ML092940763: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(StriderTol Bot change)
 
(5 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML092940763
| number = ML092940763
| issue date = 10/20/2009
| issue date = 10/20/2009
| title = Catawba Initial Exam 2008-301 Final Administrative JPMs
| title = Initial Exam 2008-301 Final Administrative JPMs
| author name =  
| author name =  
| author affiliation = NRC/RGN-II
| author affiliation = NRC/RGN-II
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 1R ADMIN Determine NCP Start Requirements CANDIDATE EXAMINER JPM 1RADMIN Page 1 of 5 CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 1R ADMIN Determine NCP Start Requirements CANDIDATE EXAMINER JPM 1RADMIN Page 1 of 5 CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task Using Data Book Figure 9 (Permissible Successive Attempts to Start Motors) determine the allowed starting time for NCP. Alternate Path Evaluation Location DYES o Simulator DNO Din-Plant
{{#Wiki_filter:CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 1R ADMIN Determine NCP Start Requirements CANDIDATE EXAMINER JPM 1RADMIN                             Page 1 of 5
[g] N/A Time Critical DYES [8J Classroom Safety Function __ [g] NO [g] N/A Evaluation Method [8J Perform DSimulate Validation 10 minutes Time JPM Type D Bank [g] New D Modified KIA 2.1.32 Ability to explain and apply all system limits and precautions (3.4/3.8)
 
Standard Determines 1B NCP can be started first at 1742. References OP/1/N61501001 (Filling and Venting the Reactor Coolant System) rev 099 OP/1/N61501002A (Reactor Coolant Pump Operation) rev 058 Unit 1 Data book Figure 9 (Permissible Successive Attempts to Start Motors) rev 001 Candidate Start Time End Time Duration ------Performance Rating 0 Satisfactory o Unsatisfactory Examiner (Printed Name) (Signature) (Date) Comments JPM 1RADMIN Page 2 of 5 CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task Using Data Book Figure 9 (Permissible Successive Attempts to Start Motors) determine the allowed starting time for NCP. Alternate Path Evaluation Location DYES o Simulator DNO Din-Plant
CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task       Using Data Book Figure 9 (Permissible Successive Attempts to Start Motors) determine the allowed starting time for NCP.
[g] N/A Time Critical DYES [8J Classroom Safety Function __ [g] NO [g] N/A Evaluation Method [8J Perform DSimulate Validation 10 minutes Time JPM Type D Bank [g] New D Modified KIA 2.1.32 Ability to explain and apply all system limits and precautions (3.4/3.8)
Alternate DYES              DNO           [g] N/A             Time Critical     DYES [g] NO Path Evaluation Location o Simulator      Din-Plant    [8J Classroom Safety Function __           [g] N/A Evaluation                                                         Validation      10 minutes
Standard Determines 1B NCP can be started first at 1742. References OP/1/N61501001 (Filling and Venting the Reactor Coolant System) rev 099 OP/1/N61501002A (Reactor Coolant Pump Operation) rev 058 Unit 1 Data book Figure 9 (Permissible Successive Attempts to Start Motors) rev 001 Candidate Start Time End Time Duration ------Performance Rating 0 Satisfactory o Unsatisfactory Examiner (Printed Name) (Signature) (Date) Comments JPM 1RADMIN Page 2 of 5 READ TO OPERATOR DIRECTION TO TRAINEE: I will explain the initial conditions, and state the task to be performed.
[8J Perform       DSimulate Time Method JPM Type   D Bank           [g] New       D Modified KIA         2.1.32 Ability to explain and apply all system limits and precautions (3.4/3.8)
All control room steps shall be performed for this JPM, including any required communications.
Standard   Determines 1B NCP can be started first at 1742.
I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:
References OP/1/N61501001 (Filling and Venting the Reactor Coolant System) rev 099 OP/1/N61501002A (Reactor Coolant Pump Operation) rev 058 Unit 1 Data book Figure 9 (Permissible Successive Attempts to Start Motors) rev 001 Candidate Start Time                     End Time   - - - - - - Duration Performance Rating   0   Satisfactory         o Unsatisfactory Examiner (Printed Name)                         (Signature)                     (Date)
NC system venting is in progress per OP/1/A/61501001 (Filling and Venting the Reactor Coolant System) Enclosure 4.3 (Reactor Coolant System Venting).
Comments JPM 1RADMIN                                                                     Page 2 of 5
At 1725 the crew reaches a step in Enclosure 4.3 which requires the start of either NCP 1A or NCP 1 B. The OAC is not available.
 
INITIATING CUE: Given the run history for these pumps today: Pump Start Time Shutdown Time Run Time NCP1A 1456 1456 20 seconds NCP1A 1535 1536 1 minute NCP1A 1650 1659 9 minutes NCP1B 1502 1502 20 seconds NCP1B 1602 1603 1 minute NCP1B 1704 1712 8 minutes State which pump can be started the earliest and at what time it can be started? JPM 1RADMIN Page 3 of 5 READ TO OPERATOR DIRECTION TO TRAINEE: I will explain the initial conditions, and state the task to be performed.
READ TO OPERATOR DIRECTION TO TRAINEE:
All control room steps shall be performed for this JPM, including any required communications.
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:
INITIAL CONDITIONS:
NC system venting is in progress per OP/1/A/61501001 (Filling and Venting the Reactor Coolant System) Enclosure 4.3 (Reactor Coolant System Venting).
NC system venting is in progress per OP/1/A/61501001 (Filling and Venting the Reactor Coolant System) Enclosure 4.3 (Reactor Coolant System Venting). At 1725 the crew reaches a step in .3 which requires the start of either NCP 1A or NCP 1B. The OAC is not available.
At 1725 the crew reaches a step in Enclosure 4.3 which requires the start of either NCP 1A or NCP 1 B. The OAC is not available.
INITIATING CUE:
INITIATING CUE: Given the run history for these pumps today: Pump Start Time Shutdown Time Run Time NCP1A 1456 1456 20 seconds NCP1A 1535 1536 1 minute NCP1A 1650 1659 9 minutes NCP1B 1502 1502 20 seconds NCP1B 1602 1603 1 minute NCP1B 1704 1712 8 minutes State which pump can be started the earliest and at what time it can be started? JPM 1RADMIN Page 3 of 5 START TIME: __ _ -.U Reviews the NCP start history. STANDARD Determines that 1A NCP has been started 3 times in a 2 hour period (requiring a 1 hour wait) and 1 B NCP 2 times in a 2 hour period (requiring a 30 min wait). COMMENTS --.U Determines how much idle time is required prior to each pumps restart. STANDARD 1A must have 1 hour idle time following shutdown. 1 B must have 30 minute idle time following shutdown.
Given the run history for these pumps today:
COMMENTS lJ Calculates earliest start time for each pump. STANDARD 1A NCP stopped at 1659 + 60 minutes = 1759 1 B NCP stopped at 1712 + 30 minutes = 1742 1 B NCP can be started first at 1742. COMMENTS TIME STOP: __ _ CRITICAL STEP __ SAT __ UNSAT CRITICAL STEP __ SAT __ UNSAT CRITICAL STEP __ SAT __ UNSAT JPM 1RADMIN Page 4 of 5 START TIME: __ _ LU Reviews the NCP start history. STANDARD Determines that 1A NCP has been started 3 times in a 2 hour period (requiring a 1 hour wait) and 1 B NCP 2 times in a 2 hour period (requiring a 30 min wait). COMMENTS LLl Determines how much idle time is required prior to each pumps restart. STANDARD 1A must have 1 hour idle time following shutdown. 1 B must have 30 minute idle time following shutdown.
Pump         Start Time         Shutdown Time            Run Time NCP1A            1456                1456            20 seconds NCP1A            1535                1536              1 minute NCP1A            1650                1659              9 minutes NCP1B            1502                1502            20 seconds NCP1B            1602                1603              1 minute NCP1B            1704                1712              8 minutes State which pump can be started the earliest and at what time it can be started?
COMMENTS Calculates earliest start time for each pump. STANDARD 1A NCP stopped at 1659 + 60 minutes = 1759 1 B NCP stopped at 1712 + 30 minutes = 1742 1 B NCP can be started first at 1742. COMMENTS TIME STOP: __ _ CRITICAL STEP __ SAT __ UNSAT CRITICAL STEP __ SAT __ UNSAT CRITICAL STEP __ SAT __ UNSAT JPM 1RADMIN Page 4 of 5 CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK) INITIAL CONDITIONS:
JPM 1RADMIN                                                                             Page 3 of 5
NC system venting is in progress per OP/1/A/6150/001 (Filling and Venting the Reactor Coolant System) Enclosure 4.3 (Reactor Coolant System Venting).
 
At 1725 the crew reaches a step in Enclosure 4.3 which requires the start of either NCP 1 A or NCP 1 B. The OAC is not available.
START TIME: _ __
INITIATING CUE: Given the run history for these pumps today: Pump Start Time Shutdown Time Run Time NCP1A 1456 1456 20 seconds NCP1A 1535 1536 1 minute NCP1A 1650 1659 9 minutes NCP1B 1502 1502 20 seconds NCP1B 1602 1603 1 minute NCP1B 1704 1712 8 minutes State which pump can be started the earliest and at what time it can be started? CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK) INITIAL CONDITIONS:
LU
NC system venting is in progress per OP/1/A/6150/001 (Filling and Venting the Reactor Coolant System) Enclosure 4.3 (Reactor Coolant System Venting).
-.U Reviews the NCP start history.                                                   CRITICAL STEP STANDARD
At 1725 the crew reaches a step in Enclosure 4.3 which requires the start of either NCP 1 A or NCP 1 B. The OAC is not available.
_ _ SAT Determines that 1A NCP has been started 3 times in a 2 hour period (requiring a 1 hour wait) and 1B NCP 2 times in a 2 hour period (requiring a 30 min wait).
INITIATING CUE: Given the run history for these pumps today: Pump Start Time Shutdown Time Run Time NCP1A 1456 1456 20 seconds NCP1A 1535 1536 1 minute NCP1A 1650 1659 9 minutes NCP1B 1502 1502 20 seconds NCP1B 1602 1603 1 minute NCP1B 1704 1712 8 minutes State which pump can be started the earliest and at what time it can be started?
_ _ UNSAT COMMENTS LLl
CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 1S ADMIN Determine Work Hours Extension Requirements CANDIDATE EXAMINER JPM 18 ADMIN Page 1 of 5 CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 1S ADMIN Determine Work Hours Extension Requirements CANDIDATE EXAMINER JPM 18 ADMIN Page 1 of 5 CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task Determine if a work hours extension is required and if so, which limits are exceeded.
--.U Determines how much idle time is required prior to each pumps restart.            CRITICAL STEP STANDARD
Alternate Path Evaluation Location DYES DNa D Simulator Din-Plant NIA Time Critical DYES IZI Classroom Safety Function __ NIA Evaluation Method IZI Perform DSimulate Validation 30 minutes Time JPM Type D Bank DNew Modified CNS 2005 NRC Exam KIA 2.1.5 Ability to use procedures related to shift staffing, such as minimum crew complement, overtime limitations, etc. (2.9*/3.9)
_ _ SAT 1A must have 1 hour idle time following shutdown.
Standard Determines that Jerry and Chad will require a "C" extension and Jerry will also require a '0' extension. (Stating the verbal description of the limit instead of the corresponding letter is acceptable)
1B must have 30 minute idle time following shutdown.
References NSD-200, Overtime Control Rev 9 Candidate Start Time End Time Duration ------Performance Rating D Satisfactory D Unsatisfactory Examiner (Printed Name) (Signature) (Date) Comments JPM 1S ADMIN Page 2 of 5 CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task Determine if a work hours extension is required and if so, which limits are exceeded.
_ _ UNSAT COMMENTS
Alternate Path Evaluation Location DYES DNa D Simulator Din-Plant NIA Time Critical DYES IZI Classroom Safety Function __ NIA Evaluation Method IZI Perform DSimulate Validation 30 minutes Time JPM Type D Bank DNew Modified CNS 2005 NRC Exam KIA 2.1.5 Ability to use procedures related to shift staffing, such as minimum crew complement, overtime limitations, etc. (2.9*/3.9)
~
Standard Determines that Jerry and Chad will require a "C" extension and Jerry will also require a '0' extension. (Stating the verbal description of the limit instead of the corresponding letter is acceptable)
lJ Calculates earliest start time for each pump.                                    CRITICAL STEP STANDARD
References NSD-200, Overtime Control Rev 9 Candidate Start Time End Time Duration ------Performance Rating D Satisfactory D Unsatisfactory Examiner (Printed Name) (Signature) (Date) Comments JPM 1S ADMIN Page 2 of 5 READ TO OPERATOR DIRECTION TO TRAINEE: I will explain the initial conditions, and state the task to be performed.
_ _ SAT 1A NCP stopped at 1659 + 60 minutes      = 1759 1B NCP stopped at 1712 + 30 minutes      = 1742                                  _ _ UNSAT 1B NCP can be started first at 1742.
All control room steps shall be performed for this JPM, including any required communications.
COMMENTS TIME STOP: _ __
I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:
JPM 1RADMIN                                                                    Page 4 of 5
 
CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
NC system venting is in progress per OP/1/A/6150/001 (Filling and Venting the Reactor Coolant System) Enclosure 4.3 (Reactor Coolant System Venting). At 1725 the crew reaches a step in .3 which requires the start of either NCP 1A or NCP 1B. The OAC is not available.
INITIATING CUE:
Given the run history for these pumps today:
Pump        Start Time        Shutdown Time          Run Time NCP1A          1456                1456            20 seconds NCP1A          1535                1536            1 minute NCP1A          1650                1659            9 minutes NCP1B          1502                1502            20 seconds NCP1B          1602                1603            1 minute NCP1B          1704                1712            8 minutes State which pump can be started the earliest and at what time it can be started?
 
CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 1S ADMIN Determine Work Hours Extension Requirements CANDIDATE EXAMINER JPM 18 ADMIN                            Page 1 of 5
 
CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task        Determine if a work hours extension is required and if so, which limits are exceeded.
Alternate DYES              DNa          ~ NIA                Time Critical      DYES ~NO Path Evaluation                                                          Safety Function _ _        ~ NIA Location D Simulator        Din-Plant    IZI Classroom Evaluation                                                          Validation        30 minutes Method IZI Perform        DSimulate Time JPM Type    D Bank            DNew          ~ Modified            CNS 2005 NRC Exam KIA        2.1.5 Ability to use procedures related to shift staffing, such as minimum crew complement, overtime limitations, etc. (2.9*/3.9)
Standard    Determines that Jerry and Chad will require a "C" extension and Jerry will also require a '0' extension. (Stating the verbal description of the limit instead of the corresponding letter is acceptable)
References  NSD-200, Overtime Control Rev 9 Candidate Start Time                      End Time  ------
Duration Performance Rating    D Satisfactory        D  Unsatisfactory Examiner (Printed Name)                        (Signature)                    (Date)
Comments JPM 1S ADMIN                                                                        Page 2 of 5
 
READ TO OPERATOR DIRECTION TO TRAINEE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
Given the following work history:
Given the following work history:
* Tom and Chad were on vacation Monday through Wednesday.
* Tom and Chad were on vacation Monday through Wednesday.
* Jerry worked the previous 3 days in a day-staff position with a total of 32 hours with no turnover hours.
* Jerry worked the previous 3 days in a day-staff position with a total of 32 hours with no turnover hours.
* Hursel was off Monday and worked overtime Tuesday and Wednesday with a total of 26 hours including a total of 2 hours of turnover time. Operator Arrives Finishes TIO Starts TIO Leaves Thursday Jerry 0615 0630 1845 1900 Tom 0630 0700 1830 1845 Chad 0645 0700 1845 1915 Hursel 0630 0645 1815 1830 Friday Jerry 0645 0715 1800 1815 Tom 0615 0630 1845 1900 Chad 0600 0615 1600 1615 Hursel 0645 0700 1915 1930 Saturday Jerry 0400 0415 1715 1730 Tom 0715 0730 1845 1905 Chad 0515 0530 1915 1930 Hursel 0645 0700 1845 1900 Sunday Jerry 0630 0645 1830 1845 Tom 0630 0645 1830 1845 Chad 0630 0645 1830 1845 Hursel 0630 0645 1830 1845 INITIATING CUE: It is 0800 Sunday morning, and you are the dayshift shift CRS. The OSM has asked you to determine if based on recent work history and the projected work schedule (indicated in grey), any operator(s) on this shift will require a work hours extension and if so, which limits the operator(s) have exceeded.
* Hursel was off Monday and worked overtime Tuesday and Wednesday with a total of 26 hours including a total of 2 hours of turnover time.
Operator       Arrives     Finishes TIO   Starts TIO     Leaves Thursday Jerry           0615           0630         1845         1900 Tom             0630           0700         1830         1845 Chad             0645           0700         1845         1915 Hursel           0630           0645         1815         1830 Friday Jerry           0645           0715         1800         1815 Tom             0615           0630         1845         1900 Chad             0600           0615         1600         1615 Hursel           0645           0700         1915         1930 Saturday Jerry           0400           0415         1715         1730 Tom             0715           0730         1845         1905 Chad             0515           0530         1915         1930 Hursel           0645           0700         1845         1900 Sunday Jerry           0630           0645         1830         1845 Tom             0630           0645         1830         1845 Chad             0630           0645         1830         1845 Hursel           0630           0645         1830         1845 INITIATING CUE:
It is 0800 Sunday morning, and you are the dayshift shift CRS. The OSM has asked you to determine if based on recent work history and the projected work schedule (indicated in grey), any operator(s) on this shift will require a work hours extension and if so, which limits the operator(s) have exceeded.
Assume:
Assume:
* any required work extensions for days prior to today have already been completed by another SRO.
* any required work extensions for days prior to today have already been completed by another SRO.
* The projected work schedule becomes the actual schedule worked. JPM 1S ADMIN Page 3 of 5 READ TO OPERATOR DIRECTION TO TRAINEE: I will explain the initial conditions, and state the task to be performed.
* The projected work schedule becomes the actual schedule worked.
All control room steps shall be performed for this JPM, including any required communications.
JPM 1S ADMIN                                                                             Page 3 of 5
I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:
 
START TIME: _ __
1 Determine if the operators meet any of the following limits:                      CRITICAL STEP
: a. > 16 hours straight (excluding shift turnover time)
: b. > 16 hours in any 24-hour period (excluding shift turnover time)
: c. > 24 hours (28 hours for MNS and ONS) in any 48-hour period (excluding shift turnover time)
: d. > 72 hours in any 7-day period (excluding shift turnover time)
: e. < 8-hour break between scheduled work periods (including shift turnover time)
STANDARD
_ _ SAT Determines that Jerry and Chad will require a "C" extension and Jerry will also require a 'D' extension.
_ _ UNSAT Operator    Arrives  Done    Starts  Leaves    TID    Limit  TfW    Limit T/O      T/O                        24            72 after          after next shift Jerry exceeds condition Conly Chad exceeds conditions C and D EXAMINER NOTE: Student may state the actual verbiage of the limit instead of the corresponding letter. This should be considered acceptable.
COMMENTS TIME STOP: _ __
JPM 1S ADMIN                                                                      Page 4 of 5
 
CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
Given the following work history:
Given the following work history:
* Tom and Chad were on vacation Monday through Wednesday.
* Tom and Chad were on vacation Monday through Wednesday.
* Jerry worked the previous 3 days in a day-staff position with a total of 32 hours with no turnover hours.
* Jerry worked the previous 3 days in a day-staff position with a total of 32 hours with no turnover hours.
* Hursel was off Monday and worked overtime Tuesday and Wednesday with a total of 26 hours including a total of 2 hours of turnover time. Operator Arrives Finishes TIO Starts TIO Leaves Thursday Jerry 0615 0630 1845 1900 Tom 0630 0700 1830 1845 Chad 0645 0700 1845 1915 Hursel 0630 0645 1815 1830 Friday Jerry 0645 0715 1800 1815 Tom 0615 0630 1845 1900 Chad 0600 0615 1600 1615 Hursel 0645 0700 1915 1930 Saturday Jerry 0400 0415 1715 1730 Tom 0715 0730 1845 1905 Chad 0515 0530 1915 1930 Hursel 0645 0700 1845 1900 Sunday Jerry 0630 0645 1830 1845 Tom 0630 0645 1830 1845 Chad 0630 0645 1830 1845 Hursel 0630 0645 1830 1845 INITIATING CUE: It is 0800 Sunday morning, and you are the dayshift shift CRS. The OSM has asked you to determine if based on recent work history and the projected work schedule (indicated in grey), any operator(s) on this shift will require a work hours extension and if so, which limits the operator(s) have exceeded.
* Hursel was off Monday and worked overtime Tuesday and Wednesday with a total of 26 hours including a total of 2 hours of turnover time.
Operator         Arrives   Finishes TIO   Starts TIO   Leaves Thursday Jerry             0615         0630         1845       1900 Tom               0630         0700         1830       1845 Chad             0645         0700         1845       1915 Hursel           0630         0645         1815       1830 Friday Jerry             0645         0715
* 1800       1815 Tom               0615         0630         1845       1900 Chad             0600         0615         1600       1615 Hursel           0645         0700         1915       1930 Saturday Jerry             0400         0415         1715       1730 Tom               0715         0730         1845       1905 Chad             0515         0530         1915       1930 Hursel           0645         0700         1845       1900 Sunday Jerry             0630         0645         1830       1845 Tom               0630         0645         1830       1845 Chad             0630         0645       ..
1830       1845 Hursel           0630         0645         1830       1845 INITIATING CUE:
It is 0800 Sunday morning, and you are the dayshift shift CRS. The OSM has asked you to determine if based on recent work history and the projected work schedule (indicated in grey), any operator(s) on this shift will require a work hours extension per NSD 200 (Work Hour Guidelines and Limits) and if so, which limits the operator(s) have exceeded.
Assume:
Assume:
* any required work extensions for days prior to today have already been completed by another SRO.
* any required work extensions for days prior to today have already been completed by another SRO.
* The projected work schedule becomes the actual schedule worked. JPM 1S ADMIN Page 3 of 5 START TIME: __ _ 1 Determine if the operators meet any of the following limits: a. > 16 hours straight (excluding shift turnover time) b. > 16 hours in any 24-hour period (excluding shift turnover time) c. > 24 hours (28 hours for MNS and ONS) in any 48-hour period (excluding shift turnover time) d. > 72 hours in any 7-day period (excluding shift turnover time) e. < 8-hour break between scheduled work periods (including shift turnover time) STANDARD Determines that Jerry and Chad will require a "C" extension and Jerry will also require a 'D' extension.
* The projected work schedule becomes the actual schedule worked.
Operator Arrives Done Starts Leaves TID T/O T/O Jerry exceeds condition Conly Chad exceeds conditions C and D Limit 24 after TfW Limit 72 after next shift EXAMINER NOTE: Student may state the actual verbiage of the limit instead of the corresponding letter. This should be considered acceptable.
RECORD ANSWERS IN THE TABLE BELOW Name                     Work hour limit exceeded                       Limit(s) exceeded (select one)                         (select any that apply)
COMMENTS TIME STOP: __ _ JPM 1S ADMIN CRITICAL STEP __ SAT __ UNSAT Page 4 of 5 START TIME: __ _ 1 Determine if the operators meet any of the following limits: a. > 16 hours straight (excluding shift turnover time) b. > 16 hours in any 24-hour period (excluding shift turnover time) c. > 24 hours (28 hours for MNS and ONS) in any 48-hour period (excluding shift turnover time) d. > 72 hours in any 7-day period (excluding shift turnover time) e. < 8-hour break between scheduled work periods (including shift turnover time) STANDARD Determines that Jerry and Chad will require a "C" extension and Jerry will also require a 'D' extension.
Jerry                         DYES       o NO                 o a     o b       DC     od       De Tom                           DYES       o NO                 o a     o b       DC     od       De Chad                         DYES       o NO                 o a     o b       DC     od       De Hursel                       DYES       o NO                 o a     o b       DC     od       De
Operator Arrives Done Starts Leaves TID T/O T/O Jerry exceeds condition Conly Chad exceeds conditions C and D Limit 24 after TfW Limit 72 after next shift EXAMINER NOTE: Student may state the actual verbiage of the limit instead of the corresponding letter. This should be considered acceptable.
 
COMMENTS TIME STOP: __ _ JPM 1S ADMIN CRITICAL STEP __ SAT __ UNSAT Page 4 of 5 CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK) INITIAL CONDITIONS:
CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 2R2S ADMIN Perform a Manual Shutdown Margin Calculation (Unit at Power)
Given the following work history:
CANDIDATE EXAMINER JPM 2R2S ADMIN                             Page 1 of 9
* Tom and Chad were on vacation Monday through Wednesday.
 
* Jerry worked the previous 3 days in a day-staff position with a total of 32 hours with no turnover hours.
CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task       Perform a manual shutdown margin calculation (Unit at Power) per OP/O/A/61 00/006 (Reactivity Balance Calculation)
* Hursel was off Monday and worked overtime Tuesday and Wednesday with a total of 26 hours including a total of 2 hours of turnover time. Operator Arrives Finishes TIO Starts TIO Leaves Thursday Jerry 0615 0630 1845 1900 Tom 0630 0700 1830 1845 Chad 0645 0700 1845 1915 Hursel 0630 0645 1815 1830 Friday Jerry 0645 0715
Alternate Path DYES             DNO             r8J N/A           Time Critical     DYES       r8J NO Evaluation D Simulator       Din-Plant       C8J Classroom       Safety Function __           r8J N/A Location Evaluation                                                       Validation        25 minutes Method C8J Perform       DSimulate Time JPM Type   D Bank           DNew           r8J Modified       OP-CN-RT-RB-121 KIA         2.1.25 Ability to interpret reference materials, such as graphs, curves, tables, etc. I (CFR: 41.10/43.5/45.12) 3.9/4.2 Standard   Candidate determines that required shutdown margin is 1300 pcm and current shutdown margin is 1128 pcm, therefore, adequate shutdown margin does not exist per the Unit 1 Core Operating Limits Report References OP/O/A/61 00/006 (Reactivity Balance Calculation), Rev. 73 Unit 1 Reactor Operating Data Book (R.O.D.)
* 1800 1815 Tom 0615 0630 1845 1900 Chad 0600 0615 1600 1615 Hursel 0645 0700 1915 1930 Saturday Jerry 0400 0415 1715 1730 Tom 0715 0730 1845 1905 Chad 0515 0530 1915 1930 Hursel 0645 0700 1845 1900 Sunday Jerry 0630 0645 1830 1845 Tom 0630 0645 1830 1845 Chad 0630 0645 .. 1830 1845 Hursel 0630 0645 1830 1845 INITIATING CUE: It is 0800 Sunday morning, and you are the dayshift shift CRS. The OSM has asked you to determine if based on recent work history and the projected work schedule (indicated in grey), any operator(s) on this shift will require a work hours extension per NSD 200 (Work Hour Guidelines and Limits) and if so, which limits the operator(s) have exceeded.
VERIFY ROD BOOK VALUES MATCH JPM PRIOR TO ADMINISTRATION Candidate Start Time                     End Time     - - - - - - Duration Performance Rating   D Satisfactory             D Unsatisfactory Examiner (Printed Name)                         (Signature)                   (Date)
Assume:
Comments JPM 2R2S ADMIN                                                                   Page 2 of 9
* any required work extensions for days prior to today have already been completed by another SRO.
 
* The projected work schedule becomes the actual schedule worked. RECORD ANSWERS IN THE TABLE BELOW Name Work hour limit exceeded Limit(s) exceeded (select one) (select any that apply) Jerry DYES o NO o a o b DC od Tom DYES o NO o a o b DC od Chad DYES o NO o a o b DC od Hursel DYES o NO o a o b DC od De De De De CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK) INITIAL CONDITIONS:
READ TO OPERATOR DIRECTION TO TRAINEE:
Given the following work history:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handQut sheet I provided you.
* Tom and Chad were on vacation Monday through Wednesday.
INITIAL CONDITIONS:
* Jerry worked the previous 3 days in a day-staff position with a total of 32 hours with no turnover hours.
* Hursel was off Monday and worked overtime Tuesday and Wednesday with a total of 26 hours including a total of 2 hours of turnover time. Operator Arrives Finishes TIO Starts TIO Leaves Thursday Jerry 0615 0630 1845 1900 Tom 0630 0700 1830 1845 Chad 0645 0700 1845 1915 Hursel 0630 0645 1815 1830 Friday Jerry 0645 0715
* 1800 1815 Tom 0615 0630 1845 1900 Chad 0600 0615 1600 1615 Hursel 0645 0700 1915 1930 Saturday Jerry 0400 0415 1715 1730 Tom 0715 0730 1845 1905 Chad 0515 0530 1915 1930 Hursel 0645 0700 1845 1900 Sunday Jerry 0630 0645 1830 1845 Tom 0630 0645 1830 1845 Chad 0630 0645 .. 1830 1845 Hursel 0630 0645 1830 1845 INITIATING CUE: It is 0800 Sunday morning, and you are the dayshift shift CRS. The OSM has asked you to determine if based on recent work history and the projected work schedule (indicated in grey), any operator(s) on this shift will require a work hours extension per NSD 200 (Work Hour Guidelines and Limits) and if so, which limits the operator(s) have exceeded.
Assume:
* any required work extensions for days prior to today have already been completed by another SRO.
* The projected work schedule becomes the actual schedule worked. RECORD ANSWERS IN THE TABLE BELOW Name Work hour limit exceeded Limit(s) exceeded (select one) (select any that apply) Jerry DYES o NO o a o b DC od Tom DYES o NO o a o b DC od Chad DYES o NO o a o b DC od Hursel DYES o NO o a o b DC od De De De De CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 2R2S ADMIN Perform a Manual Shutdown Margin Calculation (Unit at Power) CANDIDATE EXAMINER JPM 2R2S ADMIN Page 1 of 9 CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 2R2S ADMIN Perform a Manual Shutdown Margin Calculation (Unit at Power) CANDIDATE EXAMINER JPM 2R2S ADMIN Page 1 of 9 CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task Perform a manual shutdown margin calculation (Unit at Power) per OP/O/A/61 00/006 (Reactivity Balance Calculation)
Alternate Path Evaluation Location DYES D Simulator DNO Din-Plant r8J N/A Time Critical DYES r8J NO C8J Classroom Safety Function __ r8J N/A Evaluation Method C8J Perform DSimulate Validation 25 minutes Time JPM Type D Bank DNew r8J Modified OP-CN-RT -RB-121 KIA 2.1.25 Ability to interpret reference materials, such as graphs, curves, tables, etc. I (CFR: 41.10/43.5/45.12) 3.9/4.2 Standard Candidate determines that required shutdown margin is 1300 pcm and current shutdown margin is 1128 pcm, therefore, adequate shutdown margin does not exist per the Unit 1 Core Operating Limits Report References OP/O/A/61 00/006 (Reactivity Balance Calculation), Rev. 73 Unit 1 Reactor Operating Data Book (R.O.D.) VERIFY ROD BOOK VALUES MATCH JPM PRIOR TO ADMINISTRATION Candidate Start Time End Time Duration ------Performance Rating D Satisfactory D Unsatisfactory Examiner (Printed Name) (Signature) (Date) Comments JPM 2R2S ADMIN Page 2 of 9 CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task Perform a manual shutdown margin calculation (Unit at Power) per OP/O/A/61 00/006 (Reactivity Balance Calculation)
Alternate Path Evaluation Location DYES D Simulator DNO Din-Plant r8J N/A Time Critical DYES r8J NO C8J Classroom Safety Function __ r8J N/A Evaluation Method C8J Perform DSimulate Validation 25 minutes Time JPM Type D Bank DNew r8J Modified OP-CN-RT -RB-121 KIA 2.1.25 Ability to interpret reference materials, such as graphs, curves, tables, etc. I (CFR: 41.10/43.5/45.12) 3.9/4.2 Standard Candidate determines that required shutdown margin is 1300 pcm and current shutdown margin is 1128 pcm, therefore, adequate shutdown margin does not exist per the Unit 1 Core Operating Limits Report References OP/O/A/61 00/006 (Reactivity Balance Calculation), Rev. 73 Unit 1 Reactor Operating Data Book (R.O.D.) VERIFY ROD BOOK VALUES MATCH JPM PRIOR TO ADMINISTRATION Candidate Start Time End Time Duration ------Performance Rating D Satisfactory D Unsatisfactory Examiner (Printed Name) (Signature) (Date) Comments JPM 2R2S ADMIN Page 2 of 9 READ TO OPERATOR DIRECTION TO TRAINEE: I will explain the initial conditions, and state the task to be performed.
All control room steps shall be performed for this JPM, including any required communications.
I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handQut sheet I provided you. INITIAL CONDITIONS:
You are the Unit 1 OATC. The Reactivity Computer (REACT) is out of-service.
You are the Unit 1 OATC. The Reactivity Computer (REACT) is out of-service.
Current plant conditions are as follows:
Current plant conditions are as follows:
* Power level = 80%
* Power level =80%
* NC Tavg = 579.5 OF
* NC Tavg = 579.5 OF
* Boron Concentration:
* Boron Concentration: 959 ppm
959 ppm
* Core burnup: 200 EFPD
* Core burnup: 200 EFPD
* Shutdown rod bank position:
* Shutdown rod bank position: 226 steps
226 steps
* Control rod bank A: 226 steps
* Control rod bank A: 226 steps
* Control rod bank B: 226 steps
* Control rod bank B: 226 steps
* Control rod bank C: 226 steps
* Control rod bank C: 226 steps
* Control rod bank D: 200 steps INITIATING CUE: You have just been informed by the Control Room SRO that the following rods are untrippable:
* Control rod bank D: 200 steps INITIATING CUE:
You have just been informed by the Control Room SRO that the following rods are untrippable:
* G-13
* G-13
* K-2
* K-2
* P-4 Perform a Shutdown Margin Calculation per OP/O/A/61 00/006 (Reactivity Balance Calculation) and determine if Core Operating Limits Report requirement for shutdown margin is satisfied.
* P-4 Perform a Shutdown Margin Calculation per OP/O/A/61 00/006 (Reactivity Balance Calculation) and determine if Core Operating Limits Report requirement for shutdown margin is satisfied.
Calculation verification is waived. JPM 2R2S ADMIN Page 3 of 9 READ TO OPERATOR DIRECTION TO TRAINEE: I will explain the initial conditions, and state the task to be performed.
Calculation verification is waived.
All control room steps shall be performed for this JPM, including any required communications.
JPM 2R2S ADMIN                                                                         Page 3 of 9
I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handQut sheet I provided you. INITIAL CONDITIONS:
 
You are the Unit 1 OATC. The Reactivity Computer (REACT) is out of-service.
START TIME: _ __
Current plant conditions are as follows:
LU Candidate obtains a copy of OP/o/Al61 001006 (Reactivity Balance Calculation)     CRITICAL STEP and from initiating cue and determines that Enclosure 4.3 is applicable.
* Power level = 80%
STANDARD Candidate obtains a copy of OP/OIAl61 001006 (Reactivity Balance Calculation).   - - SAT
* NC Tavg = 579.5 OF
                                                                                    - - UNSAT EXAMINER NOTE When the candidate locates the appropriate procedure, give himlher a copy of o P101Al61 001006.
* Boron Concentration:
COMMENTS 2J LU Limits and Precautions have been reviewed.
959 ppm
STANDARD Examinee reviews Limits and Precautions.                                         - - SAT
* Core burnup: 200 EFPD
                                                                                    - - UNSAT EXAMINER CUE Candidate should be able to determine per initial conditions that Tavg is within 1&deg;F based on power level and Tref program.
* Shutdown rod bank position:
COMMENTS JPM 2R2S ADMIN                                                                   Page 4 of 9
226 steps
 
* Control rod bank A: 226 steps
ll-J
* Control rod bank B: 226 steps
~ OP/O/A/6100/o06         Enc14.3     Step 2.1 Determine the following information:                                             CRITICAL STEP STANDARD
* Control rod bank C: 226 steps
_ _ SAT Operator records the following data using the initial conditions.
* Control rod bank D: 200 steps INITIATING CUE: You have just been informed by the Control Room SRO that the following rods are untrippable:
_ _ UNSAT
* G-13
* K-2
* P-4 Perform a Shutdown Margin Calculation per OP/O/A/61 00/006 (Reactivity Balance Calculation) and determine if Core Operating Limits Report requirement for shutdown margin is satisfied.
Calculation verification is waived. JPM 2R2S ADMIN Page 3 of 9 START TIME: __ _ LU Candidate obtains a copy of OP/o/Al61 001006 (Reactivity Balance Calculation)
CRITICAL STEP and from initiating cue and determines that Enclosure 4.3 is applicable.
STANDARD Candidate obtains a copy of OP/OIAl61 001006 (Reactivity Balance Calculation).  
--SAT UNSAT --EXAMINER NOTE When the candidate locates the appropriate procedure, give himlher a copy of o P 101 Al61 001006. COMMENTS 2J Limits and Precautions have been reviewed.
STANDARD Examinee reviews Limits and Precautions.  
--SAT UNSAT --EXAMINER CUE Candidate should be able to determine per initial conditions that Tavg is within 1&deg;F based on power level and Tref program. COMMENTS JPM 2R2S ADMIN Page 4 of 9 START TIME: __ _ LU Candidate obtains a copy of OP/o/Al61 001006 (Reactivity Balance Calculation)
CRITICAL STEP and from initiating cue and determines that Enclosure 4.3 is applicable.
STANDARD Candidate obtains a copy of OP/OIAl61 001006 (Reactivity Balance Calculation).
--SAT UNSAT --EXAMINER NOTE When the candidate locates the appropriate procedure, give himlher a copy of o P 101 Al61 001006. COMMENTS LU Limits and Precautions have been reviewed.
STANDARD Examinee reviews Limits and Precautions.
--SAT UNSAT --EXAMINER CUE Candidate should be able to determine per initial conditions that Tavg is within 1&deg;F based on power level and Tref program. COMMENTS JPM 2R2S ADMIN Page 4 of 9 OP/O/A/6100/o06 Enc14.3 Step 2.1 Determine the following information:
STANDARD Operator records the following data using the initial conditions.
* Unit: 1
* Unit: 1
* Date/Time:
* Date/Time: Current Date/Time
Current Date/Time
* Present Power: 80%
* Present Power: 80%
* NC System Boron Concentration 959 ppm
* NC System Boron Concentration 959 ppm
* Current Burnup: 200 EFPD
* Current Burnup: 200 EFPD
* Present Control Bank Position:
* Present Control Bank Position: 200 SWD, Control Bank 0
200 SWD, Control Bank 0
* Present Shutdown bank Position: ALL @ 226
* Present Shutdown bank Position:
ALL @ 226
* Quantity of misaligned rods: ...Q
* Quantity of misaligned rods: ...Q
* Number of untrippable RCCA(s):
* Number of untrippable RCCA(s): ~
* Untrippable RCCA(s) core location(s):
* Untrippable RCCA(s) core location(s): G-13. K-2. P-4 COMMENTS
G-13. K-2. P-4 COMMENTS OP/O/A/61001006 Encl 4.3 Step 2.3.1.1 Determine total available rod worth. (Step 2.2 is NIA due to REACTBAL unavailable)
~      OP/O/A/61001006 Encl 4.3       Step 2.3.1.1 Determine total available rod worth. (Step 2.2 is NIA due to REACTBAL             CRITICAL STEP unavailable)
STANDARD Determine total available rod worth to be 5084 pcm per section 5.7 of Reactor Operating Data (R.O.D.) Manual. COMMENTS OP/O/A/61001006 Encl 4.3 Step 2.3.1.2 !f only one RCCA is untrippable, determine reactivity worth ..... STANDARD Determines there are multiple untrippable RCCA's and does not perform step 2.3.1.2. COMMENTS JPM 2R2S ADMIN CRITICAL STEP __ SAT __ UNSAT CRITICAL STEP __ SAT __ UNSAT CRITICAL STEP __ SAT __ UNSAT Page 5 of 9 ll-J OP/O/A/6100/o06 Enc14.3 Step 2.1 Determine the following information:
STANDARD
STANDARD Operator records the following data using the initial conditions.
_ _ SAT Determine total available rod worth to be 5084 pcm per section 5.7 of Reactor Operating Data (R.O.D.) Manual.
* Unit: 1
_ _ UNSAT COMMENTS
* Date/Time:
~ OP/O/A/61001006 Encl 4.3           Step 2.3.1.2
Current Date/Time
  !f only one RCCA is untrippable, determine reactivity worth   .....               CRITICAL STEP STANDARD
* Present Power: 80%
_ _ SAT Determines there are multiple untrippable RCCA's and does not perform step 2.3.1.2.
* NC System Boron Concentration 959 ppm
_ _ UNSAT COMMENTS JPM 2R2S ADMIN                                                                 Page 5 of 9
* Current Burnup: 200 EFPD
 
