ML20127H864: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot change)
(StriderTol Bot change)
 
Line 25: Line 25:
==Dear Mr. Struble,==
==Dear Mr. Struble,==


By letter dated March 31, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20091H586), Vistra Operations Company LLC (the licensee) submitted a license amendment request for Comanche Peak Nuclear Power Plant, Unit Nos. 1 and 2. The proposed amendment would revise Technical Specification (TS) 3.8.1, AC Sources
By {{letter dated|date=March 31, 2020|text=letter dated March 31, 2020}} (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20091H586), Vistra Operations Company LLC (the licensee) submitted a license amendment request for Comanche Peak Nuclear Power Plant, Unit Nos. 1 and 2. The proposed amendment would revise Technical Specification (TS) 3.8.1, AC Sources
-- Operating. The proposed change will revise the emergency diesel generator surveillance requirement steady state frequency band in multiple surveillance requirements from a band from 58.8 Hz to 61.2 Hz to a band from 59.9 Hz to 60.1 Hz. The proposed amendment would also remove historical information from TS 3.8.1 and a Note from SR 3.8.1.13.
-- Operating. The proposed change will revise the emergency diesel generator surveillance requirement steady state frequency band in multiple surveillance requirements from a band from 58.8 Hz to 61.2 Hz to a band from 59.9 Hz to 60.1 Hz. The proposed amendment would also remove historical information from TS 3.8.1 and a Note from SR 3.8.1.13.
The purpose of this correspondence is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The purpose of this correspondence is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

Latest revision as of 03:30, 22 August 2022

NRR E-mail Capture - Comanche Peak - Acceptance of License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating (L-2020-LLA-0059)
ML20127H864
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 05/05/2020
From: Dennis Galvin
NRC/NRR/DORL/LPL4
To: Struble G
Vistra Operations Company
References
L-2020-LLA-0059
Download: ML20127H864 (3)


Text

From: Galvin, Dennis Sent: Tuesday, May 5, 2020 5:55 PM To: Struble, Garry Cc: Jack Hicks (Jack.Hicks@luminant.com); Dixon-Herrity, Jennifer

Subject:

Comanche Peak - Acceptance of License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating (L-2020-LLA-0059)

Dear Mr. Struble,

By letter dated March 31, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20091H586), Vistra Operations Company LLC (the licensee) submitted a license amendment request for Comanche Peak Nuclear Power Plant, Unit Nos. 1 and 2. The proposed amendment would revise Technical Specification (TS) 3.8.1, AC Sources

-- Operating. The proposed change will revise the emergency diesel generator surveillance requirement steady state frequency band in multiple surveillance requirements from a band from 58.8 Hz to 61.2 Hz to a band from 59.9 Hz to 60.1 Hz. The proposed amendment would also remove historical information from TS 3.8.1 and a Note from SR 3.8.1.13.

The purpose of this correspondence is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

Consistent with 10 CFR 50.90, an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staffs detailed technical review by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 750 hours0.00868 days <br />0.208 hours <br />0.00124 weeks <br />2.85375e-4 months <br /> to complete. The NRC staff expects to complete this review by May 2020. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, and unanticipated addition of scope to the review. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

If you have any questions, please contact me at (301) 415-6256.

Respectfully, Dennis Galvin, Project Manager Plant Licensing Branch 4 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-445, 50-446

Hearing Identifier: NRR_DRMA Email Number: 568 Mail Envelope Properties (SA9PR09MB5519882A842B0B18C127ECD7FBA70)

Subject:

Comanche Peak - Acceptance of License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating (L-2020-LLA-0059)

Sent Date: 5/5/2020 5:54:53 PM Received Date: 5/5/2020 5:54:00 PM From: Galvin, Dennis Created By: Dennis.Galvin@nrc.gov Recipients:

"Jack Hicks (Jack.Hicks@luminant.com)" <Jack.Hicks@luminant.com>

Tracking Status: None "Dixon-Herrity, Jennifer" <Jennifer.Dixon-Herrity@nrc.gov>

Tracking Status: None "Struble, Garry" <Garry.Struble@luminant.com>

Tracking Status: None Post Office: SA9PR09MB5519.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3737 5/5/2020 5:54:00 PM Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: