:==
==Dear Sir or Madam:==
This letter documents the U.S. Nuclear Regulatory Commission (NRC) staff's plan to perform a regulatory audit of Entergy Operations, lnc.'s (the licensee) supporting calculations of the Flood Hazard Reevaluation Report (FHRR) submittal related to the Near-Term Task Force Recommendation 2.1 for Arkansas Nuclear One, Units 1 and 2 (ANO). This technical audit will be performed consistent with NRC Office of Nuclear Reactor Regulation, Office Instruction LIC-111, "Regulatory Audits," dated December 29, 2008 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML082900195).
 
The audit will be conducted over multiple sessions, as needed, and the NRC staff will develop an audit summary report to document its observations and conclusions within 90 days of the final audit session. The audit will provide the NRC staff with a better understanding of the ANO FHRR, which was submitted on September 14, 2016 (ADAMS Accession No. ML16260A060).
This letter documents the U.S. Nuclear Regulatory Commission (NRC) staff's plan to perform a regulatory audit of Entergy Operations, lnc.'s (the licensee) supporting calculations of the Flood Hazard Reevaluation Report (FHRR) submittal related to the Near-Term Task Force Recommendation 2.1 for Arkansas Nuclear One, Units 1 and 2 (ANO). This technical audit will be performed consistent with NRC Office of Nuclear Reactor Regulation, Office Instruction LIC-111, "Regulatory Audits," dated December 29, 2008 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML082900195). The audit will be conducted over multiple sessions, as needed, and the NRC staff will develop an audit summary report to document its observations and conclusions within 90 days of the final audit session.
Specifically, the audit will provide the NRC with a better understanding of the analyses of the flooding hazards presented in the ANO FHRR. The audit is intended to support completion of the staff's review of the FHRR and the subsequent issuance of a staff assessment.
The audit will provide the NRC staff with a better understanding of the ANO FHRR, which was submitted on September 14, 2016 (ADAMS Accession No. ML16260A060). Specifically, the audit will provide the NRC with a better understanding of the analyses of the flooding hazards presented in the ANO FHRR. The audit is intended to support completion of the staff's review of the FHRR and the subsequent issuance of a staff assessment.
The enclosed audit plan outlines the process that will allow the NRC staff to identify additional information that may be necessary for licensees to supplement their FHRRs, and resolve any technical concerns.
The enclosed audit plan outlines the process that will allow the NRC staff to identify additional information that may be necessary for licensees to supplement their FHRRs, and resolve any technical concerns. The details of this audit have been discussed with Mr. Donald Bentley of your staff.
The details of this audit have been discussed with Mr. Donald Bentley of your staff. If you have any questions, please contact me at (301) 415-2621 or by e-mail at Robert.Bernardo@nrc.gov.
 
Docket Nos. 50-313 and 50-368  
If you have any questions, please contact me at (301) 415-2621 or by e-mail at Robert.Bernardo@nrc.gov.
Sincerely,
                                              /t-->>zr~
Robert Bernardo, Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation Docket Nos. 50-313 and 50-368


==Enclosure:==
==Enclosure:==


Audit Plan cc w/encl: Distribution via Listserv Sincerely, Robert Bernardo, Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation NRC PLAN FOR THE AUDIT OF ENTERGY OPERATIONS.
Audit Plan cc w/encl: Distribution via Listserv
INC.'S FLOOD HAZARD REEVALUATION REPORT SUBMITTAL RELATING TO THE NEAR-TERM TASK FORCE RECOMMENDATION 2.1-FLOODING FOR ARKANSAS NUCLEAR ONE. UNITS 1 AND 2 BACKGROUND AND AUDIT BASIS By letter dated March 12, 2012, the U.S. Nuclear Regulatory Commission (NRC) issued a request for information to all power reactor licensees and holders of construction permits in active or deferred status, pursuant to Title 1 O of the Code of Federal Regulations (1 O CFR), Section 50.54(f), "Conditions of license" (hereafter referred to as the "50.54(f) letter'').
 
