ML17263A526: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:ttl'igRP jfpVEZE ROCHESTER GAS AND ELECTRIC CORPORATION
{{#Wiki_filter:ttl'igRP jfpVEZE ROCHESTER GAS AND ELECTRIC CORPORATION           ~ 89 EAST AVENUE, ROCHESTER N.Y..14649-0001 ROBERT     C   MECREDY                                                             T Et.E PHONE Vice President                                                                AREA CODE 71B   546 2700
~89 EAST AVENUE, ROCHESTER N.Y..14649-0001 ROBERT C MECREDY Vice President@irma Nuclear Production T Et.E PHONE AREA CODE 71B 546 2700 January 10, 1994 U.S.Nuclear Regulatory Commission Attn: Allen R.Johnson Project Directorate I-3 Document Control Desk Washington, DC 20555  
@irma Nuclear Production January 10, 1994 U.S. Nuclear Regulatory Commission Attn: Allen R. Johnson Project Directorate I-3 Document         Control Desk Washington,         DC 20555


==Subject:==
==Subject:==
Reply to a Notice of Violation NRC Inspection Report No.50-244/93-21, dated December 10, 1993 R.E.Ginna Nuclear Power Plant Docket No.50-244  
Reply to   a Notice of Violation NRC Inspection Report No. 50-244/93-21, dated December 10, 1993 R.E. Ginna Nuclear Power Plant Docket No. 50-244
 
==Dear Mr. Johnson:==


==Dear Mr.Johnson:==
During an NRC inspection conducted on October 4, 1993 to October 13, 1993, a violation of NRC requirements was identified.
During an NRC inspection conducted on October 4, 1993 to October 13, 1993, a violation of NRC requirements was identified.
In accordance with the"General Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part 2, Appendix C, the violation is listed below: "Plant technical specification 4.6.1.e.3.a requires that at least once per 18 months during shutdown, each emergency diesel generator shall be demonstrated to be operable by simulating a loss of offsite power in conjunction with a safety injection test signal and verifying de-energization of the emergency buses and load shedding from the emergency buses." Contrary to the above, on October 11, 1993, it was determined that testing to verify load shedding from the emergency buses was not performed during the 18 month surveillance testing.(1)the reason for the violation, or, if contested, the basis for disputing the violation:
In accordance with the "General Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part 2, Appendix C, the violation is listed below:
Rochester Gas&Electric Corporation (RG&E)accepts the violation.
                        "Plant technical specification 4.6.1.e.3.a requires that at least once per 18 months during shutdown, each emergency diesel generator shall be demonstrated to be operable by simulating a loss of offsite power in conjunction with a safety injection test signal and verifying de-energization of the emergency buses and load shedding from the emergency buses."
We acknowledge that plant procedures did not adequately test the bus undervoltage logic, as required by Technical Specification (TS)4.6.1.e.3.(a).
Contrary to the above, on October 11, 1993, it was determined that testing to verify load shedding from the emergency buses was not performed during the 18 month surveillance testing.
Lettex: Page 2  
(1)       the reason for the violation, or,     if contested, the basis for disputing the violation:
Rochester Gas & Electric Corporation (RG&E) accepts the violation.
We acknowledge that plant procedures             did not adequately test the bus undervoltage logic, as required by Technical Specification (TS) 4 . 6. 1.e. 3 . (a) .
 
Lettex:     Page 2


==Subject:==
==Subject:==
Violation Response 93-21-01 Date: January 10, 1994 The reason for the violation, as stated in LER 93-005 (Docket Number 50-244, LER 93-005, dated November 10, 1993)was a mis-interpretation of TS surveillance requirements.
Violation Response   93-21-01 Date:       January 10, 1994 The reason for the violation, as stated         in LER 93-005 (Docket Number 50-244, LER 93-005, dated November         10, 1993) was a mis-interpretation of TS surveillance requirements. The load shedding requirement of TS 4.6.1.e.3.{a) was interpreted as the shedding of non-essential loads powered from the emergency buses.               The shedding   of non-essential   loads had been tested   by simulating a safety injection (SI) signal during performance of procedures RSSP-2.1   (Safety Injection Functional Test) and RSSP-2.1A. (Safety Injection Functional Test Alignment / Realignment), which are performed each refueling outage.           The need to verify load shedding capabilities of safeguards loads, with undervoltage and SI present, had not been considexed.
The load shedding requirement of TS 4.6.1.e.3.{a) was interpreted as the shedding of non-essential loads powered from the emergency buses.The shedding of non-essential loads had been tested by simulating a safety injection (SI)signal during performance of procedures RSSP-2.1 (Safety Injection Functional Test)and RSSP-2.1A.(Safety Injection Functional Test Alignment/Realignment), which are performed each refueling outage.The need to verify load shedding capabilities of safeguards loads, with undervoltage and SI present, had not been considexed.
(2) the corrective steps that have been taken and the results achieved:
(2)the corrective steps that have been taken and the results achieved: The immediate corrective action was to perform the surveillance tests necessary to verify load shedding capability from the emergency buses.A procedure change notice (PCN)was developed for each associated PT-9.1 procedure (monthly surveillance test procedures for testing undervoltage protection for 480 volt safeguards busses 14, 16, 17, and 18).Testing was started on October 11, 1993, and was completed on October 12, 1993, within twenty-four hours of discovery.
The immediate corrective action was to perform the surveillance tests necessary to verify load shedding capability from the emergency buses. A procedure change notice (PCN) was developed for each associated PT-9.1 procedure (monthly surveillance test procedures for testing undervoltage protection for 480 volt safeguards busses 14, 16, 17, and 18). Testing was started on October 11, 1993, and was completed on October 12, 1993, within twenty-four hours of discovery. Details of this testing and test methodology are discussed in Attachment l.             (To perfoim this testing, individual components were declared inoperable, one at a time, fox brief periods. No more than one component was inoperable at a given time, and the diesel generators (DGs) were maintained operable during the entire testing pexiod.)
Details of this testing and test methodology are discussed in Attachment l.(To perfoim this testing, individual components were declared inoperable, one at a time, fox brief periods.No more than one component was inoperable at a given time, and the diesel generators (DGs)were maintained operable during the entire testing pexiod.)The guidance of NRC Generic Letter{GL)87-09, entitled"Sections 3.0 and 4.0 of the Standard Technical Specifications (STS)on the Applicability of Limiting Conditions for Operation and Surveillance Requirements", was followed.Both the"A" and"B" DGs were available to perform all intended functions throughout the discovery and surveillance testing period.This testing demonstrated end-to-end operability of the under-voltage protection system.It verified undervoltage signals to safeguards components, and undervoltage in conjunction with SI signal to the Component Cooling'ater (CCW)pumps.Initial testing of the"B" CCW pump undervoltage
The guidance of NRC Generic Letter {GL) 87-09, entitled "Sections 3.0 and 4.0 of the Standard Technical Specifications (STS) on the Applicability of Limiting Conditions for Operation     and Surveillance Requirements", was followed.         Both the "A" and "B" DGs were available to perform all intended functions throughout the discovery and surveillance testing period.
/SI trip logic was indeterminate.
This testing demonstrated end-to-end operability of the under-voltage protection system.       It verified undervoltage signals to safeguards components, and undervoltage in conjunction with SI signal to the Component Cooling'ater (CCW) pumps.                 Initial testing of the "B" CCW pump undervoltage / SI trip logic was indeterminate.     At that time, the "B" CCW pump was declared inoperable, until further testing was conducted.           The pump was subsequently verified to be fully operable, and was returned to service approximately twelve hours later.
At that time, the"B" CCW pump was declared inoperable, until further testing was conducted.
The testing conducted on October 11-12, in combination with the surveillance tests conducted during the 1993 outage, met the requixements of TS 4.6.1.e.3.(a), and verified that the safeguards functions would have performed as required.
The pump was subsequently verified to be fully operable, and was returned to service approximately twelve hours later.The testing conducted on October 11-12, in combination with the surveillance tests conducted during the 1993 outage, met the requixements of TS 4.6.1.e.3.(a), and verified that the safeguards functions would have performed as required.
 