* Present Control Bank Position:
~    OP/O/A/61001006 Enc14.3       Step 2.3.1.3 IF there are multiple untrippable RCCA's, perform the following:                     CRITICAL STEP Determine untrippable RCCA of step 2.1.10 with the highest reactivity worth penalty. (Section 5.8 of RO.D. Manual)
200 SWD, Control Bank 0
STANDARD
* Present Shutdown bank Position:
_ _ SAT Refers to section 5.8 of the RO.D. Manual. Determines RCCA G-13 rod worth is 232 pem, P-4 rod worth is 28 pem and RCCA K-2 Rod worth is 290 pem.
ALL @ 226
_ _ UNSAT Chooses K-2 I 290 pem.
* Quantity of misaligned rods: ...Q
COMMENTS
* Number of untrippable RCCA(s):
~ OP/O/A/61001006 Enc14.3           Step 2.3.1.3 Determine maximum stuck rod worth during cycle (Section                               CRITICAL STEP 5.7 of the RO.D. manual).
* Untrippable RCCA(s) core location(s):
STANDARD
G-13. K-2. P-4 COMMENTS OP/O/A/61001006 Encl 4.3 Step 2.3.1.1 Determine total available rod worth. (Step 2.2 is NIA due to REACTBAL unavailable)
_ _ SAT Determines maximum stuck rod worth during cycle is 895 pem per section 5.7 of the RO.D. Manual.
STANDARD Determine total available rod worth to be 5084 pcm per section 5.7 of Reactor Operating Data (R.O.D.) Manual. COMMENTS OP/O/A/61001006 Encl 4.3 Step 2.3.1.2 !f only one RCCA is untrippable, determine reactivity worth ..... STANDARD Determines there are multiple untrippable RCCA's and does not perform step 2.3.1.2. COMMENTS JPM 2R2S ADMIN CRITICAL STEP __ SAT __ UNSAT CRITICAL STEP __ SAT __ UNSAT CRITICAL STEP __ SAT __ UNSAT Page 5 of 9 OP/O/A/61001006 Enc14.3 Step 2.3.1.3 IF there are multiple untrippable RCCA's, perform the following:
_ _ UNSAT COMMENTS
Determine untrippable RCCA of step 2.1.10 with the highest reactivity worth penalty. (Section 5.8 of RO.D. Manual) STANDARD Refers to section 5.8 of the RO.D. Manual. Determines RCCA G-13 rod worth is 232 pem, P-4 rod worth is 28 pem and RCCA K-2 Rod worth is 290 pem. Chooses K-2 I 290 pem. COMMENTS OP/O/A/61001006 Enc14.3 Step 2.3.1.3 Determine maximum stuck rod worth during cycle (Section 5.7 of the RO.D. manual). STANDARD Determines maximum stuck rod worth during cycle is 895 pem per section 5.7 of the RO.D. Manual. COMMENTS OP/O/A/61001006 Enc14.3 Step 2.3.1.3/2.3.1.4 CRITICAL STEP __ SAT __ UNSAT CRITICAL STEP __ SAT __ UNSAT Calculate total untrippable RCCA reactivity worth penalty for multiple untrippable CRITICAL STEP RCCA's STANDARD Calculates a penalty at 2080 pem and records. __ SAT (3-1)x(895)
~    OP/O/A/61001006 Enc14.3       Step 2.3.1.3/2.3.1.4 Calculate total untrippable RCCA reactivity worth penalty for multiple untrippable   CRITICAL STEP RCCA's STANDARD
+ (290) = 2080 pem UNSAT COMMENTS JPM 2R2S ADMIN Page 6 of 9 OP/O/A/61001006 Enc14.3 Step 2.3.1.3 IF there are multiple untrippable RCCA's, perform the following:
_ _ SAT Calculates a penalty at 2080 pem and records.
Determine untrippable RCCA of step 2.1.10 with the highest reactivity worth penalty. (Section 5.8 of RO.D. Manual) STANDARD Refers to section 5.8 of the RO.D. Manual. Determines RCCA G-13 rod worth is 232 pem, P-4 rod worth is 28 pem and RCCA K-2 Rod worth is 290 pem. Chooses K-2 I 290 pem. COMMENTS OP/O/A/61001006 Enc14.3 Step 2.3.1.3 Determine maximum stuck rod worth during cycle (Section 5.7 of the RO.D. manual). STANDARD Determines maximum stuck rod worth during cycle is 895 pem per section 5.7 of the RO.D. Manual. COMMENTS OP/O/A/61001006 Enc14.3 Step 2.3.1.3/2.3.1.4 CRITICAL STEP __ SAT __ UNSAT CRITICAL STEP __ SAT __ UNSAT Calculate total untrippable RCCA reactivity worth penalty for multiple untrippable CRITICAL STEP RCCA's STANDARD Calculates a penalty at 2080 pem and records. __ SAT (3-1)x(895)  
UNSAT (3-1)x(895) + (290) = 2080 pem COMMENTS JPM 2R2S ADMIN                                                                     Page 6 of 9
+ (290) = 2080 pem UNSAT COMMENTS JPM 2R2S ADMIN Page 6 of 9 ULJ OP/O/A/61001006 Ene! 4.3 Step 2.3.1.5 Calculate total untrippable RCCA reactivity worth penalty for multiple untrippable RCCA's STANDARD Determines from Section 5.6.3 of the R.O.D. Manual: (page 1 of 6) Bk D @ 200 steps) Reactivity worth 44 pem (CB) Reactivity worth of HFP, Eq Xenon to be 0 pem (SB) Calculates inserted reactivity worth of 44 pem. COMMENTS OP/O/A/61001006 Ene! 4.3 Step 2.3.1.6 Calculate available reactivity worth of trippable rods. STANDARD Determines:
 
Total available rod worth 5084 pem (Step 2.3.1.1) Untrippable RCCA penalty 2080 pem (Step 2.3.1.4) Inserted Rod Worth 44 pem (Step 2.3.1.5) Calculates available worth of trippable RCCA's is 2960 pem (5084 pem) -(2080 pem) -(44 pem) = 2960 pem COMMENTS W1J OP/O/A/61001006 Ene! 4.3 Step 2.3.1.7 Calculate total misaligned RCCA reactivity worth below: STANDARD Determines no rods are misaligned or dropped and calculates Q.: o X 200 pem = 0 pem COMMENTS CRITICAL STEP __ SAT UNSAT CRITICAL STEP __ SAT __ UNSAT SAT __ UNSAT JPM 2R2S ADMIN Page 7 of 9 ULJ OP/O/A/61001006 Ene! 4.3 Step 2.3.1.5 Calculate total untrippable RCCA reactivity worth penalty for multiple untrippable RCCA's STANDARD Determines from Section 5.6.3 of the R.O.D. Manual: (page 1 of 6) Bk D @ 200 steps) Reactivity worth 44 pem (CB) Reactivity worth of HFP, Eq Xenon to be 0 pem (SB) Calculates inserted reactivity worth of 44 pem. COMMENTS OP/O/A/61001006 Ene! 4.3 Step 2.3.1.6 Calculate available reactivity worth of trippable rods. STANDARD Determines:
ULJ OP/O/A/61001006       Ene! 4.3   Step 2.3.1.5 Calculate total untrippable RCCA reactivity worth penalty for multiple untrippable   CRITICAL STEP RCCA's STANDARD
Total available rod worth 5084 pem (Step 2.3.1.1) Untrippable RCCA penalty 2080 pem (Step 2.3.1.4) Inserted Rod Worth 44 pem (Step 2.3.1.5) Calculates available worth of trippable RCCA's is 2960 pem (5084 pem) -(2080 pem) -(44 pem) = 2960 pem COMMENTS W1J OP/O/A/61001006 Ene! 4.3 Step 2.3.1.7 Calculate total misaligned RCCA reactivity worth below: STANDARD Determines no rods are misaligned or dropped and calculates Q.: o X 200 pem = 0 pem COMMENTS CRITICAL STEP __ SAT UNSAT CRITICAL STEP __ SAT __ UNSAT SAT __ UNSAT JPM 2R2S ADMIN Page 7 of 9 OP/O/A/61001006 Ene! 4.3 Step 2.3.2 Calculate SDM for present conditions.
_ _ SAT Determines from Section 5.6.3 of the R.O.D. Manual:
STANDARD Determines:
(page 1 of 6) Bk D @ 200 steps)
Determines in step 2.4 available worth of trippable RCA's 2960 pcm Total misaligned RCCA reactivity worth 0 pcm Power defect of 1343 pcm per section 5.9 of RO.D. Manual Transient Flux Redistribution Allowance of 489 pcm per Section 5.7 of the RO.D. Manual. Calculates present SDM of 1128 pcm (2960 pcm) -(0 pcm) -(1343 pcm) -(489 pcm) = 1128 pcm COMMENTS OPIOIA/61001006 Ene! 4.3 Step 2.3.2 Verify present SDM is 1300 pcm per the applicable Technical Specification via COLR STANDARD Candidates determines that adequate shutdown margin does not exist since actual is 1128 pcm and the COLR requirement is1300 pcm. EXAMINER CUE: Another operator will take actions and complete the procedure.
UNSAT Reactivity worth 44 pem (CB)
COMMENTS TIME STOP: __ _ CRITICAL STEP SAT UNSAT CRITICAL STEP SAT UNSAT JPM 2R2S ADMIN Page 8 of 9 OP/O/A/61001006 Ene! 4.3 Step 2.3.2 Calculate SDM for present conditions.
Reactivity worth of HFP, Eq Xenon to be 0 pem (SB)
STANDARD Determines:
Calculates inserted reactivity worth of 44 pem.
Determines in step 2.4 available worth of trippable RCA's 2960 pcm Total misaligned RCCA reactivity worth 0 pcm Power defect of 1343 pcm per section 5.9 of RO.D. Manual Transient Flux Redistribution Allowance of 489 pcm per Section 5.7 of the RO.D. Manual. Calculates present SDM of 1128 pcm (2960 pcm) -(0 pcm) -(1343 pcm) -(489 pcm) = 1128 pcm COMMENTS OPIOIA/61001006 Ene! 4.3 Step 2.3.2 Verify present SDM is 1300 pcm per the applicable Technical Specification via COLR STANDARD Candidates determines that adequate shutdown margin does not exist since actual is 1128 pcm and the COLR requirement is1300 pcm. EXAMINER CUE: Another operator will take actions and complete the procedure.
COMMENTS
COMMENTS TIME STOP: __ _ CRITICAL STEP SAT UNSAT CRITICAL STEP SAT UNSAT JPM 2R2S ADMIN Page 8 of 9 CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK) INITIAL CONDITIONS:
~ OP/O/A/61001006 Ene! 4.3           Step 2.3.1.6 Calculate available reactivity worth of trippable rods.                             CRITICAL STEP STANDARD
_ _ SAT Determines:
Total available rod worth 5084 pem (Step 2.3.1.1)
_ _ UNSAT Untrippable RCCA penalty 2080 pem (Step 2.3.1.4)
Inserted Rod Worth 44 pem (Step 2.3.1.5)
Calculates available worth of trippable RCCA's is 2960 pem (5084 pem) - (2080 pem) - (44 pem)       =2960 pem COMMENTS W1J OP/O/A/61001006       Ene! 4.3   Step 2.3.1.7 Calculate total misaligned RCCA reactivity worth below:
STANDARD SAT Determines no rods are misaligned or dropped and calculates Q.:
_ _ UNSAT o X 200 pem =0 pem COMMENTS JPM 2R2S ADMIN                                                                     Page 7 of 9
 
~ OP/O/A/61001006 Ene! 4.3         Step 2.3.2 Calculate SDM for present conditions.                                             CRITICAL STEP STANDARD SAT Determines:
Determines in step 2.4 available worth of trippable RCA's 2960 pcm UNSAT Total misaligned RCCA reactivity worth 0 pcm Power defect of 1343 pcm per section 5.9 of RO.D. Manual Transient Flux Redistribution Allowance of 489 pcm per Section 5.7 of the RO.D. Manual.
Calculates present SDM of 1128 pcm (2960 pcm) - (0 pcm) - (1343 pcm) - (489 pcm)     = 1128 pcm COMMENTS
~ OPIOIA/61001006 Ene! 4.3         Step 2.3.2 Verify present SDM is ~ 1300 pcm per the applicable Technical Specification via   CRITICAL STEP COLR STANDARD SAT Candidates determines that adequate shutdown margin does not exist since actual is 1128 pcm and the COLR requirement is1300 pcm.
UNSAT EXAMINER CUE:
Another operator will take actions and complete the procedure.
COMMENTS TIME STOP: _ __
JPM 2R2S ADMIN                                                                   Page 8 of 9
 
CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
You are the Unit 1 OATC. The Reactivity Computer (REACT) is out of-service.
You are the Unit 1 OATC. The Reactivity Computer (REACT) is out of-service.
Current plant conditions are as follows:
Current plant conditions are as follows:
* Power level = 80%
* Power level = 80%
* NC Tavg = 579.5 of
* NC Tavg = 579.5 of
* Boron Concentration:
* Boron Concentration: 959 ppm
959 ppm
* Core burnup: 200 EFPD
* Core burnup: 200 EFPD
* Shutdown rod bank position:
* Shutdown rod bank position: 226 steps
226 steps
* Control rod bank A: 226 steps
* Control rod bank A: 226 steps
* Control rod bank B: 226 steps
* Control rod bank B: 226 steps
* Control rod bank C: 226 steps
* Control rod bank C: 226 steps
* Control rod bank D: 200 steps INITIATING CUE: You have just been informed by the Control Room SRO that the following rods are untrippable:
* Control rod bank D: 200 steps INITIATING CUE:
* G-13
You have just been informed by the Control Room SRO that the following rods are untrippable:
* K-2
* P-4 Perform a Shutdown Margin Calculation per OP/O/A/61 00/006 (Reactivity Balance Calculation) and determine if Core Operating Limits Report requirement for shutdown margin is satisfied.
Calculation verification is waived. CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK) INITIAL CONDITIONS:
You are the Unit 1 OATC. The Reactivity Computer (REACT) is out of-service.
Current plant conditions are as follows:
* Power level = 80%
* NC Tavg = 579.5 of
* Boron Concentration:
959 ppm
* Core burnup: 200 EFPD
* Shutdown rod bank position:
226 steps
* Control rod bank A: 226 steps
* Control rod bank B: 226 steps
* Control rod bank C: 226 steps
* Control rod bank D: 200 steps INITIATING CUE: You have just been informed by the Control Room SRO that the following rods are untrippable:
* G-13
* G-13
* K-2
* K-2
* P-4 Perform a Shutdown Margin Calculation per OP/O/A/61 00/006 (Reactivity Balance Calculation) and determine if Core Operating Limits Report requirement for shutdown margin is satisfied.
* P-4 Perform a Shutdown Margin Calculation per OP/O/A/61 00/006 (Reactivity Balance Calculation) and determine if Core Operating Limits Report requirement for shutdown margin is satisfied.
Calculation verification is waived.
Calculation verification is waived.
CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 3RADMIN Complete a Unit Vent Flow Manual Calculation per PT/1/A14450/017 CANDIDATE EXAMINER JPM 3RADMIN Page 1 of 8 CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 3RADMIN Complete a Unit Vent Flow Manual Calculation per PT/1/A14450/017 CANDIDATE EXAMINER JPM 3RADMIN Page 1 of 8 CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task Calculate Unit Vent flow manually per PT/1/A/44501017 (Unit Vent Flow Manual Calculation).
 
Alternate Path Evaluation Location DYES DNO Simulator Din-Plant C8J N/A Time Critical DYES D Classroom Safety Function __ C8J NO C8J N/A Evaluation Method Perform DSimulate Validation 10 minutes Time JPM Type D Bank DNew C8J Mod ified MNS 2007 NRC exam (A3) KIA 2.2.12 Knowledge of surveillance procedures. (CFR: 41.10/45.13)
CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 3RADMIN Complete a Unit Vent Flow Manual Calculation per PT/1/A14450/017 CANDIDATE EXAMINER JPM 3RADMIN                             Page 1 of 8
(3.0/3.4)
 
Standard Unit Vent flow is calculated to be 117450 scfm +1-1000. References PT/1/A/44501017 (Unit Vent Flow Manual Calculation) rev 012 SLC 16.11-7 (Radioactive Gaseous Effluent Monitoring Instrumentation)
CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task       Calculate Unit Vent flow manually per PT/1/A/44501017 (Unit Vent Flow Manual Calculation).
Candidate Start Time End Time Duration Performance Rating D Satisfactory D Unsatisfactory Examiner (Printed Name) (Signature) (Date) Comments JPM 3RADMIN Page 2 of 8 CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task Calculate Unit Vent flow manually per PT/1/A/44501017 (Unit Vent Flow Manual Calculation).
Alternate Path DYES               DNO           C8J N/A             Time Critical   DYES     C8J NO Evaluation
Alternate Path Evaluation Location DYES DNO Simulator Din-Plant C8J N/A Time Critical DYES D Classroom Safety Function __ C8J NO C8J N/A Evaluation Method Perform DSimulate Validation 10 minutes Time JPM Type D Bank DNew C8J Mod ified MNS 2007 NRC exam (A3) KIA 2.2.12 Knowledge of surveillance procedures. (CFR: 41.10/45.13)  
              ~ Simulator       Din-Plant     D Classroom Safety Function __         C8J N/A Location Evaluation                                                       Validation       10 minutes
(3.0/3.4)
              ~ Perform        DSimulate Method                                                            Time JPM Type   D Bank             DNew         C8J Mod ified       MNS 2007 NRC exam (A3)
Standard Unit Vent flow is calculated to be 117450 scfm +1-1000. References PT/1/A/44501017 (Unit Vent Flow Manual Calculation) rev 012 SLC 16.11-7 (Radioactive Gaseous Effluent Monitoring Instrumentation)
KIA         2.2.12 Knowledge of surveillance procedures. (CFR: 41.10/45.13) (3.0/3.4)
Candidate Start Time End Time Duration Performance Rating D Satisfactory D Unsatisfactory Examiner (Printed Name) (Signature) (Date) Comments JPM 3RADMIN Page 2 of 8 SIMULATOR SETUP UseSNAP __ Fail VFP 5310 to 0 Place OOS sticker on VFP 5310 (1A VF Flow) SET VA FLOW TO 56000 READ TO OPERATOR DIRECTION TO TRAINEE: I will explain the initial conditions, and state the task to be performed.
Standard   Unit Vent flow is calculated to be 117450 scfm +1- 1000.
All control room steps shall be performed for this JPM, including any required communications.
References PT/1/A/44501017 (Unit Vent Flow Manual Calculation) rev 012 SLC 16.11-7 (Radioactive Gaseous Effluent Monitoring Instrumentation)
I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:
Candidate Start Time                     End Time                     Duration Performance Rating   D Satisfactory           D Unsatisfactory Examiner (Printed Name)                       (Signature)                   (Date)
Comments JPM 3RADMIN                                                                       Page 2 of 8
 
SIMULATOR SETUP UseSNAP _ _
Fail VFP 5310 to 0 Place OOS sticker on VFP 5310 (1A VF Flow)
SET VA FLOW TO 56000 READ TO OPERATOR DIRECTION TO TRAINEE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
* Both Units are operating at 100% power.
* Both Units are operating at 100% power.
* No va release is in progress.
* No va release is in progress.
Line 228: Line 248:
* The Waste Evaporator and Recycle Evaporator are secured.
* The Waste Evaporator and Recycle Evaporator are secured.
* The Unit Vent Stack Flow Rate Meter is inoperable.
* The Unit Vent Stack Flow Rate Meter is inoperable.
* Auxiliary Building NLO has called the control room to report 1ABUXF Discharge Air Flow (1ABUX-AFMD-1) is reading 27000 scfm. INITIATING CUE: Calculate Unit Vent flow per PT/1/A/44501017 (Unit Vent Flow Manual Calculation)
* Auxiliary Building NLO has called the control room to report 1ABUXF Discharge Air Flow (1ABUX-AFMD-1) is reading 27000 scfm.
Enclosure 13.1. JPM 3R ADMIN Page 3 of 8 SIMULATOR SETUP UseSNAP __ Fail VFP 5310 to 0 Place OOS sticker on VFP 5310 (1A VF Flow) SET VA FLOW TO 56000 READ TO OPERATOR DIRECTION TO TRAINEE: I will explain the initial conditions, and state the task to be performed.
INITIATING CUE:
All control room steps shall be performed for this JPM, including any required communications.
Calculate Unit Vent flow per PT/1/A/44501017 (Unit Vent Flow Manual Calculation) Enclosure 13.1.
I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:
JPM 3R ADMIN                                                                             Page 3 of 8
* Both Units are operating at 100% power.
 