The request was issued in connection with implementing lessons learned from the 2011 accident at the Fukushima Dai-ichi nuclear power plant, as documented in the report of the NRC's Term Task Force. Recommendation 2.1 of that document recommended that the staff issue orders to all licensees to reevaluate seismic and flooding hazards for their sites against current NRC requirements and guidance.
NRC PLAN FOR THE AUDIT OF ENTERGY OPERATIONS. INC.'S FLOOD HAZARD REEVALUATION REPORT SUBMITTAL RELATING TO THE NEAR-TERM TASK FORCE RECOMMENDATION 2.1-FLOODING FOR ARKANSAS NUCLEAR ONE. UNITS 1 AND 2 BACKGROUND AND AUDIT BASIS By letter dated March 12, 2012, the U.S. Nuclear Regulatory Commission (NRC) issued a request for information to all power reactor licensees and holders of construction permits in active or deferred status, pursuant to Title 1O of the Code of Federal Regulations (1 O CFR),
Subsequent staff requirements memoranda associated with SECY 11-0124 and SECY-11-0137 instructed the NRC staff to issue requests for information to licensees pursuant to 10 CFR 50.54(f).
Section 50.54(f), "Conditions of license" (hereafter referred to as the "50.54(f) letter''). The request was issued in connection with implementing lessons learned from the 2011 accident at the Fukushima Dai-ichi nuclear power plant, as documented in the report of the NRC's Near-Term Task Force. Recommendation 2.1 of that document recommended that the staff issue orders to all licensees to reevaluate seismic and flooding hazards for their sites against current NRC requirements and guidance. Subsequent staff requirements memoranda associated with SECY 11-0124 and SECY-11-0137 instructed the NRC staff to issue requests for information to licensees pursuant to 10 CFR 50.54(f).
By letter dated September 14, 2016 (Agencywide Documents Access and Management System Accession No. ML16260A060), Entergy Operations, Inc. (Entergy, the licensee) submitted its Flood Hazard Reevaluation Report (FHRR) for Arkansas Nuclear One, Units 1 and 2 (ANO) in response to the 50.54(f) letter. The NRC staff has begun its review of the aforementioned submittal and plans to conduct a regulatory audit of Entergy to aid in its review of the licensee's FHRR. REGULATORY AUDIT SCOPE AND METHODOLOGY The areas of focus for the regulatory audit are the information contained in the ANO FHRR submittal, and all associated and relevant supporting documentation used in the development of the aforementioned document including, but not limited to, methodology, process information, calculations, computer models, etc. The audit will be conducted and completed over several meetings as necessary.
By letter dated September 14, 2016 (Agencywide Documents Access and Management System Accession No. ML16260A060), Entergy Operations, Inc. (Entergy, the licensee) submitted its Flood Hazard Reevaluation Report (FHRR) for Arkansas Nuclear One, Units 1 and 2 (ANO) in response to the 50.54(f) letter. The NRC staff has begun its review of the aforementioned submittal and plans to conduct a regulatory audit of Entergy to aid in its review of the licensee's FHRR.
INFORMATION AND OTHER MATERIAL NECESSARY FOR THE REGULATORY AUDIT The information required for the audit is the licensee's revised model and supporting calculations, as well as documentation related to the local intense precipitation analyses.
REGULATORY AUDIT SCOPE AND METHODOLOGY The areas of focus for the regulatory audit are the information contained in the ANO FHRR submittal, and all associated and relevant supporting documentation used in the development of the aforementioned document including, but not limited to, methodology, process information, calculations, computer models, etc. The audit will be conducted and completed over several meetings as necessary.
Other information needs will be discussed as audit meetings are scheduled.
INFORMATION AND OTHER MATERIAL NECESSARY FOR THE REGULATORY AUDIT The information required for the audit is the licensee's revised model and supporting calculations, as well as documentation related to the local intense precipitation analyses. Other information needs will be discussed as audit meetings are scheduled.
Enclosure   NRC AUDIT TEAM Title Team Member Affiliation Team Leader, NRR/JLD Robert Bernardo NRC Branch Chief, NRO/DSEA Chris Cook NRC Branch Chief, NRO/DSEA Michelle Bensi NRC Technical Lead Ken See NRC Technical Support Various Contractors Taylor Engineering LOGISTICS The audit meetings will be coordinated with Entergy staff. DELIVERABLES The NRC team will develop an audit summary report to convey the audit results. The report will be placed in ADAMS within 90 days of the completion of the final audit session, and will be publicly available.
Enclosure
The information discussed in the audit may be included, fully or in part, in the development of the staff assessment as a result of the NRC staff's review of the FHRR. The NRC staff will request the licensee to submit any specific information the NRC staff needs to complete its staff assessment. If you have any questions, please contact me at (301) 415-2621 or by e-mail at Robert.Bernardo@nrc.gov.
Docket Nos. 50-313 and 50-368