Letter: Page 3  
Letter:     Page 3


==Subject:==
==Subject:==
Violation Response 93-21-01 Date: January 10, 1994 RG&E personnel subsequently reviewed the requirements of TS 4.6.1, and compared these requirements with surveillance proce-dures.No other noncompliances were identified.
Violation   Response   93-21-01 Date:       January 10, 1994 RG&E   personnel subsequently reviewed the requirements of TS 4.6.1, and compared these requirements with surveillance proce-dures. No other noncompliances were identified.
(3)the corrective steps that will be taken to avoid further violations:
(3)   the corrective steps       that will be taken   to avoid further violations:
0 A review of Section 4 of the Ginna TS will be performed to ensure that there are implementing procedures for every surveillance required by TS.This review will be completed prior to completion of the next scheduled refueling outage.Results of a preliminary review of Section 4 have determined that there are sufficient procedural controls for implementing Section 4 requirements.
0     A review of Section 4 of the Ginna TS will be performed to ensure that there are implementing procedures for every surveillance required by TS. This review will be completed prior to completion of the next scheduled refueling outage.
0 0 A review of the identified implementing procedures will be performed to ensure that these procedures do, in fact, implement the TS requirements.
Results of a preliminary review of Section 4 have determined that there are sufficient procedural controls for implementing Section 4 requirements.
This review will be completed prior to completion of the next scheduled refueling outage.Procedures that verify load shedding capability will be upgraded to include safeguards loads, for conditions of undervoltage and SI, prior to completion of the next scheduled refueling outage.(4)the date when full compliance will be achieved: Full compliance with TS 4.6.1.e.3.(a) was achieved on October 12, 1993, at the completion of surveillance testing.Very truly yours, Robert C.Mecredy xc: Mr.Allen R.Johnson (Mail Stop 14D1)PWR Project Directorate I-3 Washington, DC 20555 U.S.Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406 Ginna USNRC Senior Resident Inspector Attachment 1 PT-9.1 Series Test Details The purpose of this test was to verify undervoltage safeguards load shedding capability.
0     A review of the identified implementing procedures will be performed to ensure that these procedures do, in fact, implement the TS requirements.       This review will be completed prior to completion of the next scheduled refueling outage.
Monthly TS surveillance testing currently ensures each safeguards breaker can be stripped from the bus using the trip coil.To verify the undervoltage stripping capability, all that was necessary was to verify the integrity of the undervoltage logic contacts and associated circuitry, to the trip coils.Jumpers were used to simulate SI for the CCW pumps because their breakers trip on undervoltage coincident with SI signal.Testing Sequence: 1~Manipulate test switches and develop an undervoltage condition using test equipment.
0    Procedures   that verify load shedding capability will be upgraded   to include safeguards loads, for conditions of undervoltage and SI, prior to completion of the next scheduled refueling outage.
2~Verify auxiliary output relays energize to cause the trip function, initiated by appropriate operation of the intermediate digital control logic circuitry.
(4)   the date   when full compliance will be     achieved:
3~4~5.6.Return test switches to normal and remove test equipment.
Full compliance with TS 4.6.1.e.3.(a) was achieved on October 12, 1993, at the completion of surveillance testing.
Verify component being tested is not, in service.Measure the continuity of wiring between the undervoltage auxiliary relays and the breaker switchgear, using DC voltage measurements to ground.)t Verify normally open output relay contacts using resistance measurements.
Very truly yours, Robert C. Mecredy xc:   Mr. Allen R. Johnson     (Mail Stop   14D1)
7~8.Locally trip the associated auxiliary relay and verify proper indicator lamp response and relay contacts indicate closed by resistance measurement.
PWR Project Directorate I-3 Washington,   DC 20555 U.S. Nuclear Regulatory Commission Region I 475 Allendale   Road King of Prussia,   PA 19406 Ginna USNRC   Senior Resident Inspector
Reset the auxiliary relay and verify relay contacts indicate open by resistance measurement.
 