* No va release is in progress.
START TIME: _ __
* No GWRs are in progress.
~MINERNOTE When candidate locates PT/1/A/44501017, hand out a copy of the PT provided.
* The Waste Evaporator and Recycle Evaporator are secured.
~
* The Unit Vent Stack Flow Rate Meter is inoperable.
Operator locates and records VA System flow.                                   CRITICAL STEP STANDARD
* Auxiliary Building NLO has called the control room to report 1ABUXF Discharge Air Flow (1ABUX-AFMD-1) is reading 27000 scfm. INITIATING CUE: Calculate Unit Vent flow per PT/1/A/44501017 (Unit Vent Flow Manual Calculation)
_ _ SAT Operator locates 1VAP5280 on 1MC-3 and records 56,000 scfm.
Enclosure 13.1. JPM 3R ADMIN Page 3 of 8 START TIME: __ _
_ _ UNSAT EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
When candidate locates PT/1/A/44501017, hand out a copy of the PT provided. Operator locates and records VA System flow. STANDARD Operator locates 1 VAP5280 on 1 MC-3 and records 56,000 scfm. EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
EXAMINER NOTE: Range of 55000 to 57000 scfm is acceptable.
EXAMINER NOTE: Range of 55000 to 57000 scfm is acceptable.
COMMENTS lLJ Operator locates and records VE 1 A flow to stack. STANDARD Locates 1 VEP5180, notes VE 1 A is shutdown and records 0 scfm. EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
COMMENTS lLJ Operator locates and records VE 1A flow to stack.
COMMENTS Operator locates and records VE 1 B flow to stack. STANDARD Locates 1VEP5200, notes VE 1B is shutdown and records Oscfm. EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
STANDARD
COMMENTS JPM 3RADMIN CRITICAL STEP __ SAT __ UNSAT __ SAT __ UNSAT __ SAT UNSAT Page 4 of 8 START TIME: __ _
_ _ SAT Locates 1VEP5180, notes VE 1A is shutdown and records 0 scfm.
When candidate locates PT/1/A/44501017, hand out a copy of the PT provided. Operator locates and records VA System flow. STANDARD Operator locates 1 VAP5280 on 1 MC-3 and records 56,000 scfm. EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
_ _ UNSAT EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
EXAMINER NOTE: Range of 55000 to 57000 scfm is acceptable.
COMMENTS
COMMENTS lLJ Operator locates and records VE 1 A flow to stack. STANDARD Locates 1 VEP5180, notes VE 1 A is shutdown and records 0 scfm. EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
~
COMMENTS Operator locates and records VE 1 B flow to stack. STANDARD Locates 1VEP5200, notes VE 1B is shutdown and records Oscfm. EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
Operator locates and records VE 1B flow to stack.
COMMENTS JPM 3RADMIN CRITICAL STEP __ SAT __ UNSAT __ SAT __ UNSAT __ SAT UNSAT Page 4 of 8 LU Operator locates and records VF 1 A flow to stack. STANDARD Locates 1 VFP531 0, notes VF reading is OOS and uses 33130 scfm from enclosure 13.2. EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
STANDARD
COMMENTS Operator locates and records VF 1 B flow to stack. STANDARD Locates 1VFP5340, notes VF 1 B is shutdown and records Oscfm. EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
_ _ SAT Locates 1VEP5200, notes VE 1B is shutdown and records Oscfm.
COMMENTS LLJ Records 1ABUX-AFMD-1 flow. STANDARD Records 27000 scfm based on initial cue. COMMENTS Operator records VP flows. STANDARD Based on initial cues VP is secured. Flows recorded as 0 scfm or N/A. COMMENTS JPM 3RADMIN CRITICAL STEP __ SAT __ UNSAT SAT __ UNSAT CRITICAL STEP __ SAT __ UNSAT __ SAT __ UNSAT Page 5 of 8 LU Operator locates and records VF 1 A flow to stack. STANDARD Locates 1 VFP531 0, notes VF reading is OOS and uses 33130 scfm from enclosure 13.2. EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
UNSAT EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
COMMENTS Operator locates and records VF 1 B flow to stack. STANDARD Locates 1VFP5340, notes VF 1 B is shutdown and records Oscfm. EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
COMMENTS JPM 3RADMIN                                                                   Page 4 of 8
COMMENTS LLJ Records 1ABUX-AFMD-1 flow. STANDARD Records 27000 scfm based on initial cue. COMMENTS Operator records VP flows. STANDARD Based on initial cues VP is secured. Flows recorded as 0 scfm or N/A. COMMENTS JPM 3RADMIN CRITICAL STEP __ SAT __ UNSAT SAT __ UNSAT CRITICAL STEP __ SAT __ UNSAT __ SAT __ UNSAT Page 5 of 8 LU Operator records WG flow and VQ flow. STANDARD Based on initial cues records flow as 0 scfm or N/A SAT UNSAT COMMENTS Operator records TL flow CRITICAL STEP STANDARD Based on initial cue and procedure notes records 1260 scfm. --SAT UNSAT --COMMENTS UQJ Operator records NB and WL flows. STANDARD Based on initial cues records flow as 0 scfm or N/A. --SAT UNSAT --COMMENTS WJ Operator records ZJ flow to stack. CRITICAL STEP STANDARD Based on initial cue and procedure notes records 60 scfm. --SAT UNSAT --COMMENTS JPM 3RADMIN Page 6 of 8 Operator records WG flow and VQ flow. STANDARD Based on initial cues records flow as 0 scfm or N/A SAT UNSAT COMMENTS Operator records TL flow CRITICAL STEP STANDARD Based on initial cue and procedure notes records 1260 scfm. --SAT UNSAT --COMMENTS Operator records NB and WL flows. STANDARD Based on initial cues records flow as 0 scfm or N/A. --SAT UNSAT --COMMENTS -.:!.!J Operator records ZJ flow to stack. CRITICAL STEP STANDARD Based on initial cue and procedure notes records 60 scfm. --SAT UNSAT --COMMENTS JPM 3RADMIN Page 6 of 8 Calculate total vent flow. CRITICAL STEP STANDARD Calculates total vent flow to stack as 117450 scfm. --SAT (56000)+(33130)+(27000)+(1260)+(60)  
 
= 117450 --UNSAT Due to reading instruments, 116450 -118450 scfm is considered acceptable.
LU Operator locates and records VF 1A flow to stack.                             CRITICAL STEP STANDARD
COMMENTS WlJ Complete PT and submit to WCCSRO. CRITICAL STEP STANDARD Records that acceptance criteria is met and signs off remaining procedure steps. --SAT UNSAT --EXAMINER NOTE Candidate may create a Discrepancy Sheet based on gauge VFP5310 having an OOS sticker on it. Although not required, it is not incorrect to submit one. COMMENTS TIME STOP: __ _ JPM 3RADMIN Page 7 of 8 Calculate total vent flow. CRITICAL STEP STANDARD Calculates total vent flow to stack as 117450 scfm. --SAT (56000)+(33130)+(27000)+(1260)+(60)
_ _ SAT Locates 1VFP531 0, notes VF reading is OOS and uses 33130 scfm from enclosure 13.2.
= 117450 --UNSAT Due to reading instruments, 116450 -118450 scfm is considered acceptable.
_ _ UNSAT EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
COMMENTS WlJ Complete PT and submit to WCCSRO. CRITICAL STEP STANDARD Records that acceptance criteria is met and signs off remaining procedure steps. --SAT UNSAT --EXAMINER NOTE Candidate may create a Discrepancy Sheet based on gauge VFP5310 having an OOS sticker on it. Although not required, it is not incorrect to submit one. COMMENTS TIME STOP: __ _ JPM 3RADMIN Page 7 of 8 CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK) INITIAL CONDITIONS:
COMMENTS
~
Operator locates and records VF 1B flow to stack.
STANDARD SAT Locates 1VFP5340, notes VF 1B is shutdown and records Oscfm.
_ _ UNSAT EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
COMMENTS LLJ Records 1ABUX-AFMD-1 flow.                                                   CRITICAL STEP STANDARD
_ _ SAT Records 27000 scfm based on initial cue.
_ _ UNSAT COMMENTS
~
Operator records VP flows.
STANDARD
_ _ SAT Based on initial cues VP is secured. Flows recorded as 0 scfm or N/A.
_ _ UNSAT COMMENTS JPM 3RADMIN                                                                 Page 5 of 8
 
~
LU Operator records WG flow and VQ flow.
STANDARD SAT Based on initial cues records flow as 0 scfm or N/A UNSAT COMMENTS
~
~
Operator records TL flow                                       CRITICAL STEP STANDARD Based on initial cue and procedure notes records 1260 scfm.   - - SAT
                                                                  - - UNSAT COMMENTS
~
UQJ Operator records NB and WL flows.
STANDARD Based on initial cues records flow as 0 scfm or N/A.         - - SAT
                                                                  - - UNSAT COMMENTS WJ
-.:!.!J Operator records ZJ flow to stack.                             CRITICAL STEP STANDARD Based on initial cue and procedure notes records 60 scfm.     - - SAT
                                                                  - - UNSAT COMMENTS JPM 3RADMIN                                                   Page 6 of 8
 
~
Calculate total vent flow.                                                         CRITICAL STEP STANDARD Calculates total vent flow to stack as 117450 scfm.                               - - SAT (56000)+(33130)+(27000)+(1260)+(60)     = 117450                                 - - UNSAT Due to reading instruments, 116450 -118450 scfm is considered acceptable.
COMMENTS WlJ Complete PT and submit to WCCSRO.                                                   CRITICAL STEP STANDARD Records that acceptance criteria is met and signs off remaining procedure steps.   - - SAT
                                                                                    - - UNSAT EXAMINER NOTE Candidate may create a Discrepancy Sheet based on gauge VFP5310 having an OOS sticker on it. Although not required, it is not incorrect to submit one.
COMMENTS TIME STOP: _ __
JPM 3RADMIN                                                                       Page 7 of 8
 
CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
* Both Units are operating at 100% power.
* Both Units are operating at 100% power.
* No VQ release is in progress.
* No VQ release is in progress.
Line 262: Line 317:
* The Waste Evaporator and Recycle Evaporator are secured.
* The Waste Evaporator and Recycle Evaporator are secured.
* The Unit Vent Stack Flow Rate Meter is inoperable.
* The Unit Vent Stack Flow Rate Meter is inoperable.
* Auxiliary Building NLO has called the control room to report 1 ABUXF Discharge Air Flow (1ABUX-AFMD-1) is reading 27000 scfm. INITIATING CUE: Calculate Unit Vent flow per PT/1/A/44501017 (Unit Vent Flow Manual Calculation)
* Auxiliary Building NLO has called the control room to report 1ABUXF Discharge Air Flow (1ABUX-AFMD-1) is reading 27000 scfm.
Enclosure 13.1. CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK) INITIAL CONDITIONS:
INITIATING CUE:
* Both Units are operating at 100% power.
Calculate Unit Vent flow per PT/1/A/44501017 (Unit Vent Flow Manual Calculation) Enclosure 13.1.
* No VQ release is in progress.
 
* No GWRs are in progress.
* The Waste Evaporator and Recycle Evaporator are secured.
* The Unit Vent Stack Flow Rate Meter is inoperable.
* Auxiliary Building NLO has called the control room to report 1 ABUXF Discharge Air Flow (1ABUX-AFMD-1) is reading 27000 scfm. INITIATING CUE: Calculate Unit Vent flow per PT/1/A/44501017 (Unit Vent Flow Manual Calculation)
Enclosure 13.1.
CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 3S ADMIN Determine SLC requirements and complete a Unit Vent Flow Manual Calculation per PT/1/A14450/017.
CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 3S ADMIN Determine SLC requirements and complete a Unit Vent Flow Manual Calculation per PT/1/A14450/017.
CANDIDATE EXAMINER JPM 3S ADMIN Page 1 of 9 CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 3S ADMIN Determine SLC requirements and complete a Unit Vent Flow Manual Calculation per PT/1/A14450/017.
CANDIDATE EXAMINER JPM 3S ADMIN                             Page 1 of 9
CANDIDATE EXAMINER JPM 3S ADMIN Page 1 of 9 CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task Determine SLC actions and calculate Unit Vent flow manually per PT/1/A/44501017 (Unit Vent Flow Manual Calculation).
 
Alternate Path Evaluation Location DYES I:8:l Simulator DNO [gI N/A Din-Plant D Classroom Time Critical DYES [gI NO Safety Function __ [gI N/A Evaluation Method I:8:l Perform DSimulate Validation 14 minutes Time JPM Type o Bank [gI New o Modified KIA 2.2.12 Knowledge of surveillance procedures. (CFR: 41.101 45.13) (3.013.4)
CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task       Determine SLC actions and calculate Unit Vent flow manually per PT/1/A/44501017 (Unit Vent Flow Manual Calculation).
Standard Determine SLC action D applies. Perform the Unit Vent Flow PT within 4 hours and restore OOS meter to operable within 30 days. Unit Vent flow is calculated to be 117450 scfm +1-1000 scfm. References PT/1/A/44501017 (Unit Vent Flow Manual Calculation)
Alternate DYES               DNO           [gI N/A           Time Critical   DYES [gI NO Path Evaluation                                                      Safety Function __         [gI N/A Location I:8:l Simulator     Din-Plant     D Classroom Evaluation                                                       Validation      14 minutes Method I:8:l Perform       DSimulate Time JPM Type   o Bank             [gI New       o Modified KIA         2.2.12 Knowledge of surveillance procedures. (CFR: 41.101 45.13) (3.013.4)
Rev 012 SLC 16.11-7 (Radioactive Gaseous Effluent Monitoring Instrumentation)
Standard   Determine SLC action D applies. Perform the Unit Vent Flow PT within 4 hours and restore OOS meter to operable within 30 days. Unit Vent flow is calculated to be 117450 scfm +1- 1000 scfm.
PT/1/A/46001002A (Mode 1 Periodic Surveillance Items) Rev 208 Candidate Start Time End Time Duration ------Performance Rating D Satisfactory D Unsatisfactory Examiner (Printed Name) (Signature)
References PT/1/A/44501017 (Unit Vent Flow Manual Calculation) Rev 012 SLC 16.11-7 (Radioactive Gaseous Effluent Monitoring Instrumentation)
Comments JPM 3SADMIN Page 2 of 9 (Date) CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task Determine SLC actions and calculate Unit Vent flow manually per PT/1/A/44501017 (Unit Vent Flow Manual Calculation).
PT/1/A/46001002A (Mode 1 Periodic Surveillance Items) Rev 208 Candidate Start Time                       End Time   ------
Alternate Path Evaluation Location DYES I:8:l Simulator DNO [gI N/A Din-Plant D Classroom Time Critical DYES [gI NO Safety Function __ [gI N/A Evaluation Method I:8:l Perform DSimulate Validation 14 minutes Time JPM Type o Bank [gI New o Modified KIA 2.2.12 Knowledge of surveillance procedures. (CFR: 41.101 45.13) (3.013.4)
Duration Performance Rating     D Satisfactory         D Unsatisfactory Examiner (Printed Name)                     (Signature)                      (Date)
Standard Determine SLC action D applies. Perform the Unit Vent Flow PT within 4 hours and restore OOS meter to operable within 30 days. Unit Vent flow is calculated to be 117450 scfm +1-1000 scfm. References PT/1/A/44501017 (Unit Vent Flow Manual Calculation)
Comments JPM 3SADMIN                                                                     Page 2 of 9
Rev 012 SLC 16.11-7 (Radioactive Gaseous Effluent Monitoring Instrumentation)
 
PT/1/A/46001002A (Mode 1 Periodic Surveillance Items) Rev 208 Candidate Start Time End Time Duration ------Performance Rating D Satisfactory D Unsatisfactory Examiner (Printed Name) (Signature)
SIMULATOR SETUP Use SNAP -   --,--_
Comments JPM 3SADMIN Page 2 of 9 (Date)
Fail VFP 5310 to 0 Place OOS sticker on VFP 5310 (1A VF Flow)
SIMULATOR SETUP Use SNAP --Fail VFP 5310 to 0 Place OOS sticker on VFP 5310 (1A VF Flow) SET VA FLOW TO 56000 READ TO OPERATOR DIRECTION TO TRAINEE: I will explain the initial conditions, and state the task to be performed.
SET VA FLOW TO 56000 READ TO OPERATOR DIRECTION TO TRAINEE:
All control room steps shall be performed for this JPM, including any required communications.
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:
INITIAL CONDITIONS:
* Both Units are operating at 100% power.
* Both Units are operating at 100% power.
* No va release is in progress.
* No va release is in progress.
Line 292: Line 342:
* The Waste Evaporator and Recycle Evaporator are secured.
* The Waste Evaporator and Recycle Evaporator are secured.
* All systems are in normal alignment.
* All systems are in normal alignment.
INITIATING CUE: The RO performing the Unit 1 Mode 1 Periodic Surveillance notified you that flow on OAC point C1 A 1104 was 94000 scfm during the Unit Vent Stack Flow Rate Meter Channel Check. Determine what actions (if any) are required to comply with SLCs and the method used to verify any required actions. JPM 3S ADMIN Page 3 of 9 SIMULATOR SETUP Use SNAP --,--_ Fail VFP 5310 to 0 Place OOS sticker on VFP 5310 (1A VF Flow) SET VA FLOW TO 56000 READ TO OPERATOR DIRECTION TO TRAINEE: I will explain the initial conditions, and state the task to be performed.
INITIATING CUE:
All control room steps shall be performed for this JPM, including any required communications.
The RO performing the Unit 1 Mode 1 Periodic Surveillance notified you that flow on OAC point C1 A 1104 was 94000 scfm during the Unit Vent Stack Flow Rate Meter Channel Check. Determine what actions (if any) are required to comply with SLCs and the method used to verify any required actions.
I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:
JPM 3S ADMIN                                                                             Page 3 of 9
* Both Units are operating at 100% power.
 
