Line 13: Line 13:
| document type = Letter, Request for Additional Information (RAI)
| document type = Letter, Request for Additional Information (RAI)
| page count = 3
| page count = 3
| project = CAC:MF6985, CAC:MF6986
}}
=Text=
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 15, 2016 Mr. C. R. Pierce Regulatory Affairs Director Southern Nuclear Operating Company, Inc. P. 0. Box 1295/Bin -038 Birmingham, AL 35201-1295 SUBJECT: EDWIN I. HATCH NUCLEAR PLANT, UNITS 1 AND 2 -REQUEST FOR ADDITIONAL INFORMATION (CAC NOS. MF6985 AND MF6986) Dear Mr. Pierce: By letter dated October 15, 2015, as supplemented by letter dated March 16, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML 15288A528 and ML 16076A219, respectively), Southern Nuclear Operating Company submitted a license amendment request for Edwin I. Hatch Nuclear Plant (HNP), Units 1 and 2. The proposed license amendment request would revise HNP Technical Specifications Surveillance Requirements 3.6.4.1.3 to increase the allowable time for the Standby Gas Treatment System to draw down the secondary containment to negative pressure from 2 minutes to 10 minutes. Upon reviewing the March 16, 2016 supplement, the U.S. Nuclear Regulatory Commission staff has found that further information is needed to complete its review. The information request is included in the attached document. Please provide your response within 30 days of the date of this letter. Docket Nos.: 50-321 and 50-366 Enclosure: As stated cc w/enclosure: Distribution via Listserv Sincerely, ft!h,) Michael D. Orenak, Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation REQUEST FOR ADDITIONAL INFORMATION REGARDING CHANGES TO SURVEILLANCE REQUIREMENT 3.6.4.1.3 EDWIN I. HATCH NUCLEAR PLANT, UNITS 1 AND 2 SOUTHERN NUCLEAR OPERATING COMPANY, INC. DOCKET NOS. 50-321 AND 50-366 By letter dated October 15, 2015, as supplemented by letter dated March 16, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML 15288A528 and ML 16076A219, respectively), Southern Nuclear Operating Company (SNC, or the licensee) submitted a license amendment request for Edwin I. Hatch Nuclear Plant (HNP), Units 1 and 2. The proposed license amendment request would revise HNP Technical Specifications Surveillance Requirement (SR) 3.6.4.1.3 to increase the allowable time for the standby gas treatment system (SGTS) to draw down the secondary containment to negative pressure from 2 minutes to 10 minutes. Upon reviewing the March 16, 2016, supplement, the U.S. Nuclear Regulatory Commission staff has found that the following information is needed to complete its review. RAl-10 In the response to RAl-7 of the March 16, 2016, supplement, SNC states: This reduction was justified by noting that wind speeds of greater than 24 mph are not frequent, based on Plant Hatch meteorological conditions. At this wind speed, exfiltration would occur at 0.12 inches of water vacuum. a) Please provide further detail as to what "exfiltration would occur at 0.12 inches of water vacuum" means. Does it mean that the exfiltration would not occur at 0.125 inches of water vacuum with 24 mph winds? b) Please provide the basis for the required 0.12 inches of water vacuum with 24 mph wind speed in the form of a one-page summary of the test or analysis. Enclosure Mr. C. R. Pierce Regulatory Affairs Director April 15, 2016 Southern Nuclear Operating Company, Inc. P. 0. Box 1295/Bin -038 Birmingham, AL 35201-1295 SUBJECT: EDWIN I. HATCH NUCLEAR PLANT, UNITS 1 AND 2 -REQUEST FOR ADDITIONAL INFORMATION (CAC NOS. MF6985 AND MF6986) Dear Mr. Pierce: By letter dated October 15, 2015, as supplemented by letter dated March 16, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML 15288A528 and ML 16076A219, respectively), Southern Nuclear Operating Company submitted a license amendment request for Edwin I. Hatch Nuclear Plant (HNP), Units 1 and 2. The proposed license amendment request would revise HNP Technical Specifications Surveillance Requirements 3.6.4.1.3 to increase the allowable time for the Standby Gas Treatment System to draw down the secondary containment to negative pressure from 2 minutes to 10 minutes. Upon reviewing the March 16, 2016 supplement, the U.S. Nuclear Regulatory Commission staff has found that further information is needed to complete its review. The information request is included in the attached document. Please provide your response within 30 days of the date of this letter. Sincerely, /RA/ Michael D. Orenak, Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 50-321 and 50-366 Enclosure: As stated cc w/enclosure: Distribution via Listserv DISTRIBUTION: PUBLIC LPL2-1 R/F RidsAcrs_MailCTR Resource RidsNrrDorllpl2-1 Resource RidsNrrLASFigueroa Resource SPeng, NRR RidsNrrPMHatch Resource KBucholtz, NRR RidsRgn2MailCenter Resource ADAMS Accession No.: ML 16098A144 *via memo OFFICE NRR/LPLll-1/PM NRR/LPLll-1/LA NRR/SCVB/BC NAME MOrenak SFigueroa RDennig DATE 04/14/16 04/07/16 04/14/16 OFFICE NRR/LPLll-1/BC NRR/LPLll-1/PM NAME MMarkely MOrenak DATE 04/14/16 04/15/16 OFFICIAL RECORD COPY 
}}
}}

Revision as of 10:27, 21 March 2018