9.Repeat steps 1-8 for all four channels (27/X, 27/BX, 27D/X, and 27D/BX).One test anomoly was identified, as noted in the violation response.Relay 86-16B, associated with the"B" CCW pump breaker, failed to meet the specified resistance acceptance criteria.Emergency Maintenance procedure EM-778 was performed to verify the contact did in fact trip the breaker.After being verified, the contact was reworked by simple burnishing of exposed contact surfaces.~~~v  
Attachment     1 PT-9.1 Series Test Details The purpose   of this test   was to verify undervoltage safeguards load shedding capability.
~'i 0 ACCELERATED DISTRIBUTION DEMONSTRATION SYSTEM REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)CCESSION NBR:9402010169 DOC.DATE'4/01/10 NOTARIZED:
Monthly TS surveillance testing currently ensures each safeguards breaker can be stripped from the bus using the trip coil. To verify the undervoltage stripping capability, all that was necessary was to verify the integrity of the undervoltage logic contacts and associated circuitry, to the trip coils. Jumpers were used to simulate SI for the CCW pumps because their breakers trip on undervoltage coincident with SI signal.
NO FACIL:50-244 Robert Emmet Ginna Nuclear Plant, Unit 1, Rochester G AUTH.NAME AUTHOR AFFILIATION MECREDY,R.C.
Testing Sequence:
Rochester Gas&Electric Corp.RECIP.NAME RECIPIENT AFFILIATION JOHNSON,A.R.
1 ~   Manipulate test switches and develop an undervoltage condition using test equipment.
Project Directorate I-3 I
2 ~   Verify auxiliary output relays energize to cause the trip function, initiated by appropriate operation of the intermediate digital control logic circuitry.
3 ~   Return test switches to normal and remove test equipment.
4 ~    Verify component being tested is not, in service.
: 5. Measure the continuity of wiring between the undervoltage auxiliary relays and the breaker switchgear, using DC voltage measurements to ground.     )
t
: 6. Verify normally open output relay contacts using resistance measurements.
7 ~   Locally trip the associated auxiliary relay and verify proper indicator lamp response and relay contacts indicate closed by resistance measurement.
: 8. Reset the auxiliary relay and verify relay contacts indicate open by resistance measurement.
: 9. Repeat steps 1 8 for all four channels (27/X, 27/BX, 27D/X, and 27D/BX).
One test   anomoly was identified, as noted in the violation response. Relay 86-16B, associated with the "B" CCW pump breaker, failed to   meet the specified resistance acceptance criteria.
Emergency   Maintenance procedure EM-778 was performed to verify the contact did in fact trip the breaker. After being verified, the contact was reworked by simple burnishing of exposed contact surfaces.                       ~ ~   ~ v
 
~ 'i 0
 
ACCELERATED DISTRIBUTION DEMONSTRATION SYSTEM REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)
CCESSION NBR:9402010169               DOC.DATE'4/01/10 NOTARIZED: NO               DOCKET FACIL:50-244 Robert Emmet Ginna Nuclear Plant, Unit 1, Rochester                 G 05000244 AUTH. NAME           AUTHOR AFFILIATION MECREDY,R.C.         Rochester Gas &       Electric Corp.
RECIP.NAME           RECIPIENT AFFILIATION JOHNSON,A.R.               ProjectI Directorate I-3


==SUBJECT:==
==SUBJECT:==
Responds to violations noted in insp rept 50-244/93-21.
Responds to violations noted in insp rept 50-244/93-21.
Corrective actions:surveillance tests necessary to verify load shedding capability from emergency buses performed&procedure revised.DISTRIBUTION CODE: IE01D COPIES RECEIVED:LTR 2 ENCL SIZE: TITLE: General (50 Dkt)-Insp Rept/Notice of Vi&o ation Response NOTES:License Exp date in'ccordance with 10CFR2,2.109(9/19/72).
Corrective actions:surveillance tests necessary to verify load shedding capability from emergency buses performed &                         D procedure revised.
DOCKET 05000244 D$/05000244 RECIPIENT ID CODE/NAME PD1-3 PD INTERNAL: AEOD/DEIB AEOD/DS P/TPAB DEDRO NRR/DRCH/HHFB NRR/DRSS/PEPB NRR/PMAS/ILPB2
DISTRIBUTION CODE: IE01D TITLE: General      (50 COPIES RECEIVED:LTR   2 ENCL Dkt)-Insp Rept/Notice of Vi&o ation Response SIZE:              $
~BI~REG FILM 02 RGNT FILE Ol EXTERNAL EG&G/BRYCE i J H~NSIC COPIES LTTR ENCL 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 RECIPIENT ID CODE/NAME JOHNSON,A AEOD/DSP/ROAB AEOD/TTC NRR/DORS/OEAB NRR/DRIL/RPEB-NRR/PMAS/ILPB1 NUDOCS-ABSTRACT OGC/HDS1 RES/HFB NRC PDR COPIES LTTR ENCL 1 1 1 1 1 1 1 1'1 1 1 1 1 1 1 1 1 1 1 D D R D S NOTE TO ALL"RIDS" RECIPIENTS:
                                                                                                /
D D PLEASE HELP US TO REDUCE WASTE!CONTACT THE DOCUMENT CONTROL DESK, ROOM P 1-37 (EXT.20079)TO ELIMINATE YOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEEDI OTAL NUMBER OF COPIES REQUIRED: LTTR 22 ENCL 22  
NOTES:License Exp       date in'ccordance with 10CFR2,2.109(9/19/72).               05000244 RECIPIENT              COPIES          RECIPIENT          COPIES            D ID  CODE/NAME            LTTR ENCL      ID CODE/NAME       LTTR ENCL PD1-3 PD                     1    1    JOHNSON,A              1    1            D INTERNAL: AEOD/DEIB                     1    1    AEOD/DSP/ROAB          1    1 AEOD/DS P/TPAB               1    1    AEOD/TTC                1    1 DEDRO                       1    1    NRR/DORS/OEAB          1    1' NRR/DRCH/HHFB               1    1    NRR/DRIL/RPEB-              1 NRR/DRSS/PEPB               1    1    NRR/PMAS/ILPB1          1    1 NRR/PMAS/ILPB2
''t"'l'i"~lliPjt'I
            ~BI~
/'l'gjll,"i,",iiel't I t,/f//IP'(/
REG FILM         02 1
ROCHESTER GAS AND ELECTRIC CORPORATION ROBERT C.MECREDY Vice Ptesident Ctnna Nuetear Ptoduetion
1 1
,/net~~~VA~~G ToAtt II F I$Tate~89 EAST AVENUE, ROCHESTER N.Y.14649.OO0'I TELEPHONE AREA CODE 716 546'2700 January 10, 1994 U.S.Nuclear Regulatory Commission Attn: Allen R.Johnson Project Directorate I-3 Document Control Desk Washington, DC 20555  
1 1
1 NUDOCS-ABSTRACT OGC/HDS1 RES/HFB 1
1 1
1 1
1 RGNT    FILE    Ol        1     1 EXTERNAL    EG&G/BRYCE i J H    ~        1     1     NRC PDR                1   1 NSIC                        1     1 R
D S
D D
NOTE TO ALL "RIDS" RECIPIENTS:
PLEASE HELP US TO REDUCE WASTE! CONTACT THE DOCUMENT CONTROL DESK, ROOM P 1-37 (EXT. 20079) TO ELIMINATEYOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEEDI OTAL NUMBER OF COPIES REQUIRED: LTTR               22   ENCL   22
 