* No va release is in progress.
START TIME: _ __
* No GWRs are in progress.
W-J Determines if any applicable SLCs exist.                                           CRITICAL STEP STANDARD
* The Waste Evaporator and Recycle Evaporator are secured.
_ _ SAT Operator determines directly or through reference to Daily Surveillance PT that SLC 16.11-7 action D applies. This requires PT/1 IA/44501017 (Unit Vent Flow
* All systems are in normal alignment.
_ _ UNSAT Manual Calculation) be performed every 4 hours and the instrument returned to operable within 30 days.
INITIATING CUE: The RO performing the Unit 1 Mode 1 Periodic Surveillance notified you that flow on OAC point C1 A 1104 was 94000 scfm during the Unit Vent Stack Flow Rate Meter Channel Check. Determine what actions (if any) are required to comply with SLCs and the method used to verify any required actions. JPM 3S ADMIN Page 3 of 9 START TIME: __ _ W-J Determines if any applicable SLCs exist. STANDARD Operator determines directly or through reference to Daily Surveillance PT that SLC 16.11-7 action D applies. This requires PT/1 IA/44501017 (Unit Vent Flow Manual Calculation) be performed every 4 hours and the instrument returned to operable within 30 days. Student may also state that Action K applies (30 day report). EXAMINER CUE OSM requests that you complete an Enclosure 13.1 of PT/1/A/44501017.
Student may also state that Action K applies (30 day report).
EXAMINER CUE OSM requests that you complete an Enclosure 13.1 of PT/1/A/44501017.
EXAMINER NOTE When candidate locates a copy of PT/1/A/44501017, provide him with the partially completed copy provided.
EXAMINER NOTE When candidate locates a copy of PT/1/A/44501017, provide him with the partially completed copy provided.
COMMENTS LU Operator locates and records VA System flow. STANDARD Operator locates 1 VAP5280 on 1 MC-3 and records 56,000 scfm. EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
COMMENTS LU Operator locates and records VA System flow.                                       CRITICAL STEP STANDARD
_ _ SAT Operator locates 1VAP5280 on 1MC-3 and records 56,000 scfm.
_ _ UNSAT EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
EXAMINER NOTE: Range of 55000 to 57000 scfm is acceptable.
EXAMINER NOTE: Range of 55000 to 57000 scfm is acceptable.
COMMENTS Operator locates and records VE 1A flow to stack. STANDARD Locates 1VEP5180, notes VE 1A is shutdown and records 0 scfm. EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
COMMENTS
COMMENTS JPM 3S ADMIN CRITICAL STEP __ SAT __ UNSAT CRITICAL STEP __ SAT __ UNSAT __ SAT __ UNSAT Page 4 of 9 START TIME: __ _ W-J Determines if any applicable SLCs exist. STANDARD Operator determines directly or through reference to Daily Surveillance PT that SLC 16.11-7 action D applies. This requires PT/1 IA/44501017 (Unit Vent Flow Manual Calculation) be performed every 4 hours and the instrument returned to operable within 30 days. Student may also state that Action K applies (30 day report). EXAMINER CUE OSM requests that you complete an Enclosure 13.1 of PT/1/A/44501017.
~
EXAMINER NOTE When candidate locates a copy of PT/1/A/44501017, provide him with the partially completed copy provided.
Operator locates and records VE 1A flow to stack.
COMMENTS LU Operator locates and records VA System flow. STANDARD Operator locates 1 VAP5280 on 1 MC-3 and records 56,000 scfm. EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
STANDARD
EXAMINER NOTE: Range of 55000 to 57000 scfm is acceptable.
_ _ SAT Locates 1VEP5180, notes VE 1A is shutdown and records 0 scfm.
COMMENTS Operator locates and records VE 1A flow to stack. STANDARD Locates 1VEP5180, notes VE 1A is shutdown and records 0 scfm. EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
_ _ UNSAT EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
COMMENTS JPM 3S ADMIN CRITICAL STEP __ SAT __ UNSAT CRITICAL STEP __ SAT __ UNSAT __ SAT __ UNSAT Page 4 of 9 Operator locates and records VE 1 B flow to stack. STANDARD Locates 1 VEP5200, notes VE 1 B is shutdown and records 0 scfm. EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
COMMENTS JPM 3S ADMIN                                                                     Page 4 of 9
COMMENTS Operator locates and records VF 1 A flow to stack. STANDARD Locates 1VFP5310; notes VF reading is OOS and uses 33130 scfm from enclosure 13.2. EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
 
COMMENTS Operator locates and records VF 1 B flow to stack. STANDARD Locates 1 VFP5340, notes VF 1 B is shutdown and records 0 scfm. EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
~
COMMENTS JPM 3S ADMIN __ SAT __ UNSAT CRITICAL STEP __ SAT __ UNSAT __ SAT __ UNSAT Page 5 of 9 Operator locates and records VE 1 B flow to stack. STANDARD Locates 1 VEP5200, notes VE 1 B is shutdown and records 0 scfm. EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
Operator locates and records VE 1B flow to stack.
COMMENTS Operator locates and records VF 1 A flow to stack. STANDARD Locates 1VFP5310; notes VF reading is OOS and uses 33130 scfm from enclosure 13.2. EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
STANDARD
COMMENTS Operator locates and records VF 1 B flow to stack. STANDARD Locates 1 VFP5340, notes VF 1 B is shutdown and records 0 scfm. EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
_ _ SAT Locates 1VEP5200, notes VE 1B is shutdown and records 0 scfm.
COMMENTS JPM 3S ADMIN __ SAT __ UNSAT CRITICAL STEP __ SAT __ UNSAT __ SAT __ UNSAT Page 5 of 9 Determines need to get 1ABUX-AFMD-1 flow reading locally. STANDARD NLO dispatched.
_ _ UNSAT EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
EXAMINER CUE: 1ABUX-AFMO-1 reads 27000 scfm. COMMENTS &.J Records 1ABUX-AFMD-1 flow. STANDARD Records 27000 scfm based on examiner cue. COMMENTS Operator records VP flows. STANDARD Based on initial cues VP is secured. Flows recorded as 0 scfm or N/A. COMMENTS Operator records WG flow and VO flow. STANDARD Based on initial cues records flow as 0 scfm or N/A COMMENTS JPM 3S ADMIN CRITICAL STEP SAT __ UNSAT CRITICAL STEP __ SAT __ UNSAT __ SAT __ UNSAT __ SAT __ UNSAT Page 6 of 9 Determines need to get 1ABUX-AFMD-1 flow reading locally. STANDARD NLO dispatched.
COMMENTS
EXAMINER CUE: 1ABUX-AFMO-1 reads 27000 scfm. COMMENTS &.J Records 1ABUX-AFMD-1 flow. STANDARD Records 27000 scfm based on examiner cue. COMMENTS Operator records VP flows. STANDARD Based on initial cues VP is secured. Flows recorded as 0 scfm or N/A. COMMENTS Operator records WG flow and VO flow. STANDARD Based on initial cues records flow as 0 scfm or N/A COMMENTS JPM 3S ADMIN CRITICAL STEP SAT __ UNSAT CRITICAL STEP __ SAT __ UNSAT __ SAT __ UNSAT __ SAT __ UNSAT Page 6 of 9 U1J Operator records TL flow CRITICAL STEP STANDARD Based on initial cue and procedure notes records 1260 scfm. SAT UNSAT COMMENTS Operator records NB and .WL flows. STANDARD Based on initial cues records flow as 0 scfm or N/A. SAT UNSAT COMMENTS Operator records ZJ flow to stack. CRITICAL STEP STANDARD Based on initial cue and procedure notes records 60 scfm. SAT UNSAT COMMENTS JPM 3S ADMIN Page 7 of 9 U1J Operator records TL flow CRITICAL STEP STANDARD Based on initial cue and procedure notes records 1260 scfm. SAT UNSAT COMMENTS Operator records NB and .WL flows. STANDARD Based on initial cues records flow as 0 scfm or N/A. SAT UNSAT COMMENTS Operator records ZJ flow to stack. CRITICAL STEP STANDARD Based on initial cue and procedure notes records 60 scfm. SAT UNSAT COMMENTS JPM 3S ADMIN Page 7 of 9 Calculate total vent flow. STANDARD Calculates total vent flow to stack as 117450 scfm. (56000)+(33130)+(27000)+(1260)+(60)  
~
= 117450 EXAMINER NOTE Due to reading instruments, 116450 -118450 scfm is considered acceptable.
Operator locates and records VF 1A flow to stack.                             CRITICAL STEP STANDARD
COMMENTS Lill Complete PT and submit to WCCSRO. STANDARD Records that acceptance criteria is met and signs off remaining procedure steps. COMMENTS TIME STOP: __ _ JPM 3S ADMIN CRITICAL STEP __ SAT UNSAT CRITICAL STEP __ SAT __ UNSAT Page 8 of 9 Calculate total vent flow. STANDARD Calculates total vent flow to stack as 117450 scfm. (56000)+(33130)+(27000)+(1260)+(60)
_ _ SAT Locates 1VFP5310; notes VF reading is OOS and uses 33130 scfm from enclosure 13.2.
= 117450 EXAMINER NOTE Due to reading instruments, 116450
_ _ UNSAT EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
-118450 scfm is considered acceptable.
COMMENTS
COMMENTS Lill Complete PT and submit to WCCSRO. STANDARD Records that acceptance criteria is met and signs off remaining procedure steps. COMMENTS TIME STOP: __ _ JPM 3S ADMIN CRITICAL STEP __ SAT UNSAT CRITICAL STEP __ SAT __ UNSAT Page 8 of 9 CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK) INITIAL CONDITIONS:
~
Operator locates and records VF 1B flow to stack.
STANDARD
_ _ SAT Locates 1VFP5340, notes VF 1B is shutdown and records 0 scfm.
_ _ UNSAT EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.
COMMENTS JPM 3S ADMIN                                                                 Page 5 of 9
 
~
Determines need to get 1ABUX-AFMD-1 flow reading locally.               CRITICAL STEP STANDARD SAT NLO dispatched.
_ _ UNSAT EXAMINER CUE: 1ABUX-AFMO-1 reads 27000 scfm.
COMMENTS
&.J Records 1ABUX-AFMD-1 flow.                                               CRITICAL STEP STANDARD
_ _ SAT Records 27000 scfm based on examiner cue.
_ _ UNSAT COMMENTS
~
Operator records VP flows.
STANDARD
_ _ SAT Based on initial cues VP is secured. Flows recorded as 0 scfm or N/A.
_ _ UNSAT COMMENTS
~
Operator records WG flow and VO flow.
STANDARD
_ _ SAT Based on initial cues records flow as 0 scfm or N/A
_ _ UNSAT COMMENTS JPM 3S ADMIN                                                           Page 6 of 9
 
U1J Operator records TL flow                                       CRITICAL STEP STANDARD SAT Based on initial cue and procedure notes records 1260 scfm.
UNSAT COMMENTS
~
Operator records NB and .WL flows.
STANDARD SAT Based on initial cues records flow as 0 scfm or N/A.
UNSAT COMMENTS
~
Operator records ZJ flow to stack.                             CRITICAL STEP STANDARD SAT Based on initial cue and procedure notes records 60 scfm.
UNSAT COMMENTS JPM 3S ADMIN                                                 Page 7 of 9
 
~
Calculate total vent flow.                                                         CRITICAL STEP STANDARD
_ _ SAT Calculates total vent flow to stack as 117450 scfm.
UNSAT (56000)+(33130)+(27000)+(1260)+(60)     =117450 EXAMINER NOTE Due to reading instruments, 116450 -118450 scfm is considered acceptable.
COMMENTS Lill Complete PT and submit to WCCSRO.                                                   CRITICAL STEP STANDARD
_ _ SAT Records that acceptance criteria is met and signs off remaining procedure steps.
_ _ UNSAT COMMENTS TIME STOP: _ __
JPM 3S ADMIN                                                                       Page 8 of 9
 
CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
* Both Units are operating at 100% power.
* Both Units are operating at 100% power.
* No va release is in progress.
* No va release is in progress.
Line 329: Line 427:
* The Waste Evaporator and Recycle Evaporator are secured.
* The Waste Evaporator and Recycle Evaporator are secured.
* All systems are in normal alignment.
* All systems are in normal alignment.
INITIATING CUE: The RO performing the Unit 1 Mode 1 Periodic Surveillance notified you that flow on OAC point C1 A 1104 was 94000 scfm during the Unit Vent Stack Flow Rate Meter Channel Check. Determine what actions (if any) are required to comply with SLCs and the method used to verify any required actions. CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK) INITIAL CONDITIONS:
INITIATING CUE:
* Both Units are operating at 100% power.
The RO performing the Unit 1 Mode 1 Periodic Surveillance notified you that flow on OAC point C1 A 1104 was 94000 scfm during the Unit Vent Stack Flow Rate Meter Channel Check. Determine what actions (if any) are required to comply with SLCs and the method used to verify any required actions.
* No va release is in progress.
 
* No GWRs are in progress.
CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 4R4S ADMIN Calculate the Maximum Permissible Stay Time Within Duke Power ALERT Administrative Dose Limits CANDIDATE EXAMINER JPM 4R4S ADMIN                           Page 1 of 5
* The Waste Evaporator and Recycle Evaporator are secured.
 
* All systems are in normal alignment.
CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task       Calculate the maximum permissible stay time within Duke Power ALERT administrative dose limits.
INITIATING CUE: The RO performing the Unit 1 Mode 1 Periodic Surveillance notified you that flow on OAC point C1 A 1104 was 94000 scfm during the Unit Vent Stack Flow Rate Meter Channel Check. Determine what actions (if any) are required to comply with SLCs and the method used to verify any required actions.
Alternate DYES             DNO           ~  N/A*           Time Critical     DYES ~NO Path Evaluation                                                      Safety Function _ _        ~ N/A Location D Simulator       Din-Plant     IZl Classroom Evaluation                                                      Validation       7 minutes Method IZl Perform      DSimulate Time JPM Type    o Bank            ~New          o Modified KIA         2.3.4 Knowledge of radiation exposure limits and contamination control, including permissible levels in excess of those authorized. (CFR: 43.4 1 45.10) 2.5/3.1 Standard   Stay time is correctly calculated and the Duke Power ALERT administrative dose limit is not exceeded (reference NSD 507).
CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 4R4S ADMIN Calculate the Maximum Permissible Stay Time Within Duke Power ALERT Administrative Dose Limits CANDIDATE EXAMINER JPM 4R4S ADMIN Page 1 of 5 CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 4R4S ADMIN Calculate the Maximum Permissible Stay Time Within Duke Power ALERT Administrative Dose Limits CANDIDATE EXAMINER JPM 4R4S ADMIN Page 1 of 5 CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task Calculate the maximum permissible stay time within Duke Power ALERT administrative dose limits. Alternate Path Evaluation Location Evaluation Method JPM Type DYES D Simulator IZl Perform o Bank DNO Din-Plant DSimulate N/A* Time Critical DYES IZl Classroom Safety Function __ Validation 7 minutes Time o Modified KIA 2.3.4 Knowledge of radiation exposure limits and contamination control, including permissible levels in excess of those authorized. (CFR: 43.4 1 45.10) 2.5/3.1 N/A Standard Stay time is correctly calculated and the Duke Power ALERT administrative dose limit is not exceeded (reference NSD 507). References Duke Power Company, Radiation Worker Training Student Guide NSD 507 rev 13 Candidate Start Time End Time Duration ------Performance Rating D Satisfactory D Unsatisfactory Examiner (Printed Name) (Signature)
References Duke Power Company, Radiation Worker Training Student Guide NSD 507 rev 13 Candidate Start Time                   End Time     ------
Comments (Date) JPM 4R4S ADMIN Page 2 of 5 CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task Calculate the maximum permissible stay time within Duke Power ALERT administrative dose limits. Alternate Path Evaluation Location Evaluation Method JPM Type DYES D Simulator IZl Perform o Bank DNO Din-Plant DSimulate N/A* Time Critical DYES IZl Classroom Safety Function __ Validation 7 minutes Time o Modified KIA 2.3.4 Knowledge of radiation exposure limits and contamination control, including permissible levels in excess of those authorized. (CFR: 43.4 1 45.10) 2.5/3.1 N/A Standard Stay time is correctly calculated and the Duke Power ALERT administrative dose limit is not exceeded (reference NSD 507). References Duke Power Company, Radiation Worker Training Student Guide NSD 507 rev 13 Candidate Start Time End Time Duration ------Performance Rating D Satisfactory D Unsatisfactory Examiner (Printed Name) (Signature)
Duration Performance Rating   D Satisfactory           D   Unsatisfactory Examiner (Printed Name)                       (Signature)                   (Date)
Comments (Date) JPM 4R4S ADMIN Page 2 of 5 READ TO OPERATOR DIRECTION TO TRAINEE: I will explain the initial conditions, and state the task to be performed.
Comments JPM 4R4S ADMIN                                                                 Page 2 of 5
All control room steps shall be performed for this JPM, including any required communications.
 