==Enclosure:==
NRC AUDIT TEAM Title                  Team Member                          Affiliation Team Leader, NRR/JLD        Robert Bernardo            NRC Branch Chief, NRO/DSEA      Chris Cook                  NRC Branch Chief, NRO/DSEA      Michelle Bensi              NRC Technical Lead              Ken See                    NRC Technical Support          Various Contractors        Taylor Engineering LOGISTICS The audit meetings will be coordinated with Entergy staff.
DELIVERABLES The NRC team will develop an audit summary report to convey the audit results. The report will be placed in ADAMS within 90 days of the completion of the final audit session, and will be publicly available.
The information discussed in the audit may be included, fully or in part, in the development of the staff assessment as a result of the NRC staff's review of the FHRR. The NRC staff will request the licensee to submit any specific information the NRC staff needs to complete its staff assessment.


Audit Plan cc w/encl: Distribution via Listserv DISTRIBUTION:
ML16315A265 OFFICE   NRR/JLD/JHMB/PM         NRR/JLD/JHMB/LA         NRR/JLD/JHMB/BC(A)   NRR/JLD/JHMB/PM NAME     RBernardo               Slent                   GBowman               RBernardo DATE     11/3/16                 11 I 10 /16             11/14 /16             11/14 /16}}
PUBLIC JLD R/F RidsNrrDorllpl4-2 Sincerely, IRA/ Robert Bernardo, Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation RidsNRRJLD Resource HJones, NRO GBowman, NRR KSee, NRO RBernardo, NRR MFranovich, NRR CCook, NRO BHarvey,NRO MBensi, NRO KErwin, NRO RidsNrrPMANO Resource ADAMS Accession No.: ML16315A265 OFFICE NRR/JLD/JHMB/PM NRR/JLD/JHMB/LA NRR/JLD/JHMB/BC(A)
NAME RBernardo Slent GBowman DATE 11/3/16 11 I 10 /16 11/14 /16 OFFICIAL RECORD COPY NRR/JLD/JHMB/PM RBernardo 11/14 /16}}

Latest revision as of 12:07, 30 October 2019

Nuclear Regulatory Commission Plan for the Audit of Entergy Operations, Inc'S Flood Hazard Reevaluation Report Submittal Relating to the Near-Term Task Force Recommendation 2.1-Flooding for Arkansas Nuclear One, Units 1 and 2
ML16315A265
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 11/14/2016
From: Robert Bernardo
Japan Lessons-Learned Division
To:
Entergy Operations
Bernardo R, NRR/JLD, 415-2621
References
CAC MF8379, CAC MF8380
Download: ML16315A265 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 14, 2016 Vice President, Operations Arkansas Nuclear One Entergy Operations, Inc.

1448 S.R. 333 Russellville, AR 72802

SUBJECT:

NUCLEAR REGULATORY COMMISSION PLAN FOR THE AUDIT OF ENTERGY OPERATIONS, INC.'S FLOOD HAZARD REEVALUATION REPORT SUBMITTAL RELATING TO THE NEAR-TERM TASK FORCE RECOMMENDATION 2.1-FLOODING FOR ARKANSAS NUCLEAR ONE, UNITS 1 AND 2 (CAC NOS. MF8380 AND MF8379)

Dear Sir or Madam:

This letter documents the U.S. Nuclear Regulatory Commission (NRC) staff's plan to perform a regulatory audit of Entergy Operations, lnc.'s (the licensee) supporting calculations of the Flood Hazard Reevaluation Report (FHRR) submittal related to the Near-Term Task Force Recommendation 2.1 for Arkansas Nuclear One, Units 1 and 2 (ANO). This technical audit will be performed consistent with NRC Office of Nuclear Reactor Regulation, Office Instruction LIC-111, "Regulatory Audits," dated December 29, 2008 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML082900195). The audit will be conducted over multiple sessions, as needed, and the NRC staff will develop an audit summary report to document its observations and conclusions within 90 days of the final audit session.