                                                                                                                                            ,/
            't"'l'i"~lliPjt'I                                                                                               ~ ~ ~ VA ~ ~ G net
                            /'l'gjll,"i,",iiel't
'                          I     t,/f//IP'(/
ROCHESTER GAS AND ELECTRIC CORPORATION                                         ~
F II 89 EAST AVENUE, ROCHESTER N.Y. 14649.OO0'I I
ToAtt
                                                                                                                                              $ Tate ROBERT C. MECREDY                                                                                                TELEPHONE Vice Ptesident                                                                                            AREA CODE 716     546'2700 Ctnna Nuetear Ptoduetion January 10, 1994 U.S. Nuclear Regulatory Commission Attn: Allen R. Johnson Project Directorate I-3 Document                               Control Desk Washington,                                   DC   20555


==Subject:==
==Subject:==
Reply to a Notice of Violation NRC Inspection Report No.50-244/93-21, dated December 10, 1993 R.E.Ginna Nuclear Power Plant Docket No.50-244  
Reply to     a Notice of Violation NRC Inspection Report No. 50-244/93-21, dated December 10, 1993 R.E. Ginna Nuclear Power Plant Docket No. 50-244
 
==Dear Mr. Johnson:==


==Dear Mr.Johnson:==
During an NRC inspection conducted on October 4, 1993 to October 13, 1993, a violation of NRC requirements was identified.
During an NRC inspection conducted on October 4, 1993 to October 13, 1993, a violation of NRC requirements was identified.
In acccrdance with the"General Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part 2, Appendix C, the violation is listed below: "Plant technical specification 4.6.l.e.3.a requires that at least once per 18 months during shutdown, each emergency diesel generator shall be demonstrated to be operable by simulating a loss of offsite power in conjunction with a safety injection test signal and verifying de-energization of the emergency buses and load shedding from the emergency buses." Contrary to the above, on October 11, 1993, it was determined that testing to verify load shedding from the emergency buses was not performed during the 18 month surveillance testing.(1)the reason for the violation, or, if contested, the basis for disputing the violation:
In acccrdance with the "General Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part 2, Appendix C, the violation is listed below:
Rochester Gas&Electric Corporation (RG&E)accepts the violation.
                                                  "Plant technical specification 4.6.l.e.3.a requires that at least once per 18 months during shutdown, each emergency diesel generator shall be demonstrated to be operable by simulating a loss of offsite power in conjunction with a safety injection test signal and verifying de-energization of the emergency buses and load shedding from the emergency buses."
We acknowledge that plant procedures did not adequately test the bus undervoltage logic, as required by Technical Specification (TS)4.6.1.e.3.(a).gw~I To iQ'.9402010169 940110 PDR ADOCK 05000244 9 PDR 0'
Contrary to the above, on October 11, 1993, it was determined that testing to verify load shedding from the emergency buses was not performed during the 18 month surveillance testing.
Letter: Page 2  
(1)                             the reason for the violation, or, disputing the violation:
if contested, the basis for Rochester Gas & Electric Corporation (RG&E) accepts the violation.
We acknowledge that plant procedures did not adequately test the bus undervoltage logic, as required by Technical Specification (TS) 4. 6. 1.e.3. (a) .
gw ~I To iQ '.
9402010169 940110 PDR                       ADOCK 05000244 9                                                     PDR
 
0' Letter:     Page 2


==Subject:==
==Subject:==
"Violation Response 93-21-01 Date: January 10, 1994 The reason for the violation, as stated in LER 93-005 (Docket Number 50-244, LER 93-005, dated November 10, 1993)was a mis-interpretation'of TS surveill'ance requirements.
  "Violation Response 93-21-01 Date:       January 10, 1994 The reason for the violation, as stated             in LER   93-005   (Docket Number 50-244, LER 93-005, dated November           10,   1993) was a mis-interpretation'of TS surveill'ance requirements. The load shedding requirement of TS 4.6.1.e.3.(a) was interpreted as the shedding of non-essential loads powered from ,the emergency buses.                   The shedding of non-essential loads had been tested by .simulating a safety injection (SI) signal .during performance of procedures RSSP-2.1 (Safety Injection Functional Test) and RSSP-2.1A (Safety Injection Functional Test Alignment / Realignment), which are performed each refueling outage.               The need to verify load shedding capabilities of safeguards loads, with undervoltage and SI present, had not been considered.,
The load shedding requirement of TS 4.6.1.e.3.(a) was interpreted as the shedding of non-essential loads powered from ,the emergency buses.The shedding of non-essential loads had been tested by.simulating a safety injection (SI)signal.during performance of procedures RSSP-2.1 (Safety Injection Functional Test)and RSSP-2.1A (Safety Injection Functional Test Alignment/Realignment), which are performed each refueling outage.The need to verify load shedding capabilities of safeguards loads, with undervoltage and SI present, had not been considered., l (2)the corrective steps that have been taken and the results achieved: The immediate corrective action was to perform the surveillance tests necessary to verify load shedding capability from the emergency buses.A procedure change notice (PCN)was developed for each associated PT-9.1 procedure (monthly surveillance test procedures for testing'undervoltage protection for 480 volt safeguards busses 14, 16, 17, and 18).Testing was started on October 11, 1993, and was completed on October 12, 1993, within twenty-four hours of discovery.
l (2) the corrective steps that have been taken and the results achieved:
Details of this testing and test methodology are discussed in Attachment 1..(To perform this testing, indiyidua2.
The immediate corrective action was to perform the surveillance tests necessary to verify load shedding capability from the emergency buses.       A procedure change notice (PCN) was developed for each   associated     PT-9.1 procedure (monthly surveillance test procedures for       testing 'undervoltage protection for 480 volt safeguards   busses   14, 16, 17, and 18).       Testing was started on October 11, 1993,     and was   completed on October   12, 1993, within twenty-four hours of discovery. Details of this testing and test methodology are discussed in Attachment 1.. (To perform this testing, indiyidua2. components were declared inoperable, one at a time, for brief periods. No more than one component was inoperable at a given time, and the diesel generators (DGs) were maintained operable during the entire testing period.)
components were declared inoperable, one at a time, for brief periods.No more than one component was inoperable at a given time, and the diesel generators (DGs)were maintained operable during the entire testing period.)The guidance of.NRC Generic Letter (GL)87-09, entitled"Sections 3.0 and 4.0 of the Standard Technical Specifications (STS)on the Applicability of Limiting Conditions for Operation and Surveillance Requirements", was followed.,Both the"A" and"B" DGs were available to perform all intended functions throughout the discovery.
The guidance of.NRC Generic Letter (GL) 87-09, entitled "Sections 3.0 and 4.0 of the Standard Technical Specifications (STS) on the Applicability of Limiting Conditions for Operation         and Surveillance Requirements", was followed. ,Both the "A" and "B" DGs were available to perform all intended functions throughout the discovery. and surveillance testing period.
and surveillance testing period.This testing demonstrated end-to-end operability of the under-voltage protection system.It verified undervoltage signals to safeguards components, and undervoltage in conjunction with SI signal to the Component Cooling Water (CCW)pumps.Initial testing of the"B" CCW pump undervoltage
This testing demonstrated end-to-end operability of the under-voltage protection system.         It verified undervoltage signals to safeguards components, and undervoltage in conjunction with SI signal to the Component Cooling Water (CCW) pumps.                     Initial testing of the       "B" CCW pump undervoltage "B"
/SI trip logic was indeterminate.
                                                      / SI trip     logic was indeterminate.       At that time, the           CCW pump     was   declared inoperable, until further testing         was conducted.     The pump was subsequently   verified,to     be fully operable,   and was   returned   to service approximately twelve hours later.
At that time, the"B" CCW pump was declared inoperable, until further testing was conducted.
The testing conducted on October 11-12, in combination with the surveillance tests conducted during the 1993 outage, met the requirements of TS 4.6.1.e.3.(a), and verified that the safeguards functions would have performed as required.
The pump was subsequently verified,to be fully operable, and was returned to service approximately twelve hours later.The testing conducted on October 11-12, in combination with the surveillance tests conducted during the 1993 outage, met the requirements of TS 4.6.1.e.3.(a), and verified that the safeguards functions would have performed as required.
 