I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:
READ TO OPERATOR DIRECTION TO TRAINEE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
An individual has been assigned to perform work in the RCA. The individual's current annual dose is 1374 mR. The area where the work is to be performed has the following radiological characteristics:
An individual has been assigned to perform work in the RCA. The individual's current annual dose is 1374 mR. The area where the work is to be performed has the following radiological characteristics:
* General area dose rate -55 mRlhr
* General area dose rate - 55 mRlhr
* Airborne contamination -8 DAC This individual is the only person onsite who is currently qualified to perform the work, however he is NOT respirator qualified.
* Airborne contamination - 8 DAC This individual is the only person onsite who is currently qualified to perform the work, however he is NOT respirator qualified. Due to the critical nature of the work, RP will perform additional monitoring to allow the work to proceed without requiring a respirator.
Due to the critical nature of the work, RP will perform additional monitoring to allow the work to proceed without requiring a respirator.
INITIATING CUE:
INITIATING CUE: Calculate the maximum permissible time the individual can work in this area without exceeding the Duke Power ALERT administrative dose limit. Maximum permissible stay time is: ______ _ JPM 4R4S ADMIN Page 3 of 5 READ TO OPERATOR DIRECTION TO TRAINEE: I will explain the initial conditions, and state the task to be performed.
Calculate the maximum permissible time the individual can work in this area without exceeding the Duke Power ALERT administrative dose limit.
All control room steps shall be performed for this JPM, including any required communications.
Maximum permissible stay time is: _ _ _ _ _ __
I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:
JPM 4R4S ADMIN                                                                           Page 3 of 5
 
START TIME: _ __
-.LJ Calculates overall dose rate for comparison to limit and current dose. CRITICAL STEP STANDARD
_ _ SAT 8 DAC-hr x 2.5mRlDAC-hr + 55 mRlhr      =75 mRlhr total
_ _ UNSAT COMMENTS
~
Determines available dose to reach the DPC ALERT dose limit.               CRITICAL STEP STANDARD
_ _ SAT 1600 (alert limit) -1374 (current dose) = 226 mR
_ _ UNSAT COMMENTS
~
Determines the maximum permissible stay time within the DPC ALERT dose    CRITICAL STEP limit.
STANDARD
_ _ SAT 226 mRlhr / 75mRlhr    =3.01 hours    (3 hours is acceptable)
_ _ UNSAT COMMENTS TIME STOP: _ __
JPM 4R4S ADMIN                                                          Page 4 of 5
 
CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
An individual has been assigned to perform work in the RCA. The individual's current annual dose is 1374 mR. The area where the work is to be performed has the following radiological characteristics:
An individual has been assigned to perform work in the RCA. The individual's current annual dose is 1374 mR. The area where the work is to be performed has the following radiological characteristics:
* General area dose rate -55 mRlhr
* General area dose rate - 55 mRlhr
* Airborne contamination -8 DAC This individual is the only person onsite who is currently qualified to perform the work, however he is NOT respirator qualified.
* Airborne contamination - 8 DAC This individual is the only person onsite who is currently qualified to perform the work, however he is NOT respirator qualified. Due to the critical nature of the work, RP will perform additional monitoring to allow the work to proceed without requiring a respirator.
Due to the critical nature of the work, RP will perform additional monitoring to allow the work to proceed without requiring a respirator.
INITIATING CUE:
INITIATING CUE: Calculate the maximum permissible time the individual can work in this area without exceeding the Duke Power ALERT administrative dose limit. Maximum permissible stay time is: ______ _ JPM 4R4S ADMIN Page 3 of 5 START TIME: __ _ -.LJ Calculates overall dose rate for comparison to limit and current dose. STANDARD 8 DAC-hr x 2.5mRlDAC-hr
Calculate the maximum permissible time the individual can work in this area without exceeding the Duke Power ALERT administrative dose limit.
+ 55 mRlhr = 75 mRlhr total COMMENTS Determines available dose to reach the DPC ALERT dose limit. STANDARD 1600 (alert limit) -1374 (current dose) = 226 mR COMMENTS Determines the maximum permissible stay time within the DPC ALERT dose limit. STANDARD 226 mRlhr / 75mRlhr = 3.01 hours (3 hours is acceptable)
Maximum permissible stay time is: _ _ _ _ _ __
COMMENTS TIME STOP: __ _ JPM 4R4S ADMIN CRITICAL STEP __ SAT __ UNSAT CRITICAL STEP __ SAT __ UNSAT CRITICAL STEP __ SAT __ UNSAT Page 4 of 5 START TIME: __ _ -.LJ Calculates overall dose rate for comparison to limit and current dose. STANDARD 8 DAC-hr x 2.5mRlDAC-hr
 
+ 55 mRlhr = 75 mRlhr total COMMENTS Determines available dose to reach the DPC ALERT dose limit. STANDARD 1600 (alert limit) -1374 (current dose) = 226 mR COMMENTS Determines the maximum permissible stay time within the DPC ALERT dose limit. STANDARD 226 mRlhr / 75mRlhr = 3.01 hours (3 hours is acceptable)
CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 55 ADMIN Upgrade an Emergency Classification and Complete an Emergency Notification Form CANDIDATE EXAMINER JPM 5S ADMIN                             Page 1 of 7
COMMENTS TIME STOP: __ _ JPM 4R4S ADMIN CRITICAL STEP __ SAT __ UNSAT CRITICAL STEP __ SAT __ UNSAT CRITICAL STEP __ SAT __ UNSAT Page 4 of 5 CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK) INITIAL CONDITIONS:
 
An individual has been assigned to perform work in the RCA. The individual's current annual dose is 1374 mR. The area where the work is to be performed has the following radiological characteristics:
CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task       Upgrade to a higher emergency classification and complete an Emergency Notification Form.
* General area dose rate -55 mRlhr
Alternate DYES             DNO           r:g] N/A             Time Critical     r:g] YES DNO Path Evaluation                                                      Safety Function __           r:g] N/A D Simulator       Din-Plant   [2J Classroom Location Evaluation                                                       Validation        11 minutes
* Airborne contamination -8 DAC This individual is the only person onsite who is currently qualified to perform the work, however he is NOT respirator qualified.
[2J Perform       DSimulate Method                                                          Time JPM Type   r:g] Bank         DNew         D Modified           2003 NRC Exam KIA         2.4.41 Knowledge of the emergency action level thresholds and classifications (CFR: 43.5/45.11) 2.3/4.1 Standard   Candidate classifies the event as an Alert within 15 minutes of starting the JPM, and correctly completes the follow-up notification form within 15 minutes of determining the classification.
Due to the critical nature of the work, RP will perform additional monitoring to allow the work to proceed without requiring a respirator.
References RP/O/A/5000/001 (Classification of Emergency) rev 019 RP/O/A/50001003 (Alert) rev 042 RP/O/A/5000/006A (Notification of States and Counties from the Control Room) rev 023 Candidate Start Time                   End Time
INITIATING CUE: Calculate the maximum permissible time the individual can work in this area without exceeding the Duke Power ALERT administrative dose limit. Maximum permissible stay time is: ______ _ CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK) INITIAL CONDITIONS:
                                            - - - - - - Duration Performance Rating     D Satisfactory           D Unsatisfactory Examiner (Printed Name)                       (Signature)                     (Date)
An individual has been assigned to perform work in the RCA. The individual's current annual dose is 1374 mR. The area where the work is to be performed has the following radiological characteristics:
Comments JPM 5S ADMIN                                                                   Page 2 of 7
* General area dose rate -55 mRlhr
 
* Airborne contamination -8 DAC This individual is the only person onsite who is currently qualified to perform the work, however he is NOT respirator qualified.
READ TO OPERATOR DIRECTION TO TRAINEE:
Due to the critical nature of the work, RP will perform additional monitoring to allow the work to proceed without requiring a respirator.
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIATING CUE: Calculate the maximum permissible time the individual can work in this area without exceeding the Duke Power ALERT administrative dose limit. Maximum permissible stay time is: ______ _
INITIAL CONDITIONS:
CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 55 ADMIN Upgrade an Emergency Classification and Complete an Emergency Notification Form CANDIDATE EXAMINER JPM 5S ADMIN Page 1 of 7 CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 55 ADMIN Upgrade an Emergency Classification and Complete an Emergency Notification Form CANDIDATE EXAMINER JPM 5S ADMIN Page 1 of 7 CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task Upgrade to a higher emergency classification and complete an Emergency Notification Form. Alternate Path Evaluation Location DYES DNO D Simulator Din-Plant r:g] N/A Time Critical r:g] YES [2J Classroom Safety Function __ DNO r:g] N/A Evaluation Method [2J Perform DSimulate Validation 11 minutes Time JPM Type r:g] Bank DNew D Modified 2003 NRC Exam KIA 2.4.41 Knowledge of the emergency action level thresholds and classifications (CFR: 43.5/45.11) 2.3/4.1 Standard Candidate classifies the event as an Alert within 15 minutes of starting the JPM, and correctly completes the follow-up notification form within 15 minutes of determining the classification.
References RP/O/A/5000/001 (Classification of Emergency) rev 019 RP/O/A/50001003 (Alert) rev 042 RP/O/A/5000/006A (Notification of States and Counties from the Control Room) rev 023 Candidate Start Time End Time Duration ------Performance Rating D Satisfactory D Unsatisfactory Examiner (Printed Name) (Signature) (Date) Comments JPM 5S ADMIN Page 2 of 7 CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task Upgrade to a higher emergency classification and complete an Emergency Notification Form. Alternate Path Evaluation Location DYES DNO D Simulator Din-Plant r:g] N/A Time Critical r:g] YES [2J Classroom Safety Function __ DNO r:g] N/A Evaluation Method [2J Perform DSimulate Validation 11 minutes Time JPM Type r:g] Bank DNew D Modified 2003 NRC Exam KIA 2.4.41 Knowledge of the emergency action level thresholds and classifications (CFR: 43.5/45.11) 2.3/4.1 Standard Candidate classifies the event as an Alert within 15 minutes of starting the JPM, and correctly completes the follow-up notification form within 15 minutes of determining the classification.
References RP/O/A/5000/001 (Classification of Emergency) rev 019 RP/O/A/50001003 (Alert) rev 042 RP/O/A/5000/006A (Notification of States and Counties from the Control Room) rev 023 Candidate Start Time End Time Duration ------Performance Rating D Satisfactory D Unsatisfactory Examiner (Printed Name) (Signature) (Date) Comments JPM 5S ADMIN Page 2 of 7 READ TO OPERATOR DIRECTION TO TRAINEE: I will explain the initial conditions, and state the task to be performed.
All control room steps shall be performed for this JPM, including any required communications.
I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:
* Unit 1 was shutdown three days ago and is now in Mode 5 with loops filled.
* Unit 1 was shutdown three days ago and is now in Mode 5 with loops filled.
* Reactor Coolant temperature was 143 0 F. * "A" train NO, KC and RN in service.
* Reactor Coolant temperature was 143 0 F.
* 1 B NO pump is red tagged for repairs and unavailable.
*     "A" train NO, KC and RN in service.
* 1B NO pump is red tagged for repairs and unavailable.
* An Unusual Event was declared at 0830 per 4.7.U.1 (Natural and Destructive Phenomena Affecting the Protected Area) when Security reported a tornado touched down on the southwest side of the Protected Area.
* An Unusual Event was declared at 0830 per 4.7.U.1 (Natural and Destructive Phenomena Affecting the Protected Area) when Security reported a tornado touched down on the southwest side of the Protected Area.
* At 0850, a loss of power occurred on Unit 1 ETA and ETB busses.
* At 0850, a loss of power occurred on Unit 1 ETA and ETB busses.
* 1 A DIG failed to start. INITIATING CUE: Current time is 0915. Reactor Coolant temperature is currently at 181 0 F and increasing.
* 1A DIG failed to start.
INITIATING CUE:
Current time is 0915.
0 Reactor Coolant temperature is currently at 181 F and increasing.
Based on the current plant conditions, determine the emergency classification and prepare the next Emergency Notification Form for transmittal.
Based on the current plant conditions, determine the emergency classification and prepare the next Emergency Notification Form for transmittal.
This JPM is Time Critical.
This JPM is Time Critical.
JPM 5S ADMIN Page 3 of 7 READ TO OPERATOR DIRECTION TO TRAINEE: I will explain the initial conditions, and state the task to be performed.
JPM 5S ADMIN                                                                           Page 3 of 7
All control room steps shall be performed for this JPM, including any required communications.
 
I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:
START TIME: _ _ _ (When initiating cue is read to candidate)
* Unit 1 was shutdown three days ago and is now in Mode 5 with loops filled.
~
* Reactor Coolant temperature was 143 0 F. * "A" train NO, KC and RN in service.
Compare actual plant conditions to the Emergency Action Levels listed, then             CRITICAL STEP declare the appropriate Emergency Class as indicated.
* 1 B NO pump is red tagged for repairs and unavailable.
STANDARD
* An Unusual Event was declared at 0830 per 4.7.U.1 (Natural and Destructive Phenomena Affecting the Protected Area) when Security reported a tornado touched down on the southwest side of the Protected Area.
_ _ SAT Candidate uses RP-01 and from the initial conditions, determines the unit is in an
* At 0850, a loss of power occurred on Unit 1 ETA and ETB busses.
_ _ UNSAT Alert based on Enclosure 4.4 page 2 of 3:
* 1 A DIG failed to start. INITIATING CUE: Current time is 0915. Reactor Coolant temperature is currently at 181 0 F and increasing.
4.4.A.2 Inability to Maintain Plant In Cold Shutdown Operating Mode 5:
Based on the current plant conditions, determine the emergency classification and prepare the next Emergency Notification Form for transmittal.
(4.4.A.2-1 Total Loss of ND AND Uncontrolled reactor coolant temperature rise to greater than 180&deg;F.)
This JPM is Time Critical.
EXAMINER NOTE To meet the critical step, the candidate must make the declaration within 15 minutes of the START TIME recorded above. When candidate determines classification, record the time for this critical step. _ _ __
JPM 5S ADMIN Page 3 of 7 START TIME: ___ (When initiating cue is read to candidate) Compare actual plant conditions to the Emergency Action Levels listed, then declare the appropriate Emergency Class as indicated.
EXAMINER NOTE If candidate correctly states 4.4.A.2 as the classification, provide the preprinted sheet for this classification, otherwise, provide a blank ENF.
STANDARD CRITICAL STEP Candidate uses RP-01 and from the initial conditions, determines the unit is in an __ SAT Alert based on Enclosure 4.4 page 2 of 3: 4.4.A.2 Inability to Maintain Plant In Cold Shutdown Operating Mode 5: (4.4.A.2-1 Total Loss of ND AND Uncontrolled reactor coolant temperature rise to greater than 180&deg;F.) EXAMINER NOTE To meet the critical step, the candidate must make the declaration within 15 minutes of the START TIME recorded above. When candidate determines classification, record the time for this critical step. ___ _ EXAMINER NOTE If candidate correctly states 4.4.A.2 as the classification, provide the preprinted sheet for this classification, otherwise, provide a blank ENF. COMMENTS JPM 5S ADMIN __ UNSAT Page 4 of 7 START TIME: ___ (When initiating cue is read to candidate) Compare actual plant conditions to the Emergency Action Levels listed, then declare the appropriate Emergency Class as indicated.
COMMENTS JPM 5S ADMIN                                                                         Page 4 of 7
STANDARD CRITICAL STEP Candidate uses RP-01 and from the initial conditions, determines the unit is in an __ SAT Alert based on Enclosure 4.4 page 2 of 3: 4.4.A.2 Inability to Maintain Plant In Cold Shutdown Operating Mode 5: (4.4.A.2-1 Total Loss of ND AND Uncontrolled reactor coolant temperature rise to greater than 180&deg;F.) EXAMINER NOTE To meet the critical step, the candidate must make the declaration within 15 minutes of the START TIME recorded above. When candidate determines classification, record the time for this critical step. ___ _ EXAMINER NOTE If candidate correctly states 4.4.A.2 as the classification, provide the preprinted sheet for this classification, otherwise, provide a blank ENF. COMMENTS JPM 5S ADMIN __ UNSAT Page 4 of 7 2J Complete an Emergency Notification Form for the classification level determined.
 
CRITICAL STEP* STANDARD Candidate refers to RP/o/A/5000106A "Notification of States and Counties from the Control Room and completes the ENF per the guidelines in Enclosure 4.3 within 15 minutes of the time recorded in Step 1 of the JPM. Line 1: Actual Event checked, Message #2 *Line 2: Initial checked Line 3: Catawba Nuclear Station *Line 4: Alert checked and enters appropriate information from event number 4.4.A.2 Line 5: None checked *Line 6: None checked Line 7: N/A checked Line 8: Stable or Degrading Line 9: Not filled in (no data) *Line 10: Mark Declaration and enters date and time event is declared.
2J Complete an Emergency Notification Form for the classification level determined. CRITICAL STEP*
*Line 11: Unit 1 Line 12: Enters 0% and time reactor shutdown (3 days ago) Lines 13-16: leaves these blank *Line 17: signs as Emergency Coordinator with date and time. EXAMINER CUE If asked, state that "surveys are not yet available".
STANDARD
EXAMINER NOTE To meet the critical step, the candidate must complete an Emergency Notification Form and submit it for transmittal within 15 minutes of the time recorded in Step 1 of the JPM. When the candidate submits the form, record the time for this critical step. ____ _ COMMENTS __ SAT UNSAT JPM 5S ADMIN Page 5 of 7 2J Complete an Emergency Notification Form for the classification level determined.
_ _ SAT Candidate refers to RP/o/A/5000106A "Notification of States and Counties from the Control Room and completes the ENF per the guidelines in Enclosure 4.3 within 15 minutes of the time recorded in Step 1 of the JPM.                             UNSAT Line 1: Actual Event checked, Message #2
CRITICAL STEP* STANDARD Candidate refers to RP/o/A/5000106A "Notification of States and Counties from the Control Room and completes the ENF per the guidelines in Enclosure 4.3 within 15 minutes of the time recorded in Step 1 of the JPM. Line 1: Actual Event checked, Message #2 *Line 2: Initial checked Line 3: Catawba Nuclear Station *Line 4: Alert checked and enters appropriate information from event number 4.4.A.2 Line 5: None checked *Line 6: None checked Line 7: N/A checked Line 8: Stable or Degrading Line 9: Not filled in (no data) *Line 10: Mark Declaration and enters date and time event is declared.  
        *Line 2: Initial checked Line 3: Catawba Nuclear Station
*Line 11: Unit 1 Line 12: Enters 0% and time reactor shutdown (3 days ago) Lines 13-16: leaves these blank *Line 17: signs as Emergency Coordinator with date and time. EXAMINER CUE If asked, state that "surveys are not yet available".
        *Line 4: Alert checked and enters appropriate information from event number 4.4.A.2 Line 5: None       checked
EXAMINER NOTE To meet the critical step, the candidate must complete an Emergency Notification Form and submit it for transmittal within 15 minutes of the time recorded in Step 1 of the JPM. When the candidate submits the form, record the time for this critical step. ____ _ COMMENTS __ SAT UNSAT JPM 5S ADMIN Page 5 of 7 TIME STOP: __ _ JPM 5S ADMIN Page 6 of 7 TIME STOP: __ _ JPM 5S ADMIN Page 6 of 7 CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK) INITIAL CONDITIONS:
        *Line 6: None       checked Line 7: N/A       checked Line 8: Stable or Degrading Line 9: Not filled in (no data)
* Unit 1 was shutdown three days ago and is now in Mode 5 with loops filled.
        *Line 10: Mark Declaration and enters date and time event is declared.
* Reactor Coolant temperature was 143 0 F. * "A" train NO, KC and RN in service.
        *Line 11: Unit 1 Line 12: Enters 0% and time reactor shutdown (3 days ago)
* 1 B NO pump is red tagged for repairs and unavailable.
Lines 13-16: leaves these blank
* An Unusual Event was declared at 0830 per 4.7.U.1 (Natural and Destructive Phenomena Affecting the Protected Area) when Security reported a tornado touched down on the southwest side of the Protected Area.
        *Line 17: signs as Emergency Coordinator with date and time.
* At 0850, a loss of power occurred on Unit 1 ETA and ETB busses.
EXAMINER CUE If asked, state that "surveys are not yet available".
* 1 A DIG failed to start. INITIATING CUE: Current time is 0915. Reactor Coolant temperature is currently at 181 0 F and increasing.
EXAMINER NOTE To meet the critical step, the candidate must complete an Emergency Notification Form and submit it for transmittal within 15 minutes of the time recorded in Step 1 of the JPM. When the candidate submits the form, record the time for this critical step. _ _ _ __
Based on the current plant conditions, determine the emergency classification and prepare the next Emergency Notification Form for transmittal.
COMMENTS JPM 5S ADMIN                                                                   Page 5 of 7
This JPM is Time Critical.
 
CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK) INITIAL CONDITIONS:
TIME STOP: _ __
JPM 5S ADMIN   Page 6 of 7
 
CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
* Unit 1 was shutdown three days ago and is now in Mode 5 with loops filled.
* Unit 1 was shutdown three days ago and is now in Mode 5 with loops filled.
* Reactor Coolant temperature was 143 0 F. * "A" train NO, KC and RN in service.
0
* 1 B NO pump is red tagged for repairs and unavailable.
* Reactor Coolant temperature was 143 F.
*   "A" train NO, KC and RN in service.
* 1B NO pump is red tagged for repairs and unavailable.
* An Unusual Event was declared at 0830 per 4.7.U.1 (Natural and Destructive Phenomena Affecting the Protected Area) when Security reported a tornado touched down on the southwest side of the Protected Area.
* An Unusual Event was declared at 0830 per 4.7.U.1 (Natural and Destructive Phenomena Affecting the Protected Area) when Security reported a tornado touched down on the southwest side of the Protected Area.
* At 0850, a loss of power occurred on Unit 1 ETA and ETB busses.
* At 0850, a loss of power occurred on Unit 1 ETA and ETB busses.
* 1 A DIG failed to start. INITIATING CUE: Current time is 0915. Reactor Coolant temperature is currently at 181 0 F and increasing.
* 1A DIG failed to start.
INITIATING CUE:
Current time is 0915.
Reactor Coolant temperature is currently at 181 0 F and increasing.
Based on the current plant conditions, determine the emergency classification and prepare the next Emergency Notification Form for transmittal.
Based on the current plant conditions, determine the emergency classification and prepare the next Emergency Notification Form for transmittal.
This JPM is Time Critical.}}
This JPM is Time Critical.}}

Latest revision as of 22:07, 21 March 2020

Initial Exam 2008-301 Final Administrative JPMs
ML092940763
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 10/20/2009
From:
NRC/RGN-II
To:
Duke Energy Carolinas
References
50-413/08-301, 50-414/08-301
Download: ML092940763 (48)


Text

CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 1R ADMIN Determine NCP Start Requirements CANDIDATE EXAMINER JPM 1RADMIN Page 1 of 5

CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task Using Data Book Figure 9 (Permissible Successive Attempts to Start Motors) determine the allowed starting time for NCP.