Edwin I. Hatch Nuclear Plant, Units 1 and 2 - Request for Additional Information (CAC Nos. MF6985 and MF6986)
ML16098A144
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 04/15/2016
From: Orenak M D
Plant Licensing Branch II
To: Pierce C R
Southern Nuclear Operating Co
Orenak M D
References
CAC MF6985, CAC MF6986
Download: ML16098A144 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 15, 2016 Mr. C. R. Pierce Regulatory Affairs Director Southern Nuclear Operating Company, Inc. P. 0. Box 1295/Bin -038 Birmingham, AL 35201-1295 SUBJECT: EDWIN I. HATCH NUCLEAR PLANT, UNITS 1 AND 2 -REQUEST FOR ADDITIONAL INFORMATION (CAC NOS. MF6985 AND MF6986) Dear Mr. Pierce: By letter dated October 15, 2015, as supplemented by letter dated March 16, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML 15288A528 and ML 16076A219, respectively), Southern Nuclear Operating Company submitted a license amendment request for Edwin I. Hatch Nuclear Plant (HNP), Units 1 and 2. The proposed license amendment request would revise HNP Technical Specifications Surveillance Requirements 3.6.4.1.3 to increase the allowable time for the Standby Gas Treatment System to draw down the secondary containment to negative pressure from 2 minutes to 10 minutes. Upon reviewing the March 16, 2016 supplement, the U.S. Nuclear Regulatory Commission staff has found that further information is needed to complete its review. The information request is included in the attached document. Please provide your response within 30 days of the date of this letter. Docket Nos.: 50-321 and 50-366 Enclosure: As stated cc w/enclosure: Distribution via Listserv Sincerely, ft!h,) Michael D. Orenak, Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation REQUEST FOR ADDITIONAL INFORMATION REGARDING CHANGES TO SURVEILLANCE REQUIREMENT 3.6.4.1.3 EDWIN I. HATCH NUCLEAR PLANT, UNITS 1 AND 2 SOUTHERN NUCLEAR OPERATING COMPANY, INC. DOCKET NOS. 50-321 AND 50-366 By letter dated October 15, 2015, as supplemented by letter dated March 16, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML 15288A528 and ML 16076A219, respectively), Southern Nuclear Operating Company (SNC, or the licensee) submitted a license amendment request for Edwin I. Hatch Nuclear Plant (HNP), Units 1 and 2. The proposed license amendment request would revise HNP Technical Specifications Surveillance Requirement (SR) 3.6.4.1.3 to increase the allowable time for the standby gas treatment system (SGTS) to draw down the secondary containment to negative pressure from 2 minutes to 10 minutes. Upon reviewing the March 16, 2016, supplement, the U.S. Nuclear Regulatory Commission staff has found that the following information is needed to complete its review. RAl-10 In the response to RAl-7 of the March 16, 2016, supplement, SNC states: This reduction was justified by noting that wind speeds of greater than 24 mph are not frequent, based on Plant Hatch meteorological conditions. At this wind speed, exfiltration would occur at 0.12 inches of water vacuum. a) Please provide further detail as to what "exfiltration would occur at 0.12 inches of water vacuum" means. Does it mean that the exfiltration would not occur at 0.125 inches of water vacuum with 24 mph winds? b) Please provide the basis for the required 0.12 inches of water vacuum with 24 mph wind speed in the form of a one-page summary of the test or analysis. Enclosure Mr. C. R. Pierce Regulatory Affairs Director April 15, 2016 Southern Nuclear Operating Company, Inc. P. 0. Box 1295/Bin -038 Birmingham, AL 35201-1295 SUBJECT: EDWIN I. HATCH NUCLEAR PLANT, UNITS 1 AND 2 -REQUEST FOR ADDITIONAL INFORMATION (CAC NOS. MF6985 AND MF6986) Dear Mr. Pierce: By letter dated October 15, 2015, as supplemented by letter dated March 16, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML 15288A528 and ML 16076A219, respectively), Southern Nuclear Operating Company submitted a license amendment request for Edwin I. Hatch Nuclear Plant (HNP), Units 1 and 2. The proposed license amendment request would revise HNP Technical Specifications Surveillance Requirements 3.6.4.1.3 to increase the allowable time for the Standby Gas Treatment System to draw down the secondary containment to negative pressure from 2 minutes to 10 minutes. Upon reviewing the March 16, 2016 supplement, the U.S. Nuclear Regulatory Commission staff has found that further information is needed to complete its review. The information request is included in the attached document. Please provide your response within 30 days of the date of this letter. Sincerely, /RA/ Michael D. Orenak, Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 50-321 and 50-366 Enclosure: As stated cc w/enclosure: Distribution via Listserv DISTRIBUTION: PUBLIC LPL2-1 R/F RidsAcrs_MailCTR Resource RidsNrrDorllpl2-1 Resource RidsNrrLASFigueroa Resource SPeng, NRR RidsNrrPMHatch Resource KBucholtz, NRR RidsRgn2MailCenter Resource ADAMS Accession No.: ML 16098A144 *via memo OFFICE NRR/LPLll-1/PM NRR/LPLll-1/LA NRR/SCVB/BC NAME MOrenak SFigueroa RDennig DATE 04/14/16 04/07/16 04/14/16 OFFICE NRR/LPLll-1/BC NRR/LPLll-1/PM NAME MMarkely MOrenak DATE 04/14/16 04/15/16 OFFICIAL RECORD COPY