Letter: Page 3 Subja't: Violation Response 93-21-01 Date: January 10, 1994 RG&E personnel subsequently reviewed the requirements of TS 4.6.1, and compared these requirements with surveillance proce-dures.No other noncompliances were identified.
Letter:     Page   3 Subja't:   Violation     Response   93-21-01 Date:       January 10, 1994 RG&E   personnel     subsequently reviewed the requirements of TS 4.6.1,   and compared     these requirements with surveillance proce-dures. No other noncompliances were identified.
(3')the corrective steps that will be taken to avoid further violations:
(3') the corrective steps         that will   be taken   to avoid further violations:
0 0 0 A review of Section 4 of the Ginna TS will be performed to ensure that there are implementing procedures for every surveillance required by TS.This review will be completed prior to completion of the next scheduled refueling outage.Results of a preliminary review of Section 4 have determined that there are sufficient procedural controls for implementing Section 4 requirements.
0     A review of Section 4 of the Ginna TS will be performed to ensure   that there are implementing procedures for every surveillance required by TS. This review will be completed prior to completion of the next scheduled refueling outage.
A review of the identified implementing procedures will be performed to ensure that these procedures do, in fact, implement the TS requirements.
Results of a preliminary review of Section 4 have determined that there are sufficient procedural controls for implementing Section 4 requirements.
This review will be completed prior to completion of the next scheduled refueling outage.Procedures that verify load shedding capability will be upgraded to include safeguards loads, for conditions of undervoltage and SI, prior to completion of the next scheduled refueling outage.(4)the date when full compliance will be achieved: Full compliance with TS 4.6.1.e.3.(a) was achieved on.October 12, 1993, at the completion of surveillance testing.Very truly yours, Robert C.Mecredy xc: Mr.Allen R.Johnson (Mail Stop 14D1)PWR Project Directorate I-3 Washington, DC 20555 U.S.Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406 Ginna USNRC Senior Resident Inspector Attachment 1 PT-9.1 Series Test Details The purpose of this test was to verify undervoltage safeguards load shedding capability.
0      A review of the identified implementing procedures will be performed to ensure that these procedures do, in fact, implement the TS requirements.         This review will be completed prior to completion of the next scheduled refueling outage.
Monthly TS surveillance test'ing currently ensures each safeguards breaker can be stripped from the bus using the trip coil.To verify the undervoltage stripping capability, all that was necessary was to verify the integrity of the undervoltage logic contacts and associated circuitry, to the trip coils.Zumpers were used to simulate SI for the CCW pumps because their breakers trip on undervoltage coincident with SI signal.Testing Sequence: 1~Manipulate test switches and develop an undervoltage condition using test equipment.
0    Procedures     that verify load shedding capability will be upgraded     to include safeguards loads, for conditions of undervoltage and SI, prior to completion of the next scheduled refueling outage.
2~Verify auxiliary output relays energize to cause the trip function, initiated by appropriate operation of the intermediate digital control logic circuitry.
(4)   the date   when   full compliance will be     achieved:
3~4~5.Return test switches to normal and remove test equipment.
Full compliance with       TS 4.6.1.e.3.(a) was achieved on .
Verify component being tested is not in service.Measure the continuity of wiring between the undervoltage auxiliary relays and the breaker switchgear, using DC voltage measurements to ground.6.Verify normally open output relay contacts using resistance measurements.
October 12, 1993, at the completion of surveillance testing.
7~8.Locally trip the associated auxiliary relay and verify proper indicator lamp response and relay contacts indicate closed by resistance measurement.
Very truly   yours, Robert C. Mecredy xc:   Mr. Allen R. Johnson (Mail Stop       14D1)
Reset the auxiliary relay and verify relay contacts indicate open by resistance measurement.
PWR Project Directorate I-3 Washington,     DC 20555 U.S. Nuclear Regulatory Commission Region I 475 Allendale   Road King of Prussia,     PA 19406 Ginna   USNRC   Senior Resident Inspector
9.Repeat steps 1-8 for all four channels (27/X, 27/BX, 27D/X, and 27D/BX).One test anomoly was identified, as noted in the violation response.Relay 86-16B, associated with the"B" CCW pump breaker, failed to meet the specified resistance acceptance criteria.Emergency Maintenance'rocedure EM-778 was performed to verify the contact did in fact trip.the breaker.After being verified, the contact was reworked by simple burnishing of exposed contact surfaces.  
 