Alternate DYES DNO [g] N/A Time Critical DYES [g] NO Path Evaluation Location o Simulator Din-Plant [8J Classroom Safety Function __ [g] N/A Evaluation Validation 10 minutes

[8J Perform DSimulate Time Method JPM Type D Bank [g] New D Modified KIA 2.1.32 Ability to explain and apply all system limits and precautions (3.4/3.8)

Standard Determines 1B NCP can be started first at 1742.

References OP/1/N61501001 (Filling and Venting the Reactor Coolant System) rev 099 OP/1/N61501002A (Reactor Coolant Pump Operation) rev 058 Unit 1 Data book Figure 9 (Permissible Successive Attempts to Start Motors) rev 001 Candidate Start Time End Time - - - - - - Duration Performance Rating 0 Satisfactory o Unsatisfactory Examiner (Printed Name) (Signature) (Date)

Comments JPM 1RADMIN Page 2 of 5

READ TO OPERATOR DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

NC system venting is in progress per OP/1/A/61501001 (Filling and Venting the Reactor Coolant System) Enclosure 4.3 (Reactor Coolant System Venting). At 1725 the crew reaches a step in .3 which requires the start of either NCP 1A or NCP 1B. The OAC is not available.

INITIATING CUE:

Given the run history for these pumps today:

Pump Start Time Shutdown Time Run Time NCP1A 1456 1456 20 seconds NCP1A 1535 1536 1 minute NCP1A 1650 1659 9 minutes NCP1B 1502 1502 20 seconds NCP1B 1602 1603 1 minute NCP1B 1704 1712 8 minutes State which pump can be started the earliest and at what time it can be started?

JPM 1RADMIN Page 3 of 5

START TIME: _ __

LU

-.U Reviews the NCP start history. CRITICAL STEP STANDARD

_ _ SAT Determines that 1A NCP has been started 3 times in a 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> period (requiring a 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> wait) and 1B NCP 2 times in a 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> period (requiring a 30 min wait).

_ _ UNSAT COMMENTS LLl

--.U Determines how much idle time is required prior to each pumps restart. CRITICAL STEP STANDARD

_ _ SAT 1A must have 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> idle time following shutdown.

1B must have 30 minute idle time following shutdown.

_ _ UNSAT COMMENTS

~

lJ Calculates earliest start time for each pump. CRITICAL STEP STANDARD

_ _ SAT 1A NCP stopped at 1659 + 60 minutes = 1759 1B NCP stopped at 1712 + 30 minutes = 1742 _ _ UNSAT 1B NCP can be started first at 1742.

COMMENTS TIME STOP: _ __

JPM 1RADMIN Page 4 of 5

CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

NC system venting is in progress per OP/1/A/6150/001 (Filling and Venting the Reactor Coolant System) Enclosure 4.3 (Reactor Coolant System Venting). At 1725 the crew reaches a step in .3 which requires the start of either NCP 1A or NCP 1B. The OAC is not available.

INITIATING CUE:

Given the run history for these pumps today:

Pump Start Time Shutdown Time Run Time NCP1A 1456 1456 20 seconds NCP1A 1535 1536 1 minute NCP1A 1650 1659 9 minutes NCP1B 1502 1502 20 seconds NCP1B 1602 1603 1 minute NCP1B 1704 1712 8 minutes State which pump can be started the earliest and at what time it can be started?

CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 1S ADMIN Determine Work Hours Extension Requirements CANDIDATE EXAMINER JPM 18 ADMIN Page 1 of 5

CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task Determine if a work hours extension is required and if so, which limits are exceeded.

Alternate DYES DNa ~ NIA Time Critical DYES ~NO Path Evaluation Safety Function _ _ ~ NIA Location D Simulator Din-Plant IZI Classroom Evaluation Validation 30 minutes Method IZI Perform DSimulate Time JPM Type D Bank DNew ~ Modified CNS 2005 NRC Exam KIA 2.1.5 Ability to use procedures related to shift staffing, such as minimum crew complement, overtime limitations, etc. (2.9*/3.9)

Standard Determines that Jerry and Chad will require a "C" extension and Jerry will also require a '0' extension. (Stating the verbal description of the limit instead of the corresponding letter is acceptable)

References NSD-200, Overtime Control Rev 9 Candidate Start Time End Time ------

Duration Performance Rating D Satisfactory D Unsatisfactory Examiner (Printed Name) (Signature) (Date)

Comments JPM 1S ADMIN Page 2 of 5

READ TO OPERATOR DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Given the following work history:

  • Tom and Chad were on vacation Monday through Wednesday.
  • Jerry worked the previous 3 days in a day-staff position with a total of 32 hours3.703704e-4 days <br />0.00889 hours <br />5.291005e-5 weeks <br />1.2176e-5 months <br /> with no turnover hours.
  • Hursel was off Monday and worked overtime Tuesday and Wednesday with a total of 26 hours3.009259e-4 days <br />0.00722 hours <br />4.298942e-5 weeks <br />9.893e-6 months <br /> including a total of 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> of turnover time.

Operator Arrives Finishes TIO Starts TIO Leaves Thursday Jerry 0615 0630 1845 1900 Tom 0630 0700 1830 1845 Chad 0645 0700 1845 1915 Hursel 0630 0645 1815 1830 Friday Jerry 0645 0715 1800 1815 Tom 0615 0630 1845 1900 Chad 0600 0615 1600 1615 Hursel 0645 0700 1915 1930 Saturday Jerry 0400 0415 1715 1730 Tom 0715 0730 1845 1905 Chad 0515 0530 1915 1930 Hursel 0645 0700 1845 1900 Sunday Jerry 0630 0645 1830 1845 Tom 0630 0645 1830 1845 Chad 0630 0645 1830 1845 Hursel 0630 0645 1830 1845 INITIATING CUE:

It is 0800 Sunday morning, and you are the dayshift shift CRS. The OSM has asked you to determine if based on recent work history and the projected work schedule (indicated in grey), any operator(s) on this shift will require a work hours extension and if so, which limits the operator(s) have exceeded.

Assume:

  • any required work extensions for days prior to today have already been completed by another SRO.
  • The projected work schedule becomes the actual schedule worked.

JPM 1S ADMIN Page 3 of 5

START TIME: _ __

1 Determine if the operators meet any of the following limits: CRITICAL STEP

a. > 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> straight (excluding shift turnover time)
b. > 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> in any 24-hour period (excluding shift turnover time)
c. > 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> (28 hours3.240741e-4 days <br />0.00778 hours <br />4.62963e-5 weeks <br />1.0654e-5 months <br /> for MNS and ONS) in any 48-hour period (excluding shift turnover time)
d. > 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> in any 7-day period (excluding shift turnover time)
e. < 8-hour break between scheduled work periods (including shift turnover time)

STANDARD

_ _ SAT Determines that Jerry and Chad will require a "C" extension and Jerry will also require a 'D' extension.

_ _ UNSAT Operator Arrives Done Starts Leaves TID Limit TfW Limit T/O T/O 24 72 after after next shift Jerry exceeds condition Conly Chad exceeds conditions C and D EXAMINER NOTE: Student may state the actual verbiage of the limit instead of the corresponding letter. This should be considered acceptable.

COMMENTS TIME STOP: _ __

JPM 1S ADMIN Page 4 of 5

CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

Given the following work history:

  • Tom and Chad were on vacation Monday through Wednesday.
  • Jerry worked the previous 3 days in a day-staff position with a total of 32 hours3.703704e-4 days <br />0.00889 hours <br />5.291005e-5 weeks <br />1.2176e-5 months <br /> with no turnover hours.
  • Hursel was off Monday and worked overtime Tuesday and Wednesday with a total of 26 hours3.009259e-4 days <br />0.00722 hours <br />4.298942e-5 weeks <br />9.893e-6 months <br /> including a total of 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> of turnover time.

Operator Arrives Finishes TIO Starts TIO Leaves Thursday Jerry 0615 0630 1845 1900 Tom 0630 0700 1830 1845 Chad 0645 0700 1845 1915 Hursel 0630 0645 1815 1830 Friday Jerry 0645 0715

  • 1800 1815 Tom 0615 0630 1845 1900 Chad 0600 0615 1600 1615 Hursel 0645 0700 1915 1930 Saturday Jerry 0400 0415 1715 1730 Tom 0715 0730 1845 1905 Chad 0515 0530 1915 1930 Hursel 0645 0700 1845 1900 Sunday Jerry 0630 0645 1830 1845 Tom 0630 0645 1830 1845 Chad 0630 0645 ..

1830 1845 Hursel 0630 0645 1830 1845 INITIATING CUE:

It is 0800 Sunday morning, and you are the dayshift shift CRS. The OSM has asked you to determine if based on recent work history and the projected work schedule (indicated in grey), any operator(s) on this shift will require a work hours extension per NSD 200 (Work Hour Guidelines and Limits) and if so, which limits the operator(s) have exceeded.

Assume:

  • any required work extensions for days prior to today have already been completed by another SRO.
  • The projected work schedule becomes the actual schedule worked.

RECORD ANSWERS IN THE TABLE BELOW Name Work hour limit exceeded Limit(s) exceeded (select one) (select any that apply)

Jerry DYES o NO o a o b DC od De Tom DYES o NO o a o b DC od De Chad DYES o NO o a o b DC od De Hursel DYES o NO o a o b DC od De

CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 2R2S ADMIN Perform a Manual Shutdown Margin Calculation (Unit at Power)

CANDIDATE EXAMINER JPM 2R2S ADMIN Page 1 of 9

CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task Perform a manual shutdown margin calculation (Unit at Power) per OP/O/A/61 00/006 (Reactivity Balance Calculation)

Alternate Path DYES DNO r8J N/A Time Critical DYES r8J NO Evaluation D Simulator Din-Plant C8J Classroom Safety Function __ r8J N/A Location Evaluation Validation 25 minutes Method C8J Perform DSimulate Time JPM Type D Bank DNew r8J Modified OP-CN-RT-RB-121 KIA 2.1.25 Ability to interpret reference materials, such as graphs, curves, tables, etc. I (CFR: 41.10/43.5/45.12) 3.9/4.2 Standard Candidate determines that required shutdown margin is 1300 pcm and current shutdown margin is 1128 pcm, therefore, adequate shutdown margin does not exist per the Unit 1 Core Operating Limits Report References OP/O/A/61 00/006 (Reactivity Balance Calculation), Rev. 73 Unit 1 Reactor Operating Data Book (R.O.D.)

VERIFY ROD BOOK VALUES MATCH JPM PRIOR TO ADMINISTRATION Candidate Start Time End Time - - - - - - Duration Performance Rating D Satisfactory D Unsatisfactory Examiner (Printed Name) (Signature) (Date)

Comments JPM 2R2S ADMIN Page 2 of 9

READ TO OPERATOR DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handQut sheet I provided you.

INITIAL CONDITIONS:

You are the Unit 1 OATC. The Reactivity Computer (REACT) is out of-service.

Current plant conditions are as follows:

  • Power level =80%
  • NC Tavg = 579.5 OF
  • Boron Concentration: 959 ppm
  • Core burnup: 200 EFPD
  • Shutdown rod bank position: 226 steps

You have just been informed by the Control Room SRO that the following rods are untrippable:

  • G-13
  • K-2
  • P-4 Perform a Shutdown Margin Calculation per OP/O/A/61 00/006 (Reactivity Balance Calculation) and determine if Core Operating Limits Report requirement for shutdown margin is satisfied.

Calculation verification is waived.

JPM 2R2S ADMIN Page 3 of 9

START TIME: _ __

LU Candidate obtains a copy of OP/o/Al61 001006 (Reactivity Balance Calculation) CRITICAL STEP and from initiating cue and determines that Enclosure 4.3 is applicable.

STANDARD Candidate obtains a copy of OP/OIAl61 001006 (Reactivity Balance Calculation). - - SAT

- - UNSAT EXAMINER NOTE When the candidate locates the appropriate procedure, give himlher a copy of o P101Al61 001006.

COMMENTS 2J LU Limits and Precautions have been reviewed.

STANDARD Examinee reviews Limits and Precautions. - - SAT

- - UNSAT EXAMINER CUE Candidate should be able to determine per initial conditions that Tavg is within 1°F based on power level and Tref program.

COMMENTS JPM 2R2S ADMIN Page 4 of 9

ll-J

~ OP/O/A/6100/o06 Enc14.3 Step 2.1 Determine the following information: CRITICAL STEP STANDARD

_ _ SAT Operator records the following data using the initial conditions.

_ _ UNSAT

  • Unit: 1
  • Date/Time: Current Date/Time
  • Present Power: 80%
  • NC System Boron Concentration 959 ppm
  • Current Burnup: 200 EFPD
  • Present Control Bank Position: 200 SWD, Control Bank 0
  • Present Shutdown bank Position: ALL @ 226
  • Quantity of misaligned rods: ...Q
  • Number of untrippable RCCA(s): ~
  • Untrippable RCCA(s) core location(s): G-13. K-2. P-4 COMMENTS

~ OP/O/A/61001006 Encl 4.3 Step 2.3.1.1 Determine total available rod worth. (Step 2.2 is NIA due to REACTBAL CRITICAL STEP unavailable)

STANDARD

_ _ SAT Determine total available rod worth to be 5084 pcm per section 5.7 of Reactor Operating Data (R.O.D.) Manual.

_ _ UNSAT COMMENTS

~ OP/O/A/61001006 Encl 4.3 Step 2.3.1.2

!f only one RCCA is untrippable, determine reactivity worth ..... CRITICAL STEP STANDARD

_ _ SAT Determines there are multiple untrippable RCCA's and does not perform step 2.3.1.2.

_ _ UNSAT COMMENTS JPM 2R2S ADMIN Page 5 of 9

~ OP/O/A/61001006 Enc14.3 Step 2.3.1.3 IF there are multiple untrippable RCCA's, perform the following: CRITICAL STEP Determine untrippable RCCA of step 2.1.10 with the highest reactivity worth penalty. (Section 5.8 of RO.D. Manual)

STANDARD

_ _ SAT Refers to section 5.8 of the RO.D. Manual. Determines RCCA G-13 rod worth is 232 pem, P-4 rod worth is 28 pem and RCCA K-2 Rod worth is 290 pem.

_ _ UNSAT Chooses K-2 I 290 pem.

COMMENTS

~ OP/O/A/61001006 Enc14.3 Step 2.3.1.3 Determine maximum stuck rod worth during cycle (Section CRITICAL STEP 5.7 of the RO.D. manual).

STANDARD

_ _ SAT Determines maximum stuck rod worth during cycle is 895 pem per section 5.7 of the RO.D. Manual.

_ _ UNSAT COMMENTS

~ OP/O/A/61001006 Enc14.3 Step 2.3.1.3/2.3.1.4 Calculate total untrippable RCCA reactivity worth penalty for multiple untrippable CRITICAL STEP RCCA's STANDARD

_ _ SAT Calculates a penalty at 2080 pem and records.

UNSAT (3-1)x(895) + (290) = 2080 pem COMMENTS JPM 2R2S ADMIN Page 6 of 9

ULJ OP/O/A/61001006 Ene! 4.3 Step 2.3.1.5 Calculate total untrippable RCCA reactivity worth penalty for multiple untrippable CRITICAL STEP RCCA's STANDARD

_ _ SAT Determines from Section 5.6.3 of the R.O.D. Manual:

(page 1 of 6) Bk D @ 200 steps)

UNSAT Reactivity worth 44 pem (CB)

Reactivity worth of HFP, Eq Xenon to be 0 pem (SB)

Calculates inserted reactivity worth of 44 pem.

COMMENTS

~ OP/O/A/61001006 Ene! 4.3 Step 2.3.1.6 Calculate available reactivity worth of trippable rods. CRITICAL STEP STANDARD

_ _ SAT Determines:

Total available rod worth 5084 pem (Step 2.3.1.1)

_ _ UNSAT Untrippable RCCA penalty 2080 pem (Step 2.3.1.4)

Inserted Rod Worth 44 pem (Step 2.3.1.5)

Calculates available worth of trippable RCCA's is 2960 pem (5084 pem) - (2080 pem) - (44 pem) =2960 pem COMMENTS W1J OP/O/A/61001006 Ene! 4.3 Step 2.3.1.7 Calculate total misaligned RCCA reactivity worth below:

STANDARD SAT Determines no rods are misaligned or dropped and calculates Q.:

_ _ UNSAT o X 200 pem =0 pem COMMENTS JPM 2R2S ADMIN Page 7 of 9

~ OP/O/A/61001006 Ene! 4.3 Step 2.3.2 Calculate SDM for present conditions. CRITICAL STEP STANDARD SAT Determines:

Determines in step 2.4 available worth of trippable RCA's 2960 pcm UNSAT Total misaligned RCCA reactivity worth 0 pcm Power defect of 1343 pcm per section 5.9 of RO.D. Manual Transient Flux Redistribution Allowance of 489 pcm per Section 5.7 of the RO.D. Manual.

Calculates present SDM of 1128 pcm (2960 pcm) - (0 pcm) - (1343 pcm) - (489 pcm) = 1128 pcm COMMENTS

~ OPIOIA/61001006 Ene! 4.3 Step 2.3.2 Verify present SDM is ~ 1300 pcm per the applicable Technical Specification via CRITICAL STEP COLR STANDARD SAT Candidates determines that adequate shutdown margin does not exist since actual is 1128 pcm and the COLR requirement is1300 pcm.

UNSAT EXAMINER CUE:

Another operator will take actions and complete the procedure.

COMMENTS TIME STOP: _ __

JPM 2R2S ADMIN Page 8 of 9

CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

You are the Unit 1 OATC. The Reactivity Computer (REACT) is out of-service.

Current plant conditions are as follows:

  • Power level = 80%
  • NC Tavg = 579.5 of
  • Boron Concentration: 959 ppm
  • Core burnup: 200 EFPD
  • Shutdown rod bank position: 226 steps

You have just been informed by the Control Room SRO that the following rods are untrippable:

  • G-13
  • K-2
  • P-4 Perform a Shutdown Margin Calculation per OP/O/A/61 00/006 (Reactivity Balance Calculation) and determine if Core Operating Limits Report requirement for shutdown margin is satisfied.

Calculation verification is waived.

CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 3RADMIN Complete a Unit Vent Flow Manual Calculation per PT/1/A14450/017 CANDIDATE EXAMINER JPM 3RADMIN Page 1 of 8

CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task Calculate Unit Vent flow manually per PT/1/A/44501017 (Unit Vent Flow Manual Calculation).

Alternate Path DYES DNO C8J N/A Time Critical DYES C8J NO Evaluation

~ Simulator Din-Plant D Classroom Safety Function __ C8J N/A Location Evaluation Validation 10 minutes

~ Perform DSimulate Method Time JPM Type D Bank DNew C8J Mod ified MNS 2007 NRC exam (A3)

KIA 2.2.12 Knowledge of surveillance procedures. (CFR: 41.10/45.13) (3.0/3.4)

Standard Unit Vent flow is calculated to be 117450 scfm +1- 1000.