The audit will provide the NRC staff with a better understanding of the ANO FHRR, which was submitted on September 14, 2016 (ADAMS Accession No. ML16260A060). Specifically, the audit will provide the NRC with a better understanding of the analyses of the flooding hazards presented in the ANO FHRR. The audit is intended to support completion of the staff's review of the FHRR and the subsequent issuance of a staff assessment.

The enclosed audit plan outlines the process that will allow the NRC staff to identify additional information that may be necessary for licensees to supplement their FHRRs, and resolve any technical concerns. The details of this audit have been discussed with Mr. Donald Bentley of your staff.

If you have any questions, please contact me at (301) 415-2621 or by e-mail at Robert.Bernardo@nrc.gov.

Sincerely,

/t-->>zr~

Robert Bernardo, Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation Docket Nos. 50-313 and 50-368

Enclosure:

Audit Plan cc w/encl: Distribution via Listserv

NRC PLAN FOR THE AUDIT OF ENTERGY OPERATIONS. INC.'S FLOOD HAZARD REEVALUATION REPORT SUBMITTAL RELATING TO THE NEAR-TERM TASK FORCE RECOMMENDATION 2.1-FLOODING FOR ARKANSAS NUCLEAR ONE. UNITS 1 AND 2 BACKGROUND AND AUDIT BASIS By letter dated March 12, 2012, the U.S. Nuclear Regulatory Commission (NRC) issued a request for information to all power reactor licensees and holders of construction permits in active or deferred status, pursuant to Title 1O of the Code of Federal Regulations (1 O CFR),

Section 50.54(f), "Conditions of license" (hereafter referred to as the "50.54(f) letter). The request was issued in connection with implementing lessons learned from the 2011 accident at the Fukushima Dai-ichi nuclear power plant, as documented in the report of the NRC's Near-Term Task Force. Recommendation 2.1 of that document recommended that the staff issue orders to all licensees to reevaluate seismic and flooding hazards for their sites against current NRC requirements and guidance. Subsequent staff requirements memoranda associated with SECY 11-0124 and SECY-11-0137 instructed the NRC staff to issue requests for information to licensees pursuant to 10 CFR 50.54(f).

By letter dated September 14, 2016 (Agencywide Documents Access and Management System Accession No. ML16260A060), Entergy Operations, Inc. (Entergy, the licensee) submitted its Flood Hazard Reevaluation Report (FHRR) for Arkansas Nuclear One, Units 1 and 2 (ANO) in response to the 50.54(f) letter. The NRC staff has begun its review of the aforementioned submittal and plans to conduct a regulatory audit of Entergy to aid in its review of the licensee's FHRR.

REGULATORY AUDIT SCOPE AND METHODOLOGY The areas of focus for the regulatory audit are the information contained in the ANO FHRR submittal, and all associated and relevant supporting documentation used in the development of the aforementioned document including, but not limited to, methodology, process information, calculations, computer models, etc. The audit will be conducted and completed over several meetings as necessary.

INFORMATION AND OTHER MATERIAL NECESSARY FOR THE REGULATORY AUDIT The information required for the audit is the licensee's revised model and supporting calculations, as well as documentation related to the local intense precipitation analyses. Other information needs will be discussed as audit meetings are scheduled.

Enclosure

NRC AUDIT TEAM Title Team Member Affiliation Team Leader, NRR/JLD Robert Bernardo NRC Branch Chief, NRO/DSEA Chris Cook NRC Branch Chief, NRO/DSEA Michelle Bensi NRC Technical Lead Ken See NRC Technical Support Various Contractors Taylor Engineering LOGISTICS The audit meetings will be coordinated with Entergy staff.

DELIVERABLES The NRC team will develop an audit summary report to convey the audit results. The report will be placed in ADAMS within 90 days of the completion of the final audit session, and will be publicly available.

The information discussed in the audit may be included, fully or in part, in the development of the staff assessment as a result of the NRC staff's review of the FHRR. The NRC staff will request the licensee to submit any specific information the NRC staff needs to complete its staff assessment.

ML16315A265 OFFICE NRR/JLD/JHMB/PM NRR/JLD/JHMB/LA NRR/JLD/JHMB/BC(A) NRR/JLD/JHMB/PM NAME RBernardo Slent GBowman RBernardo DATE 11/3/16 11 I 10 /16 11/14 /16 11/14 /16