Attachment   1 PT-9.1 Series Test Details The purpose   of this test was to verify undervoltage safeguards load shedding capability.
Monthly TS surveillance test'ing currently ensures each safeguards breaker can be stripped from the bus using the trip coil. To verify the undervoltage stripping capability, all that was necessary was to verify the integrity of the undervoltage logic contacts and associated circuitry, to the trip coils. Zumpers were used to simulate SI for the CCW pumps because their breakers trip on undervoltage coincident with SI signal.
Testing Sequence:
1 ~   Manipulate test switches and develop an undervoltage condition using test equipment.
2 ~   Verify auxiliary output relays energize to cause the trip function, initiated by appropriate operation of the intermediate digital control logic circuitry.
3 ~   Return test switches to normal and remove test equipment.
4 ~    Verify component being tested is not in service.
: 5. Measure the continuity of wiring between the undervoltage auxiliary relays and the breaker switchgear, using DC voltage measurements to ground.
: 6. Verify normally open output relay contacts using resistance measurements.
7 ~   Locally trip the associated auxiliary relay and verify proper indicator lamp response and relay contacts indicate closed by resistance measurement.
: 8. Reset the auxiliary relay and verify relay contacts indicate open by resistance measurement.
: 9. Repeat steps 1 8   for all four   channels (27/X, 27/BX, 27D/X, and 27D/BX).
One test   anomoly was identified, as noted in the violation response. Relay 86-16B, associated with the "B" CCW pump breaker, failed to   meet the specified resistance acceptance       criteria.
Emergency Maintenance'rocedure     EM-778 was performed to verify the contact did in fact trip .the breaker. After being verified, the contact was reworked by simple burnishing of exposed contact surfaces.
 
~l}}
~l}}

Latest revision as of 18:22, 29 October 2019

Responds to Violations Noted in Insp Rept 50-244/93-21. Corrective Actions:Surveillance Tests Necessary to Verify Load Shedding Capability from Emergency Buses Performed & Procedure Revised
ML17263A526
Person / Time
Site: Ginna Constellation icon.png
Issue date: 01/10/1994
From: Mecredy R
ROCHESTER GAS & ELECTRIC CORP.
To: Andrea Johnson
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM), Office of Nuclear Reactor Regulation
References
NUDOCS 9402010169
Download: ML17263A526 (12)


Text

ttl'igRP jfpVEZE ROCHESTER GAS AND ELECTRIC CORPORATION ~ 89 EAST AVENUE, ROCHESTER N.Y..14649-0001 ROBERT C MECREDY T Et.E PHONE Vice President AREA CODE 71B 546 2700

@irma Nuclear Production January 10, 1994 U.S. Nuclear Regulatory Commission Attn: Allen R. Johnson Project Directorate I-3 Document Control Desk Washington, DC 20555

Subject:

Reply to a Notice of Violation NRC Inspection Report No. 50-244/93-21, dated December 10, 1993 R.E. Ginna Nuclear Power Plant Docket No. 50-244

Dear Mr. Johnson:

During an NRC inspection conducted on October 4, 1993 to October 13, 1993, a violation of NRC requirements was identified.

In accordance with the "General Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part 2, Appendix C, the violation is listed below:

"Plant technical specification 4.6.1.e.3.a requires that at least once per 18 months during shutdown, each emergency diesel generator shall be demonstrated to be operable by simulating a loss of offsite power in conjunction with a safety injection test signal and verifying de-energization of the emergency buses and load shedding from the emergency buses."

Contrary to the above, on October 11, 1993, it was determined that testing to verify load shedding from the emergency buses was not performed during the 18 month surveillance testing.

(1) the reason for the violation, or, if contested, the basis for disputing the violation:

Rochester Gas & Electric Corporation (RG&E) accepts the violation.

We acknowledge that plant procedures did not adequately test the bus undervoltage logic, as required by Technical Specification (TS) 4 . 6. 1.e. 3 . (a) .

Lettex: Page 2

Subject:

Violation Response 93-21-01 Date: January 10, 1994 The reason for the violation, as stated in LER 93-005 (Docket Number 50-244, LER 93-005, dated November 10, 1993) was a mis-interpretation of TS surveillance requirements. The load shedding requirement of TS 4.6.1.e.3.{a) was interpreted as the shedding of non-essential loads powered from the emergency buses. The shedding of non-essential loads had been tested by simulating a safety injection (SI) signal during performance of procedures RSSP-2.1 (Safety Injection Functional Test) and RSSP-2.1A. (Safety Injection Functional Test Alignment / Realignment), which are performed each refueling outage. The need to verify load shedding capabilities of safeguards loads, with undervoltage and SI present, had not been considexed.

(2) the corrective steps that have been taken and the results achieved:

The immediate corrective action was to perform the surveillance tests necessary to verify load shedding capability from the emergency buses. A procedure change notice (PCN) was developed for each associated PT-9.1 procedure (monthly surveillance test procedures for testing undervoltage protection for 480 volt safeguards busses 14, 16, 17, and 18). Testing was started on October 11, 1993, and was completed on October 12, 1993, within twenty-four hours of discovery. Details of this testing and test methodology are discussed in Attachment l. (To perfoim this testing, individual components were declared inoperable, one at a time, fox brief periods. No more than one component was inoperable at a given time, and the diesel generators (DGs) were maintained operable during the entire testing pexiod.)

The guidance of NRC Generic Letter {GL) 87-09, entitled "Sections 3.0 and 4.0 of the Standard Technical Specifications (STS) on the Applicability of Limiting Conditions for Operation and Surveillance Requirements", was followed. Both the "A" and "B" DGs were available to perform all intended functions throughout the discovery and surveillance testing period.

This testing demonstrated end-to-end operability of the under-voltage protection system. It verified undervoltage signals to safeguards components, and undervoltage in conjunction with SI signal to the Component Cooling'ater (CCW) pumps. Initial testing of the "B" CCW pump undervoltage / SI trip logic was indeterminate. At that time, the "B" CCW pump was declared inoperable, until further testing was conducted. The pump was subsequently verified to be fully operable, and was returned to service approximately twelve hours later.