References PT/1/A/44501017 (Unit Vent Flow Manual Calculation) rev 012 SLC 16.11-7 (Radioactive Gaseous Effluent Monitoring Instrumentation)

Candidate Start Time End Time Duration Performance Rating D Satisfactory D Unsatisfactory Examiner (Printed Name) (Signature) (Date)

Comments JPM 3RADMIN Page 2 of 8

SIMULATOR SETUP UseSNAP _ _

Fail VFP 5310 to 0 Place OOS sticker on VFP 5310 (1A VF Flow)

SET VA FLOW TO 56000 READ TO OPERATOR DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

  • Both Units are operating at 100% power.
  • No va release is in progress.
  • No GWRs are in progress.
  • The Waste Evaporator and Recycle Evaporator are secured.
  • The Unit Vent Stack Flow Rate Meter is inoperable.
  • Auxiliary Building NLO has called the control room to report 1ABUXF Discharge Air Flow (1ABUX-AFMD-1) is reading 27000 scfm.

INITIATING CUE:

Calculate Unit Vent flow per PT/1/A/44501017 (Unit Vent Flow Manual Calculation) Enclosure 13.1.

JPM 3R ADMIN Page 3 of 8

START TIME: _ __

~MINERNOTE When candidate locates PT/1/A/44501017, hand out a copy of the PT provided.

~

Operator locates and records VA System flow. CRITICAL STEP STANDARD

_ _ SAT Operator locates 1VAP5280 on 1MC-3 and records 56,000 scfm.

_ _ UNSAT EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.

EXAMINER NOTE: Range of 55000 to 57000 scfm is acceptable.

COMMENTS lLJ Operator locates and records VE 1A flow to stack.

STANDARD

_ _ SAT Locates 1VEP5180, notes VE 1A is shutdown and records 0 scfm.

_ _ UNSAT EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.

COMMENTS

~

Operator locates and records VE 1B flow to stack.

STANDARD

_ _ SAT Locates 1VEP5200, notes VE 1B is shutdown and records Oscfm.

UNSAT EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.

COMMENTS JPM 3RADMIN Page 4 of 8

LU Operator locates and records VF 1A flow to stack. CRITICAL STEP STANDARD

_ _ SAT Locates 1VFP531 0, notes VF reading is OOS and uses 33130 scfm from enclosure 13.2.

_ _ UNSAT EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.

COMMENTS

~

Operator locates and records VF 1B flow to stack.

STANDARD SAT Locates 1VFP5340, notes VF 1B is shutdown and records Oscfm.

_ _ UNSAT EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.

COMMENTS LLJ Records 1ABUX-AFMD-1 flow. CRITICAL STEP STANDARD

_ _ SAT Records 27000 scfm based on initial cue.

_ _ UNSAT COMMENTS

~

Operator records VP flows.

STANDARD

_ _ SAT Based on initial cues VP is secured. Flows recorded as 0 scfm or N/A.

_ _ UNSAT COMMENTS JPM 3RADMIN Page 5 of 8

~

LU Operator records WG flow and VQ flow.

STANDARD SAT Based on initial cues records flow as 0 scfm or N/A UNSAT COMMENTS

~

~

Operator records TL flow CRITICAL STEP STANDARD Based on initial cue and procedure notes records 1260 scfm. - - SAT

- - UNSAT COMMENTS

~

UQJ Operator records NB and WL flows.

STANDARD Based on initial cues records flow as 0 scfm or N/A. - - SAT

- - UNSAT COMMENTS WJ

-.:!.!J Operator records ZJ flow to stack. CRITICAL STEP STANDARD Based on initial cue and procedure notes records 60 scfm. - - SAT

- - UNSAT COMMENTS JPM 3RADMIN Page 6 of 8

~

Calculate total vent flow. CRITICAL STEP STANDARD Calculates total vent flow to stack as 117450 scfm. - - SAT (56000)+(33130)+(27000)+(1260)+(60) = 117450 - - UNSAT Due to reading instruments, 116450 -118450 scfm is considered acceptable.

COMMENTS WlJ Complete PT and submit to WCCSRO. CRITICAL STEP STANDARD Records that acceptance criteria is met and signs off remaining procedure steps. - - SAT

- - UNSAT EXAMINER NOTE Candidate may create a Discrepancy Sheet based on gauge VFP5310 having an OOS sticker on it. Although not required, it is not incorrect to submit one.

COMMENTS TIME STOP: _ __

JPM 3RADMIN Page 7 of 8

CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

  • Both Units are operating at 100% power.
  • No VQ release is in progress.
  • No GWRs are in progress.
  • The Waste Evaporator and Recycle Evaporator are secured.
  • The Unit Vent Stack Flow Rate Meter is inoperable.
  • Auxiliary Building NLO has called the control room to report 1ABUXF Discharge Air Flow (1ABUX-AFMD-1) is reading 27000 scfm.

INITIATING CUE:

Calculate Unit Vent flow per PT/1/A/44501017 (Unit Vent Flow Manual Calculation) Enclosure 13.1.

CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 3S ADMIN Determine SLC requirements and complete a Unit Vent Flow Manual Calculation per PT/1/A14450/017.

CANDIDATE EXAMINER JPM 3S ADMIN Page 1 of 9

CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task Determine SLC actions and calculate Unit Vent flow manually per PT/1/A/44501017 (Unit Vent Flow Manual Calculation).

Alternate DYES DNO [gI N/A Time Critical DYES [gI NO Path Evaluation Safety Function __ [gI N/A Location I:8:l Simulator Din-Plant D Classroom Evaluation Validation 14 minutes Method I:8:l Perform DSimulate Time JPM Type o Bank [gI New o Modified KIA 2.2.12 Knowledge of surveillance procedures. (CFR: 41.101 45.13) (3.013.4)

Standard Determine SLC action D applies. Perform the Unit Vent Flow PT within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> and restore OOS meter to operable within 30 days. Unit Vent flow is calculated to be 117450 scfm +1- 1000 scfm.

References PT/1/A/44501017 (Unit Vent Flow Manual Calculation) Rev 012 SLC 16.11-7 (Radioactive Gaseous Effluent Monitoring Instrumentation)

PT/1/A/46001002A (Mode 1 Periodic Surveillance Items) Rev 208 Candidate Start Time End Time ------

Duration Performance Rating D Satisfactory D Unsatisfactory Examiner (Printed Name) (Signature) (Date)

Comments JPM 3SADMIN Page 2 of 9

SIMULATOR SETUP Use SNAP - --,--_

Fail VFP 5310 to 0 Place OOS sticker on VFP 5310 (1A VF Flow)

SET VA FLOW TO 56000 READ TO OPERATOR DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

  • Both Units are operating at 100% power.
  • No va release is in progress.
  • No GWRs are in progress.
  • The Waste Evaporator and Recycle Evaporator are secured.
  • All systems are in normal alignment.

INITIATING CUE:

The RO performing the Unit 1 Mode 1 Periodic Surveillance notified you that flow on OAC point C1 A 1104 was 94000 scfm during the Unit Vent Stack Flow Rate Meter Channel Check. Determine what actions (if any) are required to comply with SLCs and the method used to verify any required actions.

JPM 3S ADMIN Page 3 of 9

START TIME: _ __

W-J Determines if any applicable SLCs exist. CRITICAL STEP STANDARD

_ _ SAT Operator determines directly or through reference to Daily Surveillance PT that SLC 16.11-7 action D applies. This requires PT/1 IA/44501017 (Unit Vent Flow

_ _ UNSAT Manual Calculation) be performed every 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> and the instrument returned to operable within 30 days.

Student may also state that Action K applies (30 day report).

EXAMINER CUE OSM requests that you complete an Enclosure 13.1 of PT/1/A/44501017.

EXAMINER NOTE When candidate locates a copy of PT/1/A/44501017, provide him with the partially completed copy provided.

COMMENTS LU Operator locates and records VA System flow. CRITICAL STEP STANDARD

_ _ SAT Operator locates 1VAP5280 on 1MC-3 and records 56,000 scfm.

_ _ UNSAT EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.

EXAMINER NOTE: Range of 55000 to 57000 scfm is acceptable.

COMMENTS

~

Operator locates and records VE 1A flow to stack.

STANDARD

_ _ SAT Locates 1VEP5180, notes VE 1A is shutdown and records 0 scfm.

_ _ UNSAT EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.

COMMENTS JPM 3S ADMIN Page 4 of 9

~

Operator locates and records VE 1B flow to stack.

STANDARD

_ _ SAT Locates 1VEP5200, notes VE 1B is shutdown and records 0 scfm.

_ _ UNSAT EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.

COMMENTS

~

Operator locates and records VF 1A flow to stack. CRITICAL STEP STANDARD

_ _ SAT Locates 1VFP5310; notes VF reading is OOS and uses 33130 scfm from enclosure 13.2.

_ _ UNSAT EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.

COMMENTS

~

Operator locates and records VF 1B flow to stack.

STANDARD

_ _ SAT Locates 1VFP5340, notes VF 1B is shutdown and records 0 scfm.

_ _ UNSAT EXAMINER NOTE: May provide a picture of the control board gauge instead of locating in the simulator.

COMMENTS JPM 3S ADMIN Page 5 of 9

~

Determines need to get 1ABUX-AFMD-1 flow reading locally. CRITICAL STEP STANDARD SAT NLO dispatched.

_ _ UNSAT EXAMINER CUE: 1ABUX-AFMO-1 reads 27000 scfm.

COMMENTS

&.J Records 1ABUX-AFMD-1 flow. CRITICAL STEP STANDARD

_ _ SAT Records 27000 scfm based on examiner cue.

_ _ UNSAT COMMENTS

~

Operator records VP flows.

STANDARD

_ _ SAT Based on initial cues VP is secured. Flows recorded as 0 scfm or N/A.

_ _ UNSAT COMMENTS

~

Operator records WG flow and VO flow.

STANDARD

_ _ SAT Based on initial cues records flow as 0 scfm or N/A

_ _ UNSAT COMMENTS JPM 3S ADMIN Page 6 of 9

U1J Operator records TL flow CRITICAL STEP STANDARD SAT Based on initial cue and procedure notes records 1260 scfm.

UNSAT COMMENTS

~

Operator records NB and .WL flows.

STANDARD SAT Based on initial cues records flow as 0 scfm or N/A.

UNSAT COMMENTS

~

Operator records ZJ flow to stack. CRITICAL STEP STANDARD SAT Based on initial cue and procedure notes records 60 scfm.

UNSAT COMMENTS JPM 3S ADMIN Page 7 of 9

~

Calculate total vent flow. CRITICAL STEP STANDARD

_ _ SAT Calculates total vent flow to stack as 117450 scfm.

UNSAT (56000)+(33130)+(27000)+(1260)+(60) =117450 EXAMINER NOTE Due to reading instruments, 116450 -118450 scfm is considered acceptable.

COMMENTS Lill Complete PT and submit to WCCSRO. CRITICAL STEP STANDARD

_ _ SAT Records that acceptance criteria is met and signs off remaining procedure steps.

_ _ UNSAT COMMENTS TIME STOP: _ __

JPM 3S ADMIN Page 8 of 9

CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

  • Both Units are operating at 100% power.
  • No va release is in progress.
  • No GWRs are in progress.
  • The Waste Evaporator and Recycle Evaporator are secured.
  • All systems are in normal alignment.

INITIATING CUE:

The RO performing the Unit 1 Mode 1 Periodic Surveillance notified you that flow on OAC point C1 A 1104 was 94000 scfm during the Unit Vent Stack Flow Rate Meter Channel Check. Determine what actions (if any) are required to comply with SLCs and the method used to verify any required actions.

CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 4R4S ADMIN Calculate the Maximum Permissible Stay Time Within Duke Power ALERT Administrative Dose Limits CANDIDATE EXAMINER JPM 4R4S ADMIN Page 1 of 5

CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task Calculate the maximum permissible stay time within Duke Power ALERT administrative dose limits.

Alternate DYES DNO ~ N/A* Time Critical DYES ~NO Path Evaluation Safety Function _ _ ~ N/A Location D Simulator Din-Plant IZl Classroom Evaluation Validation 7 minutes Method IZl Perform DSimulate Time JPM Type o Bank ~New o Modified KIA 2.3.4 Knowledge of radiation exposure limits and contamination control, including permissible levels in excess of those authorized. (CFR: 43.4 1 45.10) 2.5/3.1 Standard Stay time is correctly calculated and the Duke Power ALERT administrative dose limit is not exceeded (reference NSD 507).

References Duke Power Company, Radiation Worker Training Student Guide NSD 507 rev 13 Candidate Start Time End Time ------

Duration Performance Rating D Satisfactory D Unsatisfactory Examiner (Printed Name) (Signature) (Date)

Comments JPM 4R4S ADMIN Page 2 of 5

READ TO OPERATOR DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

An individual has been assigned to perform work in the RCA. The individual's current annual dose is 1374 mR. The area where the work is to be performed has the following radiological characteristics:

  • General area dose rate - 55 mRlhr
  • Airborne contamination - 8 DAC This individual is the only person onsite who is currently qualified to perform the work, however he is NOT respirator qualified. Due to the critical nature of the work, RP will perform additional monitoring to allow the work to proceed without requiring a respirator.

INITIATING CUE:

Calculate the maximum permissible time the individual can work in this area without exceeding the Duke Power ALERT administrative dose limit.

Maximum permissible stay time is: _ _ _ _ _ __

JPM 4R4S ADMIN Page 3 of 5

START TIME: _ __

-.LJ Calculates overall dose rate for comparison to limit and current dose. CRITICAL STEP STANDARD

_ _ SAT 8 DAC-hr x 2.5mRlDAC-hr + 55 mRlhr =75 mRlhr total

_ _ UNSAT COMMENTS

~

Determines available dose to reach the DPC ALERT dose limit. CRITICAL STEP STANDARD

_ _ SAT 1600 (alert limit) -1374 (current dose) = 226 mR

_ _ UNSAT COMMENTS

~

Determines the maximum permissible stay time within the DPC ALERT dose CRITICAL STEP limit.

STANDARD

_ _ SAT 226 mRlhr / 75mRlhr =3.01 hours1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> (3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> is acceptable)

_ _ UNSAT COMMENTS TIME STOP: _ __

JPM 4R4S ADMIN Page 4 of 5

CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

An individual has been assigned to perform work in the RCA. The individual's current annual dose is 1374 mR. The area where the work is to be performed has the following radiological characteristics:

  • General area dose rate - 55 mRlhr
  • Airborne contamination - 8 DAC This individual is the only person onsite who is currently qualified to perform the work, however he is NOT respirator qualified. Due to the critical nature of the work, RP will perform additional monitoring to allow the work to proceed without requiring a respirator.

INITIATING CUE:

Calculate the maximum permissible time the individual can work in this area without exceeding the Duke Power ALERT administrative dose limit.

Maximum permissible stay time is: _ _ _ _ _ __

CATAWBA 2008 INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE JPM 55 ADMIN Upgrade an Emergency Classification and Complete an Emergency Notification Form CANDIDATE EXAMINER JPM 5S ADMIN Page 1 of 7

CATAWBA INITIAL LICENSE EXAMINATION JOB PERFORMANCE MEASURE Task Upgrade to a higher emergency classification and complete an Emergency Notification Form.

Alternate DYES DNO r:g] N/A Time Critical r:g] YES DNO Path Evaluation Safety Function __ r:g] N/A D Simulator Din-Plant [2J Classroom Location Evaluation Validation 11 minutes

[2J Perform DSimulate Method Time JPM Type r:g] Bank DNew D Modified 2003 NRC Exam KIA 2.4.41 Knowledge of the emergency action level thresholds and classifications (CFR: 43.5/45.11) 2.3/4.1 Standard Candidate classifies the event as an Alert within 15 minutes of starting the JPM, and correctly completes the follow-up notification form within 15 minutes of determining the classification.

References RP/O/A/5000/001 (Classification of Emergency) rev 019 RP/O/A/50001003 (Alert) rev 042 RP/O/A/5000/006A (Notification of States and Counties from the Control Room) rev 023 Candidate Start Time End Time

- - - - - - Duration Performance Rating D Satisfactory D Unsatisfactory Examiner (Printed Name) (Signature) (Date)

Comments JPM 5S ADMIN Page 2 of 7

READ TO OPERATOR DIRECTION TO TRAINEE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

  • Unit 1 was shutdown three days ago and is now in Mode 5 with loops filled.
  • "A" train NO, KC and RN in service.
  • 1B NO pump is red tagged for repairs and unavailable.
  • An Unusual Event was declared at 0830 per 4.7.U.1 (Natural and Destructive Phenomena Affecting the Protected Area) when Security reported a tornado touched down on the southwest side of the Protected Area.
  • At 0850, a loss of power occurred on Unit 1 ETA and ETB busses.
  • 1A DIG failed to start.

INITIATING CUE:

Current time is 0915.

0 Reactor Coolant temperature is currently at 181 F and increasing.

Based on the current plant conditions, determine the emergency classification and prepare the next Emergency Notification Form for transmittal.

This JPM is Time Critical.

JPM 5S ADMIN Page 3 of 7

START TIME: _ _ _ (When initiating cue is read to candidate)

~

Compare actual plant conditions to the Emergency Action Levels listed, then CRITICAL STEP declare the appropriate Emergency Class as indicated.

STANDARD

_ _ SAT Candidate uses RP-01 and from the initial conditions, determines the unit is in an

_ _ UNSAT Alert based on Enclosure 4.4 page 2 of 3:

4.4.A.2 Inability to Maintain Plant In Cold Shutdown Operating Mode 5:

(4.4.A.2-1 Total Loss of ND AND Uncontrolled reactor coolant temperature rise to greater than 180°F.)

EXAMINER NOTE To meet the critical step, the candidate must make the declaration within 15 minutes of the START TIME recorded above. When candidate determines classification, record the time for this critical step. _ _ __

EXAMINER NOTE If candidate correctly states 4.4.A.2 as the classification, provide the preprinted sheet for this classification, otherwise, provide a blank ENF.

COMMENTS JPM 5S ADMIN Page 4 of 7

2J Complete an Emergency Notification Form for the classification level determined. CRITICAL STEP*

STANDARD

_ _ SAT Candidate refers to RP/o/A/5000106A "Notification of States and Counties from the Control Room and completes the ENF per the guidelines in Enclosure 4.3 within 15 minutes of the time recorded in Step 1 of the JPM. UNSAT Line 1: Actual Event checked, Message #2

  • Line 2: Initial checked Line 3: Catawba Nuclear Station
  • Line 4: Alert checked and enters appropriate information from event number 4.4.A.2 Line 5: None checked
  • Line 6: None checked Line 7: N/A checked Line 8: Stable or Degrading Line 9: Not filled in (no data)
  • Line 10: Mark Declaration and enters date and time event is declared.
  • Line 11: Unit 1 Line 12: Enters 0% and time reactor shutdown (3 days ago)

Lines 13-16: leaves these blank

  • Line 17: signs as Emergency Coordinator with date and time.

EXAMINER CUE If asked, state that "surveys are not yet available".

EXAMINER NOTE To meet the critical step, the candidate must complete an Emergency Notification Form and submit it for transmittal within 15 minutes of the time recorded in Step 1 of the JPM. When the candidate submits the form, record the time for this critical step. _ _ _ __

COMMENTS JPM 5S ADMIN Page 5 of 7

TIME STOP: _ __

JPM 5S ADMIN Page 6 of 7

CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

  • Unit 1 was shutdown three days ago and is now in Mode 5 with loops filled.

0

  • "A" train NO, KC and RN in service.
  • 1B NO pump is red tagged for repairs and unavailable.
  • An Unusual Event was declared at 0830 per 4.7.U.1 (Natural and Destructive Phenomena Affecting the Protected Area) when Security reported a tornado touched down on the southwest side of the Protected Area.
  • At 0850, a loss of power occurred on Unit 1 ETA and ETB busses.
  • 1A DIG failed to start.

INITIATING CUE:

Current time is 0915.

Reactor Coolant temperature is currently at 181 0 F and increasing.

Based on the current plant conditions, determine the emergency classification and prepare the next Emergency Notification Form for transmittal.

This JPM is Time Critical.