| title = Letter Regarding a Condition at the Construction Site Concerning Magnetic Particle Weld Indications on Sleeves Cadwelded to the Containment Liner Knuckle Plate and Advising That the Report Will Be Provided by December 15, 1978
| title = Letter Regarding a Condition at the Construction Site Concerning Magnetic Particle Weld Indications on Sleeves Cadwelded to the Containment Liner Knuckle Plate and Advising That the Report Will Be Provided by December 15, 1978
| author name = Rhode G K
| author name = Rhode G
| author affiliation = Niagara Mohawk Power Corp
| author affiliation = Niagara Mohawk Power Corp
| addressee name = Carlson R T
| addressee name = Carlson R
| addressee affiliation = NRC/IE
| addressee affiliation = NRC/IE
| docket = 05000410
| docket = 05000410

Revision as of 05:43, 18 June 2019

Letter Regarding a Condition at the Construction Site Concerning Magnetic Particle Weld Indications on Sleeves Cadwelded to the Containment Liner Knuckle Plate and Advising That the Report Will Be Provided by December 15, 1978
ML18018A916
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 09/22/1978
From: Rhode G
Niagara Mohawk Power Corp
To: Robert Carlson
NRC/IE
References
Download: ML18018A916 (4)


Text

r gy@g rm+REGULATORY

'INFORMATlON DISTRIBUTION SYSTEM (RIDS>DISTRIBUTION FOR INCOMING MATERIAL 50-410 REC: CARLSON R T NIAGARA MOHAWK PNR ORG: RIRODE G K NIAGARA MOHAWK PWR DOCD ATE: 09l22/78 DATE RCVD: 09/27/78 DOCTYPE:,LETTER NOTARIZED:

NO COPIES RECEIVED

SUBJECT:

LTR 1 ENCL 0 ADVISING CONSTRUCTION DEFICIENCY REPT CONCERNING MAGNETIC PARTICLE WELD INDICATIONS ON SLEEVES CADWELDED TO Tl-IE CONTAINMENT LINER KNUCKLE PLATE OF SUBJECT FACILITY, WILL BE SUBMITTED BY 12/15/78.PLANT NAME: NINE MILE POINT-UNIT 2 REVIEWER INITIAL: X JM DISTRIBUTOR INITIAL: DISTRIBUTION OF THIS MATERIAL IS AS FOLLOWS I CONSTRUCTION DEFICIENCY REPORT (1,0CFR50.55E><DISTRIBUTION CODE 8019)FQR ACTION: INTERNAL: EXTERNAL: ASST DIR VASSALLO+4LTR ONLY<1)PRQJ MGR ONLY (1)I 5 E+<LTR ONLY(2)GOSSICK 5 STAFF~~h>>LTR ONLY(i>DIRECTOR DPM++LTR ONLY<1)QAB<~L'TR ONLY(1)AD FQR ENG+<LTR ONLY(1)AD FOR PLANT SYSTEMS+@LTR ONLY(STANDARDS DEV.+~LTR ONLY(1)FERD DREHER/IE4~LTR ONLY(i>LPDR S OSWEGOz NY>>+LTR ONLY<1)TERA4~+LTR ONLY(1>NSIC4~~LTR ONLY<1)ACRS CAT B>>~tLTR ONLY(ih>BR CHIEF LWR84 BC+<LTR ONLY<1)LIC ASST LWR04 LA>>>>LTR ONLY(l)h NRC PDR>>+LTR ONLY(i>OELD44LTR ONLY(1)M I PC++LTR ONLY (1)DEPUTY DIR DPM+<LTR ONLY<i)DIRECTOR DSS++LTR-ONLY(i>AD FOR REAC SFTY4%LTR ONLY<i)AD FOR SYS 8c PROJy>LTR ONLY(i>K SEYFRIT/IE4+LTR ONLY<i)DISTRIBUTION:

LTR 41 ENCL 0 SI ZF: 1P SHHHt+%%%%%%4HHl 0i+%%%0l>>88%%%3HI>>>>+4>>>>%%THE END r h I~h hJ r CONTROL NBR: 781780128 1Ã>>>>%%%%4>>>>>>%%>>%%>>>>%++%

%%%%%+%%%%%4%8 I c, I' 5 7 MIASMA"6 U MQHA'PdK-~~~L~1 NIAGARA MOHAWK POWER CORPORATION/300 ERIE BOULEVARD WEST, SYRACUSE, N.Y.13202/TELEPHON f31 4-511 September 22, 1978 Office of Inspection and Enforcement Region I Attention:

Mr.R.T.Carlson, Chief Reactor Construction and Engineering Support Branch U.S.Nuclear Regulatory Commission

'631 Park Avenue King of Prussia, PA 19406 Cg C>C.)CA

Dear Mr.Garison:

Re: Nine Mile Point Unit 2 Docket No.50-410 On June 21, 1978, Mr.R.W.McDaughy of your staff wa's informed by telephone that.Niagara Mohawk was evaluating a condition at Nine Mile Point Unit 2 construction site which may be a reportable deficiency under 10CFR50.55(e).

This condition concerned magnetic particle weld indications on.sleeves cadwelded to the containment liner knuckle plate.By letter dated July 21, 1978, you were informed that further information was unavailable due to a work stoppage and a report would be provided by September 30, 1978 describing our evaluation of this condition.

A three-pronged investigation into this problem is underway.Investigations are in progress on a mock-up portion of the containment liner,, sister sleeves, and production, items in the field.Since the work stoppage at Unit 2 was longer than originally anticipated, our report will not be available as previously scheduled.

It is now planned that this report will be provided by December 15, 1978.Very truly yours, NIAGARA MOHAWK POWER CORPORATION Ger d K.Rho e, Vice President System Pro ect Management Xc: Director of Inspection and Enforcement U.S.Nuclear Regulatory Commission Washington, D.C.20555 78i78Py28 5'~o Tt H'4 Pg~g I I~'i