The testing conducted on October 11-12, in combination with the surveillance tests conducted during the 1993 outage, met the requixements of TS 4.6.1.e.3.(a), and verified that the safeguards functions would have performed as required.

Letter: Page 3

Subject:

Violation Response 93-21-01 Date: January 10, 1994 RG&E personnel subsequently reviewed the requirements of TS 4.6.1, and compared these requirements with surveillance proce-dures. No other noncompliances were identified.

(3) the corrective steps that will be taken to avoid further violations:

0 A review of Section 4 of the Ginna TS will be performed to ensure that there are implementing procedures for every surveillance required by TS. This review will be completed prior to completion of the next scheduled refueling outage.

Results of a preliminary review of Section 4 have determined that there are sufficient procedural controls for implementing Section 4 requirements.

0 A review of the identified implementing procedures will be performed to ensure that these procedures do, in fact, implement the TS requirements. This review will be completed prior to completion of the next scheduled refueling outage.

0 Procedures that verify load shedding capability will be upgraded to include safeguards loads, for conditions of undervoltage and SI, prior to completion of the next scheduled refueling outage.

(4) the date when full compliance will be achieved:

Full compliance with TS 4.6.1.e.3.(a) was achieved on October 12, 1993, at the completion of surveillance testing.

Very truly yours, Robert C. Mecredy xc: Mr. Allen R. Johnson (Mail Stop 14D1)

PWR Project Directorate I-3 Washington, DC 20555 U.S. Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406 Ginna USNRC Senior Resident Inspector

Attachment 1 PT-9.1 Series Test Details The purpose of this test was to verify undervoltage safeguards load shedding capability.

Monthly TS surveillance testing currently ensures each safeguards breaker can be stripped from the bus using the trip coil. To verify the undervoltage stripping capability, all that was necessary was to verify the integrity of the undervoltage logic contacts and associated circuitry, to the trip coils. Jumpers were used to simulate SI for the CCW pumps because their breakers trip on undervoltage coincident with SI signal.

Testing Sequence:

1 ~ Manipulate test switches and develop an undervoltage condition using test equipment.

2 ~ Verify auxiliary output relays energize to cause the trip function, initiated by appropriate operation of the intermediate digital control logic circuitry.

3 ~ Return test switches to normal and remove test equipment.

4 ~ Verify component being tested is not, in service.

5. Measure the continuity of wiring between the undervoltage auxiliary relays and the breaker switchgear, using DC voltage measurements to ground. )

t

6. Verify normally open output relay contacts using resistance measurements.

7 ~ Locally trip the associated auxiliary relay and verify proper indicator lamp response and relay contacts indicate closed by resistance measurement.

8. Reset the auxiliary relay and verify relay contacts indicate open by resistance measurement.
9. Repeat steps 1 8 for all four channels (27/X, 27/BX, 27D/X, and 27D/BX).

One test anomoly was identified, as noted in the violation response. Relay 86-16B, associated with the "B" CCW pump breaker, failed to meet the specified resistance acceptance criteria.

Emergency Maintenance procedure EM-778 was performed to verify the contact did in fact trip the breaker. After being verified, the contact was reworked by simple burnishing of exposed contact surfaces. ~ ~ ~ v

~ 'i 0

ACCELERATED DISTRIBUTION DEMONSTRATION SYSTEM REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)

CCESSION NBR:9402010169 DOC.DATE'4/01/10 NOTARIZED: NO DOCKET FACIL:50-244 Robert Emmet Ginna Nuclear Plant, Unit 1, Rochester G 05000244 AUTH. NAME AUTHOR AFFILIATION MECREDY,R.C. Rochester Gas & Electric Corp.

RECIP.NAME RECIPIENT AFFILIATION JOHNSON,A.R. ProjectI Directorate I-3

SUBJECT:

Responds to violations noted in insp rept 50-244/93-21.

Corrective actions:surveillance tests necessary to verify load shedding capability from emergency buses performed & D procedure revised.

DISTRIBUTION CODE: IE01D TITLE: General (50 COPIES RECEIVED:LTR 2 ENCL Dkt)-Insp Rept/Notice of Vi&o ation Response SIZE: $

/

NOTES:License Exp date in'ccordance with 10CFR2,2.109(9/19/72). 05000244 RECIPIENT COPIES RECIPIENT COPIES D ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD1-3 PD 1 1 JOHNSON,A 1 1 D INTERNAL: AEOD/DEIB 1 1 AEOD/DSP/ROAB 1 1 AEOD/DS P/TPAB 1 1 AEOD/TTC 1 1 DEDRO 1 1 NRR/DORS/OEAB 1 1' NRR/DRCH/HHFB 1 1 NRR/DRIL/RPEB- 1 NRR/DRSS/PEPB 1 1 NRR/PMAS/ILPB1 1 1 NRR/PMAS/ILPB2

~BI~

REG FILM 02 1

1 1

1 1

1 NUDOCS-ABSTRACT OGC/HDS1 RES/HFB 1

1 1

1 1

1 RGNT FILE Ol 1 1 EXTERNAL EG&G/BRYCE i J H ~ 1 1 NRC PDR 1 1 NSIC 1 1 R

D S

D D

NOTE TO ALL "RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE! CONTACT THE DOCUMENT CONTROL DESK, ROOM P 1-37 (EXT. 20079) TO ELIMINATEYOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEEDI OTAL NUMBER OF COPIES REQUIRED: LTTR 22 ENCL 22

,/

't"'l'i"~lliPjt'I ~ ~ ~ VA ~ ~ G net

/'l'gjll,"i,",iiel't

' I t,/f//IP'(/

ROCHESTER GAS AND ELECTRIC CORPORATION ~

F II 89 EAST AVENUE, ROCHESTER N.Y. 14649.OO0'I I

ToAtt

$ Tate ROBERT C. MECREDY TELEPHONE Vice Ptesident AREA CODE 716 546'2700 Ctnna Nuetear Ptoduetion January 10, 1994 U.S. Nuclear Regulatory Commission Attn: Allen R. Johnson Project Directorate I-3 Document Control Desk Washington, DC 20555

Subject:

Reply to a Notice of Violation NRC Inspection Report No. 50-244/93-21, dated December 10, 1993 R.E. Ginna Nuclear Power Plant Docket No. 50-244

Dear Mr. Johnson:

During an NRC inspection conducted on October 4, 1993 to October 13, 1993, a violation of NRC requirements was identified.

In acccrdance with the "General Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part 2, Appendix C, the violation is listed below:

"Plant technical specification 4.6.l.e.3.a requires that at least once per 18 months during shutdown, each emergency diesel generator shall be demonstrated to be operable by simulating a loss of offsite power in conjunction with a safety injection test signal and verifying de-energization of the emergency buses and load shedding from the emergency buses."

Contrary to the above, on October 11, 1993, it was determined that testing to verify load shedding from the emergency buses was not performed during the 18 month surveillance testing.

(1) the reason for the violation, or, disputing the violation:

if contested, the basis for Rochester Gas & Electric Corporation (RG&E) accepts the violation.

We acknowledge that plant procedures did not adequately test the bus undervoltage logic, as required by Technical Specification (TS) 4. 6. 1.e.3. (a) .

gw ~I To iQ '.

9402010169 940110 PDR ADOCK 05000244 9 PDR

0' Letter: Page 2

Subject:

"Violation Response 93-21-01 Date: January 10, 1994 The reason for the violation, as stated in LER 93-005 (Docket Number 50-244, LER 93-005, dated November 10, 1993) was a mis-interpretation'of TS surveill'ance requirements. The load shedding requirement of TS 4.6.1.e.3.(a) was interpreted as the shedding of non-essential loads powered from ,the emergency buses. The shedding of non-essential loads had been tested by .simulating a safety injection (SI) signal .during performance of procedures RSSP-2.1 (Safety Injection Functional Test) and RSSP-2.1A (Safety Injection Functional Test Alignment / Realignment), which are performed each refueling outage. The need to verify load shedding capabilities of safeguards loads, with undervoltage and SI present, had not been considered.,

l (2) the corrective steps that have been taken and the results achieved:

The immediate corrective action was to perform the surveillance tests necessary to verify load shedding capability from the emergency buses. A procedure change notice (PCN) was developed for each associated PT-9.1 procedure (monthly surveillance test procedures for testing 'undervoltage protection for 480 volt safeguards busses 14, 16, 17, and 18). Testing was started on October 11, 1993, and was completed on October 12, 1993, within twenty-four hours of discovery. Details of this testing and test methodology are discussed in Attachment 1.. (To perform this testing, indiyidua2. components were declared inoperable, one at a time, for brief periods. No more than one component was inoperable at a given time, and the diesel generators (DGs) were maintained operable during the entire testing period.)

The guidance of.NRC Generic Letter (GL) 87-09, entitled "Sections 3.0 and 4.0 of the Standard Technical Specifications (STS) on the Applicability of Limiting Conditions for Operation and Surveillance Requirements", was followed. ,Both the "A" and "B" DGs were available to perform all intended functions throughout the discovery. and surveillance testing period.

This testing demonstrated end-to-end operability of the under-voltage protection system. It verified undervoltage signals to safeguards components, and undervoltage in conjunction with SI signal to the Component Cooling Water (CCW) pumps. Initial testing of the "B" CCW pump undervoltage "B"

/ SI trip logic was indeterminate. At that time, the CCW pump was declared inoperable, until further testing was conducted. The pump was subsequently verified,to be fully operable, and was returned to service approximately twelve hours later.

The testing conducted on October 11-12, in combination with the surveillance tests conducted during the 1993 outage, met the requirements of TS 4.6.1.e.3.(a), and verified that the safeguards functions would have performed as required.

Letter: Page 3 Subja't: Violation Response 93-21-01 Date: January 10, 1994 RG&E personnel subsequently reviewed the requirements of TS 4.6.1, and compared these requirements with surveillance proce-dures. No other noncompliances were identified.

(3') the corrective steps that will be taken to avoid further violations:

0 A review of Section 4 of the Ginna TS will be performed to ensure that there are implementing procedures for every surveillance required by TS. This review will be completed prior to completion of the next scheduled refueling outage.

Results of a preliminary review of Section 4 have determined that there are sufficient procedural controls for implementing Section 4 requirements.

0 A review of the identified implementing procedures will be performed to ensure that these procedures do, in fact, implement the TS requirements. This review will be completed prior to completion of the next scheduled refueling outage.

0 Procedures that verify load shedding capability will be upgraded to include safeguards loads, for conditions of undervoltage and SI, prior to completion of the next scheduled refueling outage.

(4) the date when full compliance will be achieved:

Full compliance with TS 4.6.1.e.3.(a) was achieved on .

October 12, 1993, at the completion of surveillance testing.

Very truly yours, Robert C. Mecredy xc: Mr. Allen R. Johnson (Mail Stop 14D1)

PWR Project Directorate I-3 Washington, DC 20555 U.S. Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406 Ginna USNRC Senior Resident Inspector

Attachment 1 PT-9.1 Series Test Details The purpose of this test was to verify undervoltage safeguards load shedding capability.

Monthly TS surveillance test'ing currently ensures each safeguards breaker can be stripped from the bus using the trip coil. To verify the undervoltage stripping capability, all that was necessary was to verify the integrity of the undervoltage logic contacts and associated circuitry, to the trip coils. Zumpers were used to simulate SI for the CCW pumps because their breakers trip on undervoltage coincident with SI signal.

Testing Sequence:

1 ~ Manipulate test switches and develop an undervoltage condition using test equipment.

2 ~ Verify auxiliary output relays energize to cause the trip function, initiated by appropriate operation of the intermediate digital control logic circuitry.

3 ~ Return test switches to normal and remove test equipment.

4 ~ Verify component being tested is not in service.

5. Measure the continuity of wiring between the undervoltage auxiliary relays and the breaker switchgear, using DC voltage measurements to ground.
6. Verify normally open output relay contacts using resistance measurements.

7 ~ Locally trip the associated auxiliary relay and verify proper indicator lamp response and relay contacts indicate closed by resistance measurement.

8. Reset the auxiliary relay and verify relay contacts indicate open by resistance measurement.
9. Repeat steps 1 8 for all four channels (27/X, 27/BX, 27D/X, and 27D/BX).

One test anomoly was identified, as noted in the violation response. Relay 86-16B, associated with the "B" CCW pump breaker, failed to meet the specified resistance acceptance criteria.

Emergency Maintenance'rocedure EM-778 was performed to verify the contact did in fact trip .the breaker. After being verified, the contact was reworked by simple burnishing of exposed contact surfaces.

~l